CN103334433A - Pile pulling construction method - Google Patents

Pile pulling construction method Download PDF

Info

Publication number
CN103334433A
CN103334433A CN2013102531994A CN201310253199A CN103334433A CN 103334433 A CN103334433 A CN 103334433A CN 2013102531994 A CN2013102531994 A CN 2013102531994A CN 201310253199 A CN201310253199 A CN 201310253199A CN 103334433 A CN103334433 A CN 103334433A
Authority
CN
China
Prior art keywords
pile
pile foundation
old
pulling
drilling pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013102531994A
Other languages
Chinese (zh)
Other versions
CN103334433B (en
Inventor
魏发利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201310253199.4A priority Critical patent/CN103334433B/en
Publication of CN103334433A publication Critical patent/CN103334433A/en
Application granted granted Critical
Publication of CN103334433B publication Critical patent/CN103334433B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses a pile pulling construction method which comprises the following steps of: A, preparing before pulling a pile; B, separating an old pile foundation; and C, pulling the pile. The pile pulling construction method has the advantages that the pile pulling construction method has low requirements on the construction site and has high construction efficiency; the pile pulling construction method is safe and reliable to use, has low disturbance to surrounding soil mass, has low noise, has no vibration and has no pollution; and operability is strong, large-scale equipment such as a crane and the like is not required, and construction cost is reduced.

Description

A kind of job practices of pile pulling
Technical field
The present invention relates to a kind of job practices of extracting old foundation pile of building engineering field, in particular, relate to the job practices of a kind of low noise, the simple pile pulling of construction.
Background technology
At present, quickening along with urban construction and development speed, original most of communal facilities can not satisfy user demand, particularly evident in urban traffic and housing construction, just need remodel and expand original building again, in dismounting, reconstruction and enlarging process, the underground pile foundation that all inevitably relates to is removed.Yet because the characteristics of urban renewal, near other building of following often and the existence of obstruction, removing and the job site, often obstruction is numerous, main equipments such as the pipe bit machine that conventional pile pulling technology uses and crane can't enter the job site, need clear up back main equipment such as crane to the scene and just can enter construction, delay construction speed, and the wasting manpower and material resources.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, and a kind of, low noise, shockproof, pollution-free little to peripheral soil disturbance is provided, it is flexible to construct, the job practices of the pile pulling that efficiency of construction is high.
In order to achieve the above object, the present invention has taked following technical scheme:
A kind of job practices of pile pulling comprises the steps:
Prepare before A, the pile pulling:
Select the tonnage of fork truck according to the weight of old pile foundation, fork truck is arranged on the old pile foundation limit; Set up tripod, the angle of tripod be fixed on ground, in the center of tripod movable pulley is installed, by movable pulley with the pipe bit head sling be installed in old pile foundation directly over, drilling pipe is installed in pipe bit head lower end, the old pile foundation of the drilling pipe perpendicular alignmnet center of circle;
B, separate old pile foundation:
Start under the pipe bit head drive drilling pipe and bore, the degree of depth that drilling pipe pierces is not less than the degree of depth of old pile foundation, extracts drilling pipe again out and removes the rig head;
C, pile pulling:
The steel wire loop centre position is fixed on the lower end of old pile foundation, and an end of steel wire loop is fixed on the jaw of fork truck, and the other end is fixed on the movable pulley; Fork truck and movable pulley alternately cooperate firmly, and old pile foundation is extracted.
Described tripod is provided with base, and described base is fixed by expansion bolt and ground.The internal diameter of described drilling pipe is not less than the external diameter of old pile foundation.The position of the old pile foundation of distance of described angle steel pile is not less than 5 meters.Described steel wire loop and angle steel pile are that 8 words are overlapping fixing.
Beneficial effect of the present invention: (1) requires low to the construction plant, the efficiency of construction height; (2) safe and reliable,, low noise, shockproof, pollution-free little to peripheral soil disturbance; It is (3) workable,, do not need main equipments such as crane, reduce construction cost.
Description of drawings
Fig. 1 is the schematic diagram of setting up tripod of the job practices of a kind of pile pulling of the present invention;
Fig. 2 is the schematic diagram of the old pile foundation of separation of the job practices of a kind of pile pulling of the present invention;
Fig. 3 is the schematic diagram of fixedly steel wire loop of the job practices of a kind of pile pulling of the present invention;
Fig. 4 is the schematic diagram of pile pulling process of the job practices of a kind of pile pulling of the present invention;
Among the figure: tripod 1, pipe bit head 2, drilling pipe 3, old pile foundation 4, movable pulley 5, angle steel pile 6, steel wire loop 7, fork truck 8.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is done and to describe in further detail.
As shown in the figure: in the job practices of a kind of pile pulling of the present invention, tripod 1, pipe bit head 2, drilling pipe 3, old pile foundation 4, movable pulley 5, angle steel pile 6, steel wire loop 7, fork truck 8.
The job practices of a kind of pile pulling of the present invention comprises the steps:
Prepare before A, the pile pulling:
Select the tonnage of fork truck 8 according to the weight of old pile foundation 4, fork truck 8 is arranged on old pile foundation 4 limits; Set up tripod 1, and an angle of tripod 1 is fixed on ground, described tripod 1, made by seamless steel pipe, its wall thickness and height determine that according to the degree of depth of the old foundation pile of preparing to pull out 4 tripod 1 is provided with base, and described base is fixed by expansion bolt and ground.Movable pulley 5 is installed in center at tripod 1, by movable pulley 5 with pipe bit head 2 sling be installed in old pile foundation 4 directly over, drilling pipe 3 is installed in pipe bit head 2 lower ends, the old pile foundation of drilling pipe 3 perpendicular alignmnets 4 centers of circle, the internal diameter of described drilling pipe 3 is not less than the external diameter of old pile foundation 4;
B, the old pile foundation 4 of separation:
By tripod 1 pipe bit head 2 and drilling pipe 3 suspentions are lifted, the old pile foundation 4 that 3 mouthfuls of perpendicular alignmnets of drilling pipe are residual, start pipe bit head 2, utilize drilling pipe 3 rotation, press down, cutting and separate old pile foundation 4 and on every side earth, the degree of depth that drilling pipe 3 pierces is not less than the degree of depth of old pile foundation 4, extracts drilling pipe 3 again out and removes rig head 2; Then with two steel wire loops 7, along the head of old pile foundation 4 down, in the slit by cutting and separating, old pile foundation 4 is fixedly entangled firm;
C, pile pulling:
Steel wire loop 7 is fixed on the lower end of old pile foundation 4, and an end of steel wire loop 7 is fixed on the jaw of fork truck 8, and the other end passes movable pulley 5 and angle steel pile 6 repeats to fix by 8 word interior extrapolation methods, and the position of the old pile foundation 4 of described angle steel pile 6 distances is not less than 5 meters; Fork truck 8 and movable pulley 5 alternately cooperate firmly, and pile pulling begins, and fork truck 8 and movable pulley 5 replace stressed lifting, tighten up wire rope at lifting process; When fork truck 8 is lifted to certain altitude, movable pulley 5 tightens up thereupon, and make steel wire loop 7 be in stress always, at this time fork truck tightens up wire rope again, promotes again, when old pile foundation 4 upper ends propose ground, to fasten rope in old pile foundation 4 upper ends, fell and do traction for extracting the back pile foundation, and then old pile foundation 4 was extracted, traction was fallen; Timely backfill, compacting are wanted in the hole of the old pile foundation 4 that stays at last, and the personnel of preventing fall.
The job practices of a kind of pile pulling of the present invention is used in crane and the unapproachable job site of main equipment, can carry out old pile foundation efficiently and extract work, and is safe and reliable, and the efficiency of construction height is workable, can reduce construction cost.

Claims (5)

1. the job practices of a pile pulling is characterized in that, comprises the steps:
Prepare before A, the pile pulling:
Select the tonnage of fork truck (8) according to the weight of old pile foundation (4), fork truck (8) is arranged on old pile foundation (4) limit; Set up tripod (1), an angle of tripod (1) is fixed on ground, movable pulley (5) is installed in center at tripod (1), by movable pulley (5) with pipe bit head (2) sling be installed in old pile foundation (4) directly over, drilling pipe (3) is installed in pipe bit head (2) lower end, the old pile foundation of drilling pipe (3) perpendicular alignmnet (4) center of circle;
B, separate old pile foundation (4):
Start pipe bit head (2) and drive drilling pipe (3) brill down, the degree of depth that drilling pipe (3) pierces is not less than the degree of depth of old pile foundation (4), extracts drilling pipe (3) again out and removes rig head (2);
C, pile pulling:
Steel wire loop (7) centre position is fixed on the lower end of old pile foundation (4), and an end of steel wire loop (7) is fixed on the jaw of fork truck (8), and the other end is fixed on the angle steel pile (6) by movable pulley (5); Fork truck (8) and movable pulley (5) alternately cooperate firmly then, and old pile foundation (4) is extracted.
2. the job practices of pile pulling according to claim 1 is characterized in that, described tripod (1) is provided with base, and described base is fixed by expansion bolt and ground.
3. the job practices of pile pulling according to claim 1 is characterized in that, the internal diameter of described drilling pipe (3) is not less than the external diameter of old pile foundation (4).
4. the job practices of pile pulling according to claim 1 is characterized in that, the position of described angle steel pile (6) the old pile foundation of distance (4) is not less than 5 meters.
5. the job practices of pile pulling according to claim 1 is characterized in that, described steel wire loop (7) is that 8 words are overlapping fixing with angle steel pile (6).
CN201310253199.4A 2013-06-25 2013-06-25 A kind of construction method of pile pulling Active CN103334433B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310253199.4A CN103334433B (en) 2013-06-25 2013-06-25 A kind of construction method of pile pulling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310253199.4A CN103334433B (en) 2013-06-25 2013-06-25 A kind of construction method of pile pulling

Publications (2)

Publication Number Publication Date
CN103334433A true CN103334433A (en) 2013-10-02
CN103334433B CN103334433B (en) 2015-11-18

Family

ID=49242632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310253199.4A Active CN103334433B (en) 2013-06-25 2013-06-25 A kind of construction method of pile pulling

Country Status (1)

Country Link
CN (1) CN103334433B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6284255B1 (en) * 2017-11-15 2018-02-28 株式会社徳永組 Pile cap and pile drawing method
JP6284253B1 (en) * 2017-06-15 2018-02-28 株式会社徳永組 Pile catcher and pile removal method using pile catcher
CN114482048A (en) * 2022-02-17 2022-05-13 董超 Pile extractor for hydraulic engineering

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007332559A (en) * 2006-06-12 2007-12-27 Riyouken Kiso Kk Removal method for existing underground pile
CN101130988A (en) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 Pile extractor and construction method thereof
CN101173517A (en) * 2006-10-31 2008-05-07 上海市基础工程公司 Pile-pulling construction method
CN101358452A (en) * 2007-07-30 2009-02-04 王薇 Construction method and construction equipment of total rotary rapid cutting barrier clearance and pile extracting
JP3159275U (en) * 2010-02-24 2010-05-13 博 小野寺 Pile extraction jig
CN202090349U (en) * 2011-05-19 2011-12-28 中天建设集团有限公司 Device for removing square pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007332559A (en) * 2006-06-12 2007-12-27 Riyouken Kiso Kk Removal method for existing underground pile
CN101173517A (en) * 2006-10-31 2008-05-07 上海市基础工程公司 Pile-pulling construction method
CN101358452A (en) * 2007-07-30 2009-02-04 王薇 Construction method and construction equipment of total rotary rapid cutting barrier clearance and pile extracting
CN101130988A (en) * 2007-08-16 2008-02-27 江苏华东建设基础工程总公司 Pile extractor and construction method thereof
JP3159275U (en) * 2010-02-24 2010-05-13 博 小野寺 Pile extraction jig
CN202090349U (en) * 2011-05-19 2011-12-28 中天建设集团有限公司 Device for removing square pile

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6284253B1 (en) * 2017-06-15 2018-02-28 株式会社徳永組 Pile catcher and pile removal method using pile catcher
JP2019002195A (en) * 2017-06-15 2019-01-10 株式会社徳永組 Pile catcher and pile extraction method using the same
JP6284255B1 (en) * 2017-11-15 2018-02-28 株式会社徳永組 Pile cap and pile drawing method
JP2019002265A (en) * 2017-11-15 2019-01-10 株式会社徳永組 Pile cap, and method for pulling out pile
CN114482048A (en) * 2022-02-17 2022-05-13 董超 Pile extractor for hydraulic engineering
CN114482048B (en) * 2022-02-17 2024-05-03 天津市津水建筑工程有限公司 Pile extractor for hydraulic engineering

Also Published As

Publication number Publication date
CN103334433B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN101736746B (en) Construction method for vibrator pipe sinking high-pressure grouting underpinning pile extracting
CN105649083B (en) The clear stake device of the disposable rotary-cutting type of full-sleeve and its clear piling method
CN201502061U (en) Recoverable prestressing anchor rope with double anchor heads
CN106149683A (en) A kind of cast-in-place pile construction method using double casing to pass through deep metalling
CN1963044A (en) Construction method for withdrawal of waste pile
CN103334433B (en) A kind of construction method of pile pulling
CN105332376A (en) Hydraulic manipulator pile-pulling clamping device and pile pulling machine
CN103643673B (en) Steel-pipe pile and construction method can be recycled in self-advancing type
CN203270578U (en) Underground pile foundation pulling device with steel wire rope sleeve clamp
CN101892764B (en) Method for building enclosing wall
CN204343771U (en) A kind of convenient line bar
CN202090349U (en) Device for removing square pile
CN201635074U (en) Ground anchor
CN202090346U (en) Movable combined type ground anchor
CN201915839U (en) Drilling tool of salvage rotary drilling rig
CN207047834U (en) A kind of construction system of hollow preformed pile
CN202157743U (en) Drop hammer type accurate position impact perforator
CN203270575U (en) Bored concrete pile pile-head breaking combined loosening device
CN204780894U (en) Can dismantle steel protects wound packages and puts
CN102852157B (en) Manual hole pile digging method employing top-fixing water drilling method
CN204615274U (en) A kind of actinobacillus device of transmission line
CN203559420U (en) Pile splicing construction device under quicksand geological conditions
CN210341918U (en) Novel vibration pile sinking device
CN102296610B (en) Device for removing square pile and construction method thereof
CN203383224U (en) Tension-free cast-in-place pile structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant