CN103452117B CN201310410654.7A CN201310410654A CN103452117B CN 103452117 B CN103452117 B CN 103452117B CN 201310410654 A CN201310410654 A CN 201310410654A CN 103452117 B CN103452117 B CN 103452117B
Authority
CN
China
Prior art keywords
sand
sand pocket
ship
support vessel
pocket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310410654.7A
Other languages
English (en)
Other versions
CN103452117A (zh
Inventor
王柏欢
孙曌
吴松华
廖野
赖雪冬
刘磊
俞家锐
吴拓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC WATER CONSERVANCY AND HYDROPOWER CONSTRUCTION CO.,LTD.
Original Assignee
SDC WATERWAY CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SDC WATERWAY CONSTRUCTION CO Ltd filed Critical SDC WATERWAY CONSTRUCTION CO Ltd
Priority to CN201310410654.7A priority Critical patent/CN103452117B/zh
Publication of CN103452117A publication Critical patent/CN103452117A/zh
Application granted granted Critical
Publication of CN103452117B publication Critical patent/CN103452117B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

本发明涉及一种深水袋装砂施工装置及方法,其特征在于:包括设置在砂袋(2)一侧的对拉船(1),设置在砂袋(2)另一侧与对拉船(1)配对的对拉辅助船(3),对拉船(1)由前后各两根八字型的对拉锚缆(11)固定,对拉辅助船(3)也由前后各两根八字型的对拉辅助锚缆(31)固定,对拉船(1)上设置有两个卷扬机(4),对拉辅助船(3)上也设置有两个卷扬机(4),砂袋(2)的四个角分别通过活结连接有四根拉绳(5),与对拉船(1)同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机(4)上,与对拉辅助船(3)同侧的两根拉绳的另一端分别固定在对拉辅助船(3)的两个卷扬机上,对拉船(1)上设置有泥浆泵(6),泥浆泵(6)的出口与砂袋(2)的入口连接。本发明能使砂袋袋体定位和沉放更加准确。

Description

一种深水袋装砂施工装置的施工工艺
技术领域
本发明涉及一种深水袋装砂施工装置的施工工艺。
背景技术
目前,深水袋装砂的施工装置一般采用铺排船,这种铺排船的船体非常庞大,因为一般深水袋装砂的砂袋长度少则二十多米,长则上百米,砂袋需要按照长度方向铺设在铺排船的翻板上,翻板相对船体倾斜设置,翻板的一侧固定在船体上,另一侧则倾斜伸入水中,施工过程中,一边向砂袋内充灌泥浆砂,铺排船一边后退,随着砂袋的重量不断增加,砂袋会逐渐下沉至水底。传统的采用铺排船进行深水袋装砂施工的缺陷主要有:需要使用体积庞大的铺排船,成本较高,另外,在水深大时,水流复杂,砂袋铺设效率不高,停留在水底与翻板之间的砂袋袋体易受水流干扰,产生扭曲、破损现象,铺设质量难以达到规范要求,并且难以下放到设计位置,成功率不高。
发明内容
本发明所要解决的第一个技术问题是针对上述现有技术提供一种能使砂袋袋体定位和沉放更加准确的深水袋装砂施工装置。
本发明所要解决的第二个技术问题是针对上述现有技术提供一种能使砂袋袋体定位和沉放更加准确的深水袋装砂施工工艺。
本发明解决上述第一个技术问题所采用的技术方案为:该深水袋装砂施工装置,其特征在于:包括设置在砂袋一侧的对拉船,设置在砂袋另一侧与对拉船配对的对拉辅助船,对拉船由前后各两根八字型的对拉锚缆固定,对拉辅助船也由前后各两根八字型的对拉辅助锚缆固定,对拉船上设置有两个卷扬机,对拉辅助船上也设置有两个卷扬机,砂袋的四个角分别通过活结连接有四根拉绳,与对拉船同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机上,与对拉辅助船同侧的两根拉绳的另一端分别固定在对拉辅助船的两个卷扬机上,对拉船上设置有泥浆泵,泥浆泵的出口与砂袋的入口连接。
作为改进,所述泥浆泵安装在对拉船靠近砂袋的一侧。
再改进,所述对拉船旁设置有运砂船,对拉船上安装有与运砂船连接的水力冲挖机组,水力冲挖机组的出口与泥浆泵的入口连接。
再改进,所述砂袋的四个角上安装有砂袋浮标。
再改进,泥浆泵的出口连接有一总输泥管,该总输泥管上分布有输泥管浮标,总输泥管上具有多个输出口,每个输出口通过一个软管与砂袋上的多个冲砂口连接。
再改进,砂袋的四角通过锚拉工艺由牵引绳绷紧。
本发明解决上述第二个技术问题所采用的技术方案为:一种上述结构的深水袋装砂施工装置的施工方法,其特征在于:
将对拉船和对拉辅助船行至指定地域,与当前需要冲灌的砂袋相对应,通过实时动态差分法对其精确定位,并配以抛锚艇抛好前后各两根八字型的对拉锚缆和对拉辅助锚缆,将对拉船和对拉辅助船固定好,砂袋制作时,在砂袋的四边,预留0.5m~1.5m富裕量,用足够拉力的四根拉绳和砂袋的四个角活结连接,与对拉船同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机上,与对拉辅助船同侧的两根拉绳的另一端分别固定在对拉辅助船的两个卷扬机上,并在砂袋四角系好砂袋浮标,同时辅以锚拉工艺将砂袋四角用四根牵引绳绷紧,对拉船和对拉辅助船对拉砂袋使砂袋展开,砂袋展开后重新复核砂袋四个角点的坐标,适当调整直至符合要求,开启水力冲挖机组和泥浆泵,充填砂袋,边充灌边放松拉绳和牵引绳将砂袋缓缓沉放,待砂袋充填完沉放到位后,最后解开四根拉绳和四根牵引绳,将对拉船和对拉辅助船行至下一个指定地域,与下一个需要冲灌的砂袋相对应。
与现有技术相比,本发明的优点在于:采用本发明提供的装置,即使在水深大、水流复杂的情况下,砂袋铺设效率也非常高,能使砂袋袋体定位更精准和沉放更加准确,还无需体积庞大的铺排船。
附图说明
图1为本发明实施例中深水袋装砂施工装置的俯视结构示意图;
图2为本发明实施例中深水袋装砂施工装置的侧视结构示意图(砂袋沉放到位);
图3为本发明实施例中深水袋装砂施工工艺的流程图。
具体实施方式
以下结合附图实施例对本发明作进一步详细描述。
如图1、图2所示的深水袋装砂施工装置,其包括设置在砂袋2一侧的对拉船1,设置在砂袋2另一侧与对拉船1配对的对拉辅助船3,对拉船1由前后各两根八字型的对拉锚缆11固定,对拉辅助船3也由前后各两根八字型的对拉辅助锚缆31固定,对拉船1上设置有两个卷扬机4,对拉辅助船3上也设置有两个卷扬机4,砂袋2的四个角分别通过活结连接有四根拉绳5,与对拉船1同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机4上,与对拉辅助船3同侧的两根拉绳的另一端分别固定在对拉辅助船3的两个卷扬机上,对拉船1上设置有泥浆泵6,泥浆泵6的出口与砂袋2的入口连接。
本实施例中,所述泥浆泵6安装在对拉船1靠近砂袋2的一侧。对拉船1旁设置有运砂船8,对拉船1上安装有与运砂船连接的水力冲挖机组7,水力冲挖机组的出口与泥浆泵6的入口连接。砂袋2的四个角上安装有砂袋浮标,砂袋的四角通过锚拉工艺由牵引绳12绷紧,泥浆泵6的出口连接有一总输泥管9,该总输泥管9上分布有输泥管浮标10,总输泥管9上具有多个输出口,每个输出口通过一个软管13与砂袋2上的多个冲砂口连接。
上述袋装砂施工装置的施工方法为:
将对拉船1和对拉辅助船3行至指定地域,与当前需要冲灌的砂袋相对应,通过实时动态差分法对其精确定位,并配以抛锚艇抛好前后各两根八字型的对拉锚缆和对拉辅助锚缆,将对拉船和对拉辅助船固定好,砂袋制作时,在砂袋的四边,预留0.5m~1.5m富裕量,用足够拉力的四根拉绳和砂袋的四个角活结连接,与对拉船1同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机4上,与对拉辅助船3同侧的两根拉绳的另一端分别固定在对拉辅助船3两个卷扬机上,并在砂袋四角系好砂袋浮标,同时辅以锚拉工艺将砂袋四角用四根牵引绳绷紧,对拉船1对拉辅助船3拉砂袋使砂袋展开,砂袋展开后重新复核砂袋四个角点的坐标,适当调整直至符合要求,开启水力冲挖机组和泥浆泵,充填砂袋,边充灌边放松拉绳和牵引绳将砂袋缓缓沉放,待砂袋充填完沉放到位后,最后解开四根拉绳和四根牵引绳,将对拉船1和对拉辅助船3行至下一个指定地域,与下一个需要冲灌的砂袋相对应,参见图3所示。

Claims (1)

1.一种深水袋装砂施工装置的施工工艺,其特征在于:所述深水袋装砂施工装置包括:设置在砂袋(2)一侧的对拉船(1),设置在砂袋(2)另一侧与对拉船(1)配对的对拉辅助船(3),对拉船(1)由前后各两根八字型的对拉锚缆(11)固定,对拉辅助船(3)也由前后各两根八字型的对拉辅助锚缆(31)固定,对拉船(1)上设置有两个卷扬机(4),对拉辅助船(3)上也设置有两个卷扬机(4),砂袋(2)的四个角分别通过活结连接有四根拉绳(5),与对拉船(1)同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机(4)上,与对拉辅助船(3)同侧的两根拉绳的另一端分别固定在对拉辅助船(3)的两个卷扬机上,对拉船(1)上设置有泥浆泵(6),泥浆泵(6)的出口与砂袋(2)的入口连接;所述泥浆泵(6)安装在对拉船(1)靠近砂袋(2)的一侧;所述对拉船(1)旁设置有运砂船,对拉船(1)上安装有与运砂船连接的水力冲挖机组(7),水力冲挖机组的出口与泥浆泵(6)的入口连接;所述砂袋(2)的四个角上安装有砂袋浮标;泥浆泵(6)的出口连接有一总输泥管,该总输泥管上分布有输泥管浮标,总输泥管上具有多个输出口,每个输出口通过一个软管与砂袋(2)上的多个冲砂口连接;砂袋的四角通过锚拉工艺由牵引绳绷紧;
将对拉船(1)和对拉辅助船(3)行至指定地域,与当前需要冲灌的砂袋相对应,通过实时动态差分法对其精确定位,并配以抛锚艇抛好前后各两根八字型的对拉锚缆和对拉辅助锚缆,将对拉船和对拉辅助船固定好,砂袋制作时,在砂袋的四边,预留0.5m~1.5m富裕量,用足够拉力的4根拉绳和砂袋的四个角活结连接,与对拉船(1)同侧的两根拉绳的另一端分别固定在对拉船的两个卷扬机(4)上,与对拉辅助船(3)同侧的两根拉绳的另一端分别固定在对拉辅助船(3)的两个卷扬机上,并在砂袋四角系好砂袋浮标,同时辅以锚拉工艺将砂袋四角用四根牵引绳绷紧,对拉船(1)和对拉辅助船(3)对拉砂袋使砂袋展开,砂袋展开后重新复核砂袋四个角点的坐标,适当调整直至符合要求,开启水力冲挖机组和泥浆泵,充填砂袋,边充灌边放松拉绳和牵引绳将砂袋缓缓沉放,待砂袋充填完沉放到位后,最后解开四根拉绳和四根牵引绳,将对拉船(1)和对拉辅助船(3)行至下一个指定地域,与下一个需要冲灌的砂袋相对应。
CN201310410654.7A 2013-09-10 2013-09-10 一种深水袋装砂施工装置的施工工艺 Active CN103452117B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310410654.7A CN103452117B (zh) 2013-09-10 2013-09-10 一种深水袋装砂施工装置的施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310410654.7A CN103452117B (zh) 2013-09-10 2013-09-10 一种深水袋装砂施工装置的施工工艺

Publications (2)

Publication Number Publication Date
CN103452117A CN103452117A (zh) 2013-12-18
CN103452117B true CN103452117B (zh) 2015-07-08

Family

ID=49734924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310410654.7A Active CN103452117B (zh) 2013-09-10 2013-09-10 一种深水袋装砂施工装置的施工工艺

Country Status (1)

Country Link
CN (1) CN103452117B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104120727A (zh) * 2014-07-04 2014-10-29 上海交通建设总承包有限公司 一种吊安预制袋装砂的施工方法
CN104652367B (zh) * 2015-02-15 2016-09-21 中交上航局航道建设有限公司 一种在淤泥区铺设大型袋装砂被的施工方法
CN104912080B (zh) * 2015-05-21 2016-08-31 中交上航局航道建设有限公司 一种泥浆充填袋筑堤的施工设备及工艺
CN105113456B (zh) * 2015-08-13 2017-01-25 河南鼎诚环保装备股份有限公司 一种抛沙枕堤坝加固设备
CN105484272B (zh) * 2016-01-09 2018-04-27 安徽水利开发股份有限公司 加筋充泥管袋
CN106149738B (zh) * 2016-08-22 2018-08-14 中交天航港湾建设工程有限公司 一种基于封闭水域定位管排打设充填袋的装置及施工方法
CN107165124A (zh) * 2017-05-19 2017-09-15 中交上航局航道建设有限公司 一种深水软体排对拉铺设施工方法
CN114108637B (zh) * 2021-11-05 2024-04-02 中国一冶集团有限公司 一种用于水下膜袋的定位施工方法

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1186502C (zh) * 2003-06-27 2005-01-26 中铁大桥局集团有限公司 桥梁深水基础钢吊箱、钢套箱浮运重型锚定位施工方法
CN101537875B (zh) * 2008-05-05 2012-07-04 中交一航局第二工程有限公司 趸船采用气囊助浮在直立岸壁的出运下水工艺
JP4739444B2 (ja) * 2009-10-27 2011-08-03 株式会社人工海底山脈研究所 ブロック積載・投下方法
CN102758419B (zh) * 2012-07-31 2015-01-28 长江南京航道工程局 基于活动加筋条的深水铺设联锁排施工方法
CN103215912B (zh) * 2013-03-19 2015-06-17 中交一航局第二工程有限公司 软体排浅滩陡坡对铺方法及对铺系统
CN203498838U (zh) * 2013-09-10 2014-03-26 中交上航局航道建设有限公司 一种深水袋装砂施工装置

Also Published As

Publication number Publication date
CN103452117A (zh) 2013-12-18

Similar Documents

Publication Publication Date Title
CN103452117B (zh) 一种深水袋装砂施工装置的施工工艺
CN106516021B (zh) 一种自航式水下隧道沉管运载安装一体船
CN203584490U (zh) 海缆或软管埋设装置及施工船
CN104724553B (zh) 电缆布放和回收的装置及方法
CN104480865B (zh) 一种大型钢沉井精确定位方法
WO2018068362A1 (zh) 一种深海采矿系统
CN103661801B (zh) 海洋工程水下推进器的安装辅助系统及安装方法
CN103046553A (zh) 利用铺排船深水铺设大体积加筋充泥管袋的方法
CN103407552A (zh) 单点系泊系统的配重锚链
CN203129178U (zh) 一种超大型沉管绞缆出坞系统
CN102837804A (zh) 深水中吸力锚的安装设备及安装方法
CN105952967B (zh) 一种利用浮球沉放管道的沉管作业方法
CN106149738B (zh) 一种基于封闭水域定位管排打设充填袋的装置及施工方法
CN105604079A (zh) 一种适用于大流速条件下的隧道沉管管节出坞施工方法
CN102221128B (zh) 一种基于锚墩固定的海底输油输气软管管线
CN104421491B (zh) 一种用于深水高悬跨海底管线处理的作业装备及作业方法
CN203498838U (zh) 一种深水袋装砂施工装置
CN208235530U (zh) 一种抛石管及抛石系统
CN107165124A (zh) 一种深水软体排对拉铺设施工方法
CN204703172U (zh) 一种海洋管道铺设施工用高压注浆气囊
CN108832551B (zh) 岩基海床高压海缆敷设和保护方法
CN105300635A (zh) 垂直阶梯来流海洋立管涡激-参激耦合振动试验装置
CN106764062A (zh) 一种海底管路铺设辅助装置
CN108411921A (zh) 一种抛石管及抛石系统
CN102661444B (zh) 海洋石油平台深水双管系的安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 315 200 No. 221 Yanjiang East Road, Zhenhai District, Ningbo City, Zhejiang Province

Patentee after: China Water Conservancy and Hydropower Construction Co., Ltd.

Address before: 315 200 No. 221 Yanjiang East Road, Zhenhai District, Ningbo City, Zhejiang Province

Patentee before: SDC Waterway Construction Co., Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20211013

Address after: 315200 No. 221 East Yanjiang Road, Zhenhai District, Zhejiang, Ningbo

Patentee after: CCCC WATER CONSERVANCY AND HYDROPOWER CONSTRUCTION Co.,Ltd.

Patentee after: NATIONAL ENGINEERING RESEARCH CENTER OF DREDGING TECHNOLOGY AND EQUIPMENT

Address before: 315200 No. 221 East Yanjiang Road, Zhenhai District, Zhejiang, Ningbo

Patentee before: CCCC WATER CONSERVANCY AND HYDROPOWER CONSTRUCTION Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220315

Address after: 315200 No. 221 East Yanjiang Road, Zhenhai District, Zhejiang, Ningbo

Patentee after: CCCC WATER CONSERVANCY AND HYDROPOWER CONSTRUCTION CO.,LTD.

Address before: 315200 No. 221 East Yanjiang Road, Zhenhai District, Zhejiang, Ningbo

Patentee before: CCCC WATER CONSERVANCY AND HYDROPOWER CONSTRUCTION CO.,LTD.

Patentee before: CCCC dredging technology and equipment National Engineering Research Center Co., Ltd

TR01 Transfer of patent right