Summary of the invention
Technical problem to be solved by this invention is to provide a kind of construction method of prestressing force raft foundation of reliable construction quality, overcomes the problem that crack appears in raft foundation.
Construction sequence of the present invention comprises:
(1) prepare burden
Raft foundation concrete carries out examination by traditional match ratio and joins, and then adjusts according to the feature of vacuum concrete, and concrete employing is as follows: cement consumption reduces by 8% ~ 10% than conventional cement consumption, and sand coarse aggregate ratio is higher than traditional sand coarse aggregate ratio 5%.
Sand coarse aggregate ratio is when in concrete mix, mortar amount is inadequate higher than traditional sand coarse aggregate ratio reason, and vacuum pressure mainly passes to above coarse aggregate, and the frictional force produced by dehydration and the build-in of coarse aggregate hinder further dehydration, are unfavorable for compression compact.
The slump of vacuum concrete has an optimum value, and the slump is too low, easily leaks gas during application of vacuum, not easily closely knit, and hole increases, and intensity reduces.The slump is too large, and residue water/binder ratio is also comparatively large, and easy laminated segregation, hole also increases, therefore intensity also reduces.So slump index is one of important parameter selecting vacuum concrete match ratio, slump value is determined according to ash collection ratio, here ash collection is than the ratio referring to cement weight and sandstone gross weight, specific as follows: ash collection is 5 centimetres than the best slump value being more than or equal to 0.3, ash collection is than being less than 0.3 and the best slump value being more than or equal to 0.28 is 6 centimetres, ash collection is than being less than 0.28 and the best slump value being more than or equal to 0.26 is 7 centimetres, ash collection is than being less than 0.26 and the best slump value being more than or equal to 0.24 is 8 centimetres, ash collection is 9 centimetres than the best slump value being less than 0.24.
(2) assembling reinforcement
To first eject reinforcement location line before reinforcing bar binding, guarantee that reinforcement location is accurate.The colligation of reinforcement foundation is wanted firmly, and the quantity that releases of threading off will meet the requirements.
(3) template is installed
Adopt the special template with vacuum mat.It is characterized in that template central authorities arrange suction pipe, suction pipe is fixed in template by flange, arrange trapezoidal groove in the middle part of template, trapezoidal groove bond length is 250-300mm, and trapezoidal groove minor face position arranges filter cloth, filter cloth extends to bottom trapezoidal groove, the long edge lengths of trapezoidal groove is 258-308mm, and trapezoidal groove height is 12-15mm, and trapezoidal groove hypotenuse position arranges rubber weather strip and closes, arrange air cushion plush copper in trapezoidal groove, the cavity between air cushion plush copper forms vacuum chamber.
Compared with traditional vacuum suction pad, in structure of the present invention, greatly, can ensure the effective squeezing action to concrete surface, soaking effect is good for air cushion plush copper and concrete contact area, and after water suction, concrete plastic strength is also high.The vacuum chamber that between plush copper, space is formed has certain height, and it is completely through each other, air-flow and current do not exist as in conventional plastic net because of twine interlock the drag effects that produces, therefore its vacuum is evenly distributed, each position concrete is squeezed comparatively even, and water flow is fast, and water suction is even and efficiency is high, when construction operation area is larger, its advantage is more obvious.
(4) concreting
Often building is highly that the concrete of 400 ~ 500mm carries out an application of vacuum, and vacuum processing time is 12/min, and vacuum adopts 650 ~ 700mm mercury column, and vacuum operation adopts the water suction of template Vertical dimension and concreting horizontal plane to absorb water to carry out simultaneously.
Higher vacuum causes larger pressure differential, and the squeezing action of vacuum is comparatively large, and water suction is fast, water absorption rate and volume compression amount all large.Vacuum is excessive, at the water suction initial stage, and too early formation fine grained layer and affect further soaking effect.Vacuum is too low, then absorbent time is long, and concrete plastic strength and early strength are also lower.Vacuum is relevant with concreting thickness with the vacuum operation time, and according to a large amount of engineering practice, the present invention is highly 650 ~ 700mm mercury column for the concrete of 400 ~ 500mm carries out the vacuum that vacuum operation adopts building, and the vacuum operation time is 12/min.This parameter obtains under temperature is 10 ~ 15 DEG C of conditions, if variations in temperature, the vacuum operation time will adjust, specific as follows: when temperature is 5 ~ 10 DEG C, and regulation coefficient adopts 1.1; When temperature is 15 ~ 20 DEG C, regulation coefficient adopts 0.9; When temperature is 20 ~ 25 DEG C, regulation coefficient adopts 0.85; When temperature is greater than 25 DEG C, regulation coefficient adopts 0.8.
(5) first time electric heat prestressing
After raft foundation concreting completes 1h, after raft foundation concrete has some strength, prestressed reinforcement adopts electric-heat prestressing, select three-phase low-voltage transformer, transformer should be equipped with variable resistor, simultaneously should with cooling device, the electric wire received prestressed reinforcement from electric heating transformer adopts insulation soft copper skein silk line.Carry out first time electrified regulation, electrified regulation 5min, sets up initial stress, is then fixed on bearing plate by prestressed reinforcement by anchoring piece.
Based on the feature of raft foundation, the present invention adopts electrified regulation stretch-draw, effectively ensure that prestressed stretch-draw effect, guarantees that load worked in coordination with by prestressed reinforcement and raft foundation concrete.
(6) second time application of vacuum
Start vacuum pump after first time electric heat prestressing 10min and carry out application of vacuum, vacuum processing time is 15/min, and vacuum adopts 600 ~ 650mm mercury column.Vacuum processing time parameter obtains under temperature is 10 ~ 15 DEG C of conditions, if variations in temperature, the vacuum operation time will adjust, specific as follows: when temperature is 5 ~ 10 DEG C, and regulation coefficient adopts 1.1; When temperature is 15 ~ 20 DEG C, regulation coefficient adopts 0.9; When temperature is 20 ~ 25 DEG C, regulation coefficient adopts 0.85; When temperature is greater than 25 DEG C, regulation coefficient adopts 0.8.
Concrete vacuum process, be a compression dehydration, the gas of inside concrete can be made again under suction function to produce volume expansion, and capillary tube aperture reduces, and produces Inner extrusion dehydration.Dehydration volume is always greater than concrete volume contraction.Exactly because rear portion dehydration leaves hole in concrete, the pressure reduction that they produce by negative pressure of vacuum is difficult to airtight.After prestressed stretch-draw, carry out vacuum operation, concrete can be impelled closely knit further.In addition, vacuum operation also contributes to the acceleration of water translocation process, improves concrete uniformity.
Suitably reduce vacuum in vacuum chamber during second time application of vacuum, this is that vacuum is conducive to the movement of particles of aggregates after reducing, thus reaches the effect of concrete packed uniform because after concrete dehydration, mobility reduces.
(7) second time electrified regulation, the power-off anchoring when tension reinforcing steel bar reaches the stretch value of regulation.Treat that reinforcing bar is cooled to normal temperature, check the stress in reinforcing bar with jack.Counter stress does not meet the requirements of and will carry out benefit stretch-draw, then nut and backing plate are welded.
(8) maintenance
Should be covered and moisture-keeping maintaining concrete within 12h after building.
(9) demoulding
The demoulding is carried out after concrete strength reaches 8 ~ 12MPa.
Concrete density of the present invention is higher, and raft foundation mechanical property is good.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present embodiment is described in detail.
Certain engineering raft foundation thickness is 1.2m, and raft foundation area is 820M
2, be 14 story frame structure buildings.
The present embodiment construction sequence comprises:
(1) prepare burden
Raft foundation concrete carries out examination by traditional match ratio and joins, and then adjusts according to the feature of vacuum concrete, and concrete employing is as follows: cement consumption reduces by 8% ~ 10% than conventional cement consumption, and sand coarse aggregate ratio is higher than traditional sand coarse aggregate ratio 5%.Water: 175kg, cement: 398kg, sand: 566kg, stone: 1261kg.Water: 175kg, cement: 362kg, sand: 594kg, stone: 1261kg.Slump value is 9 centimetres.
(2) assembling reinforcement
To first eject reinforcement location line before reinforcing bar binding, guarantee that reinforcement location is accurate.The colligation of reinforcement foundation is wanted firmly, and the quantity that releases of threading off will meet the requirements.
(3) template is installed
Adopt the special template with vacuum mat, Fig. 1 is dedicated templates schematic diagram, it is characterized in that template 6 central authorities arrange suction pipe 3, suction pipe 3 is fixed on template 6 by flange 4, in the middle part of template 6, trapezoidal groove is set, trapezoidal groove bond length is 250mm, trapezoidal groove minor face position arranges filter cloth 1, filter cloth 1 extends to bottom trapezoidal groove, the long edge lengths of trapezoidal groove is 258mm, trapezoidal groove height is 12mm, trapezoidal groove hypotenuse position arranges rubber weather strip 5 and closes, air cushion plush copper 2 is set in trapezoidal groove, cavity between air cushion plush copper 2 forms vacuum chamber.
(4) concreting
Often building is highly that the concrete of 400 ~ 500mm carries out an application of vacuum, and vacuum processing time is 12/min, and vacuum adopts 680 mercury column, and vacuum operation adopts the water suction of template Vertical dimension and concreting horizontal plane to absorb water to carry out simultaneously.
(5) first time electric heat prestressing
After raft foundation concreting completes 1h, after raft foundation concrete has some strength, prestressed reinforcement adopts electric-heat prestressing, select three-phase low-voltage transformer, transformer should be equipped with variable resistor, simultaneously should with cooling device, the electric wire received prestressed reinforcement from electric heating transformer adopts insulation soft copper skein silk line.Carry out first time electrified regulation, electrified regulation 5min, sets up initial stress, then by anchoring piece, prestressed reinforcement is fixed on bearing plate.
(6) second time application of vacuum
Start vacuum pump after first time electric heat prestressing 10min and carry out application of vacuum, vacuum processing time is 15/min, and vacuum adopts 620mm mercury column.
(7) second time electrified regulation, the power-off anchoring when tension reinforcing steel bar reaches the stretch value of regulation.Treat that reinforcing bar is cooled to normal temperature, check the stress in reinforcing bar with jack.Counter stress does not meet the requirements of and will carry out benefit stretch-draw, then nut and backing plate are welded.
(8) maintenance
Should be covered and moisture-keeping maintaining concrete within 12h after building.
(9) demoulding
The demoulding is carried out after concrete strength reaches 8 ~ 12MPa.