CN103485350A - 抬高的钢支撑系统与压顶圈梁的连接方法 - Google Patents

抬高的钢支撑系统与压顶圈梁的连接方法 Download PDF

Info

Publication number
CN103485350A
CN103485350A CN201310435596.3A CN201310435596A CN103485350A CN 103485350 A CN103485350 A CN 103485350A CN 201310435596 A CN201310435596 A CN 201310435596A CN 103485350 A CN103485350 A CN 103485350A
Authority
CN
China
Prior art keywords
top ring
ring beam
bracket
tie beam
collar tie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310435596.3A
Other languages
English (en)
Other versions
CN103485350B (zh
Inventor
陈辉
余振栋
袁芬
陈礼忠
李伟强
孙睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN201310435596.3A priority Critical patent/CN103485350B/zh
Publication of CN103485350A publication Critical patent/CN103485350A/zh
Application granted granted Critical
Publication of CN103485350B publication Critical patent/CN103485350B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种抬高的支撑系统与压顶圈梁连接的方法,用以解决抬高的支撑系统与压顶圈梁的连接问题。首先处理压顶板下的地基,在压顶圈梁与钢支撑系统的连接处设置支撑“牛腿”,支撑“牛腿”的主筋锚入压顶圈梁,使支撑“牛腿”与压顶圈梁结合成为一个整体。这样,抬高的钢支撑系统再与支撑“牛腿”连接,使钢支撑所承受的轴力很好的传递在支撑“牛腿”与压顶圈梁上。本发明将抬高的钢支撑系统与压顶圈梁进行连接,使其成为一个整体,不仅解决了钢支撑系统与压顶圈梁的连接,也避免了施工单位多次浇筑桥墩承台对桥墩承台的完整性造成的缺陷,使桥墩承台在后期的使用中能够体现出更好的受力性能,并且能够缩短工期,带来一定的经济效益。

Description

抬高的钢支撑系统与压顶圈梁的连接方法
技术领域
本发明涉及一种桥梁主桥墩承台围护中钢支撑系统与压顶圈梁的连接方法,尤其是一种现场的自然地坪标高低于桥墩承台的面标高的情况下,抬高的支撑系统与压顶圈梁的连接方法。
背景技术
目前,在桥墩承台的基坑围护的设计中,现场的自然地坪标高低于桥墩承台的面标高,而施工单位与桥梁的设计单位都希望能够一次性浇筑桥墩承台,因为多次浇筑会对桥墩承台的受力性能造成一定的缺陷,也会延长施工工期。因此,需要一种抬高的支撑系统与压顶圈梁的连接方法。 
发明内容
本发明是要解决由于支撑系统需要抬高,抬高的支撑系统与压顶圈梁的连接过程中会存在的技术问题,而提供一种抬高的支撑系统与压顶圈梁的连接方法。
为实现上述目的,本发明采用的技术方案是:一种抬高的支撑系统与压顶圈梁连接的方法,其具体步骤是:
(1)处理压顶板下的地基
在施工压顶圈梁与“牛腿”前,先根据支撑“牛腿”平面布置图进行测量放线,在压顶板下施工反压桩,提高压顶板下的地基承载力,以防止压顶圈梁的扭剪破坏;
(2)连接压顶圈梁与支撑“牛腿”
根据支撑“牛腿”的平面布置图,找出压顶圈梁中设置有支撑“牛腿”的位置,进行测量放线,施工压顶圈梁与“牛腿”的钢筋工程,将扶壁板的主筋与压顶圈梁的纵筋进行焊接连接,肋板的钢筋也将于压顶圈梁与压顶板的钢筋进行焊接连接;
(3)连接钢支撑系统与支撑“牛腿”
    将锚板用预埋的钢筋与支撑“牛腿”连接成一个整体,然后钢支撑系统通过焊接与锚板连接,使钢支撑系统与压顶圈梁通过支撑“牛腿”连接成为一个整体。
本发明的有益效果是:经本发明的连接,将会增强主体结构的完整性与强度,使其在后期的使用中能够体现出更好的受力性能,此外也会缩短施工工期,减少基坑暴露的时间,同时也能保证基坑的安全性。在压顶圈梁与钢支撑系统的连接处设置支撑“牛腿”, 支撑“牛腿”的主筋锚入压顶圈梁,使支撑“牛腿”与压顶圈梁结合成为一个整体。这样,抬高的钢支撑系统再与支撑“牛腿”连接,使钢支撑所承受的轴力很好的传递在支撑“牛腿”与压顶圈梁上。本发明将抬高的钢支撑系统与压顶圈梁进行连接,使其成为一个整体,不仅解决了钢支撑系统与压顶圈梁的连接,也避免了施工单位多次浇筑桥墩承台对桥墩承台的完整性造成的缺陷,使桥墩承台在后期的使用中能够体现出更好的受力性能,并且能够缩短工期,带来一定的经济效益。
附图说明
图1是抬高的支撑系统与压顶圈梁的连接示意图;
图2是支撑系统的传力示意图。
具体实施方式
下面结合附图与实施例对本发明作进一步的说明。
如图1所示,本发明的抬高的支撑系统与压顶圈梁的连接方法,其具体步骤是:
1)对压顶板1下的地基进行处理
在施工压顶圈梁4与“牛腿”10前,先根据支撑“牛腿”10平面布置图进行测量放线,在压顶板1下施工反压桩8,提高压顶板1下的地基承载力,以防止压顶圈梁4的扭剪破坏。
2)压顶圈梁4与支撑“牛腿”10的连接
根据支撑“牛腿”10的平面布置图,找出压顶圈梁4中设置有支撑“牛腿”10的位置,进行测量放线,施工压顶圈梁4与支撑“牛腿”10的钢筋工程,将扶壁板2的主筋与压顶圈梁4的纵筋进行焊接连接,肋板3的钢筋也将于压顶圈梁4与压顶板1的钢筋进行焊接连接。所有连接段钢筋的长度都应满足规范要求。
3)钢支撑7系统与支撑“牛腿”10的连接
将锚板5用预埋的钢筋6与支撑“牛腿”10连接成一个整体,然后钢支撑7系统通过焊接与锚板5连接,这样钢支撑7系统与压顶圈梁4通过支撑“牛腿”10很好地连接成为一个受力性能良好的整体。特别说明:支撑系统抬高的范围宜在1.5m以内。
如图2所示,经本发明的连接的抬高的支撑系统与压顶圈梁能承受支撑轴力11、反压桩支撑力12和抗扭弯矩13。

Claims (1)

1.一种抬高的钢支撑系统与压顶圈梁连接方法,其特征在于,具体步骤是:
1)处理压顶板(1)下的地基
在施工压顶圈梁(4)与“牛腿”(10)前,先根据支撑“牛腿”(10)平面布置图进行测量放线,在压顶板(1)下施工反压桩(8),提高压顶板(1)下的地基承载力,以防止压顶圈梁(4)的扭剪破坏;
2)连接压顶圈梁(4)与支撑“牛腿”(10)
根据支撑“牛腿”(10)的平面布置图,找出压顶圈梁(4)中设置有支撑“牛腿”(10)的位置,进行测量放线,施工压顶圈梁(4)与“牛腿”(10)的钢筋工程,将扶壁板(2)的主筋与压顶圈梁(4)的纵筋进行焊接连接,肋板(3)的钢筋也将于压顶圈梁(4)与压顶板(1)的钢筋进行焊接连接;
3)连接钢支撑系统与支撑“牛腿”(10)
    将锚板(5)用预埋的钢筋(6)与支撑“牛腿”(10)连接成一个整体,然后钢支撑(7)系统通过焊接与锚板(5)连接,使钢支撑(7)系统与压顶圈梁(4)通过支撑“牛腿”(10)连接成为一个整体。
CN201310435596.3A 2013-09-24 2013-09-24 抬高的钢支撑系统与压顶圈梁的连接方法 Active CN103485350B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310435596.3A CN103485350B (zh) 2013-09-24 2013-09-24 抬高的钢支撑系统与压顶圈梁的连接方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310435596.3A CN103485350B (zh) 2013-09-24 2013-09-24 抬高的钢支撑系统与压顶圈梁的连接方法

Publications (2)

Publication Number Publication Date
CN103485350A true CN103485350A (zh) 2014-01-01
CN103485350B CN103485350B (zh) 2016-06-01

Family

ID=49825905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310435596.3A Active CN103485350B (zh) 2013-09-24 2013-09-24 抬高的钢支撑系统与压顶圈梁的连接方法

Country Status (1)

Country Link
CN (1) CN103485350B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104975606A (zh) * 2015-06-29 2015-10-14 上海市基础工程集团有限公司 逆作基坑与相邻基坑相邻处高低跨处理方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006138125A (ja) * 2004-11-12 2006-06-01 Gecoss Corp 火打受け構造
KR100777212B1 (ko) * 2007-03-13 2007-11-21 김찬수 버팀보 조인트
CN101117800A (zh) * 2007-08-22 2008-02-06 浙江大学 一种地下工程中一桩三用的方法
CN103205973A (zh) * 2012-01-11 2013-07-17 上海市政工程设计研究总院(集团)有限公司 一种型钢水泥土搅拌桩内支撑结构及其支撑方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006138125A (ja) * 2004-11-12 2006-06-01 Gecoss Corp 火打受け構造
KR100777212B1 (ko) * 2007-03-13 2007-11-21 김찬수 버팀보 조인트
CN101117800A (zh) * 2007-08-22 2008-02-06 浙江大学 一种地下工程中一桩三用的方法
CN103205973A (zh) * 2012-01-11 2013-07-17 上海市政工程设计研究总院(集团)有限公司 一种型钢水泥土搅拌桩内支撑结构及其支撑方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104975606A (zh) * 2015-06-29 2015-10-14 上海市基础工程集团有限公司 逆作基坑与相邻基坑相邻处高低跨处理方法

Also Published As

Publication number Publication date
CN103485350B (zh) 2016-06-01

Similar Documents

Publication Publication Date Title
CN103924520B (zh) 悬索桥主缆锚固预应力管道的施工方法及装置
CN202936736U (zh) 一种斜拉桥组合梁施工桥面吊机
CN102535845A (zh) 一种连廊结构承重架的施工方法
CN104372743A (zh) 栈桥快速施工方法
CN104594204B (zh) 城市轻轨高架桥山型u梁施工支撑体系及施工方法
CN105484285A (zh) 一种拼装钢管混凝土柱式高承台塔吊基础结构及施工方法
CN104389433A (zh) 钢桁架支撑的混凝土重屋盖体系整体提升系统及施工方法
CN204589822U (zh) 一种独柱双悬臂盖梁抱箍施工支撑系统
CN113638304B (zh) 混凝土梁式桥隐盖梁结构体系及其施工方法
CN113585049A (zh) 一种可更换塑性铰的自复位预制拼装钢管混凝土桥墩节点连接结构及其作法
CN105525753A (zh) 一种构造柱与主体结构同时施工的方法及结构
CN201826437U (zh) 一种钢结构柱脚螺栓精确埋设结构
CN104831639A (zh) 一种超宽变截面连续梁0#块固结及解除施工方法
CN103233426A (zh) 一种软基中无支墩的贝雷梁支架及其支护方法
CN203640061U (zh) 地下室钢筋混凝土柱节点连接结构
CN204626266U (zh) 独柱墩桥梁免浇筑抗倾覆钢结构加固装置
CN204475184U (zh) 城市轻轨高架桥山型u梁施工支撑体系
CN105442453A (zh) 悬索桥桥塔横梁组合支架施工方法
CN110878522B (zh) 主塔下横梁施工体系及施工方法
CN102691267A (zh) 一种外置整体操作平台高墩施工方法
CN206503378U (zh) 新增挑梁施工结构
CN105088961A (zh) 一种边跨合拢段与现浇段合并的施工方法
CN102635070B (zh) 斜拉桥钢塔互拉式竖向转体施工方法
CN103485350A (zh) 抬高的钢支撑系统与压顶圈梁的连接方法
CN106320184A (zh) 一种新型装配式桥梁施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant