CN103532048A - Quickly combined large lattice type crossing frame - Google Patents
Quickly combined large lattice type crossing frame Download PDFInfo
- Publication number
- CN103532048A CN103532048A CN201310492499.8A CN201310492499A CN103532048A CN 103532048 A CN103532048 A CN 103532048A CN 201310492499 A CN201310492499 A CN 201310492499A CN 103532048 A CN103532048 A CN 103532048A
- Authority
- CN
- China
- Prior art keywords
- crossing frame
- fitting
- thick pillar
- pillar body
- lead
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention relates to a quickly combined large lattice type crossing frame. The quickly combined large lattice type crossing frame comprises a plurality of holding column bodies, six-way connecting components and stay wires, wherein each two adjacent holding column bodies are connected through one six-way connecting component; the stay wires are fixed to the holding column bodies to keep the crossing frame stable. Compared with the prior art, the quickly combined large lattice type crossing frame has the advantages of stable structure, high strength, capability of performing standard assembly, high working efficiency and the like.
Description
Technical field
The present invention relates to a kind of high voltage overhead lines construction crossing frame, especially relate to a kind of large-scale lattice crossing frame of Rapid Combination.
Background technology
The general employing of high voltage overhead lines crossing construction set up the methods such as Moso bamboo crossing frame, steel pipe crossing frame, live crossing frame as crossing over support body, and the method for catch net is sealed on top again, and this respect China construction environment complexity and construction level are all higher than abroad.Said method is for general height, the situation that construction environment and time etc. meet specified conditions is no problem, but for highly higher, the leap of engineering time compactness is just very difficult, even if often increase larger leap cost input, can not solve leap security problems, not only need the deeper cooperation by the unit of leap, often need to be crossed over during thing is stopped transport and construct at night, increased construction risk.
Summary of the invention
Object of the present invention be exactly in order to overcome the defect that above-mentioned prior art exists, provide a kind of Stability Analysis of Structures, intensity high, can carry out standardization assembling, the large-scale lattice crossing frame of the Rapid Combination of increasing work efficiency.
Object of the present invention can be achieved through the following technical solutions:
A kind of large-scale lattice crossing frame of Rapid Combination, comprise that thick pillar body, six leads to fitting and bracing wire, described thick pillar body is provided with a plurality of, leads to fitting connect between adjacent thick pillar body by six, described bracing wire is fixed on thick pillar body, keeps crossing frame stable.
Described six to lead to fitting be that the cube structure of screw is all set on six faces, and the face that described thick pillar body leads to fitting by bolt and six is connected.
Described six to lead to the area of each face of fitting identical with the area of thick pillar body cross-section.
Described a plurality of thick pillar bodies lead to fitting by six and connect into chair form or rectangular build crossing frame.
Described crossing frame is provided with and between a plurality of, adjacent crossing frames, is connected with bearing rope and protection network.
Compared with prior art, the present invention has following beneficial effect:
1, configuration aspects: because sky way railway height is generally higher or very high, periphery construction environment is most complicated, and building and mattess are more, and underground not open conduit wiring is more, other construction method needs that bracing wire is more should not be used.In this structure, first adopt framework self-stabilization structure, reduced the dependence to bracing wire, secondly according to spanning height, utilize respectively the different cross section poles such as a large amount of 450,600,700,900mm to be assembled into crossing frame structure, cross section is larger, and load is larger, can scaffolding height higher.
2, intensity aspect: first utilize pole to be far superior to the high strength of mao bamboon and building steel tube, conscientiously accomplish to bear multiple fission conductor broken string load, secondly rational frame structure, has reduced wind and carried and conduct oneself with dignity.
3, construction method aspect: reduced as dependence that live crossing frame method coordinates bracing wire and construction, reduced as the construction discreteness risk of mao bamboon frame and steel pipe frame etc., the present invention has accomplished construction standardization assembling, mechanization assembling, rapid-assembling etc., reduces the security implication that causes surrounding enviroment and may be caused by leap thing because of factors such as construction interruption, inherently safes.
4, construction cost aspect: first the present invention can unlimitedly reuse, the Work tool cost of having made thinner, secondly reduce reduce environment as occupation of land, bracing wire, may cause the use cost of underground utilities damage etc., improved in addition the service efficiency of mechanization, reduced cost of labor.
5, speed of application aspect: improved the service efficiency of mechanization during construction, accomplished to complete for 1~2 day the construction of place's crossing frame, be far superior to the construction period that the above large-scale mao bamboon of a 20m of place or steel pipe crossing frame need 2 weeks left and right time.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the end view that the present invention six leads to fitting.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.The present embodiment be take technical solution of the present invention and is implemented as prerequisite, provided detailed execution mode and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
As shown in Figure 1, a kind of large-scale lattice crossing frame of Rapid Combination, comprise that thick pillar body 1, six leads to fitting 2 and bracing wire, described thick pillar body 1 is provided with a plurality of, 1 of adjacent thick pillar body leads to fitting 2 by six and connects, described bracing wire is fixed on thick pillar body 1, for auxiliary the stable of the rear crossing frame of assembling that keep.A plurality of thick pillar bodies lead to fitting by six and connect into chair form or rectangular build crossing frame, and shape can arbitrarily change.Fig. 1 is chair form crossing frame.
As shown in Figure 2, six to lead to fitting 2 be that the cube structure of screw 3 is all set on six faces, and the face that described thick pillar body leads to fitting by bolt and six is connected, and generally uses 3~5 faces during assembling.
There is sizes in the cross section of pole body, and six to lead to the area of each face of fitting identical with the area of thick pillar body cross-section, comprises 450*450,600*600,700*700, the plurality of specifications such as 900*900.
Described crossing frame is provided with between a plurality of, adjacent crossing frames and is connected with bearing rope and protection network, in order to protection, is crossed over thing.
As adopt 600*600 pole body to set up, and single crossing frame height is 25.8m, and length is 12m, and width is 8m.Single crossing frame needs 64 sections of 600*600 pole bodies (4m is long), and six lead to 16 of fittings.As adopt 900 pole bodies highly for 26.7m.
Claims (5)
1. a large-scale lattice crossing frame for Rapid Combination, is characterized in that, comprises that thick pillar body, six leads to fitting and bracing wire, described thick pillar body is provided with a plurality of, between adjacent thick pillar body, by six, lead to fitting and connect, described bracing wire is fixed on thick pillar body, keeps crossing frame stable.
2. the large-scale lattice crossing frame of a kind of Rapid Combination according to claim 1, it is characterized in that, described six to lead to fitting be that the cube structure of screw is all set on six faces, and the face that described thick pillar body leads to fitting by bolt and six is connected.
3. the large-scale lattice crossing frame of a kind of Rapid Combination according to claim 2, is characterized in that, described six to lead to the area of each face of fitting identical with the area of thick pillar body cross-section.
4. the large-scale lattice crossing frame of a kind of Rapid Combination according to claim 1, is characterized in that, described a plurality of thick pillar bodies lead to fitting by six and connect into chair form or rectangular build crossing frame.
5. the large-scale lattice crossing frame of a kind of Rapid Combination according to claim 1, is characterized in that, described crossing frame is provided with and between a plurality of, adjacent crossing frames, is connected with bearing rope and protection network.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310492499.8A CN103532048B (en) | 2013-10-18 | 2013-10-18 | A kind of large-scale lattice crossing frame of Rapid Combination |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310492499.8A CN103532048B (en) | 2013-10-18 | 2013-10-18 | A kind of large-scale lattice crossing frame of Rapid Combination |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103532048A true CN103532048A (en) | 2014-01-22 |
CN103532048B CN103532048B (en) | 2016-05-11 |
Family
ID=49933848
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310492499.8A Active CN103532048B (en) | 2013-10-18 | 2013-10-18 | A kind of large-scale lattice crossing frame of Rapid Combination |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103532048B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103956681A (en) * | 2014-05-06 | 2014-07-30 | 国网上海市电力公司 | Holding pole lattice crossing frame for two sides of expressway |
CN103956683A (en) * | 2014-05-09 | 2014-07-30 | 国网上海市电力公司 | Crossing frame system used for 220-KV outgoing line engineering wire erection of 500-KV transformer substation |
CN106368493A (en) * | 2016-11-04 | 2017-02-01 | 上海送变电工程公司 | Two-arm hydraulic drive-in type hard capping lattice type crossing frame |
CN106972412A (en) * | 2017-03-20 | 2017-07-21 | 国家电网公司 | UHV transmission line lattice crossing frame |
CN111917090A (en) * | 2020-08-07 | 2020-11-10 | 国网湖南省电力有限公司 | 10kV line live crossing frame and erection method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2895846Y (en) * | 2006-03-23 | 2007-05-02 | 鲍俊武 | Space-structural connector |
TWM349974U (en) * | 2008-08-05 | 2009-02-01 | Jie-Xiong Wu | Structure of multi-directional assembly connector |
KR100926650B1 (en) * | 2008-06-05 | 2009-11-16 | (주)엑서런트 | Protector for underground line |
CN201661559U (en) * | 2010-02-05 | 2010-12-01 | 黄泗龙 | Joint |
CN201785877U (en) * | 2010-09-17 | 2011-04-06 | 王朝平 | Engineering framework |
CN102277999A (en) * | 2011-04-29 | 2011-12-14 | 天津送变电工程公司 | Large-section portal steel structure holding pole |
CN202206066U (en) * | 2011-08-05 | 2012-04-25 | 张勇 | Electric power live crossing frame |
CN203617612U (en) * | 2013-10-18 | 2014-05-28 | 上海送变电工程公司 | Quickly combined large lattice type crossing frame |
-
2013
- 2013-10-18 CN CN201310492499.8A patent/CN103532048B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2895846Y (en) * | 2006-03-23 | 2007-05-02 | 鲍俊武 | Space-structural connector |
KR100926650B1 (en) * | 2008-06-05 | 2009-11-16 | (주)엑서런트 | Protector for underground line |
TWM349974U (en) * | 2008-08-05 | 2009-02-01 | Jie-Xiong Wu | Structure of multi-directional assembly connector |
CN201661559U (en) * | 2010-02-05 | 2010-12-01 | 黄泗龙 | Joint |
CN201785877U (en) * | 2010-09-17 | 2011-04-06 | 王朝平 | Engineering framework |
CN102277999A (en) * | 2011-04-29 | 2011-12-14 | 天津送变电工程公司 | Large-section portal steel structure holding pole |
CN202206066U (en) * | 2011-08-05 | 2012-04-25 | 张勇 | Electric power live crossing frame |
CN203617612U (en) * | 2013-10-18 | 2014-05-28 | 上海送变电工程公司 | Quickly combined large lattice type crossing frame |
Non-Patent Citations (4)
Title |
---|
丁晨等: "抱杆自立式跨越架的研发与应用", 《电力与能源》, vol. 35, no. 2, 30 April 2014 (2014-04-30), pages 227 - 232 * |
张潇予: "某大型格构式跨越架性能分析", 《佳木斯大学学报(自然科学版)》, vol. 33, no. 3, 31 May 2015 (2015-05-31), pages 353 - 358 * |
邱强华等: "输电线路370m大跨越高塔组立施工技术", 《电力建设》, vol. 32, no. 8, 31 August 2011 (2011-08-31), pages 111 - 115 * |
顾天鲲: "电气化铁路带电跨越架", 《科技咨询导报》, no. 9, 31 December 2006 (2006-12-31), pages 94 - 95 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103956681A (en) * | 2014-05-06 | 2014-07-30 | 国网上海市电力公司 | Holding pole lattice crossing frame for two sides of expressway |
CN103956683A (en) * | 2014-05-09 | 2014-07-30 | 国网上海市电力公司 | Crossing frame system used for 220-KV outgoing line engineering wire erection of 500-KV transformer substation |
CN106368493A (en) * | 2016-11-04 | 2017-02-01 | 上海送变电工程公司 | Two-arm hydraulic drive-in type hard capping lattice type crossing frame |
CN106368493B (en) * | 2016-11-04 | 2018-09-14 | 上海送变电工程公司 | A kind of Double-arm hydraulic drive-in binds lattice crossing frame firmly |
CN106972412A (en) * | 2017-03-20 | 2017-07-21 | 国家电网公司 | UHV transmission line lattice crossing frame |
CN106972412B (en) * | 2017-03-20 | 2019-07-26 | 国家电网公司 | UHV transmission line lattice crossing frame |
CN111917090A (en) * | 2020-08-07 | 2020-11-10 | 国网湖南省电力有限公司 | 10kV line live crossing frame and erection method thereof |
CN111917090B (en) * | 2020-08-07 | 2022-03-11 | 国网湖南省电力有限公司 | 10kV line live crossing frame and erection method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN103532048B (en) | 2016-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103532048B (en) | A kind of large-scale lattice crossing frame of Rapid Combination | |
CN202559571U (en) | Net rack roof with siphon rainwater pipeline | |
CN104652600A (en) | Recoverable function framework structure system | |
CN203617612U (en) | Quickly combined large lattice type crossing frame | |
CN105064759A (en) | GFRP (glass fiber reinforced plastic) tubed reinforced concrete combination multi-circuit transmission pole | |
CN204357167U (en) | A kind of cooling stack inclined strut structure | |
CN103216014A (en) | Assembling type frame structure joint | |
CN104912203A (en) | Aluminium alloy column-plate node structure used for space structure | |
CN204753350U (en) | Combination bridge | |
CN205025154U (en) | 330kVGIS distribution device place rigid connection sail formula framework | |
CN204491828U (en) | Can restore funcitons frame structure system | |
CN203729623U (en) | Assembled machining shed for building construction | |
CN206737538U (en) | A kind of half-phase passes through half bolted 750kV steel pipe lattice types framework | |
CN204850639U (en) | GFRP pipe reinforced concrete combined member multiloop transmission of electricity pole | |
CN204225062U (en) | The inner gallery structure of bulb turbine hydropower station factory building | |
CN204551755U (en) | A kind of Staggered-truss System post and truss hinged joint | |
CN203701294U (en) | Novel lattice framework connecting piece of raw bamboo building | |
CN204139650U (en) | A kind of extension type vertical channel | |
CN204728668U (en) | Easy reassembling type scaffold | |
CN204491840U (en) | A kind of being convenient to is installed and the space frame formula self-contained flat be connected | |
CN204282533U (en) | A kind of large span height load light section steel structure | |
CN203961122U (en) | A kind of Two bors d's oeuveres C section steel purlin termination that is applicable to large span purlin | |
CN210217206U (en) | Reinforcing apparatus of ancient tower brickwork | |
CN203145547U (en) | Combined type four-stand-column rush-repair tower of high-voltage line iron tower | |
CN203808486U (en) | Steel pipe scaffold follow-up platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |