CN112482202A - Pull rod type multipurpose steel trestle bridge abutment and construction method thereof - Google Patents

Pull rod type multipurpose steel trestle bridge abutment and construction method thereof Download PDF

Info

Publication number
CN112482202A
CN112482202A CN202011167863.XA CN202011167863A CN112482202A CN 112482202 A CN112482202 A CN 112482202A CN 202011167863 A CN202011167863 A CN 202011167863A CN 112482202 A CN112482202 A CN 112482202A
Authority
CN
China
Prior art keywords
steel
abutment
soil
retaining
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011167863.XA
Other languages
Chinese (zh)
Inventor
王少兵
李洪松
石九州
叶亦盛
李建勇
解鑫鹏
温盼闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ccteb Infrastructure Construction Investment Co ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
Ccteb Infrastructure Construction Investment Co ltd
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ccteb Infrastructure Construction Investment Co ltd, China Construction Third Engineering Bureau Co Ltd filed Critical Ccteb Infrastructure Construction Investment Co ltd
Priority to CN202011167863.XA priority Critical patent/CN112482202A/en
Publication of CN112482202A publication Critical patent/CN112482202A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种拉杆式多用途钢栈桥桥台及其施工方法,所述双排钢管桩、挡土钢板桩、反拉钢板、台背填料、对拉螺杆和桥台搭板,首先在桥台前施打双排钢管桩作为整体制动措施;再针对河漫区存在的台背填土较高的情况,一方面采用钢板桩及腰梁结构实现挡土及冲刷的作用,另一方面采用对拉螺杆及反拉钢板实现土压力的平衡;然后钢板桩与反拉钢板之间填筑加固土确保台背稳定,上部设置一层混凝土桥头搭板,内部配置钢筋与钢管桩顶部焊接形成整体。采用本桥台设计及其施工方法可解决河漫区较高填方临时桥台拆除困难、沉降量大、稳定性差、台背冲刷等难题,有利于控制临时栈桥标高、桥路顺接及减少栈桥长度,从而达到降低工程造价的目的。

Figure 202011167863

The invention discloses a tie-rod-type multi-purpose steel trestle abutment and a construction method thereof. The double-row steel pipe piles, soil retaining steel sheet piles, reverse-pulling steel plates, abutment back fillers, counter-pulling screws and abutment plates are first Apply double-row steel pipe piles in front of the bridge abutment as an overall braking measure; then, in view of the high backfill situation in the Heman area, on the one hand, steel sheet piles and waist beam structures are used to achieve soil retention and scouring. On the other hand, the balance of the earth pressure is achieved by using the counter-tensioning screw and the reverse-tensioning steel plate; then, the reinforcement soil is filled between the steel sheet pile and the reverse-tensioning steel plate to ensure the stability of the back of the platform, and a layer of concrete bridge head board is arranged on the upper part, and steel bars and steel pipes are arranged inside. The top of the pile is welded to form a whole. The use of this bridge abutment design and construction method can solve the problems of difficult removal of temporary bridge abutments with high fill in the Heman area, large settlement, poor stability, abutment back scouring, etc. The length of the trestle bridge, so as to achieve the purpose of reducing the project cost.

Figure 202011167863

Description

Pull rod type multipurpose steel trestle bridge abutment and construction method thereof
Technical Field
The invention relates to the technical field of bridge engineering construction, in particular to a pull rod type multipurpose steel trestle bridge abutment and a construction method thereof.
Background
At present, a wider river flood plain is often designed in a river levee, a temporary steel trestle needs to be built when a project crosses the river levee, the service life is 2-5 years according to the construction period, in order to avoid the influence of the flood period on the steel trestle, the steel trestle is possibly designed to be higher than the river flood plain, if the steel trestle is directly built to the river levee of two banks, the steel trestle is in direct connection with an access road through a traditional concrete bridge abutment, the using amount of the steel trestle is large, and the cost is high; if only a main river crossing groove is built, a concrete bridge abutment is built on a flood plain and then is in direct connection with a flood plain sidewalk, a foundation needs to be arranged at the bottom of the concrete bridge abutment, and meanwhile, when the bridge abutment is high, concrete is adopted to design, so that the stress is complex, the size is large, the later period is difficult to break, the cost is high, and the lateral force resistance and flood-proof scouring capability of the common steel pipe bridge abutment are weak; the deep foundation pit also adopts double steel sheet piles to reach the soil retaining effect, but is not suitable for the temporary steel abutment in the flood plain area, and the steel sheet pile consumption is large, and the installation and the dismantlement construction are wasted time and energy.
Disclosure of Invention
In order to overcome the technical defects of complex concrete stress, large volume, difficult later-stage removal, high cost and the like in the traditional steel trestle construction in the prior art, the invention provides the pull rod type multipurpose steel trestle abutment and the construction method thereof, which meet the requirement of higher filling abutment, have high construction efficiency, can effectively reduce the maintenance times of the abutment and shorten the span of the steel trestle and solve the technical problems.
The invention achieves the aim through the following technical scheme, and the pull rod type multipurpose steel trestle bridge abutment comprises double rows of steel pipe piles, soil retaining steel plate piles, counter-pull steel plates, abutment back fillers, counter-pull screws and abutment butt straps. The double-row steel pipe piles are steel pipe piles with double rows of spacing of 3m and are arranged according to the width of a trestle, round steel pipes or I-shaped steel and the like are arranged among the steel pipe piles to serve as a double-row steel pipe pile connection system, fine sand or concrete is filled inside the steel pipe piles to enhance the rigidity and the transverse stability of the steel pipe piles, the soil-retaining steel plate piles are composed of one row of steel plate piles and a plurality of outer side retaining waist beams, the number of the steel plate piles is determined according to the width of a bridge abutment roadbed and the slope protection and is not less than the sum of the width of the trestle and the width of the slope protection, the length of the soil-retaining steel plate piles is determined according to the lower geological condition and the height of the bridge abutment after soil pressure analysis, the number of the outer side retaining waist beam layers is determined according to the height difference between the top surface of the bridge abutment and river overflowing, the outer side retaining waist beams are formed by welding double-spliced channel steel, the abutment back filler is positioned between the retaining steel sheet pile and the counter-pull steel sheet, is a cement soil or other reinforcing filler, is a convenient road direct-connection part for filling on the temporary trestle and the flood plain, the counter-pull screw rod adopts common screw steel, the retaining steel sheet and the counter-pull steel sheet are connected through the waist beams outside the two sides of the retaining soil, and are buried in the abutment back filler, a tension-compression balance structure is formed with the abutment back filler, a plurality of longitudinal main ribs are arranged inside the abutment butt plate, and the longitudinal main ribs extend out of the end of the upright post and are welded in the upright post at the top of the steel pipe pile.
In the specific construction process of the pull rod type multipurpose steel trestle bridge abutment, the whole construction method comprises the following construction steps:
s1: the method comprises the following steps of (1) driving a steel pipe pile, paying off according to a design position, constructing a bridge abutment steel pipe column on a river bank line or a flood plain line, determining the top elevation according to the bridge deck elevation of a trestle, erecting section steel on the pile top close to the side of a river channel, manufacturing a welding platform on the upper portion of the steel pipe column on the side of the flood plain and erecting the section steel, placing a rubber cushion block on the upper portion, erecting the section steel on the top, and pouring fine sand or concrete into the soil outlet portion of the steel pipe pile;
s2: the method comprises the following steps of (1) driving a row of soil-retaining steel sheet piles, paying off according to a design position, driving a row of soil-retaining steel sheet piles transversely next to the driven steel pipe piles along a line, and installing counter-pulling steel plates on the other sides of counter-pulling screws with intervals of more than 8 m;
s3: the method comprises the steps of (1) bench back backfilling and supporting system construction, selecting whether to partially replace and fill a foundation according to site geological conditions, backfilling between a steel sheet pile and a counter-pull steel sheet layer by layer, compacting cement layer by layer to reinforce and fill soil, excavating a notch with the depth of 150mm and the width of 100mm at the bottom according to the design position of a counter-pull screw when backfilling to a first layer waist beam at the designed bottom, mounting a counter-pull screw, fixing the notch on an outer side waist beam of a retaining soil by using a double-layer screw cap, continuously backfilling and mounting each layer of outer side waist beam of the retaining soil and the counter-pull screw, and synchronously performing 1:1 slope protection construction in the soil filling and compacting process, wherein;
s4: arranging bridge abutment buttresses, arranging a row of brackets on the upper parts of the steel sheet piles, enabling the top surfaces of the brackets to be flush with backfill reinforced soil, enabling upper embedded steel bars to penetrate into the inner side of the top of the steel pipe pile, and then pouring the concrete bridge abutment buttresses;
s5: the bridge abutment upper structure is installed, an upper bridge abutment beret beam supporting structure and prefabricated bridge decks are installed, expansion joints are arranged between the bridge abutment and the abutment back filling, and at least three prefabricated bridge decks are arranged on the abutment back and are sequentially connected with a common roadbed filling access road.
Generally, compared with the prior art, the technical scheme of the invention can achieve the following beneficial effects:
1. the pull rod type multipurpose steel trestle bridge abutment is reinforced in multiple ways, ensures the stress safety of the structure, solves the problem of weak lateral force of a steel pipe of the bridge abutment, has strong integrity, is completely a steel structure, has strong reutilization effect, is free from pollution during dismantling, has high construction efficiency and small forward connection settlement, and meets the requirement of forward connection of a temporary trestle bridge and an access road for a long time;
2. by adopting the construction method, efficient, high-quality and stable design and construction of the temporary abutment can be realized, the forward connection transition effect of the temporary bridge and the temporary road is better, the later-stage dismantling is easy, the difficult problem of abutment construction under the conditions of higher filling and river scouring is effectively solved, the on-site construction period and cost are saved, and the later-stage maintenance workload is reduced.
Drawings
The following detailed description of embodiments of the invention is provided in conjunction with the appended drawings, in which:
FIG. 1 is a schematic longitudinal section of a multi-purpose steel trestle abutment of the present invention;
FIG. 2 is a schematic view of a lower plan view of a multi-purpose steel trestle abutment of the present invention;
FIG. 3 is a schematic longitudinal section 1/2 of a multi-purpose steel trestle abutment of the present invention;
FIG. 4 is a detailed schematic view of the steel pipe pile overlap joint platform according to the present invention;
FIG. 5 is a detailed view of the connection between the retaining steel plate and the steel pipe column according to the present invention;
FIG. 6 is a detailed view of the abutment attachment plate according to the present invention;
in the figure: 1-double rows of steel pipe piles, 2-soil retaining steel plate piles, 3-counter-pulling steel plates, 4-table back filling materials, 5-counter-pulling screw rods, 6-abutment butt straps, 7-river bank lines or river runflat lines, 8-section steel, 9-Bailey beam supporting structures, 10-prefabricated panels, 11-expansion joints, 12-rubber mats, 13-steel pipe piles, 14-double rows of steel pipe pile connection systems, 15-welding platforms on the steel pipe piles, 16-soil retaining steel plates, 17-soil retaining outer side waist beams, 18-middle steel plates, 19-concrete abutment butt straps, 20-configuration main ribs and 21-brackets.
Detailed Description
As shown in fig. 1 to 3, the present invention is a schematic diagram of a longitudinal section, a lower plane and a 1/2 longitudinal section of a tie-rod type multipurpose steel trestle abutment, and comprises double rows of steel pipe piles 1, retaining steel plate piles 2, counter-pull steel plates 3, abutment back fillers 4, counter-pull screws 5 and abutment buttresses 6.
The double-row steel pipe piles 1 are steel pipe piles 13 with a double-row interval of 3m and are arranged according to the width of a trestle, round steel pipes or I-shaped steel and the like are arranged among the steel pipe piles 13 to serve as double-row steel pipe pile connection systems 14, fine sand or concrete is filled inside the double-row steel pipe piles to enhance the rigidity and the transverse stability of the double-row steel pipe piles, and as shown in fig. 4, the double-row steel pipe piles 1 is a detailed schematic diagram of a steel.
The retaining steel sheet pile 2 is composed of a row of steel sheet piles and a plurality of retaining outer side waist beams 17, the number of the retaining steel sheet piles 2 is determined according to the width of a bridge abutment roadbed and a protection slope and is not smaller than the sum of the width of a trestle and the width of the protection slope, the length of the retaining steel sheet pile 2 is determined according to the lower geological condition and the height of the bridge abutment after soil pressure analysis, the number of the retaining outer side waist beams 17 is determined according to the height difference between the top surface of the bridge abutment and river overflowing, the retaining outer side waist beams 17 are formed by welding double-spliced channel steel, the middle steel sheet 18 is welded on the steel pipe pile 13, and as shown in figure 5, the retaining steel sheet 16 and the steel pipe column.
The counter-pulling steel plate 3 is composed of a small number of steel plates, the distance between the counter-pulling steel plate 3 and the retaining steel plate pile 2 is not less than 8m, two counter-pulling steel plates are arranged at each position, and a finish-rolling deformed steel bar gap is reserved in the middle.
The platform back filler 4 is positioned between the retaining steel sheet pile and the counter-pull steel sheet, is made of cement soil or other reinforcing fillers and is a part which is directly connected with a filling convenience road on the temporary trestle and the flood plain.
The opposite-pulling screw rods 5 are made of common deformed steel bars, the soil retaining steel plates 16 and the reverse-pulling steel plates 3 are connected through the outer waist beams 17 of the soil retaining parts at two sides, and are embedded in the table back filler 4 to form a tension-compression balance structure with the table back filler 4.
A plurality of longitudinal main ribs 20 are arranged inside the abutment butt strap 6, the longitudinal main ribs 20 extend out of the end of the upright column and are bent into the upright column at the top of the steel pipe pile 13 for welding, and as shown in fig. 6, the longitudinal main ribs are a detailed schematic diagram of the abutment butt strap 6.
In the specific construction process of the pull rod type multipurpose steel trestle abutment, the construction of the steel trestle abutment is mainly completed through the following steps:
the method comprises the following steps: the method comprises the following steps of (1) driving a steel pipe pile 13, paying off according to a design position, constructing a bridge abutment steel pipe column on a river bank line or a river flood beach line 7, determining the top elevation according to the bridge deck elevation of a trestle, erecting section steel 8 on the pile top close to a river channel side, manufacturing a welding platform on the upper portion of the steel pipe column on the river flood beach side, erecting section steel 8, placing a rubber cushion block 12 on the upper portion, erecting the section steel 8 on the top portion, and pouring fine sand or concrete into the soil outlet portion of the steel pipe pile 13;
step two: the row of soil-retaining steel sheet piles 2 are arranged in a driving mode, paying off is carried out according to the designed position, the row of soil-retaining steel sheet piles 2 are transversely arranged close to the driven steel pipe piles 13 along the line, and the reverse-pulling steel plates 3 are arranged on the other sides of the counter-pulling screw rods 5 at intervals of more than 8 m;
step three: the method comprises the steps of (1) construction of a platform back backfilling and supporting system, selecting whether to locally replace and fill a foundation according to site geological conditions, backfilling between a steel sheet pile 13 and a counter-pull steel plate 3 layer by layer, compacting cement layer by layer to reinforce and fill soil, digging a notch with the depth of 150mm and the width of 100mm at the bottom according to the design position of a counter-pull screw 5 when backfilling is carried out to the mark of a first layer of waist beam at the designed bottom, installing a counter-pull screw 5, fixing the notch on an outer side waist beam 17 of a retaining soil by using a double-layer nut, continuously backfilling and installing each layer of outer side waist beam 17 of the retaining soil and the counter-pull screw 5, and synchronously carrying out 1:1 slope protection construction;
step four: arranging a bridge abutment butt strap 6, arranging a row of brackets 21 on the upper part of the steel sheet pile, enabling the top surfaces of the brackets 21 to be flush with backfill reinforcing soil, enabling upper embedded steel bars to penetrate into the inner side of the steel pipe pile top 13, and then pouring a concrete bridge abutment butt strap 19;
step five: the upper part of the bridge abutment is structurally installed, an upper bridge abutment beret beam supporting structure 9 and prefabricated bridge decks 10 are installed, expansion joints 11 are arranged between the bridge abutment and the abutment back filling, and at least three prefabricated bridge decks 10 are arranged on the abutment back and are sequentially connected with a common roadbed filling pavement.
It will be understood by those skilled in the art that the foregoing is only a preferred embodiment of the present invention, and is not intended to limit the invention, and that any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (2)

1.一种拉杆式多用途钢栈桥桥台,其特征在于,包括双排钢管桩(1)、挡土钢板桩(2)、反拉钢板(3)、台背填料(4)、对拉螺杆(5)和桥台搭板(6);1. A tie-rod-type multi-purpose steel trestle abutment, characterized in that it comprises double-row steel pipe piles (1), soil-retaining steel sheet piles (2), reverse-pull steel plates (3), abutment back fillers (4), Pull screw (5) and bridge abutment board (6); 所述双排钢管桩(1)是根据栈桥宽度设置的双排间距3m的钢管桩(13),所述钢管桩(13)之间设置圆钢管或工字钢等作为双排钢管桩连接系(14),内部填充细沙或混凝土增强其刚度及横向稳定性;The double-row steel pipe piles (1) are steel pipe piles (13) with a double-row spacing of 3m set according to the width of the trestle, and round steel pipes or I-beams etc. are arranged between the steel pipe piles (13) as the double-row steel pipe piles (13). The pipe pile connection system (14) is filled with fine sand or concrete to enhance its rigidity and lateral stability; 所述挡土钢板桩(2)由一排钢板桩及多道挡土外侧腰梁(17)组成,挡土钢板桩(2)数量根据桥台路基宽度及护坡确定,不小于栈桥宽度与护坡宽度总和,挡土钢板桩(2)的长度根据下部地质情况以及桥台高度经过土压力分析后确定,挡土外侧腰梁(17)层数根据桥台顶面与河漫高度差确定,挡土外侧腰梁(17)由双拼槽钢焊接而成,中间钢板(18)焊接在钢管桩(13)上;The soil-retaining steel sheet piles (2) are composed of a row of steel sheet piles and multiple outer waist beams (17) for soil-retention. The sum of the width, the length of the retaining sheet pile (2) is determined according to the lower geological conditions and the height of the abutment after the earth pressure analysis, and the number of layers of the outer waist beam (17) of the retaining soil is determined according to the height difference between the top surface of the abutment and the river overflow. The outer waist beam (17) of the soil is welded by double channel steel, and the middle steel plate (18) is welded on the steel pipe pile (13); 所述反拉钢板(3)由少量钢板组成,反拉钢板(3)与挡土钢板桩(2)间距不低于8m,每处设置两根并在中间预留精轧螺纹钢缝隙;The reverse-drawn steel plate (3) is composed of a small number of steel plates, and the distance between the reverse-drawn steel plate (3) and the retaining steel sheet pile (2) is not less than 8m, and two are arranged at each position, and a finish-rolled thread steel gap is reserved in the middle; 所述台背填料(4)位于挡土钢板桩与反拉钢板之间,为水泥土或其他加固填料,是临时栈桥与河漫滩上填方便道顺接部分;The platform back filler (4) is located between the retaining steel sheet pile and the reverse-tensioned steel sheet, and is cement soil or other reinforcing fillers, and is the connecting part of the temporary trestle bridge and the floodplain filled with convenience roads; 所述对拉螺杆(5)采用普通螺纹钢,通过两侧挡土外侧腰梁(17)将挡土钢板(16)及反拉钢板(3)连接,并埋在台背填料(4)之中,与台背填料(4)形成拉压平衡结构;The pair of tensioning screws (5) are made of ordinary threaded steel, and the retaining steel plate (16) and the anti-pulling steel plate (3) are connected through the outer waist beams (17) of the soil retaining on both sides, and are buried in the back of the table (4). In the middle, a tension-compression balance structure is formed with the back filler (4); 所述桥台搭板(6)内部配置多根纵向主筋(20),所述纵向主筋(20)在立柱端头伸出并弯入钢管桩(13)顶部立柱中焊接。A plurality of longitudinal main bars (20) are arranged inside the abutment deck (6), and the longitudinal main bars (20) are protruded from the ends of the uprights and bent into the top uprights of the steel pipe piles (13) for welding. 2.一种如权利要求1所述的拉杆式多用途钢栈桥桥台的施工方法,其特征在于,该施工方法包括以下步骤:2. a construction method of a tie rod type multipurpose steel trestle abutment as claimed in claim 1, is characterized in that, this construction method comprises the following steps: S1:钢管桩(13)打设,根据设计位置放线,在河岸线或河漫滩线(7)上施工桥台钢管立柱,顶部标高根据栈桥桥面标高确定,靠近河槽侧在桩顶搭设型钢(8),河漫侧钢管柱上部制作焊接平台并搭设型钢(8),上部放置橡胶垫块(12),顶部搭设型钢(8),钢管桩(13)出土部分内部灌注细沙或混凝土;S1: The steel pipe pile (13) is driven, the line is laid out according to the design position, the abutment steel pipe column is constructed on the river bank line or the floodplain line (7), and the top elevation is determined according to the bridge deck elevation of the trestle. (8) A welding platform is made on the upper part of the steel pipe column on the side of the river and a profiled steel (8) is erected, a rubber pad (12) is placed on the upper part, a profiled steel (8) is erected on the top, and the unearthed part of the steel pipe pile (13) is filled with fine sand or concrete. ; S2:排挡土钢板桩(2)打设,根据设计位置放线,沿着线路紧邻已打设的钢管桩(13)横向打设一排挡土钢板桩(2),在间隔8m以上对拉螺杆(5)另一侧安装反拉钢板(3);S2: Drive the soil-retaining steel sheet piles (2), lay out the line according to the design position, and drive a row of soil-retaining steel sheet piles (2) laterally along the line next to the steel steel pipe piles (13) that have been driven, and pull them at an interval of more than 8m. A reverse-pulling steel plate (3) is installed on the other side of the screw (5); S3:台背回填及支撑体系施工,根据现场地质情况选择是否局部换填地基,在钢板桩(13)与反拉钢板(3)之间分层回填、并逐层压实水泥加固填土,回填至设计底部第一层腰梁标时,根据对拉螺杆(5)设计位置开挖深150mm、底部100mm宽的槽口后安装对拉螺杆(5),并用双层螺帽固定于挡土外侧腰梁(17)上,继续回填并安装各层挡土外侧腰梁(17)及对拉螺杆(5),填土压实过程中应同步进行1:1护坡施工,连接至河堤的普通便道应同步施工;S3: Backfill and support system construction on the back of the platform, choose whether to replace the foundation locally according to the site geological conditions, backfill layer by layer between the steel sheet pile (13) and the reverse tension steel plate (3), and compact the cement layer by layer to reinforce the fill. When backfilling to the waist beam mark of the first layer at the bottom of the design, excavate a slot with a depth of 150mm and a width of 100mm at the bottom according to the design position of the pull screw (5), install the pull screw (5), and fix it on the retaining screw with a double-layer nut On the outer waist beam (17), continue to backfill and install the outer waist beam (17) and the tension screw (5) of each layer of soil retaining. Ordinary sidewalks should be constructed simultaneously; S4:桥台搭板(6)设置,在钢板桩上部设置一排牛腿(21),牛腿(21)顶面与回填加固土平齐,上部预埋钢筋深入至钢管桩顶(13)内侧,再浇筑混凝土桥台搭板(19);S4: The bridge abutment is set up (6), a row of corbels (21) are arranged on the upper part of the steel sheet pile, the top surface of the corbels (21) is flush with the backfill reinforcement soil, and the upper pre-embedded steel bars are deep into the top of the steel pipe pile (13). ) inside, and then pour the concrete abutment plate (19); S5:桥台上部结构安装,安装上部桥台贝雷梁支撑结构(9)及预制桥面板(10),桥台与台背填土之间设置伸缩缝(11),台背上设置不少于三块预制桥面板(10)与普通路基填土便道顺接。S5: Installation of the upper structure of the abutment, installation of the upper abutment Bailey beam support structure (9) and prefabricated bridge deck (10), expansion joints (11) are arranged between the abutment and the backfill, and many are arranged on the back of the abutment The three prefabricated bridge decks (10) are connected to the common roadbed fill road.
CN202011167863.XA 2020-10-27 2020-10-27 Pull rod type multipurpose steel trestle bridge abutment and construction method thereof Pending CN112482202A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011167863.XA CN112482202A (en) 2020-10-27 2020-10-27 Pull rod type multipurpose steel trestle bridge abutment and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011167863.XA CN112482202A (en) 2020-10-27 2020-10-27 Pull rod type multipurpose steel trestle bridge abutment and construction method thereof

Publications (1)

Publication Number Publication Date
CN112482202A true CN112482202A (en) 2021-03-12

Family

ID=74927173

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011167863.XA Pending CN112482202A (en) 2020-10-27 2020-10-27 Pull rod type multipurpose steel trestle bridge abutment and construction method thereof

Country Status (1)

Country Link
CN (1) CN112482202A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113944106A (en) * 2021-10-28 2022-01-18 中铁二十局集团有限公司 Steel trestle bridge channel for upper bridge of land short pier bridge and construction method of steel trestle bridge channel
CN114575240A (en) * 2022-03-01 2022-06-03 中国铁建大桥工程局集团有限公司 Steel trestle bridge abutment
CN114837062A (en) * 2022-06-06 2022-08-02 广东省源天工程有限公司 A steel trestle connecting platform
CN115710857A (en) * 2022-11-21 2023-02-24 中国建筑土木建设有限公司 Fabricated steel trestle bridge abutment structure and construction method thereof
CN115897372A (en) * 2022-11-07 2023-04-04 中铁大桥局第七工程有限公司 A kind of cap for protecting U-shaped abutment and its construction method
CN116043688A (en) * 2022-09-09 2023-05-02 中国建筑土木建设有限公司 Temporary Construction Method of Steel Convenience Bridge
CN117071452A (en) * 2023-10-13 2023-11-17 中国建筑第六工程局有限公司 A flood protection method for high-drop water level construction trestle bridges

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631432A (en) * 2015-01-16 2015-05-20 兰州理工大学 Flexible supporting system for prestress anchor supporting plate of sheet-pile retaining wall and construction method
CN204455801U (en) * 2014-12-25 2015-07-08 中铁大桥局集团第六工程有限公司 A kind of bridge abutment structure
CN206538672U (en) * 2017-01-18 2017-10-03 中交路桥建设有限公司 Novel fabricated truss steel trestle
CN108005104A (en) * 2017-10-27 2018-05-08 西安科技大学 A kind of combined type retaining wall structure and its construction method
KR20190004625A (en) * 2017-07-04 2019-01-14 (주)지비건설 the improved bridge structure
CN109750681A (en) * 2019-03-14 2019-05-14 兰州理工大学 A kind of filling slope frame micro-tensioned anchor plate support structure and construction method thereof
CN110847020A (en) * 2019-11-28 2020-02-28 湖北省路桥集团有限公司 Steel pipe pile steel trestle end and construction method
CN111560842A (en) * 2020-05-28 2020-08-21 中铁五局集团有限公司 A combined abutment structure for temporary trestle bridge
CN211368353U (en) * 2019-11-28 2020-08-28 湖北省路桥集团有限公司 Steel trestle steel pipe pile concrete abutment

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204455801U (en) * 2014-12-25 2015-07-08 中铁大桥局集团第六工程有限公司 A kind of bridge abutment structure
CN104631432A (en) * 2015-01-16 2015-05-20 兰州理工大学 Flexible supporting system for prestress anchor supporting plate of sheet-pile retaining wall and construction method
CN206538672U (en) * 2017-01-18 2017-10-03 中交路桥建设有限公司 Novel fabricated truss steel trestle
KR20190004625A (en) * 2017-07-04 2019-01-14 (주)지비건설 the improved bridge structure
CN108005104A (en) * 2017-10-27 2018-05-08 西安科技大学 A kind of combined type retaining wall structure and its construction method
CN109750681A (en) * 2019-03-14 2019-05-14 兰州理工大学 A kind of filling slope frame micro-tensioned anchor plate support structure and construction method thereof
CN110847020A (en) * 2019-11-28 2020-02-28 湖北省路桥集团有限公司 Steel pipe pile steel trestle end and construction method
CN211368353U (en) * 2019-11-28 2020-08-28 湖北省路桥集团有限公司 Steel trestle steel pipe pile concrete abutment
CN111560842A (en) * 2020-05-28 2020-08-21 中铁五局集团有限公司 A combined abutment structure for temporary trestle bridge

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113944106A (en) * 2021-10-28 2022-01-18 中铁二十局集团有限公司 Steel trestle bridge channel for upper bridge of land short pier bridge and construction method of steel trestle bridge channel
CN114575240A (en) * 2022-03-01 2022-06-03 中国铁建大桥工程局集团有限公司 Steel trestle bridge abutment
CN114837062A (en) * 2022-06-06 2022-08-02 广东省源天工程有限公司 A steel trestle connecting platform
CN114837062B (en) * 2022-06-06 2023-09-08 广东省源天工程有限公司 Steel trestle connecting platform
CN116043688A (en) * 2022-09-09 2023-05-02 中国建筑土木建设有限公司 Temporary Construction Method of Steel Convenience Bridge
CN115897372A (en) * 2022-11-07 2023-04-04 中铁大桥局第七工程有限公司 A kind of cap for protecting U-shaped abutment and its construction method
CN115710857A (en) * 2022-11-21 2023-02-24 中国建筑土木建设有限公司 Fabricated steel trestle bridge abutment structure and construction method thereof
CN117071452A (en) * 2023-10-13 2023-11-17 中国建筑第六工程局有限公司 A flood protection method for high-drop water level construction trestle bridges

Similar Documents

Publication Publication Date Title
CN114775352A (en) A kind of widening structure and construction method of existing roadbed and embankment section near the river
CN107700366B (en) Solid stone bare rock river bed trestle and construction method for deep water high pier long span bridge construction
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN107740339A (en) It is a kind of to be used to run the reinforced bridgehead structures of rigidity and construction method that highway administers bumping at bridge-head
CN110578287A (en) A prefabricated soil-covered corrugated steel plate-prestressed concrete composite arch bridge and its construction method
CN111254772A (en) A large cantilever structure and construction method suitable for widening old roads in cliff sections
CN116180573A (en) A bridge abutment back composite structure and construction method for controlling post-construction settlement
CN207452738U (en) The deep water high-block bridge degree bridge construction naked rock river bed trestle of hard stone
CN211922133U (en) Large cantilever structure suitable for widening old road of cliff road section
CN211368349U (en) Steel trestle end of steel pipe pile
CN102392417B (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN216765890U (en) Steel corrugated pipe culvert bottom supporting stiffening and pressing concrete layer structure
CN216193941U (en) Novel abutment structure
CN103422445B (en) Constructing method of high temporary bridge crossing river in extremely cold area
CN110847227B (en) A road embankment retaining structure
CN219653491U (en) Steel construction abutment suitable for steel trestle
CN219010959U (en) A multi-stage bridge construction platform in hard rock area of V-shaped valley
CN217438694U (en) Inclined vertical pushing pier side support with limited space
CN207512580U (en) For runing the reinforced bridgehead structures of rigidity that highway administers bumping at bridge-head
CN218911435U (en) A Supporting Structure for the Cover Plate of Half-cover Excavated Foundation Pit Applicable to Non-horizontal Terrain Conditions
CN216809531U (en) Riverbed scouring comprehensive protection structure
CN116497725A (en) Reinforcing structure and construction method of a flood-proof railway bridge
CN203795327U (en) Disassembling bracket for overpass
CN207958955U (en) A kind of corrosion resistant bridge
CN207891909U (en) A kind of corrugated steel pipe overlapping cross section structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210312

RJ01 Rejection of invention patent application after publication