CN103700026A - Free node transfer processing method for intelligent power grid dispatching - Google Patents

Free node transfer processing method for intelligent power grid dispatching Download PDF

Info

Publication number
CN103700026A
CN103700026A CN201310628740.5A CN201310628740A CN103700026A CN 103700026 A CN103700026 A CN 103700026A CN 201310628740 A CN201310628740 A CN 201310628740A CN 103700026 A CN103700026 A CN 103700026A
Authority
CN
China
Prior art keywords
node
task
flow
information
free
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310628740.5A
Other languages
Chinese (zh)
Inventor
曹宇
于永超
李恩全
苏迤
徐家慧
何蕾
庞传军
林海峰
王云峰
李飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Kedong Electric Power Control System Co Ltd
Original Assignee
Beijing Kedong Electric Power Control System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Kedong Electric Power Control System Co Ltd filed Critical Beijing Kedong Electric Power Control System Co Ltd
Priority to CN201310628740.5A priority Critical patent/CN103700026A/en
Publication of CN103700026A publication Critical patent/CN103700026A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a free node transfer processing method for intelligent power grid dispatching. The method comprises the following steps: setting a free node type, appointing processing authority, appointing priority for the authority and storing the priority into a databank; selecting transfer processing flow set in the databank and submitting data through a flow initiator; checking and acquiring initial node information and connection data of a present node in the databank, and determining a next node of the flow; respectively assigning processing flow tasks to task processors according to that whether the next node is a free node when executing the next node flow; checking and acquiring node information in the databank, and processing the tasks and submitting the data through the node task processors; feeding back to check the connection data in the databank according to the submitted data; driving the flow to a next node till all nodes in the flow are executed.

Description

A kind of free node circulation disposal route for intelligent grid scheduling
Technical field
The present invention relates to a kind of free node circulation disposal route for intelligent grid scheduling, belong to electric power system dispatching technical field.
Background technology
Socioeconomic development, has greatly promoted the universal of personal computer, network technology and has promoted.In the information age, the organizational structure becoming more meticulous, functional department's system have caused enterprises collaboration capabilities low, have greatly reduced the work efficiency of enterprise.Traditional office automation (OA) system cannot meet the needs of enterprise practical flow process, cannot effectively improve the efficiency of enterprise operation.As a kind of informationization technology of fast development, it is in service that workflow (work flow) system starts to enter into each enterprise's daily management, is widely used in the work management that relates to the multidisciplinary cooperation of many people in office environment.Workflow system, by enterprise's correlated activation is carried out to modeling, parsing and execution, carries out robotization processing to operation flow, realizes the computer realization to enterprise's scheduling process.
Workflow technology is the informationization technology that the flow definition model that sets by execution goes to support the operation flow of a collection of special setting.It is used to support definition, management and execution work flow process.At present, workflow technology has been widely used in dispatching automation of electric power systems system.
Along with expanding economy, the scale of electrical network is increasing, business is also day by day complicated.This large-scale electrical network is when bringing economic benefit and social benefit to people, and complicated dispatching of power netwoks business has also increased the difficulty of system, daily servicing, BPM.Yet, the Workflow system that in the past used is existing workflow framework mostly, need to set in advance the executor of all human activities in operation flow, and completely according to this flow definition, go to carry out in the process of implementation, but ignored variability and the ease for use of flow process in concrete business.In the practical business application of electrical network, a large amount of business demands often changes exactly, has so caused workflow technology in the past in the practical business of electrical network, often to have some functions or demand not to meet.
In current administration of power networks practical business, as interruption maintenance a few days ago, wind energy turbine set, optimize the flow processs such as operational management and turn in journey in actual flow, it is on duty by turns on duty often having some task treatment peoples, different at treatment people on duty of different time.Namely, operation flow definition phase have no idea the to set the tasks concrete handler of node, similar this situation is in processing in the past, or human intervention process flow operation, carries out task handler's appointment; Assign the task to all possible executor, by numerous executors, selected voluntarily to process.When operation flow or operational staff change, all need flow process to redefine, so greatly increased the weight of the development difficulty of Workflow system and the cost that personnel safeguard, the distribution that also easily makes the mistake, affects whole flow performing.
Summary of the invention
For the existing deficiency of prior art, technical matters to be solved by this invention is to provide by a kind of free node circulation disposal route for intelligent grid scheduling.
For realizing above-mentioned goal of the invention, the present invention adopts following technical scheme:
A free node circulation disposal route for intelligent grid scheduling, comprises the steps:
Free node type, designated treatment authority are set, are authority assigned priorities, and store the relevant position of database into;
Flow process promoter selects the circulation treatment scheme having arranged in database, and submits data to;
In database, inquire about and obtain the line data of start node information and present node, determine the next node of flow process;
While carrying out next node flow process, according to whether being free node type allocating task handler treatment scheme task respectively;
Inquire about and obtain the nodal information in database, and to the task treatment people that possesses this task of processing, send task processing messages according to nodal information;
Node task handler's Processing tasks is also submitted data to;
Return by submitting to data to search line data in database, according to line data acquisition next node;
Drive flow process to turn to subordinate's node-flow, until all nodes in flow process are all finished.
Wherein more preferably, described database comprises:
The flow config table of Stored Procedure id, title, explanation, creation-time;
The flow nodes table of memory node id, node type, node task handler, free node processing authority and free node processing priority;
The wire list of the circulation direction of Stored Procedure node table.
Wherein more preferably, described according to whether being in the step of free node type difference allocating task handler treatment scheme task, if present node is free node type,
, according to present node id querying flow node table, obtain node requested permissions information, according to the needed authority information personnel query of present node authority list, obtain personal information that should authority, and by described personal information situation Processing tasks.
Wherein more preferably, the step of described personal information situation Processing tasks further comprises:
When if the personal information getting is 0, flow process returns to promoter and points out this flow process to can not find executor, the operation that cannot circulate downwards, and flow process is return promoter;
When if the personal information getting is 1, the corresponding people of described personal information is set to the task handler of this node;
When if the personal information getting is greater than 1, then remove to obtain the precedence information of flow nodes, according to priority information handling task.
Wherein more preferably, the step of described according to priority information handling task further comprises:
If system judgement priority is when to be number of tasks preferential, inquiry the current pending total task number of statistician, compare added up quantity, and the personnel that assign the task to current task minimum data process;
If current personnel's to be selected post level information when to be post level preferential, inquired about and obtain to system judgement priority, post level is compared, this task is distributed to the people that post level is the highest;
If the personnel's to be selected status information of turning out for work is inquired about and obtained to system judgement priority, for the state of turning out for work is when preferential,, priority of task is distributed to the current personnel of turning out for work.
Wherein more preferably, described according to being whether free node type respectively in the step of allocating task handler treatment scheme task, if the non-free node type of present node,
Inquire about and obtain the nodal information in database, and according to the node task handler information of nodal information, to possessing the task treatment people transmission task processing messages of processing this task.
Free node circulation disposal route provided by the present invention has adopted priority Intelligent treatment, and has perfect fault tolerant mechanism, can prevent that flow process is stuck.Utilize the method, can reduce the workload of flow process configuring maintenance, dirigibility and adaptability are stronger.
Accompanying drawing explanation
Fig. 1 is the process flow diagram of free node circulation disposal route provided by the present invention;
Fig. 2 is in one embodiment of the present of invention, and turnaround plan is examined the schematic diagram of management process a few days ago;
Fig. 3 is in one embodiment of the present of invention, and wind energy turbine set is optimized the schematic diagram of operational management flow process.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.
As shown in Figure 1, the invention provides a kind of free node circulation disposal route for intelligent grid scheduling, be applied to (abbreviation system) in power dispatching managemant system, specifically comprise the steps: to arrange free node type, designated treatment authority, be authority assigned priorities, and store the relevant position of database into; Flow process promoter selects the circulation treatment scheme having arranged in database, and submits data to; In database, inquire about and obtain the line data of start node information and present node, determine the next node of flow process; While carrying out next node flow process according to whether being free node type allocating task handler treatment scheme task respectively; Inquire about and obtain the nodal information in database, and to the task treatment people that possesses this task of processing, send task processing messages according to nodal information; Node task handler's Processing tasks is also submitted data to; Return by submitting to data to search line data in database, according to line data acquisition next node; Drive flow process to turn to subordinate's node-flow, so circulation, until all nodes in flow process are all finished.The present invention is launched to detailed explanation below.
First, introduce configuration circulation treatment scheme: free node type, designated treatment authority are set, are authority assigned priorities, and store the step of the relevant position of database into.
In current electric power dispatch management flow process (abbreviation flow process), as shown in Figures 2 and 3, turnaround plan is examined the dispatching desk reception maintenance ticket node of management process and the wind energy turbine set confirmation node that wind energy turbine set is optimized operational management flow process a few days ago, needs operator on duty to operate to confirm in process flow operation process.Having no idea in this electric power dispatch management flow process to determine that concrete tasks carrying people's node calls free node.For example, dispatching desk receives maintenance ticket node task and by dispatcher, is processed in routine duties, dispatcher is divided into chief despatcher, scheduling main value, the secondary value of scheduling, yardman from role-security, and due to the singularity of dispatcher's work, dispatcher carries out system on duty by turns.This has just caused different time employed personnel different, when flow definition in the past, have to adjust and not only strengthen workload according to dispatcher's situation on duty, and the distribution that also easily makes the mistake, affects whole flow performing.But because operator on duty adopts system on duty by turns, so have no idea to determine concrete tasks carrying people at flow process configuration phase, so only arranging at flow process configuration phase only need to be at the needed authority relation of this node of flow process configuration phase designated treatment, as higher level, sane level, subordinate right, and concrete tasks carrying people is during process flow operation, according to authority relation, automatically specify.In the configuration of original flow process, can specify the concrete executor of artificial node, need in the present invention to create a free node type, make the type node be need to be mutual with personnel artificial node, need to not specify concrete executor at flow process configuration phase again.The flow process of below free node configuration circulation being processed is elaborated.
In database, set up the circulation treatment scheme of different data table stores configurations.During configuration flow, the variable task node of executor is configured to free node type; For free node designated treatment requested permissions (generally can be appointed as higher level, sane level or subordinate right handles); For the right of priority of authority designated treatment (generally can be appointed as number of tasks is preferential, post level preferential or the state of turning out for work preferential), when identical many people of authority, according to priority, distribute executor.The flow process essential informations such as flow process id, process name, process description, flow process creation-time are stored in the flow config table of database; The flow nodes information such as node i d, node type, node task handler are stored in the flow nodes table of database, if node type is free node, also can want authority and priority by this node required by task of stores processor; The information such as circulation direction of flow nodes table are stored in the wire list of database, and wire list records the flow nodes id of line starting point and the flow nodes id of terminal controls the circulation direction of node with this.
The present invention only configuration flow trend, not concrete executor of the artificial node of configuration flow in configuration circulation treatment scheme.In process flow operation, specify the executor of free node, when executor changes in operation flow, no longer as in flow processing in the past, need again maintenance process configuration, greatly reduced the maintenance of flow process configuration.
Secondly, introduce the concrete steps of carrying out circulation treatment scheme.
In current power dispatching managemant system process flow operation process, after completing, a node processing can automatically jump to next node according to node line.As shown in Figure 1, in the present invention, the flow process configuring condition in tables of data in Query Databases all circulates each time in system flow operational process, check whether next node is free node type, when next node is free node type, obtain and process the needed execution authority of this node, then according to the corresponding executor of authority acquiring, if when getting satisfactory execution people and being 1 people, executor is directly set and drives flow process to circulate downwards, if while getting the artificial many people of satisfactory execution, continue to obtain the priority data of execution, according to priority conditions, obtain the executor that priority is the highest, these personnel's data are set to node executor, then driving flow process to circulate downwards.Launch below to illustrate.
1) by operating personnel (dispatching of power netwoks flow process promoter), in the flow config table of database, selected the newly-built flow process having arranged and submit data to system.
2) system is inquired about querying flow node table according to flow process configuration node id in database, gets the start node information of this flow process configuration; System, according to the line data that in node i d information inquiry wire list in the data of submitting to, this node i d is starting point, is determined the next node of flow process; In wire list, inquire after line data, can be according to the node i d of line data acquisition connection end point, this terminal is the next node of flow process.
3) while carrying out next node flow process according to whether being free node type allocating task handler treatment scheme task respectively.When preparation turns to next node-flow, first obtain the next node of present node, judge the type of this node.System judges according to the next node information getting, if the non-free node of the type of this node, flow process proceeds to step 4) and carries out flow process; If the type of this node is free node, according to free node circulation disposal methods flow process, proceed to step 5);
4) inquire about and obtain the nodal information in database, and according to the node task handler information of nodal information, to possessing the task treatment people transmission task processing messages of processing this task.
5) according to present node id querying flow node table, obtain node requested permissions information, according to the needed authority information personnel query of present node authority list, obtain personal information that should authority, and by described personal information situation Processing tasks.Concrete steps are as follows:
51) if when the personal information getting is 0, flow process returns to promoter and points out this flow process to can not find executor, and operation cannot circulate downwards.
52) if when the personal information getting is 1, this personal information is set to the task handler of this node.
53) if the personal information getting is n(n, be greater than 1) during bar, then remove to obtain the precedence information of flow nodes, information handling task according to priority.Specific as follows:
531) if system judgement priority when to be number of tasks preferential, personnel query waiting task table, the current pending total task number of statistician, compares added up quantity, the personnel that assign the task to current task minimum data process.
532) if system judgement priority when to be post level preferential, personnel query post level information table obtains current personnel's to be selected post level information, obtains personnel's post level information, system compares post level, and this task is distributed to the people that post level is the highest.
533) if system judgement priority for the state of turning out for work is when preferential, the personnel query information table of turning out for work, obtains the personnel's to be selected status information of turning out for work, and priority of task is distributed to the current personnel of turning out for work;
54), if still having after screening by priority to exist is greater than 1 people's situation, obtain hiring date personnel early as node executor.
6) set after tasks carrying people, to treatment people, send task processing messages;
7) task treatment people receives after message, and login system is carried out the processing of node task and submitted data to.
8) return to step 2) by submitting to data to search line data in the wire list of database, according to line data acquisition next node;
9) drive flow process to turn to subordinate's node-flow, so circulation, until all nodes in flow process are all finished.
Multiple combination by authority, priority obtains the personal information that meets node processing necessary requirement in the present invention, and is set to the executor of free node.In the process of process flow operation, have a plurality of personal informations that authority is identical during by authority acquiring executor information, at this moment can to personnel, screen by different processing priority, obtain optimal node processing personal information.Execute phase in flow process is successively specified the executor of subordinate according to different node executors, makes whole operation flow more flexible in the process of implementation.As in the situation that finally all cannot finding executor, take flow process to return the mode to promoter, by promoter, re-start processing, with this, guarantee that flow process has existing of executor all the time, to avoid during process flow operation without executor, flow process cannot continue circulation and stuck phenomenon occurs.
Two kinds of embodiment below by power dispatching managemant system in real work illustrate respectively:
Embodiment mono-: turnaround plan is examined management process a few days ago
As shown in Figure 2, turnaround plan examines in management process that straight tune is dispatched in maintenance application submissions, turnaround plan first trial, higher level and permitted device maintenance application reports, overhauls reexamination, assign maintenance construction order, overhaul ticket connects all non-free nodes of these flow nodes types such as ticket a few days ago, when flow performing arrives above-mentioned non-free node, directly inquire about and obtain the nodal information in database, and according to the node task handler information of nodal information, to possessing the task treatment people transmission task processing messages of processing this task.Turnaround plan is examined in management process a few days ago, and it is free node that dispatching desk receives maintenance ticket node, according to the needed authority information personnel query of this node authority list, obtains the authority configuration information of free node; By this dispatching desk, receive the set authority of maintenance ticket node, obtain dispatching desk and receive maintenance ticket node to personal information that should authority, and configure this dispatching desk and receive maintenance ticket node and process by having the personnel that dispatch authority, priority is distributed with reference to attendance, and by this information status Processing tasks.So when flow performing receives maintenance ticket node to this dispatching desk, system has the personal information of dispatching authority by finding according to authority information, and preferentially select the current employed personnel that turn out for work to carry out task distribution, reduced like this intervention of forced convection's journey, both improve task flow rotary speed, avoided again wrong generation.
Embodiment bis-: wind energy turbine set is optimized operational management flow process
As shown in Figure 3, in wind energy turbine set, optimize in operational management flow process, these flow nodes types such as maintenance application submission, regulation and control place audit, the audit of system place, robotization place audit, center leader check are non-free node all, when flow performing arrives above-mentioned non-free node, directly inquire about and obtain the nodal information in database, and according to the node task handler information of nodal information, to possessing the task treatment people transmission task processing messages of processing this task.Wind energy turbine set is optimized in operational management flow process, and wind energy turbine set confirms that node is free node, and wind energy turbine set confirmation node task is processed by electric field operator on duty in routine duties, and operator on duty carries out system on duty by turns, and every day, employed personnel were indefinite.According to wind energy turbine set, confirm the needed authority information personnel query of node authority list, obtain the authority configuration information that wind energy turbine set is confirmed node; By wind energy turbine set, confirm the authority that node is set, obtain personal information that should authority, and configure wind energy turbine set and confirm that node processes by having the personnel that dispatchs authority, priority is distributed with reference to attendance, and presses this information status Processing tasks.So, when flow performing arrives this node, system will find and have the personal information of dispatching authority according to authority information, and preferentially selects the current employed personnel that turn out for work to carry out task distribution, without the artificial intervention process flow operation that participates in.Reduce like this intervention of forced convection's journey, both improved task flow rotary speed, reduced again wrong generation.
In sum, the free node circulation disposal route for intelligent grid scheduling provided by the present invention has adopted priority Intelligent treatment, and has perfect fault tolerant mechanism, can prevent that flow process is stuck.Utilize the present invention, can reduce the workload of flow process configuring maintenance, dirigibility and adaptability are stronger.
Above the free node circulation disposal route for intelligent grid scheduling provided by the present invention is had been described in detail.For one of ordinary skill in the art, any apparent change of under the prerequisite that does not deviate from connotation of the present invention, it being done, all will form infringement of patent right of the present invention, will bear corresponding legal liabilities.

Claims (6)

1. for a free node circulation disposal route for intelligent grid scheduling, it is characterized in that comprising the steps:
Free node type, designated treatment authority are set, are authority assigned priorities, and store the relevant position of database into;
Flow process promoter selects the circulation treatment scheme having arranged in database, and submits data to;
In database, inquire about and obtain the line data of start node information and present node, determine the next node of flow process;
While carrying out next node flow process according to whether being free node type allocating task handler treatment scheme task respectively;
Inquire about and obtain the nodal information in database, and to the task treatment people that possesses this task of processing, send task processing messages according to nodal information;
Node task handler's Processing tasks is also submitted data to;
Return by submitting to data to search line data in database, according to line data acquisition next node;
Drive flow process to turn to subordinate's node-flow, until all nodes in flow process are all finished.
2. free node circulation disposal route as claimed in claim 1, is characterized in that, described database comprises:
The flow config table of Stored Procedure node i d, title, explanation, creation-time;
The flow nodes table of memory node id, node type, node task handler, free node processing authority and free node processing priority;
The wire list of the circulation direction of Stored Procedure node table.
3. free node as claimed in claim 1 circulation disposal route, it is characterized in that, described according to being whether that free node type is respectively in the step of allocating task handler treatment scheme task, if present node is free node type,, according to present node id querying flow node table, obtain node requested permissions information, according to the needed authority information personnel query of present node authority list, obtain personal information that should authority, and according to described personal information situation Processing tasks.
4. free node as claimed in claim 3 circulation disposal route, is characterized in that further comprising according to the step of described personal information situation Processing tasks:
When if the personal information getting is 0, flow process returns to promoter and points out this flow process to can not find executor, the operation that cannot circulate downwards, and flow process is return promoter;
When if the personal information getting is 1, the corresponding people of described personal information is set to the task handler of this node;
If the personal information getting is when being greater than 1, then remove to obtain the precedence information of flow nodes, according to priority information handling task.
5. free node as claimed in claim 4 circulation disposal route, is characterized in that according to priority the step of information handling task further comprises:
If system judgement priority is when to be number of tasks preferential, inquiry the current pending total task number of statistician, compare added up quantity, and the personnel that assign the task to current task minimum data process;
If current personnel's to be selected post level information when to be post level preferential, inquired about and obtain to system judgement priority, post level is compared, this task is distributed to the people that post level is the highest;
If the personnel's to be selected status information of turning out for work is inquired about and obtained to system judgement priority, for the state of turning out for work is when preferential,, priority of task is distributed to the current personnel of turning out for work.
6. free node as claimed in claim 1 circulation disposal route, it is characterized in that, described according to being whether that free node type is respectively in the step of allocating task handler treatment scheme task, if the non-free node type of present node, inquire about and obtain the nodal information in database, and according to the node task handler information of nodal information, to possessing the task treatment people transmission task processing messages of processing this task.
CN201310628740.5A 2013-11-30 2013-11-30 Free node transfer processing method for intelligent power grid dispatching Pending CN103700026A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310628740.5A CN103700026A (en) 2013-11-30 2013-11-30 Free node transfer processing method for intelligent power grid dispatching

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310628740.5A CN103700026A (en) 2013-11-30 2013-11-30 Free node transfer processing method for intelligent power grid dispatching

Publications (1)

Publication Number Publication Date
CN103700026A true CN103700026A (en) 2014-04-02

Family

ID=50361545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310628740.5A Pending CN103700026A (en) 2013-11-30 2013-11-30 Free node transfer processing method for intelligent power grid dispatching

Country Status (1)

Country Link
CN (1) CN103700026A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104468367A (en) * 2014-10-27 2015-03-25 国家电网公司 Method for modifying region dispatch data network address
CN104573965A (en) * 2015-01-19 2015-04-29 浪潮软件股份有限公司 Front and rear relation circulation method and device based on parallel connection
CN106127410A (en) * 2016-07-04 2016-11-16 北京佳阳科技有限公司 Housekeeping service monitoring and managing method, Apparatus and system
CN106485389A (en) * 2015-09-01 2017-03-08 北京奇虎科技有限公司 The dynamic updating method of examination & approval stream and device
CN107861765A (en) * 2017-06-26 2018-03-30 平安普惠企业管理有限公司 Product configuration method, equipment and computer-readable recording medium
CN109377179A (en) * 2018-10-23 2019-02-22 深圳易嘉恩科技有限公司 Front-end process management system and method based on Vue
CN109816199A (en) * 2018-12-14 2019-05-28 平安医疗健康管理股份有限公司 Task processing method and processing device, server and computer readable storage medium
CN111626648A (en) * 2020-07-28 2020-09-04 太平金融科技服务(上海)有限公司 Survey task scheduling method and device, computer equipment and storage medium
CN112036823A (en) * 2020-08-25 2020-12-04 上海中通吉网络技术有限公司 Workflow-based work order transfer method, device and equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101047609A (en) * 2007-05-08 2007-10-03 中国移动通信集团福建有限公司 Working flow route control device
JP2010044662A (en) * 2008-08-15 2010-02-25 Fuji Xerox Co Ltd Program and information processor
CN102486730A (en) * 2010-12-06 2012-06-06 上海协讯软件有限公司 Workflow realization method and workflow system capable of customizing flow in user-defined manner

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101047609A (en) * 2007-05-08 2007-10-03 中国移动通信集团福建有限公司 Working flow route control device
JP2010044662A (en) * 2008-08-15 2010-02-25 Fuji Xerox Co Ltd Program and information processor
CN102486730A (en) * 2010-12-06 2012-06-06 上海协讯软件有限公司 Workflow realization method and workflow system capable of customizing flow in user-defined manner

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104468367A (en) * 2014-10-27 2015-03-25 国家电网公司 Method for modifying region dispatch data network address
CN104468367B (en) * 2014-10-27 2017-12-22 国家电网公司 A kind of method of regional dispatching data net address modification
CN104573965A (en) * 2015-01-19 2015-04-29 浪潮软件股份有限公司 Front and rear relation circulation method and device based on parallel connection
CN106485389A (en) * 2015-09-01 2017-03-08 北京奇虎科技有限公司 The dynamic updating method of examination & approval stream and device
CN106127410A (en) * 2016-07-04 2016-11-16 北京佳阳科技有限公司 Housekeeping service monitoring and managing method, Apparatus and system
CN107861765A (en) * 2017-06-26 2018-03-30 平安普惠企业管理有限公司 Product configuration method, equipment and computer-readable recording medium
CN107861765B (en) * 2017-06-26 2020-11-17 平安普惠企业管理有限公司 Product configuration method, apparatus, and computer-readable storage medium
CN109377179A (en) * 2018-10-23 2019-02-22 深圳易嘉恩科技有限公司 Front-end process management system and method based on Vue
CN109816199A (en) * 2018-12-14 2019-05-28 平安医疗健康管理股份有限公司 Task processing method and processing device, server and computer readable storage medium
CN109816199B (en) * 2018-12-14 2023-09-22 深圳平安医疗健康科技服务有限公司 Work task processing method and device, server and computer readable storage medium
CN111626648A (en) * 2020-07-28 2020-09-04 太平金融科技服务(上海)有限公司 Survey task scheduling method and device, computer equipment and storage medium
CN112036823A (en) * 2020-08-25 2020-12-04 上海中通吉网络技术有限公司 Workflow-based work order transfer method, device and equipment

Similar Documents

Publication Publication Date Title
CN103700026A (en) Free node transfer processing method for intelligent power grid dispatching
CN108416490A (en) A kind of electric communication operation and maintenance information-pushing method and system
US7650347B2 (en) System and method for job scheduling and distributing job scheduling
CN103886447A (en) Meeting room reservation method and device
CN108876140A (en) A kind of dispatching method, device, server and the medium of power communication maintenance task
CN108985709A (en) Workflow management method towards more satellite data centers collaboration Remote Sensing Products production
CN102376032A (en) Performance management system
CN105512733A (en) Planar-realistic-picture-based conference room reservation method
CN109947532A (en) A kind of big data method for scheduling task in education cloud platform
CN109377063A (en) A kind of method for scheduling task, device, equipment and storage medium
CN110134533B (en) System and method capable of scheduling data in batches
CN115829538A (en) Terminal operation and maintenance service management system
CN109242269A (en) Job instruction generation method, device, system, electronic equipment and storage medium
CN105303290A (en) Managing data in a manufacturing execution system
CN108762932A (en) A kind of cluster task scheduling system and processing method
CN112116189A (en) Production plan drafting support system
Wang et al. Energy-efficient scheduling for flexible job shop under multi-resource constraints using non-dominated sorting teaching-learning-based optimization algorithm
CN108153621B (en) Cloud disaster backup emergency switching management system
CN100473065C (en) A network-oriented machine group working management system and realizing method thereof
CN101398923A (en) Service flowpath modelling approach and system based on order number
CN117217675A (en) Digitalized system and method based on substation equipment delivery and operation and maintenance process
CN115379583A (en) Distributed scheduling method, system, computer equipment and storage medium
CN101071489A (en) Work flow management system and method for realizing work process automation
JP5008437B2 (en) System work support system
CN114418449A (en) Automatic order dispatching method and device for property management work order

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140402

RJ01 Rejection of invention patent application after publication