CN103410345A - 一种钢筋混凝土柱子加固装置及方法 - Google Patents

一种钢筋混凝土柱子加固装置及方法 Download PDF

Info

Publication number
CN103410345A
CN103410345A CN2013102852919A CN201310285291A CN103410345A CN 103410345 A CN103410345 A CN 103410345A CN 2013102852919 A CN2013102852919 A CN 2013102852919A CN 201310285291 A CN201310285291 A CN 201310285291A CN 103410345 A CN103410345 A CN 103410345A
Authority
CN
China
Prior art keywords
double threaded
threaded screw
concrete
screw
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102852919A
Other languages
English (en)
Other versions
CN103410345B (zh
Inventor
张凤勇
盛浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN201310285291.9A priority Critical patent/CN103410345B/zh
Publication of CN103410345A publication Critical patent/CN103410345A/zh
Application granted granted Critical
Publication of CN103410345B publication Critical patent/CN103410345B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明涉及一种钢筋混凝土柱子加固装置和方法,包括在原钢筋混凝土柱子上,利用自锚定位螺栓和自锚螺栓固定模板系统,解决了建筑物内中部柱子、建筑物外侧柱子和建筑物转角部位柱子加宽加厚时安装模板的难题,该装置可以有效控制钢筋混凝土加固柱的几何尺寸,防止浇筑混凝土时模板变形,达到加厚加宽原钢筋混凝土柱子并保证工程质量的目的。本发明制作容易,安装方便,针对性强,操作简单,解决了原钢筋混凝土柱子加固时模板系统安装的难题,具有良好的经济效益和社会效益。

Description

一种钢筋混凝土柱子加固装置及方法
技术领域
本发明属钢筋混凝土柱子加固技术领域,特别是涉及一种钢筋混凝土柱子加固装置及方法。
背景技术
一般在钢筋混凝土柱子加固过程中,多采用顶的方法安装模板系统,由于难以保证模板系统的强度、刚度和稳定性,浇筑混凝土时容易产生模板变形现象,会影响工程质量。
发明内容
本发明所要解决的技术问题是提供一种钢筋混凝土柱子加固装置及方法,通过自锚定位螺栓装置和方法,有利于模板系统固定提高工程质量,有利于提高效率降低成本,制作容易,安装方便,针对性强,操作简单,提高了施工效率,具有良好的应用和推广价值。
本发明解决其技术问题所采用的技术方案是:提供一种钢筋混凝土柱子加固装置,包括方木楞、模板和锚固螺杆,所述锚固螺杆一端连接钢筋混凝土加固柱侧面、另一端连接螺套,所述螺套另一端连接双头螺杆,所述螺套呈圆锥台形、小端连接锚固螺杆大端连接双头螺杆,所述双头螺杆另一端依次穿过模板、方木楞和钢管扣板,所述双头螺杆穿过钢管扣板的一端装有螺母,所述钢管扣板和方木楞之间装有2根支模钢管,所述支模钢管位于双头螺杆两侧并与双头螺杆相垂直,所述支模钢管被钢管扣板通过螺母紧固于模板的外表面上,所述螺套大端与模板装有垫圈。
所述锚固螺杆通过环氧树脂锚固在钢筋混凝土加固柱的钻洞内。
所述模板与原混凝土构件之间的距离为新浇筑混凝土构件的厚度。
一种钢筋混凝土柱子加固装置的混凝土柱子加固方法,步骤如下:
a、在钢筋混凝土加固柱侧面设置钻洞,根据新浇筑混凝土构件的厚度和锚固螺杆的长度设置钻洞深度,利用环氧树脂将锚固螺杆固定与钻洞内,使锚固螺杆露出部分与新浇筑混凝土构件相配;
b、设置好新浇筑混凝土构件的厚度,安装螺套;
c、在螺套上安装双头螺杆,在双头螺杆上套入垫圈;
d、将模板、方木楞依次安装到双头螺杆上;
e、在双头螺杆两侧、方木楞表面上布置支模钢管;
f、在双头螺杆上压上钢管扣板压住支模钢管,在双头螺杆上旋入螺母锁紧;
g、浇筑混凝土;
h、待混凝土达到强度时拆除方木楞、模板和双头螺杆,将垫圈取出;
i、利用水泥砂浆及时封闭由垫圈引起的圆孔。
所述在钢筋混凝土加固柱为立方体立柱,所述钢筋混凝土加固柱有1到4侧面有新浇筑混凝土构件。
有益效果
本发明制作容易,安装方便,针对性强,操作简单,降低了工程成本,提高了施工效率,保证了工程质量,便于推广。
附图说明
图1为本发明加固装置安装后的结构示意图。
图2为本发明完成步骤h后的状态示意图。
图3为本发明四周型浇筑的模板安装的外部示意图。
图4为本发明四周型浇筑的模板安装截面的示意图。
图5为本发明转角型浇筑的模板安装的外部示意图。
图6为本发明转角型浇筑的模板安装截面的示意图。
图7为本发明单侧浇筑的模板安装的外部示意图。
图8为本发明单侧浇筑的模板安装截面的示意图。
具体实施方式
下面结合具体实施例,进一步阐述本发明。应理解,这些实施例仅用于说明本发明而不用于限制本发明的范围。此外应理解,在阅读了本发明讲授的内容之后,本领域技术人员可以对本发明作各种改动或修改,这些等价形式同样落于本申请所附权利要求书所限定的范围。
如图1至5所示,一种钢筋混凝土柱子加固装置,包括方木楞11、模板10和锚固螺杆2,所述锚固螺杆2一端连接钢筋混凝土加固柱3侧面、另一端连接螺套1,所述螺套1另一端连接双头螺杆7,所述螺套1呈圆锥台形、小端连接锚固螺杆2大端连接双头螺杆7,所述双头螺杆7另一端依次穿过模板10、方木楞11和钢管扣板8,所述双头螺杆7穿过钢管扣板8的一端装有螺母9,所述钢管扣板8和方木楞11之间装有2根支模钢管6,所述支模钢管6位于双头螺杆7两侧并与双头螺杆7相垂直,所述支模钢管6被钢管扣板8通过螺母9紧固于模板10的外表面上,所述螺套1大端与模板10装有垫圈5。
所述锚固螺杆2通过环氧树脂锚固在钢筋混凝土加固柱3的钻洞4内。
所述模板10与原混凝土构件3之间的距离为新浇筑混凝土构件13的厚度。
一种钢筋混凝土柱子加固装置的混凝土柱子加固方法,步骤如下:
a、在钢筋混凝土加固柱3侧面设置钻洞4,根据新浇筑混凝土构件13的厚度和锚固螺杆2的长度设置钻洞4深度,利用环氧树脂将锚固螺杆2固定与钻洞4内,使锚固螺杆2露出部分与新浇筑混凝土构件13相配;
b、设置好新浇筑混凝土构件13的厚度,安装螺套1;
c、在螺套1上安装双头螺杆7,在双头螺杆7上套入垫圈5;
d、将模板10、方木楞11依次安装到双头螺杆7上;
e、在双头螺杆7两侧、方木楞11表面上布置支模钢管6;
f、在双头螺杆7上压上钢管扣板8压住支模钢管6,在双头螺杆7上旋入螺母9锁紧;
g、浇筑混凝土;
h、待混凝土达到强度时拆除方木楞11、模板10和双头螺杆7,将垫圈5取出;
i、利用水泥砂浆及时封闭由垫圈5引起的圆孔14。
所述在钢筋混凝土加固柱3为立方体立柱,所述钢筋混凝土加固柱3有1到4个侧面有新浇筑混凝土构件13。
图3和4中部柱子模板安装情况:中部柱子模板安装时,在原钢筋混凝土柱子3上钻洞4,利用环氧树脂将自锚定位螺栓15锚固在原钢筋混凝土柱子3上,控制其外露尺寸可以有效控制模板10的位置。方木楞11和模板10均为木材制作,安装时利用钢钉连接组合,自锚定位螺栓15或自锚螺栓12通过支模钢管6将模板系统有效固定,达到准确安装固定模板并承受混凝土的压力。
图1中自锚定位螺栓安装情况:自锚定位螺栓15设在钢筋混凝土加固柱13需要加宽的侧面,由圆台形螺套1、锚固螺杆2、垫圈5、双头螺杆7、钢管扣板8和螺母9组成。安装时,在原钢筋混凝土柱子3上钻洞4,利用环氧树脂将自锚定位螺栓15锚固在原钢筋混凝土柱子3上,控制其外露尺寸可以有效控制模板10的位置,达到准确安装固定模板并承受混凝土的压力。
图2中钢筋混凝土加固柱拆模后示意图:自锚定位螺栓15部位拆除后,将垫圈5取出,产生的圆孔14利用水泥砂浆及时封闭。
图7和8中外侧柱子模板安装情况:外侧柱子模板安装时,外侧不需加厚部位采用自锚螺栓12并在原钢筋混凝土柱子3上钻洞4,利用环氧树脂将自锚螺栓12锚固在原钢筋混凝土柱子3上通过支模钢管6将模板系统有效固定,其他三侧模板采用自锚定位螺栓15固定。
图5和6中的转角部位柱子模板安装情况:转角部位柱子模板安装时,不需加厚的两个侧面采用自锚螺栓12并在原钢筋混凝土柱子3上钻洞4,利用环氧树脂将自锚螺栓12锚固在原钢筋混凝土柱子3上通过支模钢管6将模板系统有效固定,其他两侧模板采用自锚定位螺栓15固定。

Claims (5)

1.一种钢筋混凝土柱子加固装置,包括方木楞(11)、模板(10)和锚固螺杆(2),其特征在于,所述锚固螺杆(2)一端连接钢筋混凝土加固柱(3)侧面、另一端连接螺套(1),所述螺套(1)另一端连接双头螺杆(7),所述螺套(1)呈圆锥台形、小端连接锚固螺杆(2)大端连接双头螺杆(7),所述双头螺杆(7)另一端依次穿过模板(10)、方木楞(11)和钢管扣板(8),所述双头螺杆(7)穿过钢管扣板(8)的一端装有螺母(9),所述钢管扣板(8)和方木楞(11)之间装有2根支模钢管(6),所述支模钢管(6)位于双头螺杆(7)两侧并与双头螺杆(7)相垂直,所述支模钢管(6)被钢管扣板(8)通过螺母(9)紧固于模板(10)的外表面上,所述螺套(1)大端与模板(10)装有垫圈(5)。
2.根据权利要求1所述的一种钢筋混凝土柱子加固装置,其特征在于,所述锚固螺杆(2)通过环氧树脂锚固在钢筋混凝土加固柱(3)的钻洞(4)内。
3.根据权利要求1所述的一种钢筋混凝土柱子加固装置,其特征在于,所述模板(10)与原混凝土构件(3)之间的距离为新浇筑混凝土构件(13)的厚度。
4.根据权利要求1、2或3所述的一种钢筋混凝土柱子加固装置的混凝土柱子加固方法,步骤如下:
a、在钢筋混凝土加固柱(3)侧面设置钻洞(4),根据新浇筑混凝土构件(13)的厚度和锚固螺杆(2)的长度设置钻洞(4)深度,利用环氧树脂将锚固螺杆(2)固定与钻洞(4)内,使锚固螺杆(2)露出部分与新浇筑混凝土构件(13)相配;
b、设置好新浇筑混凝土构件(13)的厚度,安装螺套(1);
c、在螺套(1)上安装双头螺杆(7),在双头螺杆(7)上套入垫圈(5);
d、将模板(10)、方木楞(11)依次安装到双头螺杆(7)上;
e、在双头螺杆(7)两侧、方木楞(11)表面上布置支模钢管(6);
f、在双头螺杆(7)上压上钢管扣板(8)压住支模钢管(6),在双头螺杆(7)上旋入螺母(9)锁紧;
g、浇筑混凝土;
h、待混凝土达到强度时拆除方木楞(11)、模板(10)和双头螺杆(7),将垫圈(5)取出;
i、利用水泥砂浆及时封闭由垫圈(5)引起的圆孔(14)。
5.根据权利要求4所述的一种钢筋混凝土柱子加固装置的混凝土柱子加固方法,其特征在于,所述在钢筋混凝土加固柱(3)为立方体立柱,所述钢筋混凝土加固柱(3)有1到4个侧面有新浇筑混凝土构件(13)。
CN201310285291.9A 2013-07-08 2013-07-08 一种钢筋混凝土柱子加固装置及方法 Active CN103410345B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310285291.9A CN103410345B (zh) 2013-07-08 2013-07-08 一种钢筋混凝土柱子加固装置及方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310285291.9A CN103410345B (zh) 2013-07-08 2013-07-08 一种钢筋混凝土柱子加固装置及方法

Publications (2)

Publication Number Publication Date
CN103410345A true CN103410345A (zh) 2013-11-27
CN103410345B CN103410345B (zh) 2016-12-28

Family

ID=49603382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310285291.9A Active CN103410345B (zh) 2013-07-08 2013-07-08 一种钢筋混凝土柱子加固装置及方法

Country Status (1)

Country Link
CN (1) CN103410345B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440929A (zh) * 2018-11-13 2019-03-08 贵州建工集团第六建筑工程有限责任公司 一种屋盖预应力拱板高空张拉预制牵引安装施工方法
CN110029814A (zh) * 2019-05-21 2019-07-19 广州交投城市道路建设有限公司 一种用于混凝土梁加大截面的组合式钢模架
CN111501593A (zh) * 2020-05-18 2020-08-07 施娟丽 一种市政道路工程防落石装置及施工方法
CN112240059A (zh) * 2020-10-26 2021-01-19 吕梁学院 一种可装卸式建筑结构及构件

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5762815A (en) * 1997-08-04 1998-06-09 Lee; Kou-An Apparatus for adjusting a distance between two opposed form panels
CN201225015Y (zh) * 2008-06-06 2009-04-22 中冶天工上海十三冶建设有限公司 冶金大型地下水池施工支模
CN201627372U (zh) * 2009-12-24 2010-11-10 青建集团股份公司 一种三节头对拉螺栓
CN201679233U (zh) * 2010-03-25 2010-12-22 李太平 一种模板定位结构
CN102296812A (zh) * 2011-06-10 2011-12-28 黄学贵 建筑模板成型结构、紧固件及建筑模板施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5762815A (en) * 1997-08-04 1998-06-09 Lee; Kou-An Apparatus for adjusting a distance between two opposed form panels
CN201225015Y (zh) * 2008-06-06 2009-04-22 中冶天工上海十三冶建设有限公司 冶金大型地下水池施工支模
CN201627372U (zh) * 2009-12-24 2010-11-10 青建集团股份公司 一种三节头对拉螺栓
CN201679233U (zh) * 2010-03-25 2010-12-22 李太平 一种模板定位结构
CN102296812A (zh) * 2011-06-10 2011-12-28 黄学贵 建筑模板成型结构、紧固件及建筑模板施工方法

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109440929A (zh) * 2018-11-13 2019-03-08 贵州建工集团第六建筑工程有限责任公司 一种屋盖预应力拱板高空张拉预制牵引安装施工方法
CN110029814A (zh) * 2019-05-21 2019-07-19 广州交投城市道路建设有限公司 一种用于混凝土梁加大截面的组合式钢模架
CN111501593A (zh) * 2020-05-18 2020-08-07 施娟丽 一种市政道路工程防落石装置及施工方法
CN112240059A (zh) * 2020-10-26 2021-01-19 吕梁学院 一种可装卸式建筑结构及构件

Also Published As

Publication number Publication date
CN103410345B (zh) 2016-12-28

Similar Documents

Publication Publication Date Title
CN203939227U (zh) 脚手架连墙装置
CN202913420U (zh) 可重复使用的安装地脚螺栓的定位装置
CN103410345A (zh) 一种钢筋混凝土柱子加固装置及方法
CN103088842A (zh) 毛石挡土墙加固单面模板支撑系统及施工方法
CN103835527A (zh) 一种可拆卸的顶撑装置和它的应用
CN203129203U (zh) 毛石挡土墙加固单面模板支撑系统
CN201144520Y (zh) 一种组合式门洞口模板
CN103362304B (zh) 一种自锚固定位螺栓装置进行模板锚固定位的方法
CN203891462U (zh) 清水混凝土独立柱支模装置
CN204212447U (zh) 门窗混凝土拱形过梁加固施工装置
CN204343319U (zh) 索道管柱基础预埋地脚螺栓定位模具
CN202689344U (zh) 一种拉结筋连接装置
CN204609295U (zh) 一种方形立柱模板抱箍围檩
CN203320952U (zh) 一种构造柱拉模装置
CN202969728U (zh) 预埋筒式螺母锚座
CN203939240U (zh) 一种用于柱或剪力墙模板固定的单端套丝对拉螺栓
CN104295093B (zh) 框架结构双柱间变形缝浇筑支模系统的施工方法
CN204001741U (zh) 清水混凝土连墙柱模板
CN202520011U (zh) 楼板顶撑装置
CN205742988U (zh) 模板一字拼缝防爆模组件
CN203200774U (zh) 一种大体积高杯口柱基础杯芯模板位置固定改进装置
CN202299421U (zh) 一种控制混凝土梁或墙板模板宽度的内撑
CN205035915U (zh) 房屋梁柱型材连接结构及枕木集成房屋
CN102619328B (zh) 一种工具式圈过梁模板安装夹具
CN206158192U (zh) 一种砼面上混凝土泵管的简易固定装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee after: SHANGHAI MCC NO.13 CONSTRUCTION CO., LTD.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee before: CMTCC Shanghai Shisanye Construction Co., Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee after: Shanghai twenty Metallurgical Construction Co., Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Patentee before: SHANGHAI MCC NO.13 CONSTRUCTION CO., LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190703

Address after: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee after: China Twenty Metallurgical Group Co., Ltd.

Patentee after: Shanghai twenty Metallurgical Construction Co., Ltd.

Address before: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Patentee before: Shanghai twenty Metallurgical Construction Co., Ltd.