CN103362146B - Floor slab waterproof protective layer construction method - Google Patents
Floor slab waterproof protective layer construction method Download PDFInfo
- Publication number
- CN103362146B CN103362146B CN201310344152.9A CN201310344152A CN103362146B CN 103362146 B CN103362146 B CN 103362146B CN 201310344152 A CN201310344152 A CN 201310344152A CN 103362146 B CN103362146 B CN 103362146B
- Authority
- CN
- China
- Prior art keywords
- waterproof
- layer
- grade beam
- cement board
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Revetment (AREA)
- Building Environments (AREA)
Abstract
The invention discloses a floor slab waterproof protective layer construction method. First, foundation beam structure construction is conducted. In the foundation beam structure construction, grooves are formed in the two sides of a foundation beam cushion layer. Bottoms of two cement slab templates are respectively inserted in the groove in the corresponding side. The construction steps after the foundation beam structure construction is finished are as following: (1) detaching inner supporting wood beams; (2) laying waterproof roll layers so as to form side wall waterproof roll layers, a foundation beam cushion layer waterproof roll layer and a base plate cushion layer waterproof roller layer; (3) respectively installing fixing cement slabs on the inner side wall of the side wall waterproof roller layers on the left side and the right side; (4) forming an inner support; (5) pouring foundation beam waterproof protection layer concrete on the foundation beam waterproof roll layer, and pouring base plate waterproof protection layer concrete on the base plate cushion layer waterproof roller layer. The vertical face water protection layer formed by the adoption of the method is firm, stable, and not easy to come off, and plays an effective role in protecting the waterproof layer in base plate construction.
Description
Technical field
The present invention relates to basic fish tail and waterproof layer construction method, particularly relate to a kind of grade beam floor slab waterproof protective layer construction method.
Background technology
Along with socioeconomic continuous develop rapidly, all trades and professions all at the speed-raising degree of doing one's utmost, guarantee the quality, cost declining, building trade is all the more so.Before in ground foundation engineering, adopt traditional brick loose tool construction technology, labour drops into comparatively large, and labour cost cost is high, and the wet trade such as to plaster exists technology intermission, causes claim for eot; Grade beam, cushion cap facade waterproof topping adopt tradition to plaster (concrete) etc., easy to crack, come off, and cause waterproofing course damaged, affect waterproof quality.Cement board has good workability, higher intensity, toughness, impermeability and anti-freezing property.In basic engineering construction, alternative brick loose tool is used for the constructing structure of grade beam cushion cap formwork and method has introduction at present, known features grade beam structure as shown in Figure 1, comprise the cement board template 2 of grade beam bed course 3, grade beam bed course both sides, be covered with bottom cushion 4 in both sides, cement board template top, at cement board die head, inner support flitch 6 be installed.Outside cement board template, space is filled with backfill 14, and the external corner 2-1 mill of cement board template 2 has circular arc, and the inner corner trim cement mortar of cement board template 2 is wiped with circular arc 5.
But grade beam or cushion cap adopt cement board but not formed as the construction method of waterproof facade topping.
The patent of having authorized is learnt by retrieval:
1 application number is that the Chinese patent of CN201210287265.5 discloses " a kind of cement board formwork construction method ", the invention discloses a kind of cement board formwork construction method, cement board formwork construction method of the present invention is adopted can significantly to shorten the underground construction duration, reduce overhead cost, equipment leasing cost of use etc., reduce engineering cost; Fixing, the installation of cement board, taking full advantage of construction in the past and discarding the short flitch got off, the short flitch making these discard obtains re-using; Cement board substitutes the use of brick fetal membrane, has saved a large amount of construction brick using amounts, save build by laying bricks or stones, plastering process, directly reduce cost from material and construction, and saved a large amount of labour.
2 application numbers are that the Chinese patent of CN201020265693.4 discloses " cement board base membrane ", the utility model relates to a kind of cement board base membrane, be positioned at grade beam, grade beam or periphery, cushion cap foundation ditch position, two row cement boards are had along foundation ditch extending direction is perpendicular at foundation pad end face, be close to inside cement board bottom and be fixed with inner position batten by nail, be close to cement board Basolateral in plate outer void and be fixed with outside fix batten by nail, perpendicular to foundation ditch extend to, two row cement board tops fix fixing strip, cement board top has the hole of wearing iron wire simultaneously, iron wire one end is through the hole on cement board top and tubercle, and one end extends to waterproof bed course position, foundation ditch surrounding soil is fixed on by wedge shape timber, and be cast as one with waterproof bed course.
3 application numbers are that the Chinese patent of CN201220610448.1 discloses " a kind of cushion cap structure of transvers plate ", the utility model discloses a kind of cushion cap structure of transvers plate, comprise as the GRC cement board of cushion cap foundation segment template and the timber wedge for fixing GRC cement board, described GRC cement board is vertically arranged, and GRC cement board is close to by timber wedge and underground is stretched in lower end.
Be construction method and the structure of using beam or cushion cap template based on cement board disclosed in 1-3 item patent, do not relate to the construction method problem of cement board as waterproof facade topping.
Summary of the invention
The object of the present invention is to provide a kind of structure simple; construction cost is low, applicability is strong; firm stable, difficult drop-off; adopt erection method; any cutting; construct convenient, save time, saving of labor, can ensure the quality of products again while cost-saving and a kind of floor slab waterproof protective layer construction method of safety.
A kind of floor slab waterproof protective layer construction method, first carry out grade beam structure construction, in grade beam structure construction, grade beam bed course both sides arrange groove, are inserted in respectively in the described groove of respective side bottom two cement board templates; Completing the construction sequence after grade beam structure construction is:
(1) inner support flitch is removed;
(2) sidewall waterproof roll layer, grade beam bed course waterproof roll layer and bottom cushion waterproof roll layer is formed at the top laying water-proof coiled material layer of the inside wall of grade beam both sides cement board template, grade beam bed course top, bottom cushion;
(3) on the sidewall waterproof roll layer inside wall described in the left and right sides, fixing cement board is installed respectively;
(4) interval is installed by multiple plastic expansion pipe in the horizontal direction at the waterproof slab topping handing-over position suitable for reading and to be built of described cement board, both sides cement board inside wall is mounted to few twice elongated flitch back cord all relatively, be connected by the short flitch of multiple tracks between the elongated flitch back cord of the both sides be oppositely arranged, form inner support;
(5) on grade beam bed course waterproof roll layer, build grade beam waterproofing protection layer concrete, on bottom cushion waterproof roll layer, build waterproof slab cover concrete;
The construction sequence of described groove is: be pressed into batten before the concrete initial set of grade beam bed course, the concrete absolute altitude of batten upper surface absolute altitude and grade beam bed course is consistent, brush release agent on batten, after the concrete initial set of grade beam bed course, reserved batten is tripped out, cleaning wood chip, forms groove.
The invention has the advantages that: construction cost is low, structure is simple, firmly easy for installation.At the installation plastic expansion pipe suitable for reading of the cement board of waterproof facade topping, be cast in waterproof slab cover concrete, make waterproof slab cover concrete can be combined with cement board closely, form entirety.Each cement board sidewall is installed the elongated flitch back cord of twice, between the elongated flitch back cord of two side, the short flitch of multiple tracks is installed at a certain distance, form inner support, cement board and waterproof roll are fitted tightly; Cement board is by carrying out build-in with the cast-in-place fish tail and waterproof layer of its upper and lower side plane, and form facade waterproof topping, firm stable, difficult drop-off, in construction of bottom plates, serve effective protective effect to waterproofing course.
Accompanying drawing explanation
Fig. 1 is known features cement board formwork construction method elevational schematic view;
Fig. 2 is the scheme of installation of a kind of floor slab waterproof protective layer construction method of the present invention.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.
Of the present invention a kind of floor slab waterproof protective layer construction method is as shown in Figure 2 the improvement on the constructing structure shown in Fig. 1, method of the present invention comprises the following steps: first carry out grade beam structure construction, in grade beam structure construction, grade beam bed course 3 both sides arrange groove 3-1, be inserted in correspondence respectively and arrange in described groove 3-1 bottom two cement board templates 2; Completing the construction sequence after grade beam structure construction is: (1) removes inner support flitch 6; (2) sidewall waterproof roll layer, grade beam bed course waterproof roll layer and bottom cushion waterproof roll layer is formed at the top laying water-proof coiled material layer 8 of the inside wall of grade beam 1 both sides cement board template 2, grade beam bed course 3 top, bottom cushion 4; (3) on the sidewall waterproof roll layer inside wall described in the left and right sides, fixing cement board 7 is installed respectively, as waterproof facade topping.(4) join position at the waterproof slab topping 11 suitable for reading and to be built of described cement board 7 and interval is installed by multiple plastic expansion pipe 9 in the horizontal direction, can be combined with cement board 7 closely after waterproof slab topping 11 is built, form entirety.Both sides cement board 7 inside wall is mounted to few twice elongated flitch back cord 12 all relatively, is connected by the short flitch 10 of multiple tracks between the elongated flitch back cord of the both sides be oppositely arranged, forms inner support, cement board 7 and waterproof roll 8 are fitted tightly; (5) on grade beam bed course waterproof roll layer, build grade beam waterproofing protection layer concrete 13, on bottom cushion waterproof roll layer, build waterproof slab cover concrete 11.
The construction sequence of preferred groove is: be pressed into batten before the concrete initial set of grade beam bed course 3, and the concrete absolute altitude of batten upper surface absolute altitude and grade beam bed course 3 is consistent, and on batten, brush release agent is to remove.After the concrete initial set of grade beam bed course, tripped out by reserved batten, cleaning wood chip, forms groove 3-1.
Inserting the mode be connected bottom preferred cement board template with groove is: bottom cement board template, sidewall withstands on groove inner edge, to control to locate bottom cement board template.
Embodiment 1:
First grade beam structure construction is carried out, in grade beam structure construction, grade beam bed course 3 both sides arrange groove 3-1, to be inserted in described groove 3-1 and bottom cement board template, sidewall withstands on groove inner edge, to control to locate bottom cement board template bottom cement board template 2.The construction sequence of groove is: be pressed into batten before the concrete initial set of grade beam bed course 3, and the concrete absolute altitude of batten upper surface absolute altitude and grade beam bed course 3 is consistent, and on batten, brush release agent is to remove.After the concrete initial set of grade beam bed course, tripped out by reserved batten, cleaning wood chip, forms groove 3-1.
Completing the construction sequence after grade beam structure construction is: (1) removes inner support flitch 6; (2) sidewall waterproof roll layer, grade beam bed course waterproof roll layer and bottom cushion waterproof roll layer is formed at the top laying water-proof coiled material layer 8 of the inside wall of grade beam 1 both sides cement board template 2, grade beam bed course 3 top, bottom cushion 4; (3) on the sidewall waterproof roll layer inside wall described in the left and right sides, fixing cement board 7 is installed respectively, as waterproof facade topping.(4) join position at the waterproof slab topping 11 suitable for reading and to be built of described cement board 7 and interval is installed by multiple plastic expansion pipe 9 in the horizontal direction, can be combined with cement board 7 closely after waterproof slab topping 11 is built, form entirety.Both sides cement board 7 inside wall is mounted to few twice elongated flitch back cord 12 all relatively, is connected by the short flitch 10 of multiple tracks between the elongated flitch back cord of the both sides be oppositely arranged, forms inner support, cement board 7 and waterproof roll 8 are fitted tightly; (5) on grade beam bed course waterproof roll layer, build grade beam waterproofing protection layer concrete 13, on bottom cushion waterproof roll layer, build waterproof slab cover concrete 11.
Through constructing check: cement board is by carrying out build-in with the cast-in-place fish tail and waterproof layer of its upper and lower side plane; form facade waterproof topping; firm stable, difficult drop-off; in construction of bottom plates; during installation reinforcing bar, cement board 7 is also difficult to destroy as waterproof facade topping; waterproofing course be ensure that excellent, effective protective effect is served to waterproofing course.Basement construction is complete does not find any seepage and seeping phenomenon, remains dry state.Extend the application life of whole building.Ensure that the normal usage function of building.
Claims (2)
1. a floor slab waterproof protective layer construction method, first carries out grade beam structure construction, it is characterized in that: in grade beam structure construction, and grade beam bed course both sides arrange groove, is inserted in respectively in the described groove of respective side bottom two cement board templates; Completing the construction sequence after grade beam structure construction is:
(1) inner support flitch is removed;
(2) sidewall waterproof roll layer, grade beam bed course waterproof roll layer and bottom cushion waterproof roll layer is formed at the top laying water-proof coiled material layer of the inside wall of grade beam both sides cement board template, grade beam bed course top, bottom cushion;
(3) on the sidewall waterproof roll layer inside wall described in the left and right sides, fixing cement board is installed respectively;
(4) interval is installed by multiple plastic expansion pipe in the horizontal direction at the waterproof slab topping handing-over position suitable for reading and to be built of described cement board, both sides cement board inside wall is mounted to few twice elongated flitch back cord all relatively, be connected by the short flitch of multiple tracks between the elongated flitch back cord of the both sides be oppositely arranged, form inner support;
(5) on grade beam bed course waterproof roll layer, build grade beam waterproofing protection layer concrete, on bottom cushion waterproof roll layer, build waterproof slab cover concrete;
The construction sequence of described groove is: be pressed into batten before the concrete initial set of grade beam bed course, the concrete absolute altitude of batten upper surface absolute altitude and grade beam bed course is consistent, brush release agent on batten, after the concrete initial set of grade beam bed course, reserved batten is tripped out, cleaning wood chip, forms groove.
2. floor slab waterproof protective layer construction method according to claim 1, is characterized in that: inserting the mode be connected bottom described cement board template with groove is: bottom cement board template, sidewall withstands on groove inner edge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310344152.9A CN103362146B (en) | 2013-08-08 | 2013-08-08 | Floor slab waterproof protective layer construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310344152.9A CN103362146B (en) | 2013-08-08 | 2013-08-08 | Floor slab waterproof protective layer construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103362146A CN103362146A (en) | 2013-10-23 |
CN103362146B true CN103362146B (en) | 2015-07-15 |
Family
ID=49364352
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310344152.9A Expired - Fee Related CN103362146B (en) | 2013-08-08 | 2013-08-08 | Floor slab waterproof protective layer construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103362146B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109025053A (en) * | 2018-08-03 | 2018-12-18 | 徽都建设有限公司 | A kind of processing method of cement plate waterproof layer |
CN112302045A (en) * | 2019-07-26 | 2021-02-02 | 中铁十八局集团第五工程有限公司 | Construction method of foundation beam side vertical face waterproof structure |
CN112962883B (en) * | 2021-02-01 | 2022-05-10 | 北京万兴建筑集团有限公司 | Construction method for preventing slope way of disabled people outside residential building from sinking in constructional engineering |
CN116770881B (en) * | 2023-08-03 | 2024-09-03 | 中铁四局集团有限公司 | Building foundation downward-turning component cushion layer and construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0369725A (en) * | 1989-08-10 | 1991-03-26 | Ohbayashi Corp | Constructing method for water-proof layer |
CN201762709U (en) * | 2010-07-21 | 2011-03-16 | 中建一局集团第五建筑有限公司 | Cement board base membrane |
CN102828524A (en) * | 2012-08-14 | 2012-12-19 | 董田野 | Cement board formwork construction method |
CN102888862A (en) * | 2012-09-06 | 2013-01-23 | 中国华冶科工集团有限公司 | Construction method of waterproof composite layer of lower counter member |
CN202925561U (en) * | 2012-11-16 | 2013-05-08 | 天津二建建筑工程有限公司第三分公司 | Bearing platform template structure |
-
2013
- 2013-08-08 CN CN201310344152.9A patent/CN103362146B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0369725A (en) * | 1989-08-10 | 1991-03-26 | Ohbayashi Corp | Constructing method for water-proof layer |
CN201762709U (en) * | 2010-07-21 | 2011-03-16 | 中建一局集团第五建筑有限公司 | Cement board base membrane |
CN102828524A (en) * | 2012-08-14 | 2012-12-19 | 董田野 | Cement board formwork construction method |
CN102888862A (en) * | 2012-09-06 | 2013-01-23 | 中国华冶科工集团有限公司 | Construction method of waterproof composite layer of lower counter member |
CN202925561U (en) * | 2012-11-16 | 2013-05-08 | 天津二建建筑工程有限公司第三分公司 | Bearing platform template structure |
Also Published As
Publication number | Publication date |
---|---|
CN103362146A (en) | 2013-10-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104746772B (en) | Ash concrete hollow partition board anti-cracking construction method | |
CN104358341B (en) | Building brickwork and masonry construction method of building brickwork | |
CN103362146B (en) | Floor slab waterproof protective layer construction method | |
CN108412093B (en) | Modern landscape decorative rammed earth wall and construction method thereof | |
CN103556819B (en) | A kind of construction method of reserved constructional column hole on beam slab | |
CN104405065A (en) | Wallboard structure provided with non-dismantling formwork and construction method of wallboard structure | |
CN103343582A (en) | Novel insulation filler wall system and construction method thereof | |
CN102777040A (en) | Installation process of stagger-joint dual-wallboard inner partition wall and dual-wallboard inner partition | |
CN103291003B (en) | A kind of sleeping watt construction method of pitched roof | |
CN103410173A (en) | Construction method for vertical post pouring belt plugging of underground structural outer wall | |
CN203383245U (en) | Cement board waterproof protective layer construction structure | |
CN210766835U (en) | Foundation beam side vertical face waterproof structure | |
CN203716410U (en) | Novel roof grid seam | |
CN103669746B (en) | The construction method of inverted roof heat-insulation system | |
CN101469559B (en) | Composite heat insulating walling and mounting method thereof | |
CN105625650A (en) | Construction method for roofing parapet wall flashing protective layer | |
CN103437440A (en) | Fixing device for thermal insulating prefabricated slab of building and construction method for thermal insulation of building by using reverse building method | |
CN206205166U (en) | It is a kind of can synchronous crossed construction outer wall of basement waterproofing protection structure | |
CN102251671B (en) | Exterior heat insulation on-site construction process of exterior wall based on foaming cement material | |
CN109487790A (en) | A kind of concrete heat-insulating method suitable for the big temperature difference area of High aititude | |
CN109098307A (en) | Brick output enters the wall body structure and wall building method of stone | |
CN203113378U (en) | Wall footing structure reducing contraction cracks of basement exterior wall | |
CN112302045A (en) | Construction method of foundation beam side vertical face waterproof structure | |
CN203924139U (en) | concrete component | |
CN109505422B (en) | Reinforcing method for ancient building wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150715 Termination date: 20170808 |
|
CF01 | Termination of patent right due to non-payment of annual fee |