CN103628729B - Power grid construction highway crossing support - Google Patents

Power grid construction highway crossing support Download PDF

Info

Publication number
CN103628729B
CN103628729B CN201310651537.XA CN201310651537A CN103628729B CN 103628729 B CN103628729 B CN 103628729B CN 201310651537 A CN201310651537 A CN 201310651537A CN 103628729 B CN103628729 B CN 103628729B
Authority
CN
China
Prior art keywords
power grid
grid construction
column
highway crossing
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310651537.XA
Other languages
Chinese (zh)
Other versions
CN103628729A (en
Inventor
季斌
孙云
陈俊波
张松华
陈宏学
周秋鹏
柯方超
廖晓红
孙利平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd
Hubei Electric Power Transmission and Distribution Engineering Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd
Hubei Electric Power Transmission and Distribution Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Hubei Electric Power Co Ltd, Hubei Electric Power Transmission and Distribution Engineering Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310651537.XA priority Critical patent/CN103628729B/en
Publication of CN103628729A publication Critical patent/CN103628729A/en
Application granted granted Critical
Publication of CN103628729B publication Critical patent/CN103628729B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a kind of power grid construction highway crossing support, described power grid construction highway crossing support is arranged on the below of highway crossing frame.Described power grid construction highway crossing support comprises the column be supported on road surface, reinforces the drag-line of rope column and connects described column top and for the carrying rope of support crossing frame whereabouts rope, described power grid construction highway crossing support comprises multiple described column, described column is arranged with the direction of mode separately along highway, connect with described drag-line between every two adjacent described columns, the height of described column lower than crossing frame height and higher than the minimum Clearance requirement of highway.When the rope in crossing frame relaxes for some reason, lax rope will be propped up and stop it to fall further by the carrying rope of described highway crossing support, avoid touching the normal vehicle travelled on highway, eliminate potential safety hazard, stopped the generation of accident further.

Description

Power grid construction highway crossing support
[technical field]
The present invention relates to power transmission and transformation power grid construction field, particularly relate to a kind of power grid construction highway crossing support.
[background technology]
During transmission line of electricity Poling Construction crossing highway, usually need to set up crossing frame above highway.Insulation ropes net crossing frame is positioned at above highway can hold wire when wire falls for some reason, prevents the wire road surface that drops from causing traffic accident.But the rope of crossing frame also has the lax possibility come off for some reason, and itself is also a kind of potential safety hazard for the vehicle that highway comes and goes.
Therefore, in order to avoid the security incident therefore produced, before crossing frame is set up, can consider to set up support, as the spacer assembly of crossing frame rope to driving vehicle, increase the safety factor of highway crossing construction.
[summary of the invention]
In view of this, for overcoming the deficiencies in the prior art, be necessary to provide a kind of power grid construction highway crossing support, it plays the effect supported and to ground isolation to the rope of crossing frame, increases the safety factor of power grid construction highway crossing construction.
A kind of power grid construction highway crossing support, described power grid construction highway crossing support is arranged on the below of highway crossing frame.Described power grid construction highway crossing support comprises the column be supported on road surface, reinforces the drag-line of rope column and connects described column top and for the carrying rope of support crossing frame whereabouts rope, described power grid construction highway crossing support comprises multiple described column, described column is arranged with the direction of mode separately along highway, connect with described drag-line between every two adjacent described columns, the height of described column lower than crossing frame height and higher than the minimum Clearance requirement of highway.
Wherein at least one embodiment, each described column comprises base, strut and top cylinder, described base is supported on to install described strut on road surface, and the lower end of described strut is arranged on described base, and described top cylinder is arranged on the upper end of described strut to install described carrying rope.
Wherein at least one embodiment, the both sides of described base are provided with balancing weight, and described balancing weight pushes down described base from both sides.
Wherein at least one embodiment, each described strut is provided with two bracing cable clamps kept at a certain distance away, and described bracing cable clamp is used for fixing described drag-line in cross one another mode between described strut adjacent between two.
Wherein at least one embodiment, the outside of two described columns on most side by above-mentioned anchor-hold on ground.
Wherein at least one embodiment, described carrying rope connects the described top cylinder on every two adjacent described columns downwards in turn in the mode overhang, described carrying rope overhangs lowest part should higher than described drag-line.
Wherein at least one embodiment, described strut adopts fiber glass epoxy tubing to make.
Wherein at least one embodiment, described carrying rope is Di Nima rope, and described base adopts seamless steel pipe and square plate to be welded, and described top cylinder adopts seamless steel pipe welded pulley to form.
Wherein at least one embodiment, described power grid construction highway crossing support has 2 to 8 described columns, and above-mentioned column launches along highway direction according to the mode of column interval 7.5m adjacent between two.
Wherein at least one embodiment, the height of described column is 9m, and described strut installs an above-mentioned bracing cable clamp every 3m.。
The present invention, by arranging power grid construction highway crossing support in the below of highway crossing frame, for carrying the rope on highway crossing frame, preventing it from dropping and to threaten or potential safety hazard to highway communication.When the rope in crossing frame for some reason lax drop on power grid construction highway crossing support time, lax rope will be propped up and stop it to fall further by the carrying rope above it, eliminates potential safety hazard, has stopped the generation of accident further.
[accompanying drawing explanation]
Fig. 1 is the package assembly schematic diagram of power grid construction highway crossing support of the present invention.
Fig. 2 is the structure for amplifying schematic diagram of the column of power grid construction highway crossing support in Fig. 1.
[detailed description of the invention]
For understanding the present invention better, below with reference to accompanying drawing and instantiation, invention is described in detail.
When designing support, mainly follow safety, economic, feasible principle, what time following the design focal point of power grid construction highway crossing support of the present invention considered:
First aspect, support needs to set up in the middle of speedway, on speedway, place is limited, car is many, use lifting appliance auxiliary set up unrealistic, therefore the setting up mainly to rely on and manually complete of support, this just requires that support all parts weight can not be too large, and artificial installation also should be simply light.
Second aspect, support should be able to ensure the minimum Clearance requirement of speedway (such as, 5m), and can bear the total weight (such as, 60kg) when insulating cord relaxes completely, and covers the width (such as, 30m) of crossing frame comprehensively.
Comprehensive above several aspect, support of the present invention adopts the mode of the rope connected between column and column to arrange support, and detailed construction hereafter will describe in detail.
Power grid construction highway crossing support of the present invention is arranged on the below of highway crossing frame, for carrying the rope on highway crossing frame, preventing it from dropping and to threaten or potential safety hazard to highway communication.Incorporated by reference to consulting Fig. 1 and Fig. 2, the power grid construction of the present invention preferred embodiment of highway crossing support comprises column 10, reinforces the drag-line 20 of column 10 and connect the carrying rope 30 of column 10.Power grid construction highway crossing support is equidistantly distributed by some columns 10.Such as, the power grid construction highway crossing support shown in Fig. 1 has five columns 10, and column 10 launches along highway direction according to the mode of column interval 7.5m adjacent between two.
Column 10 comprises base 12, strut 14 and top cylinder 16, as shown in Figure 2.Base 12 supports on the ground, as the mount pad of strut 14.Strut 14 lower end is arranged on base 12.Top cylinder 16 is arranged on the upper end of strut 14.The whole height of column 10 is 9m, can adapt to the height of crossing frame.In order to make the base 12 of column more firm, the both sides of base 12 have additional balancing weight 13.Balancing weight 13 pushes down base 12 from both sides, makes column 10 entirety fixing more steady.The length of strut 14 is the height of column substantially, and namely the length of strut 14 is about 9m.Strut 14 is installed on an every root strut 14 of bracing cable clamp 15(every 3m and has two bracing cable clamps 15), for stay guy 20 before strut 14 adjacent between two.In view of the feature of glass-reinforced plastic material density little (only for ordinary carbon steel 1/4 ~ 1/5), mechanical strength high (stretching of some epoxy FRP, bending and compressive strength all can reach 500Mpa), adopt fiber glass epoxy tubing article as strut 14.Consider the reason of convenient economy, base 12 adopts seamless steel pipe and square plate welding, and top cylinder 16 adopts seamless steel pipe welded pulley to form.
Carry out connecting (that is, the drag-line 20 between two bracing cable clamps 15 on adjacent between two column 10 forms " X " shape) with cross one another form between two bracing cable clamps 15 of drag-line 20 on column 10 adjacent between two.Drag-line 20 on two columns 10 on most side outside two bracing cable clamps 15 anchors to ground (as shown in fig. 1).
Carrying rope 30 is in the mode overhang downwards by connecting the top cylinder 16 of every two adjacent upright posts 10 upper ends in turn, and carrying rope 30 overhangs lowest part should higher than drag-line (namely carry between rope 30 and drag-line 20 and any interference does not occur).According to actual conditions, the Di Nima rope conduct carrying rope 30 adopting specific strength high, with load capacity.
In the above-described embodiments, the quantity of column is 5, is spaced apart 7.5m between adjacent upright posts, and the height of column is 9m, and it is applicable to the crossing frame that width is 30m.In other preferred embodiment, the number of column, spacing and height can correspondingly adjust, and the quantity of column and interval can adjust according to the width of crossing frame, the height of column lower than crossing frame height and higher than the minimum Clearance requirement of highway.Such as, the quantity of column can be 7, is spaced apart 7m between column, and applicable width is the crossing frame of 42m.The quantity of column at least 2, can reach 8.
When the rope in crossing frame for some reason lax drop on power grid construction highway crossing support time, lax rope will be propped up and stop it to fall further by the carrying rope 30 above support, avoids accident.20 rope actings in conjunction are drawn in the anchoring at the balancing weight 13 on base 12, the intersection drag-line 20 between strut 14 and two ends, increase support integral rigidity, prevent support to be out of shape because of load-bearing.
Compared to prior art, power grid construction highway crossing support of the present invention at least has the following advantages:
(1) this support mainly adopts the material that the specific strengths such as glass fiber reinforced plastic, Di Nima rope are high, reduces weight as far as possible, facilitate the transport under mal-condition and installation under the condition meeting requirement of strength.
(2) structurally, this support adopts removably, and the weight and volume after fractionation all controls within zone of reasonableness, and coupling part mainly adopts the mode of sleeve connection and pin joint, convenient on-the-spot artificial mounting or dismounting.
(3) this support is except further strengthening except carrying for carrying out highway crossing frame, also can be applicable to the occasion that other need to support.
The above embodiment only have expressed several embodiment of the present invention, and it describes comparatively concrete and detailed, but therefore can not be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.Therefore, the protection domain of patent of the present invention should be as the criterion with claims.

Claims (10)

1. a power grid construction highway crossing support, described power grid construction highway crossing support is arranged on the below of highway crossing frame, it is characterized in that: described power grid construction highway crossing support comprises the column be supported on road surface, reinforce the drag-line of rope column and connect described column top and for the carrying rope of support crossing frame whereabouts rope, described power grid construction highway crossing support comprises multiple described column, described column is arranged along highway direction in mode separately, connect with described drag-line between every two adjacent described columns, the height of described column lower than crossing frame height and higher than the minimum Clearance requirement of highway.
2. power grid construction highway crossing support according to claim 1, it is characterized in that: each described column comprises base, strut and top cylinder, described base is supported on road surface to install described strut, the lower end of described strut is arranged on described base, and described top cylinder is arranged on the upper end of described strut to install described carrying rope.
3. power grid construction highway crossing support according to claim 2, it is characterized in that: the both sides of described base are provided with balancing weight, described balancing weight pushes down described base from both sides.
4. power grid construction highway crossing support according to claim 2, it is characterized in that: each described strut is provided with two bracing cable clamps kept at a certain distance away, described bracing cable clamp is used for fixing described drag-line in cross one another mode between described strut adjacent between two.
5. power grid construction highway crossing support according to claim 2, is characterized in that: the outside of two described columns on most side by above-mentioned anchor-hold on ground.
6. power grid construction highway crossing support according to claim 2, is characterized in that: described carrying rope connects the described top cylinder on every two adjacent described columns downwards in turn in the mode overhang, described carrying rope overhangs lowest part should higher than described drag-line.
7. power grid construction highway crossing support as claimed in any of claims 2 to 6, is characterized in that: described strut adopts fiber glass epoxy tubing to make.
8. power grid construction highway crossing support according to claim 7, is characterized in that: described carrying rope is Di Nima rope, and described base adopts seamless steel pipe and square plate to be welded, and described top cylinder adopts seamless steel pipe welded pulley to form.
9. power grid construction highway crossing support according to claim 8, is characterized in that: described power grid construction highway crossing support has 2 to 8 described columns, and above-mentioned column launches along highway direction according to the mode of column interval 7.5m adjacent between two.
10. power grid construction highway crossing support according to claim 7, is characterized in that: the height of described column is 9m, and described strut installs an above-mentioned bracing cable clamp every 3m.
CN201310651537.XA 2013-12-04 2013-12-04 Power grid construction highway crossing support Active CN103628729B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310651537.XA CN103628729B (en) 2013-12-04 2013-12-04 Power grid construction highway crossing support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310651537.XA CN103628729B (en) 2013-12-04 2013-12-04 Power grid construction highway crossing support

Publications (2)

Publication Number Publication Date
CN103628729A CN103628729A (en) 2014-03-12
CN103628729B true CN103628729B (en) 2015-10-28

Family

ID=50210148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310651537.XA Active CN103628729B (en) 2013-12-04 2013-12-04 Power grid construction highway crossing support

Country Status (1)

Country Link
CN (1) CN103628729B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047362A (en) * 2014-05-23 2014-09-17 苏州工业园区设计研究院股份有限公司 Structure for preventing steel-structure support from falling

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2299351A (en) * 1995-01-25 1996-10-02 Edward Christopher Holt Crossing equipment
CN2333108Y (en) * 1997-05-25 1999-08-11 冀延君 Large span cable bridge rack
CN201172984Y (en) * 2008-04-02 2008-12-31 江西省电力设备总厂 Combined fender bracket for concrete pole
CN201465247U (en) * 2009-08-27 2010-05-12 河南省电力公司平顶山供电公司 Wire pole stay wire anti-theft device
CN202850574U (en) * 2012-09-10 2013-04-03 河南省电力公司信阳供电公司 Wire rod

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2299351A (en) * 1995-01-25 1996-10-02 Edward Christopher Holt Crossing equipment
CN2333108Y (en) * 1997-05-25 1999-08-11 冀延君 Large span cable bridge rack
CN201172984Y (en) * 2008-04-02 2008-12-31 江西省电力设备总厂 Combined fender bracket for concrete pole
CN201465247U (en) * 2009-08-27 2010-05-12 河南省电力公司平顶山供电公司 Wire pole stay wire anti-theft device
CN202850574U (en) * 2012-09-10 2013-04-03 河南省电力公司信阳供电公司 Wire rod

Also Published As

Publication number Publication date
CN103628729A (en) 2014-03-12

Similar Documents

Publication Publication Date Title
CN202530769U (en) Large span steel structure high-altitude subsection hoisting support system
CN202202587U (en) Communication base station
CN103236656A (en) Column suspension type crossing structure and operating method thereof
CN104563578A (en) Combined framework pillar for 500kV transformer substation and mounting method of combined framework pillar
CN103628729B (en) Power grid construction highway crossing support
CN202347525U (en) Prestress bow-shaped steel circuit purlin
CN204385629U (en) A kind of support for the construction of suspension bridge king-tower top rail
CN205347899U (en) Monorail train pillar construction
CN203866711U (en) Large span cable-stayed bridge tower beam three-way temporary consolidation structure
CN202530823U (en) Prestressing force truss type tube tower
CN210917440U (en) Pile foundation reinforcing apparatus for building site
CN201908429U (en) Assembly integral building overhanging discharging platform
CN204386242U (en) For the combined type truss column of 500kV transformer station
CN203835019U (en) Telegraph pole fixing device
CN102849622B (en) Mast-based section-by-section vertical lifting assembling method of tower
CN205907599U (en) Bridge view buffering guardrail
CN205979564U (en) Electric power steel pipe pole is used in city
CN104818995A (en) Method for assembling confined concrete arch frames
CN204402097U (en) For the integrated form framework of the outlet of 500kV transformer station, inlet wire, transition
CN207244453U (en) A kind of suspension bridge light anchorage mast apparatus
CN202550057U (en) Antenna holding pole device
CN201771240U (en) First-aid repair tower
CN206428815U (en) The firm sunlight shed of fixed structure
CN206742822U (en) A kind of integrated bracket for being used for evacuation platform for tunnel and power cable
CN207211909U (en) A kind of photovoltaic generating system and its photovoltaic generation pylon, connection component

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant