CN103866929A - Water tank assembly for eave and construction method thereof - Google Patents
Water tank assembly for eave and construction method thereof Download PDFInfo
- Publication number
- CN103866929A CN103866929A CN201210525825.6A CN201210525825A CN103866929A CN 103866929 A CN103866929 A CN 103866929A CN 201210525825 A CN201210525825 A CN 201210525825A CN 103866929 A CN103866929 A CN 103866929A
- Authority
- CN
- China
- Prior art keywords
- track
- mentioned
- frame
- eaves
- tank
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 67
- 238000010276 construction Methods 0.000 title claims abstract description 12
- 239000000725 suspension Substances 0.000 claims abstract description 31
- 208000002193 Pain Diseases 0.000 claims description 7
- 238000000926 separation method Methods 0.000 description 3
- 230000015572 biosynthetic process Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003754 machining Methods 0.000 description 1
Images
Landscapes
- Catching Or Destruction (AREA)
- Sewage (AREA)
Abstract
The invention relates to a water tank assembly for an eave and a construction method thereof. The water tank assembly for the eave is provided with a water tank frame, a water tank fixing frame, a flat plate-like fixed pin and an angle adjusting clip, wherein the water tank frame comprises a pipe, a track tank part, a track projection and a locking suspender; the water tank fixing frame comprises a track tank part, a fixing hole, a first track connector and a second track connector; a track projection is formed at a side end of the flat plate-like fixing pin in the length direction and can be fastened as being clamped in the track tank part formed on the water tank frame, and a track fixing lug is formed on the upper surface of the other end of the flat plate-like fixed pin in the length direction; the angle adjusting clip comprises a flat plate, a fan-shaped hook component, a second track engaging suspender, and a first track engaging suspender, and wherein the second track engaging suspender is formed on the lower side surface of the other end of the flat plate, and an engaging suspension table is formed at the tail end of the second track engaging suspender so that second track engaging suspender is correspondingly clamped and fastened with the second track connector of the water tank fixing frame, and the first track engaging suspender is formed on the lower side surface of the flat body and correspondingly clamped and fastened with the first track connector of the water tank fixing frame.
Description
Technical field
The present invention relates to eaves water bowl assembly and construction method thereof, more particularly, relate to according to the gradient on roof and change assembled state, thereby easily construct and disintegrate, not only prevent from leaking between eaves and tank, go back eaves water bowl assembly and the construction method thereof of beautifying constructure outward appearance.
Background technology
Roof structure thing is that the unit that not affected by rain, snow or sunlight as the people of protection process uses.
Such roof structure thing generally arranges roof skeleton in the upper end of pillar, and on roof skeleton, roofing slab is set and forms.
Roof structure thing is transparent or opaque roof Material to be set on the roof framework supporting by pillar form, and has tank in two marginal portions of roof Material, and this tank is discharged to the gutter of a side for collecting the water flowing down from roof.
The roof structure thing of this structure arranges tank in the manner as described below: tank is fixed on the lid of the end that is positioned at roof eaves, the end that becomes eaves is positioned at the state of tank inner side.
Roof structure thing in the past as above, the gradient on roof is according to all sizes of roof structure thing or the climate characteristic of landform of roof structure thing is set and difference.
The roof that forms this roof structure thing forms in the manner as described below, and, in snow or the more area of rain, the inclination on roof should be precipitous, so that the snow on roof or rainwater easily flow to ground, in snow or the many areas of the few and wind of rain, roof is gently set, can lack the impact of wind-engaging.
According to the variation of the inclination of the eaves of formation described above, the shape of tank also should be different, but are difficult to coordinate the eaves of this formation different angles differently to make the shape of tank main body.
Therefore, there are the following problems: on the eaves that tank are arranged on to roof time, be difficult to consider that the inclination of eaves selects tank, and produce gap between eaves and tank, flow to the inner side of roof structure thing thereby the water flowing down from roof flows through between tank and eaves.
Summary of the invention
Therefore, in order to solve the above problems, first object of the present invention is, the tank assembly that can match with the gradient on roof is provided, and second object is, provides tank is connected airtight and is arranged on eaves, thereby not only prevent leaking between eaves and tank, and eaves water bowl assembly and the construction method thereof of beautifying constructure outward appearance, the 3rd object is, even if the tank assembly that firmly supports tank and also maintain profile under outside impact is provided.
To achieve these goals, eaves water bowl assembly of the present invention has: flume frame, it comprises: body, it is formed with multiple fixed part holddown grooves at medial surface, and forms above and the back side connects and upside opening
shape; Track slot part, it is pressed length direction at the upper end, left side of above-mentioned body medial surface and forms; Track projection, it is pressed length direction in right end portion and forms; And card suspension member, it is formed at right side lateral surface; Tank fixed frame, it comprises: track slot part, it is formed at a side, thus it is protruding and fastening to sandwich with sliding type the track being formed in above-mentioned flume frame; Fixing hole, it is formed at another side, for be fixed on roof eaves by fixed part; The 1st track conjunction, it is pressed length direction at upper side and forms; And the 2nd track conjunction, it is formed with endways stings hanging platform; The steady pin of writing board shape, it is formed with track projection at a side by length direction, to sandwich the track slot part that is formed in above-mentioned flume frame and fastening, is formed with track fixed station at the upper surface of the other end by length direction; And angular adjustment folder, it comprises: platysome; Fan-shaped hook part, it is formed at a side of above-mentioned platysome, is formed as three sections by support chip, and this support chip is formed with fixed station endways, makes the track fixed station that is formed at above-mentioned steady pin sandwich and not pull out from horizontal direction; The 2nd track is stung suspension member, and it is formed at the downside of the other end of above-mentioned platysome, is formed with endways and stings hanging platform, makes to sandwich accordingly with the 2nd track conjunction of above-mentioned tank fixed frame and fastening; And the 1st track sting suspension member, it is formed at the downside of above-mentioned platysome, sandwiches accordingly and fastening with the 1st track conjunction of above-mentioned tank fixed frame.
According to the present invention as above, the tank of the various shapes that are consistent with the gradient on roof without selection is provided, and can coordinates by the change of assembling mode the tank assembly of roof gradient, thereby can more easily construct and disintegrate.
In addition, also can not will the tank of various shapes be transported to job site, thereby save portage, construction easily and can the reduction of erection time, thereby can save service charge, there is economy.
And, tank is connected airtight and is arranged on eaves, thereby can make the minimizing separation producing between lid and tank, thereby not only prevent leaking between eaves and tank, and beautifying constructure outward appearance, firmly support tank, thereby even if also maintain profile under outside impact, be very useful invention.
Brief description of the drawings
Fig. 1 is the stereogram that the flume frame of the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 2 is the stereogram that the tank fixed frame of the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 3 is the stereogram that the steady pin of the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 4 a is the stereogram that the angular adjustment folder of the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 4 b is the sectional view that the angular adjustment folder of the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 5 is the separation stereogram that the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 6 is the combination stereogram that the eaves water bowl assembly of embodiments of the invention is shown.
Fig. 7 is the sectional view that the eaves water bowl assembly of the embodiments of the invention shown in Fig. 6 is shown.
Fig. 8 is the combination stereogram that the eaves water bowl assembly of other embodiment of the present invention is shown.
Fig. 9 is the sectional view that the construction method of the eaves water bowl assembly of embodiments of the invention is shown in order.
Figure 10 is the stereogram that the steady pin of the eaves water bowl assembly of other embodiment of the present invention is shown.
Figure 11 is the stereogram that the water cover of secure bond in the flume frame of the eaves water bowl assembly of embodiments of the invention is shown.
Figure 12 is the stereogram of stinging suspension member illustrating in the flume frame of the eaves water bowl assembly that is fastened on embodiments of the invention.
Figure 13 a to Figure 13 c is the use state diagram that illustrates that the eaves water bowl assembly of embodiments of the invention is constructed under eaves.
Label declaration
10: roof eaves 20: fixed part
100: flume frame 110: body
120: fixed part holddown groove 130,210: track slot part
140,310: track projection 150: card suspension member
200: tank fixed frame 220: fixing hole
240: the 2 track conjunctions of 230: the 1 track conjunctions
241: sting hanging platform 300: steady pin
320: track fixed station 330: prevent into platform
400: angular adjustment folder 410: platysome
420: support chip 421: fixed station
430: 440: the 1 tracks of hook part are stung suspension member
Within 450: the, 2 tracks are stung suspension member 451: sting hanging platform
Within 461: the 1, connect road and within 462: the 2, connect road
Within 463: the 3, connect road 500: water cover
600: sting suspension member a, b, c: angle
W: width
Detailed description of the invention
To achieve these goals, eaves water bowl assembly of the present invention has: flume frame, it comprises: body, it is formed with multiple fixed part holddown grooves at medial surface, and forms above and the back side connects and upside opening
shape; Track slot part, it is pressed length direction at the upper end, left side of above-mentioned body medial surface and forms; Track projection, it is pressed length direction in right end portion and forms; And card suspension member, it is formed at right side lateral surface; Tank fixed frame, it comprises: track slot part, it is formed at a side, thus it is protruding and fastening to sandwich with sliding type the track being formed in above-mentioned flume frame; Fixing hole, it is formed at another side, for be fixed on roof eaves by fixed part; The 1st track conjunction, it is pressed length direction at upper side and forms; And the 2nd track conjunction, it is formed with endways stings hanging platform; The steady pin of writing board shape, it is formed with track projection at a side by length direction, to sandwich the track slot part that is formed in above-mentioned flume frame and fastening, is formed with track fixed station at the upper surface of the other end by length direction; And angular adjustment folder, it comprises: platysome; Fan-shaped hook part, it is formed at a side of above-mentioned platysome, is formed as three sections by support chip, and this support chip is formed with fixed station endways, makes the track fixed station that is formed at above-mentioned steady pin sandwich and not pull out from horizontal direction; The 2nd track is stung suspension member, and it is formed at the downside of the other end of above-mentioned platysome, is formed with endways and stings hanging platform, makes to sandwich accordingly with the 2nd track conjunction of above-mentioned tank fixed frame and fastening; And the 1st track sting suspension member, it is formed at the downside of above-mentioned platysome, sandwiches accordingly and fastening with the 1st track conjunction of above-mentioned tank fixed frame.
Below, with reference to accompanying drawing, embodiments of the invention are described.
The eaves water bowl assembly of embodiments of the invention is made up of flume frame 100, tank fixed frame 200, steady pin 300 and angular adjustment folder 400.
Fig. 1 is the stereogram that the flume frame of the eaves water bowl assembly of embodiments of the invention is shown, with reference to Fig. 1, the flume frame 100 of tank assembly of the present invention is configured to and comprises: body 110, it is formed with multiple fixed part holddown grooves 120 at medial surface, and is formed as that front and back connects and upside is open
shape; Track slot part 130, its medial surface in the upper end, left side of above-mentioned body 110 is pressed length direction and is formed; And track projection 140, it is pressed length direction in right end portion and forms, and wherein, on the right side of above-mentioned body 110, lateral surface is formed with card suspension member 150.
Fig. 2 is the stereogram that the tank fixed frame of the eaves water bowl assembly of embodiments of the invention is shown, with reference to Fig. 2, the tank fixed frame 200 of tank assembly of the present invention is formed with track slot part 210 at a side, make to sandwich and be formed at the track projection 140 of above-mentioned flume frame 100 and fastening with sliding type, and in order to be fixed on roof eaves 10 by fixed part 20, be formed with fixing hole 220 in another side.
In addition, be formed with the 1st track conjunction 230 at upper side by length direction, be formed with endways and possess the 2nd track conjunction 240 of stinging hanging platform 241.
Fig. 3 is the stereogram that the steady pin of the eaves water bowl assembly of embodiments of the invention is shown, with reference to Fig. 3, the steady pin 300 of tank assembly of the present invention is writing board shape, be formed with track projection 310 at a side by length direction, make to sandwich and be formed at the track slot part 130 of above-mentioned flume frame 100 and fastening, be formed with track fixed station 320 at the upper surface of another side by length direction.
Fig. 4 a is the stereogram that the angular adjustment folder of the eaves water bowl assembly of embodiments of the invention is shown, Fig. 4 b is the sectional view that the angular adjustment folder of the eaves water bowl assembly of embodiments of the invention is shown, with reference to Fig. 4 a and Fig. 4 b, on the angular adjustment folder 400 of tank assembly of the present invention, be formed with platysome 410 and hook part 430, this hook part 430 is fan-shaped, and be formed at a side of above-mentioned platysome 410, have by support chip 420 and be formed as three sections, be formed with fixed station 421 at the end of this support chip 420, sandwich and do not pull out from horizontal direction so that be formed at the track fixed station 320 of above-mentioned steady pin 300.
Particularly, preferably, on the hook part 430 that is formed as three sections by the support chip 420 of above-mentioned angular adjustment folder 400, with 15 degree angle (a, b, c) interval is formed with the 1st and connects road 461, the 2nd connects road 462 and the 3rd connects road 463, by the above-mentioned hook part 430 that is formed as three sections, do not need to select the tank of the various shapes that are consistent with the gradient on roof, select the 1st to connect road 461 to the 3rd any one perforation in road 463, the track projection 310 that sandwiches steady pin 300 is fastening, thereby can realize the tank assembly of the gradient that can coordinate roof.
Be formed with the 2nd track at the downside of the other end of above-mentioned platysome 410 and sting suspension member 450, it is to sandwich accordingly with the 2nd track conjunction 240 of above-mentioned tank fixed frame 200 and fastening that above-mentioned the 2nd track is stung suspension member 450.Sting in suspension member 450 at above-mentioned the 2nd track, be formed with endways and sting hanging platform 451, the above-mentioned hanging platform 451 of stinging is to form in above-mentioned angular adjustment folder 400 modes that do not depart from from tank fixed frame 200.
In addition, be formed with the 1st track at the downside of above-mentioned platysome 410 and sting suspension member 440, it is to sandwich accordingly with the 1st track conjunction 230 of above-mentioned tank fixed frame 200 and fastening that above-mentioned the 1st track is stung suspension member 440, thereby makes above-mentioned angular adjustment folder 400 firmly more fastening with tank fixed frame 200.
Fig. 5 is the separation stereogram that the eaves water bowl assembly of embodiments of the invention is shown, Fig. 6 is the combination stereogram that the eaves water bowl assembly of embodiments of the invention is shown, Fig. 7 is the sectional view that the eaves water bowl assembly of the embodiments of the invention shown in Fig. 6 is shown.
With reference to Fig. 5 to Fig. 7, eaves water bowl assembly of the present invention is by flume frame 100, tank fixed frame 200, steady pin 300 and angular adjustment folder 400 form, above-mentioned tank fixed frame 200 is fixed on the upper end of roof eaves 10 by fixed part 20, the steady pin 300 fastening with the hook part 430 of above-mentioned angular adjustment folder 400, be fastened on combination on the track slot part 130 of above-mentioned flume frame 100 with sliding type, above-mentioned flume frame 100 is fastened on sliding type on the track slot part 210 of tank fixed frame 200, above-mentioned angular adjustment folder 400 is fastened on above-mentioned tank fixed frame 200.
As mentioned above, in the eaves water bowl assembly of embodiments of the invention, tank is to sandwich the mode of cooperation and eaves and connect airtight and arrange by carrying out Precision Machining, not only prevents leaking between eaves and tank thereby have, and the advantage of beautifying constructure outward appearance.
Fig. 8 is the combination stereogram that the eaves water bowl assembly of other embodiment of the present invention is shown, with reference to Fig. 8, the steady pin 300 arranging on above-mentioned flume frame 100 and tank fixed frame 200 and angular adjustment folder 400 preferably arrange across the width of 1m.
Such method to set up is for above-mentioned flume frame 100 is more firmly supported on above-mentioned tank fixed frame 200.
Fig. 9 is the sectional view that the construction method of the eaves water bowl assembly of embodiments of the invention is shown in order, with reference to Fig. 9, make fixed part 20 by being formed at the fixing hole 220 on above-mentioned tank fixed frame 200, tank fixed frame 200 is fixed on to the upper end of roof eaves 10.
Afterwards, with the gradient on roof correspondingly, by the track fixed station of steady pin 300 320 with from be formed as the 1st hook part 430 of angular adjustment folder 400 of three sections connect road 461 to the 3rd connect one that road 463 selects fastening.
Afterwards, by fastening to the track projection 310 of steady pin 300 and the track slot part 130 of flume frame 100 that are fastened with above-mentioned angular adjustment folder 400.
Afterwards, the track projection 140 of flume frame 100 that is fastened with above-mentioned angular adjustment folder 400 and steady pin 300 is clamped into track slot part 210 combinations of the tank fixed frame 200 of the upper end that is fixed on above-mentioned roof eaves 10.
Afterwards, the 1st track of above-mentioned angular adjustment folder 400 is stung on the 1st track conjunction 230 that suspension member 440 is fastened on above-mentioned tank fixed frame 200, the 2nd track is stung suspension member 450 and is fastened on the 2nd track conjunction 240.
Figure 10 is the stereogram that the steady pin of the eaves water bowl assembly of other embodiment of the present invention is shown, with reference to Figure 10, on the upper end of a side that is formed at the track fixed station 320 on above-mentioned steady pin 300, be also formed with and prevent into platform 330, above-mentionedly prevent that platform 330 is for following object: above-mentioned track fixed station 320 is clamped into and is formed at the 1st on above-mentioned angular adjustment folder 400 and connects road 461 and connect behind road 463 to the 3rd, connect road with respect to these, not by and further do not enter, thereby above-mentioned steady pin 300 is more easily fastened on above-mentioned angular adjustment folder 400.
Figure 11 is the stereogram that is illustrated in secure bond water cover in the flume frame of eaves water bowl assembly of embodiments of the invention, with reference to Figure 11, the figure that following content is shown: water cover 500 be arranged on connect above-mentioned flume frame 100 above or the back side, make multiple fixed parts 20 fix above-mentioned water cover 500 by the fixed part holddown groove 120 being formed in above-mentioned flume frame 100.
Above-mentioned water cover 500 is for the water flowing down from roof is pooled to flume frame 100, makes to be pooled to the structure that the water in flume frame 100 moves to the direction of expecting.
Figure 12 illustrates the stereogram of stinging suspension member fastening with the flume frame of the eaves water bowl assembly of embodiments of the invention, with reference to Figure 12, effect of stinging suspension member 600 of the present invention is, be suspended to and be arranged on stinging on suspension member 600 and firmly supporting above-mentioned flume frame 100 on roof eaves 10 being formed on card suspension member 150 in flume frame 100, thereby also maintain profile while making tank assembly be subject to outside impact.
Figure 13 a to Figure 13 c illustrates the use state diagram that the eaves water bowl assembly of embodiments of the invention is constructed under eaves, with reference to Figure 13 a to Figure 13 c, the eaves water bowl assembly of embodiments of the invention, the tank that does not need to select the various shapes that coordinate with the gradient on roof is provided, can coordinate according to the change of assembling mode the tank assembly of the gradient on roof, thereby can more easily construct and disintegrate.
Claims (7)
1. an eaves water bowl assembly, is characterized in that having:
Flume frame (100), it comprises: body (110), it is formed with multiple fixed part holddown grooves (120) at medial surface, and this body (110) is formed as above and the back side connects and upside opening
shape; Track slot part (130), it is pressed length direction at the upper end, left side of above-mentioned body medial surface and forms; Track projection (140), it is pressed length direction in right end portion and forms; And card suspension member (150), it is formed at right side lateral surface;
Tank fixed frame (200), it comprises: track slot part (210), it is formed at a side, makes to sandwich and be formed at the track projection (140) of above-mentioned flume frame (100) and fastening with sliding type; Fixing hole (220), it is formed at another side, for being fixed on roof eaves (10) by fixed part (20); The 1st track conjunction (230), it is pressed length direction at upper side and forms; And the 2nd track conjunction (240), it is formed with endways stings hanging platform (241);
The steady pin (300) of writing board shape, it is formed with track projection (310) at a side by length direction, be formed at the track slot part (130) of above-mentioned flume frame (100) and fastening to sandwich, be formed with track fixed station (320) at the upper surface of another side by length direction; And
Angular adjustment folder (400), it comprises: platysome (410); Fan-shaped hook part (430), it is formed at a side of above-mentioned platysome (410), be formed as three sections by support chip (420), this support chip (420) is formed with fixed station (421) endways, and the track fixed station (320) that makes to be formed on above-mentioned steady pin (300) sandwiches and do not pull out from horizontal direction; The 2nd track is stung suspension member (450), it is formed at the downside of another side of above-mentioned platysome (410), be formed with endways and sting hanging platform (451), make to sandwich accordingly with the 2nd track conjunction (240) of above-mentioned tank fixed frame (200) and fastening; And the 1st track sting suspension member (440), it is formed at the downside of above-mentioned platysome (410), sandwiches accordingly and fastening with the 1st track conjunction (230) of above-mentioned tank fixed frame (200).
2. a construction method for eaves water bowl assembly, is characterized in that,
Make fixed part (20) by being formed at the fixing hole (220) on tank fixed frame (200), thereby above-mentioned tank fixed frame (200) is fixed on to the upper end of roof eaves (10), then, be consistent with the gradient on roof the track fixed station (320) of steady pin (300) is fastened on the hook part (430) of angular adjustment folder (400) that is formed as three sections, then, the track projection (310) of steady pin (300) and the track slot part (130) of flume frame (100) that will be fastened with above-mentioned angular adjustment folder (400) are fastening, then, the track projection (140) of above-mentioned flume frame (100) is clamped into the track slot part (210) of the tank fixed frame (200) fixing in the upper end of above-mentioned roof eaves (10) and carries out combination, then, the 1st track of above-mentioned angular adjustment folder (400) is stung to suspension member (440) and the 2nd track, and to sting suspension member (450) fastening and complete construction with the 1st track conjunction (230) of above-mentioned tank fixed frame (200) and the 2nd track conjunction (240) respectively.
3. the construction method of eaves water bowl assembly according to claim 2, is characterized in that,
Steady pin (300) and angular adjustment folder (400) in above-mentioned flume frame (100) and the upper setting of tank fixed frame (200) are to arrange across the width of lm.
4. eaves water bowl assembly according to claim 1, is characterized in that,
Be formed with and prevent into platform (330) in the upper end of a side that is formed at the track fixed station (320) on above-mentioned steady pin (300), make further not enter to sandwiching fastening direction.
5. eaves water bowl assembly according to claim 1, is characterized in that,
Upper at the hook part (430) that is formed as three sections by the support chip (420) of above-mentioned angular adjustment folder (400), with the angle of 15 degree, (a, b, interval c) are formed with the 1st and connect road (461), the 2nd and connect road (462) and the 3rd and connect road (463).
6. eaves water bowl assembly according to claim 1, is characterized in that,
Connect above-mentioned flume frame (100) above or the back side water cover (500) is set, make multiple fixed parts (20) fix above-mentioned water cover (500) by the fixed part holddown groove (120) that is formed at above-mentioned flume frame (100).
7. eaves water bowl assembly according to claim 1, is characterized in that,
The card suspension member (150) that is formed at above-mentioned flume frame (100) is suspended to the suspension member (600) of stinging being arranged on roof eaves (10) and above firmly supports above-mentioned flume frame (100).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210525825.6A CN103866929B (en) | 2012-12-07 | 2012-12-07 | Eaves tank assembly and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210525825.6A CN103866929B (en) | 2012-12-07 | 2012-12-07 | Eaves tank assembly and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103866929A true CN103866929A (en) | 2014-06-18 |
CN103866929B CN103866929B (en) | 2016-08-10 |
Family
ID=50905909
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210525825.6A Expired - Fee Related CN103866929B (en) | 2012-12-07 | 2012-12-07 | Eaves tank assembly and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103866929B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6393796B1 (en) * | 2017-04-27 | 2018-09-19 | 株式会社オーティス | Eaves support equipment |
JP7337375B2 (en) | 2019-08-30 | 2023-09-04 | 元旦ビューティ工業株式会社 | Eaves structure |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08246620A (en) * | 1995-03-13 | 1996-09-24 | Sekisui Chem Co Ltd | Hanging tool for eaves gutter |
CN2837415Y (en) * | 2005-08-23 | 2006-11-15 | 朱勇 | Roof drainage structure of sunroom |
CN200955229Y (en) * | 2006-09-25 | 2007-10-03 | 李孟东 | Hanger of water-drop eaves gutter |
CN101333821A (en) * | 2007-06-29 | 2008-12-31 | 上海外国语大学附属大境中学 | Rainwater gathering apparatus |
CN201433519Y (en) * | 2009-06-22 | 2010-03-31 | 浙江公元太阳能科技有限公司 | Eave water eliminator with sunshine rooftop section |
CN201991149U (en) * | 2011-03-18 | 2011-09-28 | 北京东方诚国际钢结构工程有限公司 | Open valley assembly |
-
2012
- 2012-12-07 CN CN201210525825.6A patent/CN103866929B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08246620A (en) * | 1995-03-13 | 1996-09-24 | Sekisui Chem Co Ltd | Hanging tool for eaves gutter |
CN2837415Y (en) * | 2005-08-23 | 2006-11-15 | 朱勇 | Roof drainage structure of sunroom |
CN200955229Y (en) * | 2006-09-25 | 2007-10-03 | 李孟东 | Hanger of water-drop eaves gutter |
CN101333821A (en) * | 2007-06-29 | 2008-12-31 | 上海外国语大学附属大境中学 | Rainwater gathering apparatus |
CN201433519Y (en) * | 2009-06-22 | 2010-03-31 | 浙江公元太阳能科技有限公司 | Eave water eliminator with sunshine rooftop section |
CN201991149U (en) * | 2011-03-18 | 2011-09-28 | 北京东方诚国际钢结构工程有限公司 | Open valley assembly |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6393796B1 (en) * | 2017-04-27 | 2018-09-19 | 株式会社オーティス | Eaves support equipment |
JP2018184786A (en) * | 2017-04-27 | 2018-11-22 | 株式会社オーティス | Eaves gutter support device |
JP7337375B2 (en) | 2019-08-30 | 2023-09-04 | 元旦ビューティ工業株式会社 | Eaves structure |
Also Published As
Publication number | Publication date |
---|---|
CN103866929B (en) | 2016-08-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101802324B (en) | Fixing structure of solar battery module, frame for the solar battery module, and fixing member | |
CN103875178B (en) | The fixture construction of solar module | |
CN108512490A (en) | Solar power generation component and its providing method with integrated support and water management | |
DE502007005396D1 (en) | Flat roof top with solar modules | |
CN102239300A (en) | Mount for installing structure, and solar cell system | |
CN103938652B (en) | Underground Station building structure | |
CN108005276B (en) | A kind of inner wall of building wall and its construction method | |
CN103866929A (en) | Water tank assembly for eave and construction method thereof | |
CN104106210A (en) | Solar power system and solar panel installation method | |
CN203186434U (en) | Vehicle body structure | |
CN207032499U (en) | A kind of assembled housing structure | |
CN206620091U (en) | Solar chip fixing device, chip assembly and automobile with drainage system | |
JP2010281048A (en) | Simplified building | |
CN202905740U (en) | Fishery photovoltaic support | |
CN202307934U (en) | Foldable solar photovoltaic support capable of being pre-installed | |
CN209620258U (en) | A kind of bracket and a kind of dismountable house | |
CN208472914U (en) | A kind of clearance type water drainage cover board with symmetrical structure | |
JP2015148082A (en) | Drainer on edge of gabled roof and attaching structure for drainer on edge of gabled roof | |
CN203834516U (en) | Rail transit underground station building structure | |
CN207892022U (en) | A kind of drainage system of glass sunlight house | |
CN203716617U (en) | Children's tent with firm structure | |
CN207538340U (en) | A kind of spine for glass sunlight house keeps off the rain harden structure | |
CN206859535U (en) | A kind of new greenhouse reinforces rainwater-collecting component with roof | |
CN206174325U (en) | Prefabricated cabin of split assembled and roof concentrated drainage structure thereof | |
JP2016011543A (en) | Photovoltaic power generation roof and frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160810 |