CN103469805B - The construction method of prestressing force raft foundation - Google Patents

The construction method of prestressing force raft foundation Download PDF

Info

Publication number
CN103469805B
CN103469805B CN201310420302.XA CN201310420302A CN103469805B CN 103469805 B CN103469805 B CN 103469805B CN 201310420302 A CN201310420302 A CN 201310420302A CN 103469805 B CN103469805 B CN 103469805B
Authority
CN
China
Prior art keywords
vacuum
concrete
raft foundation
template
trapezoidal groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310420302.XA
Other languages
Chinese (zh)
Other versions
CN103469805A (en
Inventor
叶长青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Zhongwei Construction Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310420302.XA priority Critical patent/CN103469805B/en
Publication of CN103469805A publication Critical patent/CN103469805A/en
Application granted granted Critical
Publication of CN103469805B publication Critical patent/CN103469805B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of construction method of prestressing force raft foundation, it is characterized in that the pitched roof gradient being more than or equal to 20 °, adopt two-sided envelope method constructing and overhanging model, by installing pitched roof bed die and backform makes concrete build Constrained in gradient situation, bar dowel is adopted to do support between pitched roof bed die and backform, bar dowel diameter is 22 ~ 25mm, split bolt is adopted to unify between backform and bed die, split bolt diameter is 14 ~ 16mm, split bolt setting space is 250mm ~ 300mm, in the middle of split bolt, seal ring is set, seal ring diameter is 40 ~ 50mm, steel bar horse-shaped bench is set above bed die and bears muscles and bones frame to shelve top, take segmentation to water during concreting to smash, with concreting progress from bottom to top, close pitched roof upper mould step by step.

Description

The construction method of prestressing force raft foundation
Technical field
The present invention relates to a kind of raft foundation, particularly a kind of construction method of prestressing force raft foundation.
Background technology
The concrete scale of construction of raft foundation is comparatively large, easily occurs the heat of hydration, occurs checking at inside concrete, thus affect the bearing capacity of raft foundation in casting process.The means of vacuum operation can be adopted to carry out vacuum operation to concrete, make in the de-watering extrusion compacting process of concrete physical property on vacuum coagulation, inner moisture is discharged from surface through layer of concrete, has also driven part of cement particle to move to top layer.These particles are subject to the obstruction of filter cloth and the Surface layer's concrete of dense extrusion, be trapped in Surface layer's concrete or concrete table and, in addition top layer vacuum is greater than internal vacuum, dehydration rate on the coagulation of top layer and compression ratio are also much larger than inner concrete, thus surface forms compact texture layer, make porosity reduce by more than 3%, average pore size reduces 30%, and compressive strength can double.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of construction method of prestressing force raft foundation of reliable construction quality, overcomes the problem that crack appears in raft foundation.
Construction sequence of the present invention comprises:
(1) prepare burden
Raft foundation concrete carries out examination by traditional match ratio and joins, and then adjusts according to the feature of vacuum concrete, and concrete employing is as follows: cement consumption reduces by 8% ~ 10% than conventional cement consumption, and sand coarse aggregate ratio is higher than traditional sand coarse aggregate ratio 5%.
Sand coarse aggregate ratio is when in concrete mix, mortar amount is inadequate higher than traditional sand coarse aggregate ratio reason, and vacuum pressure mainly passes to above coarse aggregate, and the frictional force produced by dehydration and the build-in of coarse aggregate hinder further dehydration, are unfavorable for compression compact.
The slump of vacuum concrete has an optimum value, and the slump is too low, easily leaks gas during application of vacuum, not easily closely knit, and hole increases, and intensity reduces.The slump is too large, and residue water/binder ratio is also comparatively large, and easy laminated segregation, hole also increases, therefore intensity also reduces.So slump index is one of important parameter selecting vacuum concrete match ratio, slump value is determined according to ash collection ratio, here ash collection is than the ratio referring to cement weight and sandstone gross weight, specific as follows: ash collection is 5 centimetres than the best slump value being more than or equal to 0.3, ash collection is than being less than 0.3 and the best slump value being more than or equal to 0.28 is 6 centimetres, ash collection is than being less than 0.28 and the best slump value being more than or equal to 0.26 is 7 centimetres, ash collection is than being less than 0.26 and the best slump value being more than or equal to 0.24 is 8 centimetres, ash collection is 9 centimetres than the best slump value being less than 0.24.
(2) assembling reinforcement
To first eject reinforcement location line before reinforcing bar binding, guarantee that reinforcement location is accurate.The colligation of reinforcement foundation is wanted firmly, and the quantity that releases of threading off will meet the requirements.
(3) template is installed
Adopt the special template with vacuum mat.It is characterized in that template central authorities arrange suction pipe, suction pipe is fixed in template by flange, arrange trapezoidal groove in the middle part of template, trapezoidal groove bond length is 250-300mm, and trapezoidal groove minor face position arranges filter cloth, filter cloth extends to bottom trapezoidal groove, the long edge lengths of trapezoidal groove is 258-308mm, and trapezoidal groove height is 12-15mm, and trapezoidal groove hypotenuse position arranges rubber weather strip and closes, arrange air cushion plush copper in trapezoidal groove, the cavity between air cushion plush copper forms vacuum chamber.
Compared with traditional vacuum suction pad, in structure of the present invention, greatly, can ensure the effective squeezing action to concrete surface, soaking effect is good for air cushion plush copper and concrete contact area, and after water suction, concrete plastic strength is also high.The vacuum chamber that between plush copper, space is formed has certain height, and it is completely through each other, air-flow and current do not exist as in conventional plastic net because of twine interlock the drag effects that produces, therefore its vacuum is evenly distributed, each position concrete is squeezed comparatively even, and water flow is fast, and water suction is even and efficiency is high, when construction operation area is larger, its advantage is more obvious.
(4) concreting
Often building is highly that the concrete of 400 ~ 500mm carries out an application of vacuum, and vacuum processing time is 12/min, and vacuum adopts 650 ~ 700mm mercury column, and vacuum operation adopts the water suction of template Vertical dimension and concreting horizontal plane to absorb water to carry out simultaneously.
Higher vacuum causes larger pressure differential, and the squeezing action of vacuum is comparatively large, and water suction is fast, water absorption rate and volume compression amount all large.Vacuum is excessive, at the water suction initial stage, and too early formation fine grained layer and affect further soaking effect.Vacuum is too low, then absorbent time is long, and concrete plastic strength and early strength are also lower.Vacuum is relevant with concreting thickness with the vacuum operation time, and according to a large amount of engineering practice, the present invention is highly 650 ~ 700mm mercury column for the concrete of 400 ~ 500mm carries out the vacuum that vacuum operation adopts building, and the vacuum operation time is 12/min.This parameter obtains under temperature is 10 ~ 15 DEG C of conditions, if variations in temperature, the vacuum operation time will adjust, specific as follows: when temperature is 5 ~ 10 DEG C, and regulation coefficient adopts 1.1; When temperature is 15 ~ 20 DEG C, regulation coefficient adopts 0.9; When temperature is 20 ~ 25 DEG C, regulation coefficient adopts 0.85; When temperature is greater than 25 DEG C, regulation coefficient adopts 0.8.
(5) first time electric heat prestressing
After raft foundation concreting completes 1h, after raft foundation concrete has some strength, prestressed reinforcement adopts electric-heat prestressing, select three-phase low-voltage transformer, transformer should be equipped with variable resistor, simultaneously should with cooling device, the electric wire received prestressed reinforcement from electric heating transformer adopts insulation soft copper skein silk line.Carry out first time electrified regulation, electrified regulation 5min, sets up initial stress, is then fixed on bearing plate by prestressed reinforcement by anchoring piece.
Based on the feature of raft foundation, the present invention adopts electrified regulation stretch-draw, effectively ensure that prestressed stretch-draw effect, guarantees that load worked in coordination with by prestressed reinforcement and raft foundation concrete.
(6) second time application of vacuum
Start vacuum pump after first time electric heat prestressing 10min and carry out application of vacuum, vacuum processing time is 15/min, and vacuum adopts 600 ~ 650mm mercury column.Vacuum processing time parameter obtains under temperature is 10 ~ 15 DEG C of conditions, if variations in temperature, the vacuum operation time will adjust, specific as follows: when temperature is 5 ~ 10 DEG C, and regulation coefficient adopts 1.1; When temperature is 15 ~ 20 DEG C, regulation coefficient adopts 0.9; When temperature is 20 ~ 25 DEG C, regulation coefficient adopts 0.85; When temperature is greater than 25 DEG C, regulation coefficient adopts 0.8.
Concrete vacuum process, be a compression dehydration, the gas of inside concrete can be made again under suction function to produce volume expansion, and capillary tube aperture reduces, and produces Inner extrusion dehydration.Dehydration volume is always greater than concrete volume contraction.Exactly because rear portion dehydration leaves hole in concrete, the pressure reduction that they produce by negative pressure of vacuum is difficult to airtight.After prestressed stretch-draw, carry out vacuum operation, concrete can be impelled closely knit further.In addition, vacuum operation also contributes to the acceleration of water translocation process, improves concrete uniformity.
Suitably reduce vacuum in vacuum chamber during second time application of vacuum, this is that vacuum is conducive to the movement of particles of aggregates after reducing, thus reaches the effect of concrete packed uniform because after concrete dehydration, mobility reduces.
(7) second time electrified regulation, the power-off anchoring when tension reinforcing steel bar reaches the stretch value of regulation.Treat that reinforcing bar is cooled to normal temperature, check the stress in reinforcing bar with jack.Counter stress does not meet the requirements of and will carry out benefit stretch-draw, then nut and backing plate are welded.
(8) maintenance
Should be covered and moisture-keeping maintaining concrete within 12h after building.
(9) demoulding
The demoulding is carried out after concrete strength reaches 8 ~ 12MPa.
Concrete density of the present invention is higher, and raft foundation mechanical property is good.
Accompanying drawing explanation
Fig. 1 dedicated templates schematic diagram.
Accompanying drawing mark: 1, filter cloth, 2, air cushion plush copper, 3, suction pipe, 4, flange, 5, rubber weather strip, 6, template.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present embodiment is described in detail.
Certain engineering raft foundation thickness is 1.2m, and raft foundation area is 820M 2, be 14 story frame structure buildings.
The present embodiment construction sequence comprises:
(1) prepare burden
Raft foundation concrete carries out examination by traditional match ratio and joins, and then adjusts according to the feature of vacuum concrete, and concrete employing is as follows: cement consumption reduces by 8% ~ 10% than conventional cement consumption, and sand coarse aggregate ratio is higher than traditional sand coarse aggregate ratio 5%.Water: 175kg, cement: 398kg, sand: 566kg, stone: 1261kg.Water: 175kg, cement: 362kg, sand: 594kg, stone: 1261kg.Slump value is 9 centimetres.
(2) assembling reinforcement
To first eject reinforcement location line before reinforcing bar binding, guarantee that reinforcement location is accurate.The colligation of reinforcement foundation is wanted firmly, and the quantity that releases of threading off will meet the requirements.
(3) template is installed
Adopt the special template with vacuum mat, Fig. 1 is dedicated templates schematic diagram, it is characterized in that template 6 central authorities arrange suction pipe 3, suction pipe 3 is fixed on template 6 by flange 4, in the middle part of template 6, trapezoidal groove is set, trapezoidal groove bond length is 250mm, trapezoidal groove minor face position arranges filter cloth 1, filter cloth 1 extends to bottom trapezoidal groove, the long edge lengths of trapezoidal groove is 258mm, trapezoidal groove height is 12mm, trapezoidal groove hypotenuse position arranges rubber weather strip 5 and closes, air cushion plush copper 2 is set in trapezoidal groove, cavity between air cushion plush copper 2 forms vacuum chamber.
(4) concreting
Often building is highly that the concrete of 400 ~ 500mm carries out an application of vacuum, and vacuum processing time is 12/min, and vacuum adopts 680 mercury column, and vacuum operation adopts the water suction of template Vertical dimension and concreting horizontal plane to absorb water to carry out simultaneously.
(5) first time electric heat prestressing
After raft foundation concreting completes 1h, after raft foundation concrete has some strength, prestressed reinforcement adopts electric-heat prestressing, select three-phase low-voltage transformer, transformer should be equipped with variable resistor, simultaneously should with cooling device, the electric wire received prestressed reinforcement from electric heating transformer adopts insulation soft copper skein silk line.Carry out first time electrified regulation, electrified regulation 5min, sets up initial stress, then by anchoring piece, prestressed reinforcement is fixed on bearing plate.
(6) second time application of vacuum
Start vacuum pump after first time electric heat prestressing 10min and carry out application of vacuum, vacuum processing time is 15/min, and vacuum adopts 620mm mercury column.
(7) second time electrified regulation, the power-off anchoring when tension reinforcing steel bar reaches the stretch value of regulation.Treat that reinforcing bar is cooled to normal temperature, check the stress in reinforcing bar with jack.Counter stress does not meet the requirements of and will carry out benefit stretch-draw, then nut and backing plate are welded.
(8) maintenance
Should be covered and moisture-keeping maintaining concrete within 12h after building.
(9) demoulding
The demoulding is carried out after concrete strength reaches 8 ~ 12MPa.

Claims (2)

1. a construction method for prestressing force raft foundation, is characterized in that construction sequence comprises:
(1) prepare burden
Raft foundation concrete carries out examination by traditional match ratio and joins, then adjust according to the feature of vacuum concrete, concrete employing is as follows: cement consumption reduces by 8% ~ 10% than conventional cement consumption, and sand coarse aggregate ratio is higher than traditional sand coarse aggregate ratio 5%, and slump value is determined according to ash collection ratio;
(2) assembling reinforcement
To first eject reinforcement location line before reinforcing bar binding, guarantee that reinforcement location is accurate; The colligation of reinforcement foundation is wanted firmly, and the quantity that releases of threading off will meet the requirements;
(3) template is installed
Adopt the special template with vacuum mat, it is characterized in that template central authorities arrange suction pipe, suction pipe is fixed in template by flange, in the middle part of template, trapezoidal groove is set, trapezoidal groove minor face position arranges filter cloth, and filter cloth extends to bottom trapezoidal groove, and trapezoidal groove hypotenuse position arranges rubber weather strip and closes, arrange air cushion plush copper in trapezoidal groove, the cavity between air cushion plush copper forms vacuum chamber;
(4) concreting
Often build is highly that the concrete of 400 ~ 500mm carries out an application of vacuum;
(5) first time electric heat prestressing
After raft foundation concreting completes 1h, after raft foundation concrete has some strength, prestressed reinforcement adopts electric-heat prestressing, select three-phase low-voltage transformer, transformer should be equipped with variable resistor, simultaneously should with cooling device, the electric wire received prestressed reinforcement from electric heating transformer adopts insulation soft copper skein silk line; Carry out first time electrified regulation, electrified regulation 5min, sets up initial stress, is then fixed on bearing plate by anchoring piece by prestressed reinforcement;
(6) second time application of vacuum
Start vacuum pump after electric heat prestressing for the first time and carry out application of vacuum;
(7) second time electrified regulation, the power-off anchoring when tension reinforcing steel bar reaches the stretch value of regulation; Treat that reinforcing bar is cooled to normal temperature, check the stress in reinforcing bar with jack; Counter stress does not meet the requirements of and will carry out benefit stretch-draw, then nut and backing plate are welded;
(8) maintenance
Should be covered and moisture-keeping maintaining concrete within 12h after building;
(9) demoulding
The demoulding is carried out after concrete strength reaches 8 ~ 12MPa.
2. the construction method of prestressing force raft foundation according to claim 1, it is characterized in that ash collection is 5 centimetres than the best slump value being more than or equal to 0.3, ash collection is than being less than 0.3 and the best slump value being more than or equal to 0.28 is 6 centimetres, ash collection is than being less than 0.28 and the best slump value being more than or equal to 0.26 is 7 centimetres, ash collection is than being less than 0.26 and the best slump value being more than or equal to 0.24 is 8 centimetres, and it is 9 centimetres that ash collects than the best slump value being less than 0.24.
CN201310420302.XA 2013-09-10 2013-09-10 The construction method of prestressing force raft foundation Expired - Fee Related CN103469805B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310420302.XA CN103469805B (en) 2013-09-10 2013-09-10 The construction method of prestressing force raft foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310420302.XA CN103469805B (en) 2013-09-10 2013-09-10 The construction method of prestressing force raft foundation

Publications (2)

Publication Number Publication Date
CN103469805A CN103469805A (en) 2013-12-25
CN103469805B true CN103469805B (en) 2015-07-29

Family

ID=49794834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310420302.XA Expired - Fee Related CN103469805B (en) 2013-09-10 2013-09-10 The construction method of prestressing force raft foundation

Country Status (1)

Country Link
CN (1) CN103469805B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836604B (en) * 2017-02-07 2022-08-12 叶长青 Method for manufacturing large-span inclined roof
CN107869147B (en) * 2017-11-21 2020-07-03 中建八局第三建设有限公司 Construction method of overlength prestressed raft

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070000264A (en) * 2005-06-27 2007-01-02 두산중공업 주식회사 Building constuction method using precast structure
CN101476324A (en) * 2009-01-20 2009-07-08 叶长青 Raft plate base and its construction method
CN101476286A (en) * 2008-11-24 2009-07-08 中铁二局股份有限公司 Railway bridge deck prestressed concrete vertical and horizontal girder lattice type floating system construction method
CN102011366A (en) * 2009-12-29 2011-04-13 中交第一航务工程局有限公司 Construction method for mud jacking of post-tensioning pre-stressed concrete box girder pipe
CN102828468A (en) * 2012-09-13 2012-12-19 永升建设集团有限公司 Construction method for controlling prefabricated crack of high-strength thin-walled box girder under high-temperature dry condition
CN103147400A (en) * 2013-03-01 2013-06-12 天津第四市政建筑工程有限公司 One-time tensioning construction method of super-long prestressed tendon for cast-in-place box girder bridge web

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06212645A (en) * 1992-12-19 1994-08-02 Yasuhiro Matsukawa Use of existing concrete for architectural foundation
JP2002294722A (en) * 2001-03-29 2002-10-09 Okumura Corp Foundation structure of structure and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070000264A (en) * 2005-06-27 2007-01-02 두산중공업 주식회사 Building constuction method using precast structure
CN101476286A (en) * 2008-11-24 2009-07-08 中铁二局股份有限公司 Railway bridge deck prestressed concrete vertical and horizontal girder lattice type floating system construction method
CN101476324A (en) * 2009-01-20 2009-07-08 叶长青 Raft plate base and its construction method
CN102011366A (en) * 2009-12-29 2011-04-13 中交第一航务工程局有限公司 Construction method for mud jacking of post-tensioning pre-stressed concrete box girder pipe
CN102828468A (en) * 2012-09-13 2012-12-19 永升建设集团有限公司 Construction method for controlling prefabricated crack of high-strength thin-walled box girder under high-temperature dry condition
CN103147400A (en) * 2013-03-01 2013-06-12 天津第四市政建筑工程有限公司 One-time tensioning construction method of super-long prestressed tendon for cast-in-place box girder bridge web

Also Published As

Publication number Publication date
CN103469805A (en) 2013-12-25

Similar Documents

Publication Publication Date Title
CN107746223B (en) Roller compacted concrete dam and construction method thereof
CN102519860A (en) Impermeability test method for asphalt concrete with impermeable function
CN103556831B (en) Huge area is without muscle abrasion-proof concrete method for constructing terrace
CN103469805B (en) The construction method of prestressing force raft foundation
CN101284394A (en) Pressure blank injecting, pressure drying gypsum mould and preparation method thereof
KR101332202B1 (en) Automatic block forming device and using the same block
CN108755337A (en) Guide hole water-permeable brick and the brick machine mold and method for preparing guide hole water-permeable brick
CN206016147U (en) A kind of moistureproof steel structure concrete construction house
CN114319875A (en) Seamless construction process for super-large-area concrete ground
CN204098025U (en) A kind of vibration sinking tube siccative pours into special-shaped bag pile and precast pile tip thereof and construction steel immersed tube
KR101238327B1 (en) Apparatus for preparing high-strength terrazzo panel
CN203174901U (en) Foam concrete roof cast-in-place slab
CN202029233U (en) Adjustable solid cubic pile mold
CN108789776A (en) A kind of environment-friendly type foaming partition plate production support device
CN204435658U (en) A kind of fibre-cement pipe brick and body of wall
CN208618467U (en) A kind of basement bottom board launching stress adjustment structure
CN207419839U (en) A kind of prefabricated combined wall board
CN207314648U (en) A kind of composite heat insulating wall building block and mould
CN110696154A (en) Process method for producing modified gypsum building block
CN2934299Y (en) Multifunctional mould plate cloth
CN201883700U (en) Structure for reinforcing floor boards or roof boards of building structures
CN219294255U (en) Baking-free brick preparation equipment with rust resistance function
CN206090841U (en) Fast -assembling room structure
TWI821690B (en) A production method and equipment of energy saving and environmental protection with lightweight insulated hive precast concrete
CN109940737A (en) Mould group mold pours the mould and preparation method thereof that do not collapse of high-strength light foamed concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Li Limin

Inventor before: Ye Changqing

COR Change of bibliographic data
TR01 Transfer of patent right

Effective date of registration: 20160527

Address after: 330200, Jiangxi, Nanchang province Nanchang County Jing Tong Township Government Office Building

Patentee after: JIANGXI ZHONGWEI CONSTRUCTION GROUP CO., LTD.

Address before: 325000 Jinchuan economic and Technological Development Zone, Tianhe Road, Wenzhou, No. 4 Zhejiang Road

Patentee before: Ye Changqing

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150729

Termination date: 20190910