CN103726617A CN201310707267.XA CN201310707267A CN103726617A CN 103726617 A CN103726617 A CN 103726617A CN 201310707267 A CN201310707267 A CN 201310707267A CN 103726617 A CN103726617 A CN 103726617A
Authority
CN
China
Prior art keywords
paving
coiled material
root
root resistance
resistance carbon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310707267.XA
Other languages
Chinese (zh)
Other versions
CN103726617B (en
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pizhou Binhe Sme Management Service Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310707267.XA priority Critical patent/CN103726617B/en
Publication of CN103726617A publication Critical patent/CN103726617A/en
Application granted granted Critical
Publication of CN103726617B publication Critical patent/CN103726617B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/254Roof garden systems; Roof coverings with high solar reflectance
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B80/00Architectural or constructional elements improving the thermal performance of buildings
    • Y02B80/32Roof garden systems

Landscapes

  • Road Paving Structures (AREA)

Abstract

The invention discloses a building roof afforestation three-layer root thorn precontrol method. The method includes the steps of substrate processing, mucilage spraying, aluminum-tin-antimony alloy coil laying, composite copper tire based SBS modified asphalt waterproof coil laying, root-resisting carbon laying and the like. The building roof afforestation three-layer root thorn precontrol method is convenient in construction and good in root-resisting thorn-controlling performance.

Description

Build roofing and plant green three layers of pre-control root thorn method
Technical field
The present invention relates to adjust roofing and plant green technology roofing root-resistant puncturing method.
Background technology
Along with the continuous deterioration of climatic environment, air layer pollutes more and more serious, and the haze frequency of occurrences is more and more higher, carbonization concentration is more and more closeer, land resources is fewer and feweri, and urban heat land effect is more and more obvious, thereby advance to build roofing and plant green technology and seem more and more important.The national U.S. of west prosperity, Germany, Britain's roofing are planted green area and are occupied larger specific gravity, and south China roofing is planted green certain ratio of also occupying.But at construction roofing, plant green technology roofing root-resistant puncturing technology and be still technical difficult point, do not have finely to solve, some roofings are planted green construction 2-3, its roofing carries out seepage, basic reason roofing root system of plant is through concrete plank layer, have to keep in repair, expend fund, artificial, function and effect are used in impact.
Summary of the invention
The object of the present invention is to provide the good construction roofing of a kind of root resistance control thorn performance to plant green three layers of pre-control root thorn method.
Technical solution of the present invention is:
Construction roofing is planted green three layers of pre-control root thorn method, it is characterized in that: comprise the following steps:
(1) base treatment: after roofing basal plane forms, sweep off floating dust, cut redundance, fill up recessed portion, then carry out levelling with mortar, make roofing smooth, the degree of deviation is ± 2mm;
(2) spraying rubber cement: adopt 325# cement: water: 901 glue=1:0.3:0.2 weight ratio is mixed, and stirs, and is then evenly sprayed on toft face, and thickness is 3mm;
(3) paving aluminium tin pewter coiled material: after rubber cement spraying, paving aluminium tin pewter coiled material, during paving, paving from top to bottom, sealing overlap joint >=5cm, carries out nip drum 1-2 time from top to bottom with Ф 20mm steel pipe after place mat, is convenient to closely knit; Sealing is welded: adopt electric welding machine to carry out sealing welding;
(4) complex copper tire base SBS modified asphalt waterproof coiled material paving: brush away the floating layer of aluminium tin pewter coiled material surface, foreign material; Then brushing basal plane agent: add gasoline to dilute neoprene asphalt adhesive, stir, evenly brush on aluminium tin pewter coiled material with round brush, at normal temperatures, brush and start to carry out paving complex copper tire base SBS modified asphalt waterproof coiled material for latter 4 hours;
Complex copper tire base SBS modified asphalt waterproof coiled material adopts hot melt to carry out paving, the heating edge paving while unreeling during paving; Hot melt edge sealing: complex copper tire JiSBS modified asphalt waterproof coiled material lap-joint is heated with fired heater, make while hot both be connected firmly, take edge overflows pitch as degree, and it is tight with sealing compound pointing that end is received head;
The compacting of calming the anger: after the paving of complex copper tire base SBS modified asphalt waterproof coiled material,, air is extruded, with the bonding integral body that becomes of aluminium tin pewter coiled material from the upper supreme nip drum that carries out with Ф 20cm steel pipe;
(5) root resistance carbon place mat:
Root resistance carbon configuration: root resistance carbon is comprised of charcoal, lime, three kinds of materials of clay, configuration part by weight 3:1:1, proportionally mixes, and evenly mix, forms root resistance carbon;
Root resistance carbon place mat, at the thick root resistance carbon-coating of copper tire base SBS modified asphalt waterproof coiled material surface uniform place mat 0.5cm, sprays water after paving, every m 2water spray 0.3kg, after surface is solid, rolls and carries out from top to bottom compacting with hollow steel;
The protection of root resistance carbon face, root resistance carbon-coating surface, brushing one deck pitch, and cover one deck geotextiles.
Charcoal in root resistance carbon is the powdery of particle diameter <1mm; Lime is pulverized limestone, and sieves with eyelet Ф <1mm steel sieve, removes impurity, and clay is through shining soil or drying, and pulverizes or pulverize, and with eyelet Ф <1mm steel, sieves and sieves, and removes impurity.
Easy construction of the present invention, root resistance control thorn performance is good.
First floor of the present invention is closed root resistance puncture layer, adopt aluminium tin pewter coiled material, this tensile strength of material >=20Mpa, fracture elongation >=30%, root-resistant puncturing is tested sharp root system and is not punctured above for 10 years, is up to state standards, and low-temperature tenderness-30, Ф 20mm drum, by damaging impact flawless or perforation.By aluminium tin pewter coiled material, place mat, on concrete pavement or on plank surface layer and on other surface layer, directly stops puncture by root system, and this one deck is closure root resistance puncture layer.
The second layer is flexible sealing, and half initiative is resisted root resistance puncture layer, after roofing basal plane place mat aluminium tin pewter coiled material, and place mat complex copper tire base SBS modified asphalt waterproof coiled material, this material solubility content>=2900g/m 2, pulling force>=800 IV/50mm, fracture elongation>=40%, root-resistant puncturing is tested sharp root system and is not punctured above for 8 years, 105 ℃ of heat resistances, low temperature flexibility-25 ℃, this material has closure root resistance performance, and root resistance dynamics is not as good as aluminium tin pewter coiled material, but this material has a kind of pitch chemicals, when phytem enters this layer, during contact pitch, there is burn phytem function, play root resistance puncture effect.
The 3rd layer is antagonism root resistance puncture layer.After second layer complex copper tire SBS modified asphalt waterproof coiled material place mat, the root resistance carbon that place mat one deck 0.5cm is thick, root resistance carbon is pressed 1:1:3 proportional arrangement by lime, clay, charcoal, when root system enters this layer, being forced to property is grown round about, must not enter lower floor, because charcoal and plant phytem have antagonism, and charcoal has stability, the time, longer root resistance effect was better, was an antagonistic root resistance puncture measure.
Adopt above three layers of root resistance puncture measure, form three layers of root resistance lancing system, carry out and have complementary advantages.
Below in conjunction with embodiment, the invention will be further described.
The specific embodiment
Construction roofing is planted green three layers of pre-control root thorn method, comprises the following steps:
(1) base treatment: after roofing basal plane forms, sweep off floating dust, cut redundance, fill up recessed portion, then carry out levelling with mortar, make roofing smooth, the degree of deviation is ± 2mm;
(2) spraying rubber cement: adopt 325# cement: water: 901 glue=1:0.3:0.2 weight ratio is mixed, and stirs, and is then evenly sprayed on toft face, and thickness is 3mm;
(3) paving aluminium tin pewter coiled material: after rubber cement spraying, paving aluminium tin pewter coiled material, during paving, paving from top to bottom, sealing overlap joint >=5cm, carries out nip drum 1-2 time from top to bottom with Ф 20mm steel pipe after place mat, is convenient to closely knit; Sealing is welded: adopt electric welding machine to carry out sealing welding;
(4) complex copper tire base SBS modified asphalt waterproof coiled material paving: brush away the floating layer of aluminium tin pewter coiled material surface, foreign material; Then brushing basal plane agent: add gasoline to dilute neoprene asphalt adhesive, neoprene asphalt adhesive and gasoline weight ratio are 10:2, stir, with round brush, evenly brush on aluminium tin pewter coiled material, at normal temperatures, brush and within latter 4 hours, start to carry out paving complex copper tire base SBS modified asphalt waterproof coiled material;
Complex copper tire base SBS modified asphalt waterproof coiled material adopts hot melt to carry out paving, the heating edge paving while unreeling during paving; Hot melt edge sealing: complex copper tire JiSBS modified asphalt waterproof coiled material lap-joint is heated with fired heater, make while hot both be connected firmly, take edge overflows pitch as degree, and it is tight with sealing compound pointing that end is received head;
The compacting of calming the anger: after the paving of complex copper tire base SBS modified asphalt waterproof coiled material,, air is extruded, with the bonding integral body that becomes of aluminium tin pewter coiled material from the upper supreme nip drum that carries out with Ф 20cm steel pipe;
(5) root resistance carbon place mat:
Root resistance carbon configuration: root resistance carbon is comprised of charcoal, lime, three kinds of materials of clay, configuration part by weight 3:1:1, proportionally mixes, and evenly mix, forms root resistance carbon;
Root resistance carbon place mat, at the thick root resistance carbon-coating of copper tire base SBS modified asphalt waterproof coiled material surface uniform place mat 0.5cm, sprays water after paving, every m 2water spray 0.3kg, after surface is solid, rolls and carries out from top to bottom compacting with hollow steel;
The protection of root resistance carbon face, root resistance carbon-coating surface, brushing one deck pitch, and cover one deck geotextiles.
Charcoal in root resistance carbon is the powdery of particle diameter <1mm; Lime is pulverized limestone, and sieves with eyelet Ф <1mm steel sieve, removes impurity, and clay is through shining soil or drying, and pulverizes or pulverize, and with eyelet Ф <1mm steel, sieves and sieves, and removes impurity.

Claims (2)

1. construction roofing is planted green three layers of pre-control root thorn method, it is characterized in that: comprise the following steps:
(1) base treatment: after roofing basal plane forms, sweep off floating dust, cut redundance, fill up recessed portion, then carry out levelling with mortar, make roofing smooth, the degree of deviation is ± 2mm;
(2) spraying rubber cement: adopt 325# cement: water: 901 glue=1:0.3:0.2 weight ratio is mixed, and stirs, and is then evenly sprayed on toft face, and thickness is 3mm;
(3) paving aluminium tin pewter coiled material: after rubber cement spraying, paving aluminium tin pewter coiled material, during paving, paving from top to bottom, sealing overlap joint >=5cm, carries out nip drum 1-2 time from top to bottom with Ф 20mm steel pipe after place mat, is convenient to closely knit; Sealing is welded: adopt electric welding machine to carry out sealing welding;
(4) complex copper tire base SBS modified asphalt waterproof coiled material paving: brush away the floating layer of aluminium tin pewter coiled material surface, foreign material; Then brushing basal plane agent: add gasoline to dilute neoprene asphalt adhesive, stir, evenly brush on aluminium tin pewter coiled material with round brush, at normal temperatures, brush and start to carry out paving complex copper tire base SBS modified asphalt waterproof coiled material for latter 4 hours;
Complex copper tire base SBS modified asphalt waterproof coiled material adopts hot melt to carry out paving, the heating edge paving while unreeling during paving; Hot melt edge sealing: complex copper tire JiSBS modified asphalt waterproof coiled material lap-joint is heated with fired heater, make while hot both be connected firmly, take edge overflows pitch as degree, and it is tight with sealing compound pointing that end is received head;
The compacting of calming the anger: after the paving of complex copper tire base SBS modified asphalt waterproof coiled material,, air is extruded, with the bonding integral body that becomes of aluminium tin pewter coiled material from the upper supreme nip drum that carries out with Ф 20cm steel pipe;
(5) root resistance carbon place mat:
Root resistance carbon configuration: root resistance carbon is comprised of charcoal, lime, three kinds of materials of clay, configuration part by weight 3:1:1, proportionally mixes, and evenly mix, forms root resistance carbon;
Root resistance carbon place mat, at the thick root resistance carbon-coating of copper tire base SBS modified asphalt waterproof coiled material surface uniform place mat 0.5cm, sprays water after paving, every m 2water spray 0.3kg, after surface is solid, rolls and carries out from top to bottom compacting with hollow steel;
The protection of root resistance carbon face, root resistance carbon-coating surface, brushing one deck pitch, and cover one deck geotextiles.
2. construction roofing according to claim 1 is planted green three layers of pre-control root thorn method, it is characterized in that: the charcoal in root resistance carbon is the powdery of particle diameter <1mm; Lime is pulverized limestone, and sieves with eyelet Ф <1mm steel sieve, removes impurity, and clay is through shining soil or drying, and pulverizes or pulverize, and with eyelet Ф <1mm steel, sieves and sieves, and removes impurity.
CN201310707267.XA 2013-12-20 2013-12-20 Build roofing and plant green three layers of pre-control root thorn method Expired - Fee Related CN103726617B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310707267.XA CN103726617B (en) 2013-12-20 2013-12-20 Build roofing and plant green three layers of pre-control root thorn method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310707267.XA CN103726617B (en) 2013-12-20 2013-12-20 Build roofing and plant green three layers of pre-control root thorn method

Publications (2)

Publication Number Publication Date
CN103726617A true CN103726617A (en) 2014-04-16
CN103726617B CN103726617B (en) 2015-10-21

Family

ID=50450888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310707267.XA Expired - Fee Related CN103726617B (en) 2013-12-20 2013-12-20 Build roofing and plant green three layers of pre-control root thorn method

Country Status (1)

Country Link
CN (1) CN103726617B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105165314A (en) * 2015-07-30 2015-12-23 葛加君 Roof long-root plant planting method
CN105603771A (en) * 2015-12-21 2016-05-25 潍坊市宏源防水材料有限公司 High-extension copper tire based root puncture-resistant waterproofing coiled material and preparation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2637987A1 (en) * 1976-08-24 1978-03-02 Andreas Boeck Cover for embankment or roof - with moulded plastic sheets supporting plant roots and sepd. from roof by plastic spacers
US4669246A (en) * 1985-02-15 1987-06-02 The Dow Chemical Company Insulated roofing system with water repellent fabric
KR100659039B1 (en) * 2006-02-28 2006-12-21 중앙방수기업주식회사 Root isolation sheet for roof, roof complex waterproof and root isolation layer structure using root isolation sheet, embossing polyvinyl sheet and rubber-asphalt membrane waterproofing material and method thereof
CN201433516Y (en) * 2009-07-10 2010-03-31 天津市奇才防水材料有限公司 Self-adhesive root penetration resistant waterproof rolling material for planted roof
CN101812901A (en) * 2010-04-09 2010-08-25 葛加君 Root-resistant puncturing method of green vegetation roof alloy dripping surface
CN101942891A (en) * 2010-09-30 2011-01-12 北京立高科技股份有限公司 Roof ecological planting system and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2637987A1 (en) * 1976-08-24 1978-03-02 Andreas Boeck Cover for embankment or roof - with moulded plastic sheets supporting plant roots and sepd. from roof by plastic spacers
US4669246A (en) * 1985-02-15 1987-06-02 The Dow Chemical Company Insulated roofing system with water repellent fabric
KR100659039B1 (en) * 2006-02-28 2006-12-21 중앙방수기업주식회사 Root isolation sheet for roof, roof complex waterproof and root isolation layer structure using root isolation sheet, embossing polyvinyl sheet and rubber-asphalt membrane waterproofing material and method thereof
CN201433516Y (en) * 2009-07-10 2010-03-31 天津市奇才防水材料有限公司 Self-adhesive root penetration resistant waterproof rolling material for planted roof
CN101812901A (en) * 2010-04-09 2010-08-25 葛加君 Root-resistant puncturing method of green vegetation roof alloy dripping surface
CN101942891A (en) * 2010-09-30 2011-01-12 北京立高科技股份有限公司 Roof ecological planting system and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105165314A (en) * 2015-07-30 2015-12-23 葛加君 Roof long-root plant planting method
CN105603771A (en) * 2015-12-21 2016-05-25 潍坊市宏源防水材料有限公司 High-extension copper tire based root puncture-resistant waterproofing coiled material and preparation method thereof
CN105603771B (en) * 2015-12-21 2018-04-03 潍坊市宏源防水材料有限公司 A kind of high extension copper tire base root resistant waterproof roll and preparation method thereof

Also Published As

Publication number Publication date
CN103726617B (en) 2015-10-21

Similar Documents

Publication Publication Date Title
CN101899889B (en) Waterproof roll with plant root impaling resistance and manufacturing method thereof
KR101434523B1 (en) Seismic Retrofitting of Concrete Structures by using Coating Fiber Mesh Grid and Inorganic Cementitious Matrix Composite
CN1163567C (en) Double waterproof materials of asphalt mastic spread film and sheet on concrete structure and its working method
CN107905052A (en) A kind of heat in low temperature season mixes temperature and pressure asphalt concrete construction method
CN103465540A (en) Preparation method and construction method of non-cured rubber asphalt paint and coil composite waterproof layer
CN205077739U (en) Plant roof waterproof roof boarding
CN203603106U (en) Cement-based composite material blanket
CN104264561A (en) A non-earthing composite structure for a waterproof pavement layer of a top plate for a road tunnel
CN110145039A (en) A kind of acrylate copolymer polyester blank in-place forming macromolecule coiled material and construction method
CN205617181U (en) Slag bituminous mixture road surface structure convenient to microwave heating snow melt
CN103726617B (en) Build roofing and plant green three layers of pre-control root thorn method
CN108086603A (en) A kind of anti-water-stopping system of existing roofing and prevent water roofing
KR101027655B1 (en) Rubberized asphalt pileup layers waterproofing materials with root barrier for the green roof and artificial foundation and its application method
CN201428184Y (en) Aluminum-plastic waterproof roll
CN207466024U (en) A kind of modified pitch root resistant waterproof roll
CN206635644U (en) A kind of waterproof structure of highway bridge
CN102817445B (en) Self-repairing anti-root-penetrating concrete waterproof structure and construction method thereof
CN205617555U (en) Roof root resistance waterproof construction is planted to basement
CN106589985A (en) Preparation method of root resistant and saline-alkaline tolerant waterproof roll
CN203559389U (en) Cement-based composite material blanket
CN201486053U (en) Water-proof coiled material for preventing plant roots from puncturing
CN105862544B (en) A kind of double-layer stress absorption band and preparation method thereof
CN108558269A (en) A kind of note formula conductive asphalt concrete, deck installation structure and method for paving
CN204547227U (en) Carry the waterproof thermal-insulated composite sheet material of self-adhesion of welding edge
CN203766159U (en) Waterproof coiled material with polyurethane film

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191128

Address after: 221000 No.1, Zhangjiagang East Road, Yitang Town, Pizhou City, Xuzhou City, Jiangsu Province

Patentee after: Pizhou Binhe SME Management Service Co., Ltd.

Address before: 226400, Development Building, east side of Taishan Road, digging Town, Rudong County, Jiangsu, Nantong 1002

Patentee before: Ge Jiajun

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151021

Termination date: 20191220