JP2002294722A - Foundation structure of structure and its construction method - Google Patents

Foundation structure of structure and its construction method

Info

Publication number
JP2002294722A
JP2002294722A JP2001095519A JP2001095519A JP2002294722A JP 2002294722 A JP2002294722 A JP 2002294722A JP 2001095519 A JP2001095519 A JP 2001095519A JP 2001095519 A JP2001095519 A JP 2001095519A JP 2002294722 A JP2002294722 A JP 2002294722A
Authority
JP
Japan
Prior art keywords
foundation
ground
concrete
pressure
solid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001095519A
Other languages
Japanese (ja)
Inventor
Kunihiko Ando
邦彦 安藤
Yukio Sato
幸雄 佐藤
Tomoyuki Maeba
知之 前場
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okumura Corp
Original Assignee
Okumura Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okumura Corp filed Critical Okumura Corp
Priority to JP2001095519A priority Critical patent/JP2002294722A/en
Publication of JP2002294722A publication Critical patent/JP2002294722A/en
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a foundation structure of a structure capable of cutting down an underground excavated amount and an outside conveyed soil amount to reduce a construction cost as well as the curtailment of a construction period and its construction method. SOLUTION: The foundation structure improves a soft ground on a bearing ground 2, the ground improved soil 3 is excavated to form a column section, a foundation beam and concrete casting parts 8 and 9 of a raft foundation bearing slab, and after reinforcing bars 11 and 12 constituted by combining a column reinforcing bar, the foundation beam 5 and every upper surface of the raft foundation bearing slab 7 with the concrete casting parts are arranged, concrete is monolithically cast to construct the foundation structure of the structure.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、構造物の基礎構造
とその施工方法に関し、特に施工時の地中掘削量や場外
搬出土量を低減することで構造物躯体の施工コストの低
減と工期の短縮を図る構造物の基礎構造とその施工方法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure of a structure and a method of constructing the same, and more particularly, to a construction cost reduction and a construction period of a structure by reducing the amount of underground excavation and the amount of excavated soil during construction. The present invention relates to a basic structure of a structure for reducing the length of a building and a method of constructing the foundation.

【0002】[0002]

【従来の技術】建築構造物、特に低層の構造物の場合に
は、建物重量が軽いことから地耐力の低い地盤に建設す
る場合にべた基礎を用いることが多くなっている。
2. Description of the Related Art In the case of architectural structures, particularly low-rise structures, solid foundations are often used for construction on a ground having a low ground bearing capacity due to the light weight of the building.

【0003】べた基礎の構造は、図4に示すように、最
下階のスラブ20の他に支持地盤2の上に耐圧版21を
設けることが一般的であり、結果的には、基礎梁22の
上下に二重のスラブを設ける構造になっている。
As shown in FIG. 4, the structure of the solid foundation is generally such that a pressure-resistant plate 21 is provided on the supporting ground 2 in addition to the slab 20 on the lowermost floor. The structure is such that double slabs are provided above and below 22.

【0004】又、このような二重スラブ構造を避けるた
めに、図5のように基礎梁24を偏平にして、梁のない
スラブ形式も考慮されてきたが、いずれの工法において
も、地中掘削量と場外に搬出する土量が大量に増加する
ことになり、環境問題や廃棄物の増大を止むなくして、
低層構造物にあっては躯体を構築する際のコストを低減
できないという問題点が指摘されていた。
In order to avoid such a double slab structure, a slab type without a beam has been considered by flattening the foundation beam 24 as shown in FIG. The amount of excavation and the amount of soil carried out of the site will increase in large quantities, and will not stop environmental problems and the increase of waste,
It has been pointed out that a low-rise structure cannot reduce the cost of building a frame.

【0005】さらに、二重スラブ構造を避ける目的で基
礎梁の上部にのみスラブを配置する図6のようなべた基
礎25の構築も検討されてきたが、基礎梁26及びスラ
ブ27の施工に際して耐圧版の下方の地盤28を乱すこ
とになって、所定の地耐力を確保することが困難になる
という品質上の問題を提起していた。
Further, construction of a solid foundation 25 as shown in FIG. 6 in which a slab is disposed only above the foundation beam in order to avoid a double slab structure has been studied. Disturbing the ground 28 below the plate causes a quality problem that it is difficult to secure a predetermined ground strength.

【0006】[0006]

【発明が解決しようとする課題】本発明は、以上の状況
に鑑みて、その問題点を解消して低層構造物を低コスト
に構築することを目的に提案するものであり、地中掘削
量と場外搬出土量を削減して躯体の施工コストの低減と
工期の短縮を図れる構造物の基礎構造とその施工方法に
提供している。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and has been proposed for the purpose of solving the problems and constructing a low-rise structure at low cost. It provides the foundation structure of structures and the method of construction that can reduce the construction cost and shorten the construction period by reducing the amount of unloaded soil.

【0007】[0007]

【課題を解決するための手段】本発明による構造物の基
礎構造は、構築される構造物を支える地盤に形成されて
支持地盤に到る地盤改良土、地盤改良土中に構造物の柱
部と柱部を連結する基礎梁及び基礎梁と天端を一致させ
て一体に設けるべた基礎耐圧版で構成しており、これに
よって所定の地耐力を確保しながら、地中掘削量と場外
搬出土量を削減すると共に躯体の施工コストを低減して
工期も短縮している。
SUMMARY OF THE INVENTION A foundation structure of a structure according to the present invention is a ground improvement soil formed on a ground supporting a structure to be constructed and reaching a support ground, and a pillar portion of the structure in the ground improvement soil. It is composed of a foundation beam that connects the base beam and the column, and a base pressure-resistant version that is provided integrally with the foundation beam and the top end aligned, thereby ensuring the prescribed ground strength and excavating underground and unloading from the field. The construction time is shortened by reducing the amount of construction and the construction cost of the skeleton.

【0008】本発明による基礎構造の施工方法は、上記
構造物の基礎構造を施工する方法であって、支持地盤上
の軟弱地盤を地盤改良し、次いで地盤改良土を掘削して
柱部と基礎梁及びべた基礎耐圧版のコンクリート打設部
分を形成して、コンクリート打設部分に柱鉄筋、基礎梁
の鉄筋及び基礎梁の鉄筋と天端を一致させたべた基礎耐
圧版の鉄筋を配置し、しかる後にコンクリート打設部分
にコンクリートを一体に打設することで、構造物の基礎
構造を施工しており、コンクリートの打設をコンクリー
ト打設部分を画成する地盤改良土の掘削面を型枠にして
施工することを特徴としている。
The method for constructing a foundation structure according to the present invention is a method for constructing a foundation structure of the above-mentioned structure, in which a soft ground on a supporting ground is ground-improved, and then a ground-improved soil is excavated to form a pillar portion and a foundation. Form the concrete casting part of the beam and solid foundation pressure-resistant version, and place the column reinforcement, the reinforcing beam of the foundation beam, and the reinforcing steel of the solid foundation pressure-resistant version with the top end coincident with the reinforcement of the foundation beam in the concrete placing part, After that, the foundation of the structure is being constructed by casting concrete into the concrete casting part, and the concrete is cast into the excavated surface of the ground improvement soil that defines the concrete casting part. It is characterized by the construction.

【0009】これによって、本発明による基礎構造の施
工方法は、地盤の地耐力を所定の値に確保するように施
工しながら、地中掘削量と場外搬出土量を削減して廃棄
物対策等の環境問題に対処すると共に、基礎梁側面の型
枠を削減し、コンクリートの打設回数を低減すること
で、躯体の施工コストの低減と工期の短縮を確立してい
る。
Accordingly, the method for constructing a foundation structure according to the present invention reduces the amount of underground excavation and the amount of excavated soil while reducing the amount of underground excavation and the amount of excavated soil while maintaining the ground strength of the ground at a predetermined value. In addition to addressing the environmental issues mentioned above, reducing the formwork on the side of the foundation beam and reducing the number of times of concrete placement has reduced the construction cost of the skeleton and shortened the construction period.

【0010】[0010]

【発明の実施の形態】本発明による構造物の基礎構造
は、構築される構造物を支える地盤に形成されて支持地
盤に到る地盤改良土、地盤改良土中に構造物の柱部と柱
部を連結する基礎梁及び基礎梁と天端を一致させて一体
に設けるべた基礎耐圧版で構成するものであり、所定の
地耐力を確保しながら構造を簡潔にしている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The basic structure of a structure according to the present invention is a ground improvement soil which is formed on a ground supporting a structure to be constructed and reaches a support ground. It is composed of a foundation beam connecting the parts and a basic pressure-resistant plate provided integrally with the foundation beam and the top end in alignment with each other, and the structure is simplified while ensuring a predetermined ground strength.

【0011】以下に、本発明による構造物の基礎構造に
おける実施の形態を図面に基づいて詳細に説明する。
An embodiment of the basic structure of a structure according to the present invention will be described below in detail with reference to the drawings.

【0012】図1は、本発明による構造物の基礎構造を
示しており、最下階の平断面(a)と最下階の形態のみ
を示す側面図(b)である。
FIG. 1 shows a basic structure of a structure according to the present invention, and is a plan view (a) of the lowest floor and a side view (b) showing only the form of the lowest floor.

【0013】本実施の形態における建築物の基礎1は、
支持地盤2の上に形成される地盤改良土3の中に構築さ
れている。
The foundation 1 of the building in this embodiment is:
It is constructed in the ground improvement soil 3 formed on the support ground 2.

【0014】地盤改良土3の範囲は、図示のように基礎
梁外郭線より基礎梁成の1/2に相当する程度に拡大さ
せており、支持地盤に到達する地表面下の軟弱地盤を地
盤改良している。
As shown in the figure, the area of the ground improvement soil 3 is enlarged from the outer periphery of the foundation beam to an extent corresponding to one half of the foundation beam, and the soft ground below the ground surface reaching the support ground is removed from the ground. Has improved.

【0015】基礎1は、図1(a)に示すように柱4間
を結合する周辺に基礎梁5を配置しており、所定の小梁
6を適宜に配置させてべた基礎耐圧版7と共に構築され
ている。
As shown in FIG. 1 (a), the foundation 1 has a foundation beam 5 disposed around the periphery connecting the columns 4 together with a basic pressure-resistant plate 7 in which predetermined small beams 6 are appropriately arranged. Have been built.

【0016】従って、図1(b)に示す側面図では、図
示のように支持地盤2の上に形成される地盤改良土3の
中に、建物の基礎梁5と天端を一致させているべた基礎
耐圧版7とが表示されており、建物の垂直荷重及び地震
等による水平力は、支持地盤2と同等の地耐力を発揮す
る地盤改良土3と基礎梁5及びべた基礎耐圧版7によっ
て確実に支持されている。
Therefore, in the side view shown in FIG. 1 (b), the foundation beam 5 of the building and the top end coincide with each other in the ground improvement soil 3 formed on the support ground 2 as shown. The solid foundation pressure resistant version 7 is displayed, and the vertical load of the building and the horizontal force due to earthquakes and the like are obtained by the ground improvement soil 3, the foundation beam 5, and the solid basic pressure resistant version 7 that exhibit the same ground strength as the supporting ground 2. It is definitely supported.

【0017】地盤改良土3と基礎梁5及びべた基礎耐圧
版7の詳細は、図2の部分拡大図において示されている
ように、地盤改良土3は、支持地盤2の上に基礎梁外郭
線より拡大させて形成している。
The details of the ground improvement soil 3, the foundation beam 5, and the solid foundation pressure-resistant plate 7 are shown in a partially enlarged view of FIG. It is formed larger than the line.

【0018】基礎梁5とべた基礎耐圧版7とは、地盤改
良土3の中とその表面に天端を一致させた面一状態に形
成されており、所要の地耐力を発揮する地盤改良土3と
一体化して耐圧版直下の地盤及び周辺の地盤を乱すこと
なく構築されている。
The foundation beams 5 and the solid foundation pressure-resistant plate 7 are formed in the ground-improved soil 3 and the surface thereof so that the top ends thereof are flush with each other, so that the ground-improved soil exerts a required ground strength. 3 and is constructed without disturbing the ground immediately below the pressure-resistant plate and the surrounding ground.

【0019】尚、本実施の形態では、基礎梁5の側面に
は、型枠を配置してコンクリートを打設しているが、追
って説明するように、この型枠は状況に合わせて省略で
きるものであり、その際には、基礎梁5とべた基礎耐圧
版7との形状も図示のものと異なってくる。
In the present embodiment, a concrete form is placed on the side surface of the foundation beam 5 and concrete is cast. However, as will be described later, this form can be omitted according to the situation. In this case, the shapes of the foundation beam 5 and the solid foundation pressure-resistant plate 7 also differ from those shown in the figure.

【0020】以上のように、本発明による構造物の基礎
構造は、地盤改良土、基礎梁及びべた基礎耐圧版とを一
体に構築しているので、二重スラブ形式のべた基礎と比
較して、所望の支持耐力を確保しながら地盤の掘削量を
減量し、場外に搬出する土量を大幅に低減して、使用コ
ンクリート量も低減していることで、基盤の施工コスト
や工期を大幅に縮小させている。
As described above, the foundation structure of the structure according to the present invention is constructed integrally with the ground improvement soil, the foundation beam and the solid foundation pressure-resistant plate, and therefore, compared with the double slab type solid foundation. The amount of ground excavation is reduced while securing the desired bearing strength, the amount of soil carried out of the site is greatly reduced, and the amount of concrete used is also reduced, significantly reducing the construction cost and construction period of the foundation. Has been reduced.

【0021】次に、上述した構造物の基礎構造を施工す
る方法について詳細に説明する。本発明による基礎構造
の施工方法は、支持地盤上の軟弱地盤を地盤改良し、次
いで地盤改良土を掘削して柱部と基礎梁及びべた基礎耐
圧版のコンクリート打設部分を形成して、コンクリート
打設部分に柱鉄筋、基礎梁の鉄筋及び基礎梁の鉄筋と天
端を一致させたべた基礎耐圧版の鉄筋を配置し、しかる
後にコンクリート打設部分にコンクリートを一体に打設
することで構成している。
Next, a method of constructing the foundation structure of the above-described structure will be described in detail. The method of constructing a foundation structure according to the present invention comprises improving the ground on the soft ground on the supporting ground, and then excavating the ground improvement soil to form a column and a foundation beam and a concrete casting portion of a solid foundation pressure-resistant plate. It is composed by placing a column reinforcing bar, a reinforcing bar of a foundation beam, and a reinforcing bar of a solid pressure-resistant version of the foundation beam in which the top end matches the reinforcing bar of the foundation beam, and then concrete is integrally poured into the concrete placing portion. are doing.

【0022】以下に、本発明による構造物の基礎構造に
おける実施の形態を図面に基づいて詳細に説明する。
Hereinafter, embodiments of the basic structure of a structure according to the present invention will be described in detail with reference to the drawings.

【0023】図3は、本発明による施工方法を工程順に
表示している。図3(a)は、地盤改良土3の施工工程
であり、支持地盤2の上の軟弱地盤を所定の工法によっ
て地盤改良している。
FIG. 3 shows the construction method according to the present invention in the order of steps. FIG. 3A shows a construction process of the ground improvement soil 3, in which the soft ground on the support ground 2 is ground improved by a predetermined construction method.

【0024】地盤改良土3の施工範囲は、基礎梁外郭線
より基礎梁成の1/2に相当する程度に拡大させるだけ
であり、周辺の地盤を乱すことなく、地中掘削量と場外
搬出土量を削減して廃棄物対策等の環境問題を回避して
いる。
The construction area of the ground improvement soil 3 is merely expanded to an extent corresponding to one half of the foundation beam from the outline of the foundation beam, and the underground excavation amount and the unloading are carried out without disturbing the surrounding ground. The amount of soil is reduced to avoid environmental problems such as waste measures.

【0025】図3(b)は、地盤改良土を掘削して柱部
と基礎梁及びべた基礎耐圧版との施工位置を形成する工
程を示している。
FIG. 3 (b) shows a process of excavating the ground improvement soil to form a working position of the column, the foundation beam and the solid foundation pressure-resistant plate.

【0026】本工程では、地盤改良土3の中に柱部、基
礎梁及びべた基礎耐圧版の配置部分を形成するために、
所定の掘削施工が行われる。
In this step, in order to form the column, the foundation beam, and the solid foundation pressure-resistant plate in the ground improvement soil 3,
Predetermined excavation work is performed.

【0027】掘削施工は、改良後の地盤を乱さないよう
に慎重に施工されるものであり、べた基礎耐圧版の配置
部分8の平面掘と基礎梁の配置部分9の筋堀とが行われ
る。
The excavation work is carried out carefully so as not to disturb the ground after the improvement, and the plane excavation of the arrangement portion 8 of the solid foundation pressure-resistant plate and the trench excavation of the arrangement portion 9 of the foundation beam are performed. .

【0028】図3(c)は、掘削後の地盤改良土の地耐
力を計測する工程を示している。本実施の形態の地盤改
良土3は、支持地盤2上の軟弱地盤に対してセメント系
固化材を用いた浅層混合処理工法によって地盤改良して
いる。
FIG. 3 (c) shows a process of measuring the ground strength of the ground improvement soil after excavation. The ground improvement soil 3 of the present embodiment is a ground improvement of a soft ground on the support ground 2 by a shallow-layer mixing method using a cement-based solidifying material.

【0029】固化材の配合条件は、軟弱地盤土の土質条
件と施工条件を勘案して所定の一軸圧縮強度(N/
2)を確保できるように固化材の添加量を選択してい
るが、次工程に移る前に、べた基礎耐圧版の配置部分8
における地耐力を確認するために平板載荷試験10を行
っている。
The compounding condition of the solidified material is determined in consideration of the soil condition of the soft ground soil and the construction condition, and the predetermined uniaxial compressive strength (N /
m 2 ), the amount of solidification material added is selected, but before moving on to the next step, the solid base pressure-resistant plate arrangement part 8
A flat plate loading test 10 is performed in order to confirm the ground strength at the time.

【0030】掘削後の地盤改良土3が、所定の地耐力を
発揮していることを確認した上で、図3(d)に示すよ
うに基礎梁、柱及びべた基礎耐圧版の配筋を施工してい
る。
After confirming that the ground improvement soil 3 after excavation has exhibited a predetermined ground strength, as shown in FIG. Has been constructed.

【0031】基礎梁の配筋11とべた基礎耐圧版の配筋
12は、柱の配筋13と同時に施工されるが、コンクリ
ート打設後の基礎梁3の天端とべた基礎耐圧版7の天端
とが一致されるように、それぞれの鉄筋が配置されてい
る。
The reinforcing bars 11 of the foundation beams and the reinforcing bars 12 of the solid foundation pressure-resistant version are constructed simultaneously with the reinforcing bars 13 of the columns. Reinforcing bars are arranged so that the top ends coincide with each other.

【0032】図3(e)は、基礎梁とべた基礎耐圧版へ
のコンクリート打設の工程を示している。
FIG. 3 (e) shows a step of placing concrete on a foundation beam and a solid foundation pressure-resistant plate.

【0033】従来におけるコンクリートの打設は、図4
に示す例のように基礎梁の配筋11とべた基礎耐圧版の
配筋12とに個別に型枠を配置し、しかる後にそれぞれ
のコンクリートを打設していたが、本実施の形態では、
基礎梁の側面とべた基礎耐圧版の下側の型枠を省略して
いる。
FIG. 4 shows a conventional method of placing concrete.
As shown in the example shown in FIG. 1, the formwork was individually arranged on the reinforcing bar 11 of the foundation beam and the reinforcing bar 12 of the solid pressure-resistant version, and then each concrete was cast, but in the present embodiment,
The formwork below the side of the foundation beam and the solid foundation pressure-resistant version is omitted.

【0034】本実施の形態におけるコンクリートの打設
は、基礎梁の配筋11とべた基礎耐圧版の配筋12とが
上述のように両方の天端が一致する一致状態に施工され
ているので、基礎梁とべた基礎耐圧版へのコンクリート
の打設を1回打設で面一に施工して、コンクリートの打
設工程を完了している。
The concrete placement according to the present embodiment is carried out in such a manner that the reinforcing bars 11 of the foundation beams and the reinforcing bars 12 of the solid foundation pressure-resistant plate are in a coincident state in which both top ends coincide as described above. The casting of concrete on the foundation beam and the solid pressure-resistant version of the foundation was carried out one time by casting and the concrete casting process was completed.

【0035】本発明による基礎構造の施工方法は、以上
のように構成されているので、地盤の地耐力を所定の値
に確保するように施工しながら、地中掘削量と場外搬出
土量を削減して廃棄物対策等の環境問題に対処すると共
に、基礎梁側面の型枠を削減し、コンクリートの打設回
数を低減することで、躯体の施工コストの低減と工期の
短縮を確立できるものである。
Since the method for constructing a foundation structure according to the present invention is constructed as described above, the amount of underground excavation and the amount of unloaded soil are reduced while maintaining the ground strength of the ground at a predetermined value. In addition to reducing environmental impacts such as waste countermeasures and reducing the number of concrete castings on the side of the foundation beams, the construction cost can be reduced and the construction period can be shortened. It is.

【0036】以上、本発明を実施の形態に基づいて詳細
に説明してきたが、本発明による構造物の基礎構造及び
その施工方法は、上記実施の形態に何ら限定されるもの
でなく、構造物を構築する区域の地盤に地盤改良土形成
し、この地盤改良土中に基礎梁とべた基礎耐圧版とを互
いの天端を一致させながら設置するという本発明の趣旨
を逸脱しない範囲において、出願時に公知のものを適用
して種々の変更が可能であることは当然のことである。
Although the present invention has been described in detail based on the embodiments, the basic structure of the structure according to the present invention and the method of constructing the structure are not limited to the above-described embodiments, and An application shall be made within the scope of the present invention in which a ground improvement soil is formed on the ground in the area where the construction is to be carried out, and a foundation beam and a solid base pressure-resistant version are installed in the ground improvement soil while matching the top ends of each other. It goes without saying that various modifications can be made by applying a known device at times.

【0037】[0037]

【発明の効果】本発明による構造物の基礎構造は、構築
される構造物を支える地盤に形成されて支持地盤に到る
地盤改良土、該地盤改良土中に構造物の柱部と該柱部を
連結する基礎梁及び該基礎梁と天端を一致させて一体に
設けるべた基礎耐圧版で構成しているので、所定の地耐
力を確保しながら、地中掘削量と場外搬出土量を削減す
ると共に躯体の施工コストを低減して工期も短縮できる
効果を発揮している。
The foundation structure of a structure according to the present invention is a ground improvement soil which is formed on a ground supporting a structure to be constructed and reaches a supporting ground, a pillar portion of a structure in the ground improvement soil and the pillar It is composed of a foundation beam connecting the parts and a solid foundation pressure-resistant version provided integrally with the foundation beam and the top end in line with each other. This has the effect of reducing the construction cost of the skeleton and shortening the construction period.

【0038】本発明による基礎構造の施工方法は、上記
構造物の基礎構造を施工する方法であって、支持地盤上
の軟弱地盤を地盤改良し、次いで地盤改良土を掘削して
柱部と基礎梁及びべた基礎耐圧版のコンクリート打設部
分を形成して、コンクリート打設部分に柱鉄筋、基礎梁
の鉄筋及び基礎梁の鉄筋と天端を一致させたべた基礎耐
圧版の鉄筋を配置し、しかる後にコンクリート打設部分
にコンクリートを一体に打設することで、構造物の基礎
構造を施工しており、併せてコンクリートの打設をコン
クリート打設部分を画成する地盤改良土の掘削面を型枠
にして施工することを特徴としているので、以下の効果
を発揮している。
The method for constructing a foundation structure according to the present invention is a method for constructing a foundation structure of the above-mentioned structure, in which a soft ground on a supporting ground is ground-improved, and then a soil-improved soil is excavated to form a pillar portion and a foundation. Form the concrete cast part of the beam and solid foundation pressure-resistant version, and place the column reinforcement, the reinforcement of the foundation beam, and the reinforcing steel of the solid foundation pressure-resistant version with the top end matched with the reinforcement of the foundation beam in the concrete poured part, After that, the foundation structure of the structure is being constructed by casting concrete integrally into the concrete casting part, and at the same time, the concrete casting is carried out by excavating the ground improvement soil that defines the concrete casting part. Since it is characterized by being constructed in a formwork, the following effects are exhibited.

【0039】 地盤改良土の地耐力を所定の値に確保
できる。 地中掘削量と場外搬出土量を削減して廃棄物対策等
の環境問題を回避できる。 基礎梁側面の型枠を削減し、コンクリートの打設回
数を低減して躯体の施工コストを低減し工期を短縮でき
る。
The ground strength of the ground improvement soil can be secured to a predetermined value. The amount of underground excavation and the amount of excavated soil can be reduced to avoid environmental problems such as waste management. The formwork on the side of the foundation beam can be reduced, the number of concrete castings can be reduced, the construction cost of the skeleton can be reduced, and the construction period can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【 図1】本発明による構造物の基礎構造を示す平断面
図(a)と側面図(b)
FIG. 1 is a plan sectional view (a) and a side view (b) showing a basic structure of a structure according to the present invention.

【 図2】本発明による構造物の基礎構造の部分拡大図FIG. 2 is a partially enlarged view of a basic structure of a structure according to the present invention.

【 図3】本発明による基礎構造の施工方法を示す施工
工程図
FIG. 3 is a construction process diagram showing a construction method of a foundation structure according to the present invention.

【 図4】従来のべた基礎構造図FIG. 4 is a diagram of a conventional solid basic structure.

【 図5】従来の他のべた基礎構造図FIG. 5 is a diagram showing another conventional solid basic structure.

【 図6】従来の他のべた基礎構造図FIG. 6 is a diagram showing another conventional solid basic structure.

【符号の説明】[Explanation of symbols]

1 基礎、 2 支持地盤、 3 地盤改良土、 4
柱、 5 基礎梁、6 小梁、 7 べた基礎耐圧版、
8 べた基礎耐圧版の配置部分、9 基礎梁の配置部
分、 10 平板載荷試験、 11 基礎梁の配筋、1
2 べた基礎耐圧版の配筋、 13 柱の配筋、20、
27 最下階のスラブ、 21 耐圧版、22、24、
26 基礎梁、 23、25 基礎、 28 地盤、
1 foundation, 2 supporting ground, 3 ground improvement soil, 4
Pillars, 5 foundation beams, 6 small beams, 7 solid pressure-resistant version,
8 Placement of solid foundation pressure-resistant version, 9 Placement of foundation beam, 10 Plate loading test, 11 Reinforcement of foundation beam, 1
2 Reinforcement of solid basic pressure-resistant version, 13 pillar reinforcement, 20,
27 slab on the lowest floor, 21 pressure-resistant version, 22, 24,
26 foundation beam, 23, 25 foundation, 28 ground,

───────────────────────────────────────────────────── フロントページの続き (72)発明者 前場 知之 大阪府大阪市阿倍野区松崎町2丁目2番2 号 株式会社奥村組内 Fターム(参考) 2D040 AB03 AC05 BB03 BD00 CA01 2D046 BA00  ────────────────────────────────────────────────── ─── Continuation of the front page (72) Tomoyuki Maeba 2-2-2, Matsuzaki-cho, Abeno-ku, Osaka-shi, Osaka F term (reference) 2D040 AB03 AC05 BB03 BD00 CA01 2D046 BA00

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 構築される構造物を支える地盤に形成さ
れて支持地盤に到る地盤改良土、該地盤改良土中に構造
物の柱部と該柱部を連結する基礎梁及び該基礎梁と天端
を一致させて一体に設けるべた基礎耐圧版で構成される
構造物の基礎構造。
1. A ground improvement soil formed on a ground supporting a structure to be constructed and reaching a support ground, a foundation beam connecting a column of a structure to the pillar in the ground improvement soil, and the foundation beam The basic structure of a structure composed of a solid pressure-resistant version that is provided integrally with the top and the top aligned.
【請求項2】 支持地盤上の軟弱地盤を地盤改良し、次
いで該地盤改良土を掘削して柱部と基礎梁及びべた基礎
耐圧版のコンクリート打設部分を形成して、該コンクリ
ート打設部分に柱鉄筋、基礎梁の鉄筋及び該基礎梁の鉄
筋と天端を一致させたべた基礎耐圧版の鉄筋を配置し、
しかる後にコンクリート打設部分にコンクリートを一体
に打設することから構成される請求項1に記載の基礎構
造の施工方法。
2. Improving the soft ground on the supporting ground, then excavating the ground improvement soil to form a column, a foundation beam, and a concrete foundation for the solid foundation pressure-resistant plate. The column reinforcing bar, the reinforcing bar of the foundation beam and the reinforcing bar of the solid foundation pressure-resistant version with the top and bottom of the reinforcing beam of the foundation beam aligned,
2. The method according to claim 1, further comprising the step of casting concrete integrally into the concrete casting portion.
【請求項3】 コンクリートの打設が、コンクリート打
設部分を画成する地盤改良土の掘削面を型枠にして施工
されることを特徴とする請求項2に記載の基礎構造の施
工方法。
3. The method according to claim 2, wherein the concrete is cast by using an excavated surface of the ground improvement soil that defines the concrete cast portion as a formwork.
JP2001095519A 2001-03-29 2001-03-29 Foundation structure of structure and its construction method Pending JP2002294722A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001095519A JP2002294722A (en) 2001-03-29 2001-03-29 Foundation structure of structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001095519A JP2002294722A (en) 2001-03-29 2001-03-29 Foundation structure of structure and its construction method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2005200984A Division JP2005299387A (en) 2005-07-08 2005-07-08 Construction method of foundation

Publications (1)

Publication Number Publication Date
JP2002294722A true JP2002294722A (en) 2002-10-09

Family

ID=18949556

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001095519A Pending JP2002294722A (en) 2001-03-29 2001-03-29 Foundation structure of structure and its construction method

Country Status (1)

Country Link
JP (1) JP2002294722A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037539A (en) * 2004-07-28 2006-02-09 Daiwa House Ind Co Ltd Column-pile joining structure
JP2007039948A (en) * 2005-08-02 2007-02-15 Canadian Home Kk Foundation construction method and foundation
JP2007303073A (en) * 2006-05-08 2007-11-22 Sumitomo Forestry Co Ltd Underground beam
CN103469805A (en) * 2013-09-10 2013-12-25 叶长青 Prestressed raft foundation construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006037539A (en) * 2004-07-28 2006-02-09 Daiwa House Ind Co Ltd Column-pile joining structure
JP2007039948A (en) * 2005-08-02 2007-02-15 Canadian Home Kk Foundation construction method and foundation
JP2007303073A (en) * 2006-05-08 2007-11-22 Sumitomo Forestry Co Ltd Underground beam
CN103469805A (en) * 2013-09-10 2013-12-25 叶长青 Prestressed raft foundation construction method

Similar Documents

Publication Publication Date Title
JP2002256573A (en) Foundation for existing foundation reinforcing steel tower and construction method for it
JP4519368B2 (en) Concrete structure and construction method thereof
CN212688680U (en) Concrete door type pier structure
JPH11229412A (en) Construction method of large-sized box culvert
JP2002294722A (en) Foundation structure of structure and its construction method
JP2005299387A (en) Construction method of foundation
JP2002180420A (en) Steel-concrete synthetic floor slab and its execution method and constitutive member of this synthetic floor slab and bridge suing this synthetic floor slab
KR20020089690A (en) A pier structure of assembly elevated road for a vehicle under 4.5 ton
JP2001271499A (en) Temporary bearing construction method for existing building by steel batter brace member
JPH1096210A (en) Method of executing enlargement of bridge pier
JP3407168B2 (en) Foundation of new building using existing pile foundation
JP3319458B2 (en) Temporary receiving method of existing building by flat beam reinforcement
JP2869764B2 (en) Reservoir construction method
JP2000192664A (en) Method for construction of building
JP2603427B2 (en) Foundation structure of reinforced concrete building
JPH07189274A (en) Framed stud and method of reversely driven rigid frame prefabrication construction
JP3690463B2 (en) Construction method of viaduct
JP3289163B2 (en) How to build underground structures
JP3690498B2 (en) Building floor structure
JPH11324323A (en) Construction method for building
JP2002061213A (en) Inverted construction method
JPH09256383A (en) Erection method of steel framed column
JPH08253944A (en) Construction method for large scale retaining wall
JP2001011942A (en) Method for building in steel frame erected from foundation after completion of foundation work
JPH04368519A (en) Anchor retaining wall

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20040601

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070925

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080708

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080902

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090407

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090811