CN103469809A CN201310442567XA CN201310442567A CN103469809A CN 103469809 A CN103469809 A CN 103469809A CN 201310442567X A CN201310442567X A CN 201310442567XA CN 201310442567 A CN201310442567 A CN 201310442567A CN 103469809 A CN103469809 A CN 103469809A
Authority
CN
China
Prior art keywords
bottom plate
base plate
power transmission
transmission tower
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310442567XA
Other languages
English (en)
Inventor
沈培锋
陈楷
龙禹
漆炜之
王展
刘春江
王迎春
谢恺
谈磊
朱轶
龙海波
赵建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nanjing Power Supply Co of Jiangsu Electric Power Co
Jiangsu Electric Power Design Institute
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nanjing Power Supply Co of Jiangsu Electric Power Co
Jiangsu Electric Power Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Nanjing Power Supply Co of Jiangsu Electric Power Co, Jiangsu Electric Power Design Institute filed Critical State Grid Corp of China SGCC
Priority to CN201310442567XA priority Critical patent/CN103469809A/zh
Publication of CN103469809A publication Critical patent/CN103469809A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

本发明公开了输电塔整板式基础,其特征在于,包括一底板,均匀分布在底板上并贯穿底板的四个立柱,所述四个立柱和底板是一体浇铸成型的,所述底板上设置有若干条横向底板主筋和若干条纵向底板箍筋,所述各立柱上设置有若干条纵向立柱主筋和若干条横向立柱箍筋,所述各立柱顶部均设置有固定设备的地脚螺栓。在底板上设置四个立柱,每个立柱上均设有地脚螺栓,可以同时固定四个设备,也可以将一个设备的四个部分固定在地脚螺栓上,使得受力更均衡,沉降量小且均匀,调整地基不均匀沉降的能力比较强,稳定性更高,通过在底板和立柱上同时设置对应的主筋和箍筋,增强了输电塔整板式基础的抗剪性能。

Description

输电塔整板式基础
技术领域
本发明涉及一种基础,尤其涉及一种输电塔整板式基础。
背景技术
基础是建筑底部与地基接触的承重构件,它的作用是把建筑上部的荷载传给地基,是房屋、桥梁、码头及其他构筑物的重要组成部分。输电塔是一种工程数量巨大而且很重要的高耸结构。作为重要生命线工程的电力设施,输电塔是通过基础将荷载传递到地基中去,无论地基或基础哪一部分出现问题或发生破坏,都将对上部输电塔造成恶劣影响甚至造成重大事故。由于地基条件的复杂性,土的物理力学性质的特殊性,人们至今对它的认识还在探索和深入,因此,基础的设计在超高压送电线路设计中占有极为重要的地位,而基础型式的选择又是影响工程总体造价主要因素之一。基础型式的选择,应结合各段地形、水文地质情况、施工条件以及输电塔型式加以确定,并且应在满足规程、规范的前提下,尽可能地降低工程造价。
发明内容
本发明的目的在于提供一种输电塔整板式基础,基础结构简洁、节省材料、施工方便、沉降量小且均匀、抗剪性能好。
为实现上述技术目的,达到上述技术效果,本发明通过以下技术方案实现:输电塔整板式基础,其特征在于,包括一底板,均匀分布在底板上并贯穿底板的四个立柱,所述四个立柱和底板是一体浇铸成型的,所述底板上设置有若干条横向底板主筋和若干条纵向底板箍筋,所述各立柱上设置有若干条纵向立柱主筋和若干条横向立柱箍筋,所述各立柱顶部均设置有固定设备的地脚螺栓。
在底板上设置四个立柱,每个立柱上均设有地脚螺栓,可以同时固定四个设备,也可以将一个设备的四个部分固定在地脚螺栓上,使得受力更均衡,沉降量小且均匀,调整地基不均匀沉降的能力比较强,稳定性更高,通过在底板和立柱上同时设置对应的主筋和箍筋,增强了输电塔整板式基础的抗剪性能。
进一步的,每个立柱位于底板两侧部分的高度相同。
进一步的,所述底板的厚度是立柱高度的五分之一到三分之一之间。
本发明的有益效果是:输电塔整板式基础可以同时固定四个设备,也可以将一个设备的四个部分固定在地脚螺栓上,使得受力更均衡,沉降量小且均匀,调整地基不均匀沉降的能力比较强,稳定性更高,通过在底板和立柱上同时设置对应的主筋和箍筋,增强了输电塔整板式基础的抗剪性能。
附图说明
图1为本发明输电塔整板式基础的结构示意图;
图2为本发明输电塔整板式基础的剖视图;
图3为本发明输电塔整板式基础的俯视图;
附图的标记含义如下:
1:底板;2:立柱;3:立柱主筋;4:立柱箍筋;5:地面;6:地脚螺栓;7:底板主筋;8:底板箍筋。
具体实施方式
下面结合附图和具体的实施例对本发明技术方案作进一步的详细描述,以使本领域的技术人员可以更好的理解本发明并能予以实施,但所举实施例不作为对本发明的限定。
图1是输电塔整板式基础的整体结构图,其包括一底板1,均匀分布在底板1上并贯穿底板1的四个立柱2,其中四个立柱2和底板1是一体浇铸成型的,优选每个立柱2位于底板1两侧部分的高度相同,即每个立柱2在高度方向上是关于底板1的水平方向是对称的,防止立柱2整体受力不均匀,影响输电塔整板式基础的使用寿命。优选底板1的厚度是立柱2高度的五分之一到三分之一之间,达到整体的性能和结构的平衡,节省材料。
图2是图1的剖视图,各立柱2顶部均设置有固定设备的地脚螺栓6,各立柱2上设置有若干条纵向立柱主筋3和若干条横向立柱箍筋4。相对应的,底板1上设置有若干条横向底板主筋7和若干条纵向底板箍筋8,如图3所示,为了图片的简洁,仅显示了部分底板主筋7和底板箍筋8。使用时,整个输电塔整板式基础除了立柱2的顶部外,全部位于地面5下的基坑中,仅立柱2的顶部伸出地面5,在底板1上设置四个立柱2,每个立柱2上均设有地脚螺栓6,可以同时固定四个设备,也可以将一个设备的四个部分固定在地脚螺栓6上,使得受力更均衡,沉降量小且均匀,调整地基不均匀沉降的能力比较强,稳定性更高,通过在底板1和立柱2上同时设置对应的主筋和箍筋,增强了输电塔整板式基础的抗剪性能。
以上仅为本发明的优选实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构或者等效流程变换,或者直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。

Claims (3)

1.输电塔整板式基础,其特征在于,包括一底板,均匀分布在底板上并贯穿底板的四个立柱,所述四个立柱和底板是一体浇铸成型的,所述底板上设置有若干条横向底板主筋和若干条纵向底板箍筋,所述各立柱上设置有若干条纵向立柱主筋和若干条横向立柱箍筋,所述各立柱顶部均设置有固定设备的地脚螺栓。
2.根据权利要求1所述的输电塔整板式基础,其特征在于,每个立柱位于底板两侧部分的高度相同。
3.根据权利要求1所述的输电塔整板式基础,其特征在于,所述底板的厚度是立柱高度的五分之一到三分之一之间。
CN201310442567XA 2013-09-26 2013-09-26 输电塔整板式基础 Pending CN103469809A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310442567XA CN103469809A (zh) 2013-09-26 2013-09-26 输电塔整板式基础

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310442567XA CN103469809A (zh) 2013-09-26 2013-09-26 输电塔整板式基础

Publications (1)

Publication Number Publication Date
CN103469809A true CN103469809A (zh) 2013-12-25

Family

ID=49794838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310442567XA Pending CN103469809A (zh) 2013-09-26 2013-09-26 输电塔整板式基础

Country Status (1)

Country Link
CN (1) CN103469809A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104775447A (zh) * 2015-04-13 2015-07-15 中国电力工程顾问集团中南电力设计院有限公司 用于陡峭山区输电塔的子母基础框架及其施工工艺
CN105421480A (zh) * 2015-11-25 2016-03-23 国家电网公司 输电塔的正方形基础分坑方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285721A (ja) * 2003-03-24 2004-10-14 Tokyo Electric Power Co Inc:The 小型いかり材を用いた送電用鉄塔基礎
CN1952273A (zh) * 2006-11-15 2007-04-25 广东省电力设计研究院 一种带挡板的掏挖基础及其施工方法
CN201598647U (zh) * 2010-01-05 2010-10-06 华中电网有限公司 一种输变电铁塔自立塔基础
CN202017214U (zh) * 2011-04-08 2011-10-26 新疆电力设计院 冻土地基电力杆塔基础
CN102995652A (zh) * 2012-10-30 2013-03-27 常州苏文电能科技有限公司 电力线路系统
CN203498856U (zh) * 2013-09-26 2014-03-26 国家电网公司 输电塔整板式基础

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285721A (ja) * 2003-03-24 2004-10-14 Tokyo Electric Power Co Inc:The 小型いかり材を用いた送電用鉄塔基礎
CN1952273A (zh) * 2006-11-15 2007-04-25 广东省电力设计研究院 一种带挡板的掏挖基础及其施工方法
CN201598647U (zh) * 2010-01-05 2010-10-06 华中电网有限公司 一种输变电铁塔自立塔基础
CN202017214U (zh) * 2011-04-08 2011-10-26 新疆电力设计院 冻土地基电力杆塔基础
CN102995652A (zh) * 2012-10-30 2013-03-27 常州苏文电能科技有限公司 电力线路系统
CN203498856U (zh) * 2013-09-26 2014-03-26 国家电网公司 输电塔整板式基础

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104775447A (zh) * 2015-04-13 2015-07-15 中国电力工程顾问集团中南电力设计院有限公司 用于陡峭山区输电塔的子母基础框架及其施工工艺
CN104775447B (zh) * 2015-04-13 2017-02-01 中国电力工程顾问集团中南电力设计院有限公司 用于陡峭山区输电塔的子母基础框架及其施工工艺
CN105421480A (zh) * 2015-11-25 2016-03-23 国家电网公司 输电塔的正方形基础分坑方法

Similar Documents

Publication Publication Date Title
CN104533105B (zh) 一种外包钢加固柱预加力装置
CN203475448U (zh) 一种公路护坡装置
CN102839677A (zh) 一种基坑内支撑多功能矩形连接件
CN104674973A (zh) 具有抗拉性能的隔震装置
CN103469809A (zh) 输电塔整板式基础
CN105610055A (zh) 低压配电柜主母排搭接装置和搭接方法
CN108442397B (zh) 装配式地基单元
CN203498856U (zh) 输电塔整板式基础
CN203361183U (zh) 一种输电塔基础
CN103469810A (zh) 输电塔独立基础
CN202466651U (zh) 一种预应力管桩轴向力试验加载装置
CN205805019U (zh) 立柱托换装置
CN202170577U (zh) 一种高层建筑的隔震结构
CN201713800U (zh) 一种周转钻孔平台
CN201722614U (zh) 军用梁支架与碗扣式脚手架相组合的桥梁梁部施工支架
CN204435927U (zh) 一种外包钢加固柱预加力装置
CN203498855U (zh) 输电塔独立基础
CN204343318U (zh) 一种新型的塔式起重机钢平台基础
CN203049956U (zh) 一种折叠舞台梯
CN206157555U (zh) 一种组合拼接式减震桥梁结构
CN202090457U (zh) 一种剪切型并联软钢建筑结构抗震阻尼器
CN213978546U (zh) 装配式桥台结构及应用其的装配式桥台
CN202543985U (zh) 一种用于基桩竖向抗压静载试验的船筏式试验装置
CN103469811B (zh) 输电塔倒翼形基础
CN203225074U (zh) 网架结构广告牌

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100761 West Chang'an Avenue, Beijing, No. 86, No.

Applicant after: State Grid Corporation of China

Applicant after: Nanjing Power Supply Co., Jiangsu Prov. Power Co.

Applicant after: Jiangsu Electric Power Company

Applicant after: Chinese energy construction group Jiangsu Prov. Power Design Inst Co., Ltd

Address before: 100761 West Chang'an Avenue, Beijing, No. 86, No.

Applicant before: State Grid Corporation of China

Applicant before: Nanjing Power Supply Co., Jiangsu Prov. Power Co.

Applicant before: Jiangsu Electric Power Company

Applicant before: Jiangsu Electric Power Designing Institute

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: NANJING POWER SUPPLY CO., JIANGSU PROV. POWER CO. JIANGSU ELECTRIC POWER COMPANY JIANGSU ELECTRIC POWER DESIGNING INST. TO: NANJING POWER SUPPLY CO., JIANGSU PROV. POWER CO. JIANGSU ELECTRIC POWER COMPANY CHINA ENERGY ENGINEERING GROUP JIANGSU ELECTRIC POWER DESIGN INSTITUTE CO., LTD.

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20131225