CN103422445B - Constructing method of high temporary bridge crossing river in extremely cold area - Google Patents

Constructing method of high temporary bridge crossing river in extremely cold area Download PDF

Info

Publication number
CN103422445B
CN103422445B CN201310397976.2A CN201310397976A CN103422445B CN 103422445 B CN103422445 B CN 103422445B CN 201310397976 A CN201310397976 A CN 201310397976A CN 103422445 B CN103422445 B CN 103422445B
Authority
CN
China
Prior art keywords
bridge
steel pipe
pile
steel
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310397976.2A
Other languages
Chinese (zh)
Other versions
CN103422445A (en
Inventor
李老民
刘亚雷
王丽梅
凡春
陆海英
李斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
China Construction Sixth Engineering Bureau Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, China Construction Sixth Engineering Bureau Civil Engineering Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201310397976.2A priority Critical patent/CN103422445B/en
Publication of CN103422445A publication Critical patent/CN103422445A/en
Application granted granted Critical
Publication of CN103422445B publication Critical patent/CN103422445B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a constructing method of a high temporary bridge crossing a river in an extremely cold area. The constructing method includes the following steps: (1) multiple sets of steel pipe piles are sequentially inserted into the opposite bank at intervals from one bank of the river, and each set of the steel pipe piles serves as a bridge pier; (2) the multiple steel pipe piles of each bridge pier are connected in a welded mode to form a circle through channel steel, and then the two transverse sides of each bridge pier are respectively provided with a reinforcing steel pipe pile with the pile body exposed out of a water surface in an inserted mode; (3) the top end of each steel pipe pile is provided with a pile cap in a welded mode; (4) the pile caps of the same-row steel pipe piles of each bridge pier are provided with an H-shaped steel capping beam in a welded mode in the transverse direction; (5) a full-length Beiley beam longitudinally arranged from one bank of the river to the opposite bank is spliced and installed on the tops of the multiple H-shaped steel capping beams; (6) a plurality of beams are welded to the full-length Beiley beam at intervals in the transverse direction, and then a full-piece steel plate is fixed to the beams; (7) mixed river sand is filled in bridge head portions at the two ends of the temporary bridge. The constructing method is high in safety and large in bearing load.

Description

The high suspension bridge construction method of rivers is crossed in a kind of extremely cold area
Technical field
The present invention relates to a kind of suspension bridge construction method, particularly relate to the high suspension bridge construction method that rivers are crossed in a kind of extremely cold area.
Background technology
Along with the fast development day by day of Chinese national economy, it is growing that construction of road and bridge is invested.In bridge construction, at present the bridge crossing over great rivers is got more and more.For convenience of rivers both sides bridge construction and transport of materials, build make-shift bridge, make the streamflow of perennial stream smooth and easy by suspension bridge in bridge both sides, can not form what and block up, and suspension bridge firm stable, safety are high, bearing load power is large.
The patent of having authorized is learnt by retrieval:
1 application number is: the Chinese patent of CN201120112826.9 discloses " Combined temporary bridge ", the utility model relates to a kind of Combined temporary bridge, comprise the guardrail of the both sides of base plate and mounting base, it is characterized in that: described guardrail comprises bottom tube and n shape pipe, described n shape pipe is arranged on the top of bottom tube by bindiny mechanism, between described bottom tube and n shape pipe, be provided with two crossbeams be parallel to each other, be provided with several vertical beam between two described crossbeams, between described bottom tube, tube connector be installed.The utility model has the advantages that: the guardrail of base plate and both sides is independent installations, can separate, taking up room and greatly reducing when depositing and transport, and carries easy accessibility, not only attractive in appearance but also safety.Be a kind of Combined temporary bridge disclosed in this patent, be not suitable for the suspension bridge crossing over great rivers.
2 application numbers are: the Chinese patent of CN201020155405.X discloses " steel suspension bridge braced structures ", the utility model discloses a kind of steel suspension bridge braced structures, comprise support column group and a left side, right Bailey bracket, its main points are: the support column of described support column group is arranged side by side, all connect through bridging between the adjacent supports post of this support column group, longitudinal beam group is fixed with in the support column upper end of longitudinal arrangement, transverse beam group is fixed with in described longitudinal beam group upper end, in this transverse beam group, two ends are symmetrically fixed with a left side, right Bailey bracket, on this left side, transverse distribution beam group is fixed with between right Bailey bracket, this transverse distribution beam group is fixed with longitudinal distribution beam group, described longitudinal distribution beam group is equipped with panel.Use of the present utility model greatly facilitates construction, the utility model cost low and be convenient to dismounting; Have be skillfully constructed, the feature such as structure is simple, implement easily, good reliability.Although this patent is disclosed is steel suspension bridge braced structures, be not suitable for the steel suspension bridge bridge pier in extremely cold area, the river freezed winter, spring, interim ice cube directly can clash into suspension bridge bridge pier, caused suspension bridge bridge pier unstability.
3. application number is: the Chinese patent of CN201210162725.1 discloses " island cofferdam construction method built by a kind of sidewalk, suspension bridge and cushion cap ", what the invention discloses a kind of sidewalk, suspension bridge and cushion cap builds island cofferdam construction method, from both sides, river course simultaneously the step that includes of construction be: (a) to carry out successively from side, river course the first pioneer road build island, the first suspension bridge build island; B () is in the pile foundation of building the first suspension bridge that island constructs of the first suspension bridge; What c () filled the first cushion cap at the first described pioneer road one sidewall while construction first suspension bridge pile foundation builds island, in the pile foundation of building the first cushion cap that island constructs of the first cushion cap; D (), after the pile foundation of the first suspension bridge completes, the Bailey bracket group that the pier stud of the pile foundation of the first suspension bridge sets up the first suspension bridge is abandoned steel truss girder; (e) repeat in the front end of the first suspension bridge described in step (a) to (d) until from the construction of building cofferdam, island completing the sidewalk in whole river course, suspension bridge and cushion cap in the middle of both sides, river course to river course.
4. application number is: the Chinese patent of CN201220231101.6 discloses " island cofferdam construction structure built by a kind of sidewalk, suspension bridge and cushion cap ", what the utility model discloses a kind of sidewalk, suspension bridge and cushion cap builds island cofferdam construction structure, it comprises multiple syndeton be connected successively from side, river course to river course opposite side, each syndeton includes sidewalk, cushion cap has been filled at a sidewall of described sidewalk, be connected by suspension bridge between two adjacent sidewalks, abandon steel truss girder in the added Bailey bracket group that is provided with of the pier stud of the pile foundation of each suspension bridge.Adopt the utility model structure: the material that cofferdam, island is built at scene is all gathered materials on the spot, and to build island material be the original sand in the Yellow River, can not pollute the Yellow River itself, protect environment.And regard the environment of Around Bridge as an organic system, the mud in work progress and discarded object etc., clear the appointed place of engineering in time, removes clean, in order to avoid polluted river channel when Practical Completion.
Although 3-4 item patent is disclosed is sidewalk, island cofferdam construction built by suspension bridge and cushion cap, be not suitable for the steel suspension bridge bridge pier in extremely cold area, the river freezed winter, spring, interim ice cube can direct shock suspension bridge bridge pier, caused suspension bridge bridge pier unstability.
Summary of the invention
The high suspension bridge construction method of rivers is crossed in the object of the present invention is to provide a kind of suspension bridge firm stable, safety high, bearing load is large and construction method is easy, saved cost, save the extremely cold area of duration.
A kind of high suspension bridge construction method of crossing over rivers of the present invention, it comprises the following steps:
(1) from the side bank of rivers successively interval to offside bank inserted to play many groups steel pipe pile, each described group steel pipe pile is as a bridge pier, and each group steel pipe pile is made up of multiple steel pipe pile, concreting in the steel pipe pile then described in each;
(2) be weldingly connected adopting channel-section steel to form a circle between many steel pipe piles of each bridge pier, connect for entirety to make each bridge pier, then at the both lateral sides reinforcing steel pipe pile that surfaces of inserted to play one pile body respectively of each bridge pier, then each is reinforced steel pipe pile be connected with the support channel-section steel that two steel pipe piles of the next-door neighbour of the corresponding bridge pier arranged adopt oblique top to arrange;
(3) at every root steel pipe pile top welding pile cover;
(4) on same row's steel pipe pile pile cover of each bridge pier, an i iron bent cap is transversely welded;
(5) many i iron bent cap top splicings, the elongated Bailey beam longitudinally arranged from the side bank of rivers to offside bank is together installed;
(6) in elongated Bailey beam, transversely many crossbeams are welded at interval, on crossbeam, then fix completely spreading steel plate;
(7) mixed river sand is adopted to fill at the end of the bridge position at suspension bridge two ends, mix around the sand of river at end of the bridge and squeeze into Larsen steel sheet pile, at the bridge floor of the end of the bridge filling mixed river sand, reinforced mesh is installed, and concreting, form end of the bridge bridge floor, described end of the bridge bridge floor is made up of ramp portion and planar section, and planar section is connected with bridge surface armor plate and is in same level position with bridge surface armor plate, the length of planar section is not less than two meters, and ramp portion is connected with highway.
The inventive method for convenience of rivers both sides bridge construction, is built make-shift bridge in bridge both sides, is made the streamflow of perennial stream smooth and easy by suspension bridge, can not form what and block up, and suspension bridge firm stable, safety are high, and bearing load is large.Build concrete in bridge pier steel pipe pile, improve the bearing capacity of bridge pier.Reinforce the steel pipe pile diagonal channel-section steel be connected with four turnings of the channel-section steel formed a circle that is connected with the support channel-section steel that the corresponding oblique top arranged is arranged and define a bridge pier reinforcement system preventing ice cube from clashing into.The suspension bridge body of a bridge is high, and flood season can not flood bridge floor temporarily.The ice cube freezed winter, spring also can not directly clash into suspension bridge bridge pier temporarily.And construction method easy, saved cost, saved the duration.
Accompanying drawing explanation
Fig. 1 is the suspension bridge schematic top plan view that the high suspension bridge construction method adopting a kind of extremely cold area of the present invention to cross over rivers is built;
Fig. 2 is the suspension bridge elevational schematic view shown in Fig. 1;
Fig. 3 is the suspension bridge side schematic view shown in Fig. 1;
Fig. 4 is the A place enlarged drawing of the suspension bridge shown in Fig. 2.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.
A kind of high suspension bridge construction method of crossing over rivers of the present invention as shown in drawings, it comprises the following steps: (1) is from the side bank of rivers successively interval to offside bank inserted to play many groups steel pipe pile, each described group steel pipe pile is as a bridge pier, each group steel pipe pile is made up of many steel pipe piles 1, then concreting in the steel pipe pile described in each root; (2) be weldingly connected adopting channel-section steel 3 to form a circle between many steel pipe piles of each bridge pier, connect for entirety to make each bridge pier, then at the both lateral sides reinforcing steel pipe pile 1-2 that surfaces of inserted to play one pile body respectively of each bridge pier, then each is reinforced steel pipe pile 1-2 be connected with the support channel-section steel 2 that two steel pipe piles of the next-door neighbour of the corresponding bridge pier arranged adopt oblique top to arrange; (3) at every root steel pipe pile top welding pile cover 4; (4) on same row's steel pipe pile pile cover of each bridge pier, an i iron bent cap 5 is transversely welded; (5) many i iron bent cap top splicings, the elongated Bailey beam 8 longitudinally arranged from the side bank of rivers to offside bank is together installed; (6) in elongated Bailey beam, transversely many crossbeams 11 are welded at interval, then fixing completely paving steel plate 12 on crossbeam; (7) adopt mixed river sand 6 to fill at the end of the bridge position at suspension bridge two ends, mix around the sand of river at end of the bridge and squeeze into Larsen steel sheet pile 7, for sealing and Stability Analysis of Structures.At the bridge floor of the end of the bridge filling mixed river sand, reinforced mesh is installed, and concreting 10, form end of the bridge bridge floor, described end of the bridge bridge floor is made up of ramp portion and planar section, planar section is connected with bridge surface armor plate and is in same level position with bridge surface armor plate, the length of planar section is not less than two meters, and ramp portion is connected with highway.
Each corner at four turnings of preferred channel-section steel 3 connects channel-section steel 9 respectively by one and is weldingly connected in diagonal positions with the i iron bent cap 5 of oblique upper.Advantage reinforces the firmness of each group steel pipe pile.
Each group steel pipe pile preferred is made up of two rows, and between two row's steel pipe piles, parallel interval is arranged.Advantage ensures each the group tolerance of steel pipe pile and balance and stability of whole suspension bridge.
Embodiment 1
(1) from the side bank of rivers successively interval to offside bank inserted to play many groups steel pipe pile, each described group steel pipe pile is as a bridge pier, each group steel pipe pile is made up of many steel pipe piles 1, and each group steel pipe pile is made up of two rows, and between two row's steel pipe piles, parallel interval is arranged.Then concreting in the steel pipe pile described in each root; (2) be weldingly connected adopting channel-section steel 3 to form a circle between many steel pipe piles of each bridge pier, connect for entirety to make each bridge pier, then at the both lateral sides reinforcing steel pipe pile 1-2 that surfaces of inserted to play one pile body respectively of each bridge pier, then each is reinforced steel pipe pile 1-2 be connected with the support channel-section steel 2 that two steel pipe piles of the next-door neighbour of the corresponding bridge pier arranged adopt oblique top to arrange; Each corner at four turnings of channel-section steel 3 connects channel-section steel 9 respectively by one and is weldingly connected in diagonal positions with i iron bent cap 5.(3) at every root steel pipe pile top welding pile cover 4; (4) on same row's steel pipe pile pile cover of each bridge pier, an i iron bent cap 5 is transversely welded; (5) many i iron bent cap top splicings, the elongated Bailey beam 8 longitudinally arranged from the side bank of rivers to offside bank is together installed; (6) in elongated Bailey beam, transversely many crossbeams 11 are welded at interval, then fixing completely paving steel plate 12 on crossbeam; (7) adopt mixed river sand 6 to fill at the end of the bridge position at suspension bridge two ends, mix around the sand of river at end of the bridge and squeeze into Larsen steel sheet pile 7, for sealing and Stability Analysis of Structures.At the bridge floor at the end of the bridge filling mixed river sand, reinforced mesh is installed, and concreting 10, form end of the bridge bridge floor, described end of the bridge bridge floor is made up of ramp portion and planar section, planar section is connected with bridge surface armor plate and is in same level position with bridge surface armor plate, the length of planar section is not less than two meters, and ramp portion is connected with highway.
Suspension bridge firm stable, safety are high after testing, and bearing load is large.Save the expense of maintenance bridge pier, through estimate cost-saving 2%, save 15 days durations.

Claims (3)

1. cross over a high suspension bridge construction method for rivers, it is characterized in that it comprises the following steps:
(1) from the side bank of rivers successively interval to offside bank inserted to play many groups steel pipe pile, each described group steel pipe pile is as a bridge pier, and each group steel pipe pile is made up of many steel pipe piles, then concreting in the steel pipe pile described in each root;
(2) be weldingly connected adopting channel-section steel to form a circle between many steel pipe piles of each bridge pier, connect for entirety to make each bridge pier, then at the both lateral sides reinforcing steel pipe pile that surfaces of inserted to play one pile body respectively of each bridge pier, then each is reinforced steel pipe pile be connected with the support channel-section steel that two steel pipe piles of the next-door neighbour of the corresponding bridge pier arranged adopt oblique top to arrange;
(3) at every root steel pipe pile top welding pile cover;
(4) on same row's steel pipe pile pile cover of each bridge pier, an i iron bent cap is transversely welded;
(5) many i iron bent cap top splicings, the elongated Bailey beam longitudinally arranged from the side bank of rivers to offside bank is together installed;
(6) in elongated Bailey beam, transversely many crossbeams are welded at interval, on crossbeam, then fix completely spreading steel plate;
(7) mixed river sand is adopted to fill at the end of the bridge position at suspension bridge two ends, mix around the sand of river at end of the bridge and squeeze into Larsen steel sheet pile, at the bridge floor of the end of the bridge filling mixed river sand, reinforced mesh is installed, and concreting, form end of the bridge bridge floor, described end of the bridge bridge floor is made up of ramp portion and planar section, and planar section is connected with bridge surface armor plate and is in same level position with bridge surface armor plate, the length of planar section is not less than two meters, and ramp portion is connected with highway.
2. a kind of high suspension bridge construction method of crossing over rivers according to claim 1, is characterized in that: each corner at four turnings of described channel-section steel is that diagonal positions is weldingly connected respectively by the i iron bent cap that connects channel-section steel and oblique upper.
3. a kind of high suspension bridge construction method of crossing over rivers according to claim 1 and 2, is characterized in that: each group steel pipe pile is made up of two rows, and between two row's steel pipe piles, parallel interval is arranged.
CN201310397976.2A 2013-09-04 2013-09-04 Constructing method of high temporary bridge crossing river in extremely cold area Active CN103422445B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310397976.2A CN103422445B (en) 2013-09-04 2013-09-04 Constructing method of high temporary bridge crossing river in extremely cold area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310397976.2A CN103422445B (en) 2013-09-04 2013-09-04 Constructing method of high temporary bridge crossing river in extremely cold area

Publications (2)

Publication Number Publication Date
CN103422445A CN103422445A (en) 2013-12-04
CN103422445B true CN103422445B (en) 2015-04-01

Family

ID=49647797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310397976.2A Active CN103422445B (en) 2013-09-04 2013-09-04 Constructing method of high temporary bridge crossing river in extremely cold area

Country Status (1)

Country Link
CN (1) CN103422445B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108166395B (en) * 2017-12-26 2019-05-10 中铁四局集团路桥工程有限公司 A kind of construction method for building beam bridge across Business Line

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005299080A (en) * 2004-04-06 2005-10-27 Hanshin Expressway Public Corp Earthquake-resistant bridge pier
JP4286737B2 (en) * 2004-07-12 2009-07-01 株式会社竹中土木 Construction method of pier
CN201826292U (en) * 2010-10-28 2011-05-11 中铁十三局集团有限公司 Bare rock steel pipe pile platform in steep slopes under deep sea
CN202273169U (en) * 2011-10-25 2012-06-13 中建七局第三建筑有限公司 Trestle
CN202530367U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Deepwater complex geology foundation construction system
CN102720136B (en) * 2012-05-22 2014-06-25 中国建筑第六工程局有限公司 Island and cofferdam construction method for roads, bridges and bearing platforms
CN102677592B (en) * 2012-05-24 2014-09-10 中国水电建设集团十五工程局有限公司 Method for erecting deepwater steel trestle and platform on exposed bedrock in shallow sea
CN202989757U (en) * 2012-07-19 2013-06-12 中铁十六局集团第一工程有限公司 Landing stage flood protection device of river bed bare rock
CN203049443U (en) * 2012-12-14 2013-07-10 中铁上海工程局有限公司 High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer

Also Published As

Publication number Publication date
CN103422445A (en) 2013-12-04

Similar Documents

Publication Publication Date Title
CN205205635U (en) Stride footpath bailey frame steel suspension bridge structure greatly
CN106978777B (en) A kind of make-shift bridge device
CN111691454A (en) Subway station and bridge co-construction structure and construction method
CN110983891B (en) Highway reconstruction and expansion assembly type roadbed structure and construction method thereof
CN202298440U (en) Steel trestle structure used on cliff terrains
CN112482202A (en) Pull rod type multipurpose steel trestle bridge abutment and construction method thereof
CN103422445B (en) Constructing method of high temporary bridge crossing river in extremely cold area
CN112359712A (en) Three-column prestressed concrete gate pier for rail transit and construction method thereof
CN201722614U (en) Bridge beam construction support combining military beam support with cuplock scaffold
CN203514199U (en) High auxiliary bridge construction structure for spanning river in extremely-cold area
CN102392417A (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN101570956B (en) Two-lane beam-bridge end reinforcement concrete frame pier in side walk
CN211978309U (en) Longitudinal reaction frame for prefabricated pier stress test
CN211228134U (en) Large cantilever prestress bent cap support device
CN111058386B (en) Viaduct construction method for overpass existing ground bridge
CN210482000U (en) Limiting device for jacking construction of large-span steel pipe concrete tied arch bridge
CN213508572U (en) Piping lane supporting construction
CN114687321A (en) Construction method of energy dissipation type gabion retaining wall revetment structure
CN109736216B (en) High-steep side slope dangerous rock falling stone protection method and combined stone blocking wall structure thereof
CN203654193U (en) Quick bridge construction structure
CN201809718U (en) Baseless ground anchoring overpass bridge
CN213978602U (en) Walking type pushing support and structural jig frame combined system
CN111877812B (en) Elevated single-column station
CN216142018U (en) Bridge foundation and bridge
CN211772934U (en) Zero number block support system of bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20180914

Granted publication date: 20150401

PP01 Preservation of patent right
PD01 Discharge of preservation of patent

Date of cancellation: 20190618

Granted publication date: 20150401

PD01 Discharge of preservation of patent