CN103699942A - 一种检修工程定额定量评估与预测方法及系统 - Google Patents
一种检修工程定额定量评估与预测方法及系统 Download PDFInfo
- Publication number
- CN103699942A CN103699942A CN201310739686.1A CN201310739686A CN103699942A CN 103699942 A CN103699942 A CN 103699942A CN 201310739686 A CN201310739686 A CN 201310739686A CN 103699942 A CN103699942 A CN 103699942A
- Authority
- CN
- China
- Prior art keywords
- quota
- project
- job task
- maintenance
- maintenance engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/80—Management or planning
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310739686.1A CN103699942B (zh) | 2013-12-26 | 2013-12-26 | 一种检修工程定额定量评估与预测方法及系统 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310739686.1A CN103699942B (zh) | 2013-12-26 | 2013-12-26 | 一种检修工程定额定量评估与预测方法及系统 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103699942A true CN103699942A (zh) | 2014-04-02 |
CN103699942B CN103699942B (zh) | 2016-06-08 |
Family
ID=50361464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310739686.1A Active CN103699942B (zh) | 2013-12-26 | 2013-12-26 | 一种检修工程定额定量评估与预测方法及系统 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103699942B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104931653A (zh) * | 2015-06-04 | 2015-09-23 | 国网河南省电力公司电力科学研究院 | 基于等值盐密参数的悬式绝缘子积污难易程度的标定方法 |
CN106326621A (zh) * | 2015-06-30 | 2017-01-11 | 中国石油化工股份有限公司 | 一种确定油田预测油气储量合理性的方法 |
CN107590553A (zh) * | 2017-08-18 | 2018-01-16 | 南京理工大学 | 一种地铁车辆维修材料定额管理办法 |
CN113379075A (zh) * | 2021-06-09 | 2021-09-10 | 国家能源集团国源电力有限公司 | 一种设备维修定额管理方法和装置 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101866461A (zh) * | 2010-06-25 | 2010-10-20 | 冀中能源峰峰集团有限公司 | 煤炭企业预算定额分解方法和系统 |
CN102222276A (zh) * | 2011-05-16 | 2011-10-19 | 广东电网公司深圳供电局 | 电网二次设备状态检修方法及装置 |
CN102495967A (zh) * | 2011-12-12 | 2012-06-13 | 山东电力集团公司济宁供电公司 | 在运电力变压器检修周期计算方法 |
CN102799959A (zh) * | 2012-06-15 | 2012-11-28 | 上海市电力公司 | 一种供电公司运维成本定额评估体系 |
-
2013
- 2013-12-26 CN CN201310739686.1A patent/CN103699942B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101866461A (zh) * | 2010-06-25 | 2010-10-20 | 冀中能源峰峰集团有限公司 | 煤炭企业预算定额分解方法和系统 |
CN102222276A (zh) * | 2011-05-16 | 2011-10-19 | 广东电网公司深圳供电局 | 电网二次设备状态检修方法及装置 |
CN102495967A (zh) * | 2011-12-12 | 2012-06-13 | 山东电力集团公司济宁供电公司 | 在运电力变压器检修周期计算方法 |
CN102799959A (zh) * | 2012-06-15 | 2012-11-28 | 上海市电力公司 | 一种供电公司运维成本定额评估体系 |
Non-Patent Citations (2)
Title |
---|
李国强: "北京市电力公司变电设备检修管理模式研究", 《中国优秀硕士学位论文全文库》, 30 September 2011 (2011-09-30) * |
贾立敏等: "基于量价分离下水电站机组检修预算定额的编制", 《广东水利水电》, 28 February 2013 (2013-02-28) * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104931653A (zh) * | 2015-06-04 | 2015-09-23 | 国网河南省电力公司电力科学研究院 | 基于等值盐密参数的悬式绝缘子积污难易程度的标定方法 |
CN106326621A (zh) * | 2015-06-30 | 2017-01-11 | 中国石油化工股份有限公司 | 一种确定油田预测油气储量合理性的方法 |
CN106326621B (zh) * | 2015-06-30 | 2019-02-01 | 中国石油化工股份有限公司 | 一种确定油田预测油气储量合理性的方法 |
CN107590553A (zh) * | 2017-08-18 | 2018-01-16 | 南京理工大学 | 一种地铁车辆维修材料定额管理办法 |
CN113379075A (zh) * | 2021-06-09 | 2021-09-10 | 国家能源集团国源电力有限公司 | 一种设备维修定额管理方法和装置 |
Also Published As
Publication number | Publication date |
---|---|
CN103699942B (zh) | 2016-06-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106384210B (zh) | 一种基于检修风险收益的输变电设备检修优先级排序方法 | |
Abiri-Jahromi et al. | A two-stage framework for power transformer asset maintenance management—Part I: Models and formulations | |
Besnard et al. | An optimization framework for opportunistic maintenance of offshore wind power system | |
Besnard et al. | A stochastic model for opportunistic maintenance planning of offshore wind farms | |
Jamil et al. | Condition-based maintenance decision making support system (DSS) of hydropower plant | |
CN106570784A (zh) | 电压监测一体化模型 | |
Sang et al. | An integrated preventive operation framework for power systems during hurricanes | |
CN103150635B (zh) | 电力设备运维方法 | |
CN102081765A (zh) | 输电设备状态检修的系统性控制方法 | |
CN104700321A (zh) | 一种输变电设备状态运行趋势分析方法 | |
CN103699942A (zh) | 一种检修工程定额定量评估与预测方法及系统 | |
Gitelman et al. | Asset Management of energy company based on risk-oriented strategy | |
Crespo et al. | Criticality Analysis for improving maintenance, felling and pruning cycles in power lines | |
CN110245163A (zh) | 一种电力系统运行隐患排查方法 | |
CN105809369A (zh) | 考虑新能源功率不确定性分布的日前计划安全校核方法 | |
Levin et al. | Optimization of impacts parameters on the equipment of electrical networks during operation according to the technical condition | |
Liu et al. | Life cycle cost estimate of power system planning | |
Lühn et al. | Multi-criteria analysis of grid expansion concepts on the low voltage level | |
Agrawal | Modeling forced outage in hydropower generating units for operations planning model | |
Xiang et al. | A preliminary study of power system reliability considering cloud service reliability | |
Aadithya | Application of energy value stream mapping as auditing tool for non-value added industrial energy management | |
Edwin et al. | Data-driven and risk-based decision support for maintenance planning on electrical power grid systems | |
Wang et al. | Application of Artificial Intelligence Technology in Power Equipment Condition Prediction and Maintenance | |
Heikkilä | A decision support system to evaluate the business impacts of machine-to-machine system | |
Nguyen et al. | Probabilistic risk-based security assessment for power systems with wind power generation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Chen Haihan Inventor after: Gao Xinhua Inventor after: Lai Qixuan Inventor after: Pan Fan Inventor after: Zeng Tong Inventor after: You Weiyang Inventor after: Sun Yihui Inventor after: Chen Zihui Inventor before: Chen Haihan Inventor before: Su Dahua Inventor before: Deng Xiaoqiang Inventor before: Gao Xinhua Inventor before: Pan Fan Inventor before: Zeng Tong Inventor before: Lai Qixuan Inventor before: You Weiyang Inventor before: Sun Yihui Inventor before: Ou Lin Inventor before: Ma Chengzhi |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: CHEN HAIHAN GAO XINHUA PAN CENG TONG LAI QIXUAN YOU WEIYANG SUN YIHUI OULIN MA CHENGZHI SU DAHUA DENG XIAOQIANG TO: CHEN HAIHAN GAO XINHUA LAI QIXUAN PAN CENG TONG YOU WEIYANG SUN YIHUI CHEN ZIHUI |
|
C53 | Correction of patent of invention or patent application | ||
CB02 | Change of applicant information |
Address after: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Applicant after: ELECTRIC POWER RESEARCH INSTITUTE, GUANGDONG POWER GRID CO., LTD. Address before: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8 Applicant before: Electrical Power Research Institute of Guangdong Power Grid Corporation |
|
COR | Change of bibliographic data |
Free format text: CORRECT: APPLICANT; FROM: ELECTRICAL POWER RESEARCH INSTITUTE OF GUANGDONG POWER GRID CORPORATION TO: ELECTRIC POWER RESEARCH INSTITUTE OF GUANGDONG POWER GRID CO., LTD. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |