CN103397654B - 一种钢筋混凝土柱转换劲性柱连接的施工方法 - Google Patents

一种钢筋混凝土柱转换劲性柱连接的施工方法 Download PDF

Info

Publication number
CN103397654B
CN103397654B CN201310310302.4A CN201310310302A CN103397654B CN 103397654 B CN103397654 B CN 103397654B CN 201310310302 A CN201310310302 A CN 201310310302A CN 103397654 B CN103397654 B CN 103397654B
Authority
CN
China
Prior art keywords
column
concrete
fixed mount
reinforced concrete
angle steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310310302.4A
Other languages
English (en)
Other versions
CN103397654A (zh
Inventor
陈明宝
庞遵富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201310310302.4A priority Critical patent/CN103397654B/zh
Publication of CN103397654A publication Critical patent/CN103397654A/zh
Application granted granted Critical
Publication of CN103397654B publication Critical patent/CN103397654B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明公开了一种钢筋混凝土柱转换劲性柱连接的施工方法,其具体技术方案如下:第一步:绑扎钢筋,支模板,浇注下部混凝土柱;第二步:下部凝土柱的混凝土初凝之前预埋(插入)固定架;第三步:根据施工现场测量控制网的坐标和标高基准点;第四步:用吊车/塔吊安装劲性柱型钢,安装四根槽钢定位导杆;第五步:劲性柱型钢和固定架焊接固定;第六步:绑扎劲性柱箍筋,支模板,从上部浇注混凝土。采用本发明所述的一种钢筋混凝土柱转换劲性柱连接的施工方法,保证了混凝土浇注过程中,劲性柱固定架的中心、水平度及其型钢柱垂直度,提高了施工质量,降低了施工成本。

Description

一种钢筋混凝土柱转换劲性柱连接的施工方法
技术领域
本发明属于建筑施工领域,具体的是由钢筋混凝土柱转换为劲性柱连接的施工方法。
背景技术
某项工程地下室筏基至地面层高度为8.5m,柱截面为:1.2m×1.2 m,筏基至地面层竖向配置40根¢32mm钢筋,设计要求-7.5m以下为钢筋混凝土柱,-7.5m以上为劲性柱,劲性柱与楼层平台一次浇注;目前采用的连接施工方法有二: 一是先安装劲性柱固定架及其型钢柱,再整体浇注混凝土;二是先安装劲性柱固定架,然后浇注下部钢筋混凝土柱;这两种施工方法中,劲性柱固定架的中心、水平度及其型钢柱垂直度受混凝土浇注影响,容易出现质量问题;另外,劲性柱固定架需和下部钢筋混凝土柱钢筋固定连接,浪费工时,增加成本;另外,整体浇注混凝土密实度很难保证。
发明内容
本发明所要解决的技术问题是提出一种钢筋混凝土柱转换劲性柱连接的施工方法,保证混凝土浇注过程中,劲性柱固定架的中心、水平度及其型钢柱垂直度,提高施工质量,降低施工成本。
为实现上述目的,本发明一种钢筋混凝土柱转换劲性柱连接的施工方法,其具体技术方案如下:
第一步:绑扎钢筋,支模板,浇注下部混凝土柱;
第二步:下部凝土柱的混凝土初凝之前预埋(插入)固定架,固定架由四根角钢组成,每根角钢焊四个Φ12mm,长50mm的锚固钉;
    第三步:根据施工现场测量控制网的坐标和标高基准点,用测量仪器放出混凝土柱的中心线,测量固定架角钢顶标高;
   第四步:用吊车/塔吊安装劲性柱型钢,安装四根槽钢定位导杆;定位导杆与固定架焊接,利用标高微调螺栓和中心微调螺栓精确控制劲性柱型钢的垂直度、中心线及标高;
   第五步:劲性柱型钢和固定架焊接固定;
   第六步:绑扎劲性柱箍筋,支模板,从上部浇注混凝土。
   所述第三步测量完固定架角钢顶标高后,混凝土柱的混凝土强度达到设计值70%后再安装固定架角钢框,并控制其标高和中心。
   所述的固定架角钢为∠63*6角钢,其插入深度不小于500mm(施工缝以下)。
   采用本发明所述的一种钢筋混凝土柱转换劲性柱连接的施工方法,保证了混凝土浇注过程中,劲性柱固定架的中心、水平度及其型钢柱垂直度,提高了施工质量,降低了施工成本。
附图说明
图1是本发明施工各部件结构示意图。
图2是A-A剖视示意图。
具体实施方式
参见附图,一种钢筋混凝土柱转换劲性柱连接的施工方法,其具体技术方案如下:
第一步:绑扎钢筋,支模板,浇注下部混凝土柱1;
第二步:下部凝土柱的混凝土初凝之前预埋(插入)固定架2,固定架由四根角钢组成,每根角钢焊四个Φ12mm,长50mm的锚固钉;
    第三步:根据施工现场测量控制网的坐标和标高基准点,用测量仪器放出混凝土柱的中心线,测量固定架角钢顶标高;
    第四步:用吊车/塔吊安装劲性柱型钢,安装四根槽钢定位导杆5;定位导杆与固定架焊接,利用标高微调螺栓3和中心微调螺栓4精确控制劲性柱型钢7的垂直度、中心线及标高;
   第五步:劲性柱型钢和固定架焊接固定;
   第六步:绑扎劲性柱6箍筋,支模板,从上部浇注混凝土。
   所述第三步测量完固定架角钢顶标高后,混凝土柱的混凝土强度达到设计值70%后再安装固定架角钢框,并控制其标高和中心。
   所述的固定架角钢为∠63*6角钢,其插入深度不小于500mm(施工缝以下)。
   采用本发明所述的一种钢筋混凝土柱转换劲性柱连接的施工方法,保证了混凝土浇注过程中,劲性柱固定架的中心、水平度及其型钢柱垂直度,提高了施工质量,降低了施工成本。

Claims (3)

1.一种钢筋混凝土柱转换劲性柱连接的施工方法,其具体技术方案如下:
第一步:绑扎钢筋,支模板,浇注下部混凝土柱;
第二步:下部混凝土柱的混凝土初凝之前预埋固定架,固定架由四根角钢组成,每根角钢焊四个Φ12mm,长50mm的锚固钉;
    第三步:根据施工现场测量控制网的坐标和标高基准点,用测量仪器放出混凝土柱的中心线,测量固定架角钢顶标高;
   第四步:用吊车/塔吊安装劲性柱型钢,安装四根槽钢定位导杆;定位导杆与固定架焊接,利用标高微调螺栓和中心微调螺栓精确控制劲性柱型钢的垂直度、中心线及标高;
   第五步:劲性柱型钢和固定架焊接固定;
   第六步:绑扎劲性柱箍筋,支模板,从上部浇注混凝土。
2.根据权利要求1所述的一种钢筋混凝土柱转换劲性柱连接的施工方法,其特征在于第三步测量完固定架角钢顶标高后,混凝土柱的混凝土强度达到设计值70%后再安装固定架角钢框,并控制其标高和中心。
3.根据权利要求1所述的一种钢筋混凝土柱转换劲性柱连接的施工方法,其特征在于所述的固定架角钢为∠63*6角钢,其插入深度不小于500mm。
CN201310310302.4A 2013-07-23 2013-07-23 一种钢筋混凝土柱转换劲性柱连接的施工方法 Active CN103397654B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310310302.4A CN103397654B (zh) 2013-07-23 2013-07-23 一种钢筋混凝土柱转换劲性柱连接的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310310302.4A CN103397654B (zh) 2013-07-23 2013-07-23 一种钢筋混凝土柱转换劲性柱连接的施工方法

Publications (2)

Publication Number Publication Date
CN103397654A CN103397654A (zh) 2013-11-20
CN103397654B true CN103397654B (zh) 2015-07-15

Family

ID=49561349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310310302.4A Active CN103397654B (zh) 2013-07-23 2013-07-23 一种钢筋混凝土柱转换劲性柱连接的施工方法

Country Status (1)

Country Link
CN (1) CN103397654B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103981897B (zh) * 2014-05-29 2016-06-29 浙江省建工集团有限责任公司 一种地下室外墙劲性柱的防水施工方法
CN110453924A (zh) * 2019-09-07 2019-11-15 吉林建筑大学 装配式建筑转换层pcf板安装施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB696144A (en) * 1950-12-13 1953-08-26 Cecil Brian Hugh Colquhoun Improvements in and relating to joining pre-cast concrete members
CN2861328Y (zh) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 逆作法工程劲性钢柱分段预埋结构
CN201339250Y (zh) * 2008-12-25 2009-11-04 中建三局第三建设工程有限责任公司 劲性结构框架梁预制钢筋骨架结构
CN202990121U (zh) * 2013-01-10 2013-06-12 中建八局第一建设有限公司青岛分公司 一种劲性结构与钢结构转换装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB696144A (en) * 1950-12-13 1953-08-26 Cecil Brian Hugh Colquhoun Improvements in and relating to joining pre-cast concrete members
CN2861328Y (zh) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 逆作法工程劲性钢柱分段预埋结构
CN201339250Y (zh) * 2008-12-25 2009-11-04 中建三局第三建设工程有限责任公司 劲性结构框架梁预制钢筋骨架结构
CN202990121U (zh) * 2013-01-10 2013-06-12 中建八局第一建设有限公司青岛分公司 一种劲性结构与钢结构转换装置

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
某高层住宅工程劲性混凝土柱的施工质量控制;林崇洪等;《山西建筑》;20070720(第21期);第246-247页 *
超高层劲性混凝土柱的施工技术措施;黄善富;《上海建设科技》;20120531(第5期);第50-52页 *

Also Published As

Publication number Publication date
CN103397654A (zh) 2013-11-20

Similar Documents

Publication Publication Date Title
CN104895092B (zh) 一种内支撑临时格构柱用作永久结构柱的方法
CN106638940B (zh) 一种装配式高层住宅混凝土预制构件施工工法
CN108265885B (zh) 高大非正交大倾角异型混凝土斜柱的施工方法
CN103850363B (zh) 预制通孔装配式钢筋混凝土剪力墙的施工方法
KR101274481B1 (ko) 커플러가 구비된 사전 매립형 앵커프레임 및 이를 이용한 철골기둥 앵커링 공법
CN210067002U (zh) 一种免支撑装配式框架结构体系
CN104963289A (zh) 一种异形墩柱大体积混凝土整体一次性浇筑施工方法
CN108035554A (zh) 超高层建筑框架柱的型钢柱支撑架施工方法
CN105525753A (zh) 一种构造柱与主体结构同时施工的方法及结构
CN103469732B (zh) 一种桥梁支座地脚螺栓预留孔的施工方法
CN104295003A (zh) 一种构造柱施工方法
JP2008274586A (ja) 柱頭部の施工方法
CN106592990A (zh) 一种装配式建筑基础柱筋精准定位工具及定位方法
CN105317052B (zh) 一种塔吊基础螺栓固定方法
CN111676993A (zh) 一种钢结构穿插施工地下室基础特殊施工方法
CN107447924A (zh) 装配式混凝土剪力墙墙体预留钢筋固定装置及施工方法
JP2011157720A (ja) 鉄道rcラーメン構造高架橋の構築方法
CN103397654B (zh) 一种钢筋混凝土柱转换劲性柱连接的施工方法
CN109457814B (zh) 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法
CN110439025A (zh) 一种狭小空间下门架式建筑物桩基托换结构及施工方法
CN212771968U (zh) 一种全预制拼装桥梁承台定位系统
CN107587770A (zh) 连体仓同步滑模施工方法
CN104947853A (zh) 一种内置支架式现浇钢筋混凝土柱子及施工方法
CN112609842A (zh) 超高层钢柱柱脚结构及其施工方法
CN203891060U (zh) 盖挖逆作车站主体结构的永久钢管柱定位系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant