CN103306209A - Prefabricated bridge concrete pouring rainproof construction method and device thereof - Google Patents

Prefabricated bridge concrete pouring rainproof construction method and device thereof Download PDF

Info

Publication number
CN103306209A
CN103306209A CN201310280830XA CN201310280830A CN103306209A CN 103306209 A CN103306209 A CN 103306209A CN 201310280830X A CN201310280830X A CN 201310280830XA CN 201310280830 A CN201310280830 A CN 201310280830A CN 103306209 A CN103306209 A CN 103306209A
Authority
CN
China
Prior art keywords
rainproof
template
awning
hopper
receiving hopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310280830XA
Other languages
Chinese (zh)
Other versions
CN103306209B (en
Inventor
黄林
陈勇
王志强
孙凤栋
闫晓光
程秀茹
李海峰
吴仁友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN201310280830.XA priority Critical patent/CN103306209B/en
Publication of CN103306209A publication Critical patent/CN103306209A/en
Application granted granted Critical
Publication of CN103306209B publication Critical patent/CN103306209B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention belongs to the technical field of prefabricated bridge concrete pouring and particularly relates to a prefabricated bridge concrete pouring rainproof construction method and a device thereof. The invention solves the problem that the construction of the existing prefabricated bridge is seriously affected by rainy seasons. The device comprises a template rainproof awning, a hopper and a rainproof mobile pouring trolley, wherein the template rainproof awning comprises a template rainproof awning framework and a template rainproof awning roof; a hopper rainproof cap is arranged at the top of the hopper; the rainproof mobile pouring trolley comprises a walking trolley, a bracket platform, a receiving hopper, a fixed chute and a rotating chute. The method comprises the steps: covering the template rainproof awning, conveying concrete by using the hopper with the rainproof cap and pouring the concrete through the rainproof mobile pouring trolley. The prefabricated bridge concrete pouring rainproof construction method and the device thereof have the benefits that the rainproof pouring construction method of prefabricated bridge concrete through the bridge template rainproof awning, the rainproof mobile pouring platform and other tools is initiatively utilized, the problem of prefabricated bridge concrete pouring construction in rainy seasons is solved, and the construction quality of the prefabricated bridge concrete in the rainy seasons is ensured.

Description

The rainproof job practices of precast bridge concreting and device thereof
Technical field
The invention belongs to the technical field of precast bridge concreting, be specifically related to the rainproof job practices of a kind of precast bridge concreting and device thereof.
Background technology
The general length of precast bridge is longer, and concrete quantity is large, and necessary continuous placing, and the time of building is long.When rainy season construction, often ran into and built the centre in the past, rained suddenly.Owing to only having the simple measures such as tarpaulin covering, often cause the water inlet of beam body concrete, even concreting is forced to interrupt, have a strong impact on concrete quality.
Summary of the invention
The present invention is subjected to affect serious problem rainy season in order to solve existing prefabricated bridge construction, and the rainproof job practices of a kind of precast bridge concreting and device thereof are provided.
The present invention adopts following technical scheme to realize: the rainproof construction equipment of precast bridge concreting, comprise that template awning, hopper and rainproof movement build chassis,
Described template awning is along the elongated layout of template total length, the template awning comprises template awning skeleton and template awning Peng Ding, the column lower end of template awning skeleton is connected on the bridge formwork bracket upright post, template awning skeleton top arranges template awning Peng Ding, the single slope of template awning Peng Ding arranges, corresponding bridge formwork from-inner-to-outer tilts, and template awning Peng Ding chooses template in two ends;
Described hopper top arranges the hopper rainhat, and the hopper rainhat is taper canopy structure,
Described rainproof movement is built chassis and is comprised running truck, rack platform, receiving hopper, fixed chute and rotating chute,
Rack platform is installed on the running truck, is provided with operating platform on the rack platform, and the rack platform top arranges frame top awning lid;
Receiving hopper is installed in rack platform top, and the receiving hopper top arranges movable receiving hopper rainhat,
Fixed chute is obliquely installed and is fixedly mounted on the rack platform, fixed chute suitable for reading under the discharging opening of receiving hopper, and the end opening of fixed chute is on rotating chute is suitable for reading;
Rotating chute is obliquely installed and rotates and is installed on the rack platform, and the height of rotating chute end opening is higher than the upper open height of bridge formwork.
Described running truck bottom arranges road wheel, and the track of road wheel is the rail that is layed in the bridge formwork inboard, and respective carter place, running truck two ends arranges respectively the rail clamping device of two pincerlike structures.
30 ° of the groove body horizontal slopes of described fixed chute and rotating chute.
Described receiving hopper rainhat is the umbrella-shaped structure that type steel skeleton consists of, and receiving hopper rainhat one side is provided with an axle sleeve, is set in to be arranged in the rotating shaft that frame top rain-proof fluffied covers, and receiving hopper rainhat opposite side pushes up rainproof overcanopy by latch and frame and is connected.
The cell body upper end of described rotating chute is fixed on the rotating shaft, cell body is divided into a pole, the upper and lower end of pole is individually fixed in cell body and the rotating shaft, the upper and lower end of rotating shaft is installed in respectively in the upper and lower bearing support, top chock is installed on the rack platform bottom, and step is installed on running truck top.
Described rail clamping device is comprised of two clamping plates and an adjusting screw, and there is the connecting bolt hole clamping plate upper end, and rail clamping device is installed on the horizontal rotating shaft of running truck bottom by bolt hole.
The rainproof job practices of precast bridge concreting is finished based on the above-mentioned rainproof construction equipment of precast bridge concreting, and its step is as follows:
1), the template awning hides,
The column lower end of template awning skeleton is by making plug by bridge formwork bracket upright post size suitable for reading, with the grafting suitable for reading of bridge formwork bracket upright post, template awning Peng Ding arranges some joints along the elongated direction of template, overlap between the adjacent segments, press the overlap joint order from beam forms one end lifting awning sections;
2), with band rainhat hopper transportation concrete,
Hopper advances to remove behind the agitator hopper rainhat tipping concrete, fills concrete bonnet elevating hopper rainhat, then with transport vehicle hopper is transported to and waits to build by the concrete beam;
3), rainproof movement builds the chassis concreting,
Before running truck moves, pack up rail clamping device, and rotating chute is rotated to groove body and bridge formwork parastate, then start chassis, running truck is moved to the position that bridge formwork needs concreting;
After running truck is in place, putting down rail clamping device is clamped on the rail, and rotating chute rotated to groove body and bridge formwork upright position, begin to lift concrete hopper to running truck receiving hopper top, remove the rainhat on the receiving hopper, open concrete hopper bottom valve and unload concrete in receiving hopper, concrete slips by fixed chute and swivel chute and delivers in the bridge formwork, carries out concreting.
The relative prior art of the present invention has following beneficial effect:
1, novel, pioneering utilize bridge formwork awning, rainproof movement to build the frock such as chassis to carry out the concrete rainproof pouring construction method of precast bridge, solve the rainy season construction problem of precast bridge concreting, guaranteed the precast bridge concrete quality of rainy season construction.
2, rainproof measure is considered comprehensively.From concrete transportation, enter the concreting overall processes such as mould, template protection and adopt an effective measure, rainproof respond well.Can uninterruptedly carry out on rainy day the concrete pouring construction of precast bridge.Therefore for accelerating construction progress, guarantee the construction period, play very important effect.
3, build chassis project organization compactness, be skillfully constructed.At chassis fixed chute and rotating chute are set dexterously, adopt relay mode delivering concrete.And the rotation by rotating chute, solve chassis and moved contradiction with two operating modes of concrete conveyance, realized the function of expection.
4, frock can be had enough to meet the need use.After bridge concrete was built use on the pedestal, all frocks can be transferred to rapidly another pedestal and install and use.Therefore greatly reduce equipment investment, improved operating efficiency.
5, safety precautions is arranged.Take that the awning column lower end is firmly inserted soldier suitable for reading, adopt the storage battery low-voltage electricity to drive chassis, the fixedly measure such as chassis of rail clamping device is set, can effectively ensure construction safety.
Description of drawings
Fig. 1 is the structural representation of template awning,
Fig. 2 is the structural representation of hopper rainhat,
Fig. 3 is the I-I sectional drawing of Fig. 2,
Fig. 4 is the structural representation that chassis is built in rainproof movement,
Fig. 5 is the view of building that chassis is built in rainproof movement,
Fig. 6 is the mobile status schematic diagram that chassis is built in rainproof movement,
Fig. 7 is receiving hopper rainhat structural representation,
Fig. 8 is the I-I sectional drawing of Fig. 7,
Fig. 9 is the rail clamping device structure schematic diagram,
Figure 10 is the lateral view of Fig. 6,
Among the figure: 1-running truck, 2-rail clamping device, 3-rack platform, 4-frame top awning lid, 5-rotating chute, 6-rotating shaft, the 7-fixed chute, 8-receiving hopper, 9-receiving hopper rainhat, the column of 10-template awning skeleton, 11-template awning Peng Ding, 12-bridge formwork, 13-bridge formwork bracket upright post, 14-hopper rainhat type steel skeleton, 15-hopper rainhat color steel top, 16-pole;
9.1-type steel skeleton, 9.2-steel plate top, 9.3-axle sleeve, 9.4-latch, 9.5-handle;
2.1-clamping plate, 2.2-adjusting screw, 2.3-bolt hole.
The specific embodiment
By reference to the accompanying drawings the specific embodiment of the present invention is described further.
The rainproof construction equipment of precast bridge concreting comprises that template awning, hopper and rainproof movement build chassis.
As shown in Figure 1, described template awning is along the elongated layout of template total length, the template awning comprises template awning skeleton and template awning Peng Ding, template awning skeleton lower end is connected on the bridge formwork bracket upright post, template awning skeleton top arranges template awning Peng Ding, the single slope of template awning Peng Ding arranges, and corresponding bridge formwork from-inner-to-outer tilts, and template awning Peng Ding chooses template in two ends.
Shown in Fig. 2,3, described hopper top arranges the hopper rainhat, and the hopper rainhat is taper canopy structure.
Rainproof movement is built chassis and is comprised of running truck, rack platform, receiving hopper, fixed chute, rotating chute five parts.See accompanying drawing 4,5,6.
1, running truck
Running truck is electric track flatcar, is driven by battery.Track at the steel rail laying of bridge formwork inboard is walked, can be to contraposition discharging between each sections of bridge length direction.The chassis two ends respectively are provided with two rail clamping devices.Rail clamping device is a pincerlike structure.Formed by two clamping plates and an adjusting screw.There is connecting screw hole clamping plate upper ends, by screw rail clamping device is installed on the horizontal rotating shaft under the running truck.Rail clamping device can rotate up and down around axle.During the running truck traveling, rail clamping device is sling with hook, leaves rail level.After running truck is in place, put down rail clamping device, outwards adjusting screw separates by tread two clamping plate, and when treating that the clamping plate head drops down onto rail web, inside adjusting screw is until clamping plate head clamping rail web.Rail clamping device structure is seen Fig. 9,10.
2, rack platform
Rack platform is made with shaped steel, is installed on the running truck, for miscellaneous equipment provides installing space.Rack platform is provided with operating platform, for workman's operation provides the scope of operation.The rack platform top prevents that with welded steel plate frame top awning lid rainwater from entering chute.
3, receiving hopper
Receiving hopper forms with welded steel plate, is installed in rack platform top, is used for the concrete of unloading.Movable steel receiving hopper rainhat is set above the receiving hopper, removes during the concrete bucket discharging, unsnatch on the material bonnet.The receiving hopper rainhat is a umbrella-shaped structure, and the one side is provided with an axle sleeve, can be set in the rotating shaft that rain-proof fluffied covers.Promote handle during use, just the receiving hopper rainhat can be pivoted and remove or cover.Its opposite side is equipped with latch, can after the receiving hopper rainhat cover, the receiving hopper rainhat be fixed in rain-proof fluffied cover; Receiving hopper rainhat structure is seen Fig. 7,8.
4, fixed chute
Fixed chute is fixedly mounted on the rack platform.30 ° of chute groove body horizontal slopes.Fixed chute is suitable for reading under the discharging opening of receiving hopper, and end opening is on rotating chute is suitable for reading.Concrete slips by fixed chute from the receiving hopper outlet and delivers to rotating chute.
5, rotating chute
Rotating chute forms with welded steel plate, is obliquely installed and rotates to be installed on the rack platform.The cell body upper end is welded on the rotating shaft.Cell body is divided into a pole, and the upper and lower side of pole is welded in respectively in cell body and the rotating shaft.The upper and lower end of rotating shaft is installed in the upper and lower bearing support.Top chock is installed on the rack platform bottom, and step is installed on running truck top.Therefore, cell body and rotating shaft can be done 180 ° of rotations together.30 ° of chute groove body horizontal slopes.The height of rotating chute end opening is higher than the upper open height of bridge formwork, and the position can reach in the middle of the bridge web.
The rainproof job practices construction sequence of precast bridge concreting:
One), step 1: hide template with awning
Intake in the template when preventing from raining, at bridge formwork awning is installed.
1, awning structure
Awning is done skeleton with shaped steel, and color steel is Peng Ding, and lean-to drainage is discharged to the template outside.Rainproof canopy is along the elongated layout of template total length.For ease of lifting, be divided into several sections of.Between joint and the joint certain overlap joint is arranged.The awning top board is chosen the template certain width.The rain shade column lower end is made plug by falsework size suitable for reading.
2, awning is installed
Before the beam body concrete is built, press the overlap joint order from beam forms one end lifting awning sections, with awning column lower end plug insert falsework suitable for reading in, be connected firmly.See accompanying drawing 1.
Two), step 2: with band rainhat hopper transportation concrete
When preventing concrete hopper transportation concrete, the hopper transportation concrete with rainhat is adopted in water inlet in the hopper.
Rainhat is a taper canopy structure.Make skeleton with angle steel, the above covers the color steel top.Hopper is removed rainhat tipping concrete after advancing agitator, fills rainhat on the concrete bonnet.Then with transport vehicle hopper is transported to and waits to build by the concrete beam.
Three), step 3: build the chassis concreting with rainproof movement
Because awning has been installed above the bridge formwork hides template top, so concrete can not be built from the lifting of template top.Build for the solution concrete enters mould, adopted the voluntarily rainproof movement of development to build chassis from the beam sides concreting.
1, trolley structure is built in rainproof movement
Rainproof movement is built chassis and is comprised of running truck, rack platform, receiving hopper, fixed chute, rotating chute five parts.
Running truck is electric track flatcar, drives with battery, walks at the track of the steel rail laying of bridge formwork inboard.Can contraposition discharging between each sections of bridge length direction.Chassis has rail clamping device.
Support is made with shaped steel, is installed on the running truck.Support is provided with operating platform, for workman's operation provides the scope of operation.The frame overhead welding has steel plate awning lid.Unload concrete receiving hopper and fixed chute that welded steel plate becomes are installed on the support.The discharging opening of receiving hopper is to suitable for reading at fixed chute, and concrete slips by fixed chute from the receiving hopper outlet and delivers to rotating chute.
Receiving hopper is provided with the receiving hopper rainhat.The receiving hopper rainhat is rotatable by the rotating shaft that is installed on frame top rain-proof fluffied and covers, and can fix by latch, and rotating chute forms with welded steel plate.Be installed in the rotating shaft of being fixed on the chassis capable of rotating 180 deg.
2, the chassis use is built in rainproof movement
Before chassis moves, pack up rail clamping device, and rotating chute is rotated to groove body and beam forms parastate, collide to avoid chute and template awning column.Then start chassis, chassis is moved to the position that bridge formwork needs concreting.
After chassis is in place, puts down rail clamping device and be clamped on the rail, and rotating chute is rotated to groove body and beam forms upright position.At this moment, can begin to lift concrete hopper to chassis receiving hopper top, remove rainhat on the receiving hopper, open concrete hopper bottom valve and in receiving hopper, unload concrete.Concrete slips by fixed chute and swivel chute and delivers in the bridge formwork, carries out concreting.
The mobile chassis of building uses view to see accompanying drawing 5,6.

Claims (7)

1. rainproof construction equipment of precast bridge concreting is characterized in that comprising that template awning, hopper and rainproof movement build chassis,
Described template awning is along the elongated layout of template total length, the template awning comprises template awning skeleton and template awning Peng Ding (11), column (10) lower end of template awning skeleton is connected on the bridge formwork (12), template awning skeleton top arranges template awning Peng Ding (11), the single slope of template awning Peng Ding (11) arranges, corresponding bridge formwork (12) from-inner-to-outer tilts, and template awning Peng Ding (11) chooses template in two ends;
Described hopper top arranges receiving hopper rainhat (9), and receiving hopper rainhat (9) is taper canopy structure;
Described rainproof movement is built chassis and is comprised running truck (1), rack platform (3), receiving hopper (8), fixed chute (7) and rotating chute (5),
Rack platform (3) is installed on the running truck (1), and rack platform is provided with operating platform on (3), and rack platform (3) top arranges frame top awning lid (4),
Receiving hopper (8) is installed in rack platform (3) top, and receiving hopper (8) top arranges movable receiving hopper rainhat (9),
Fixed chute (7) is obliquely installed and is fixedly mounted on the rack platform (3), fixed chute (7) suitable for reading under the discharging opening of receiving hopper (8), and the end opening of fixed chute (7) is on rotating chute (5) is suitable for reading;
Rotating chute (5) is obliquely installed and rotates and is installed on the rack platform (3), and the height of rotating chute (5) end opening is higher than the upper open height of bridge formwork (12).
2. the rainproof construction equipment of precast bridge concreting according to claim 1, it is characterized in that described running truck (1) bottom arranges road wheel, the track laying of road wheel is on the rail of bridge formwork (12) inboard, and respective carter place, running truck (1) two ends arranges respectively the rail clamping device (2) of two pincerlike structures.
3. the rainproof construction equipment of precast bridge concreting according to claim 1 and 2 is characterized in that 30 ° of the groove body horizontal slopes of described fixed chute (7) and rotating chute (5).
4. the rainproof construction equipment of precast bridge concreting according to claim 3, it is characterized in that the umbrella-shaped structure that receiving hopper rainhat (9) consists of for type steel skeleton (9.1), receiving hopper rainhat (9) one sides are provided with an axle sleeve (9.3), be set in and be arranged on frame and push up in the rotating shaft on the rainproof overcanopy (4), receiving hopper rainhat (9) opposite side pushes up rainproof overcanopy (4) by latch (9.4) and frame and is connected.
5. the rainproof construction equipment of precast bridge concreting according to claim 4, the cell body upper end that it is characterized in that described rotating chute is fixed on the rotating shaft (6), cell body is divided into a pole (16), the upper and lower end of pole (16) is individually fixed in cell body and the rotating shaft, the upper and lower end of rotating shaft is installed in respectively in the upper and lower bearing support, top chock is installed on rack platform (3) bottom, and step is installed on running truck (1) top.
6. the rainproof construction equipment of precast bridge concreting according to claim 5, it is characterized in that described rail clamping device is comprised of two clamping plates (2.1) and an adjusting screw (2.2), there is connecting bolt hole (2.3) clamping plate (2.1) upper end, and rail clamping device is installed on the horizontal rotating shaft of running truck bottom by bolt hole (2.3).
7. the rainproof job practices of precast bridge concreting is finished based on the rainproof construction equipment of precast bridge concreting as claimed in claim 6, and its step is as follows:
1), the template awning hides,
Plug is made by bridge formwork bracket upright post (13) size suitable for reading in template awning skeleton column (10) lower end, with bridge formwork bracket upright post (13) grafting suitable for reading, template awning Peng Ding (11) arranges some joints along the elongated direction of template, overlap between the adjacent segments, press the overlap joint order from beam forms one end lifting awning sections;
2), with band rainhat hopper transportation concrete,
Receiving hopper (8) advances to remove behind the agitator receiving hopper rainhat (9) tipping concrete, fills receiving hopper rainhat on the concrete bonnet, then with transport vehicle hopper is transported to and waits to build by the concrete beam;
3), rainproof movement builds the chassis concreting,
Before running truck (1) is mobile, packs up rail clamping device (2), and rotating chute (5) is rotated to groove body and bridge formwork (12) parastate, then start chassis, running truck is moved to the position that bridge formwork needs concreting;
After running truck (1) is in place, putting down rail clamping device (2) is clamped on the rail, and rotating chute (5) rotated to groove body and bridge formwork (12) upright position, begin to lift concrete hopper to running truck receiving hopper (8) top, remove the rainhat on the receiving hopper, open concrete hopper bottom valve and unload concrete in receiving hopper, concrete slips by fixed chute (7) and rotating chute (5) and delivers in the bridge formwork (12), carries out concreting.
CN201310280830.XA 2013-07-05 2013-07-05 The rainproof construction method of precast bridge concreting and device thereof Active CN103306209B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310280830.XA CN103306209B (en) 2013-07-05 2013-07-05 The rainproof construction method of precast bridge concreting and device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310280830.XA CN103306209B (en) 2013-07-05 2013-07-05 The rainproof construction method of precast bridge concreting and device thereof

Publications (2)

Publication Number Publication Date
CN103306209A true CN103306209A (en) 2013-09-18
CN103306209B CN103306209B (en) 2015-12-23

Family

ID=49131896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310280830.XA Active CN103306209B (en) 2013-07-05 2013-07-05 The rainproof construction method of precast bridge concreting and device thereof

Country Status (1)

Country Link
CN (1) CN103306209B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988262A (en) * 2017-05-12 2017-07-28 孙茂林 Airport runways ice and snow method for quickly eliminating
CN107725075A (en) * 2017-11-09 2018-02-23 洛阳高飞桥隧机械有限公司 A kind of application method of tunnel ditch cable trough chassis walking lining cutting device
CN109203218A (en) * 2018-11-02 2019-01-15 姚晓宁 A kind of railway prefabricated T beam concreting protection canopy
CN109577198A (en) * 2018-11-07 2019-04-05 同济大学 Fastener Fabricated platform awning skeleton suitable for section assembling construction bridges
CN110306737A (en) * 2019-07-09 2019-10-08 周丽博 A kind of precast bridge concreting rain-proof constructing device
CN113216605A (en) * 2021-05-16 2021-08-06 无锡住信建筑构件有限公司 Assembly type building node based on assembly type building energy-saving component
CN117225838A (en) * 2023-11-13 2023-12-15 中铁三局集团建筑安装工程有限公司 Self-propelled robot for cleaning operation of ultra-long large-diameter heating pipeline
CN107725075B (en) * 2017-11-09 2024-05-03 洛阳高飞桥隧机械有限公司 Use method of tunnel ditch cable trough trolley walking lining device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07180367A (en) * 1993-12-22 1995-07-18 Shimizu Corp Movable roof for casting concrete
JP3177127B2 (en) * 1995-05-16 2001-06-18 照夫 羽取 Precast concrete roadside gutters
JP2006188838A (en) * 2004-12-29 2006-07-20 Koji Yomogihara Form coat
CN201850711U (en) * 2010-09-04 2011-06-01 中铁十一局集团第二工程有限公司 Rainproof sun shelter
CN202594209U (en) * 2012-05-24 2012-12-12 青岛港(集团)有限公司 Automatic rain-proof cover for hoppers
CN102888993A (en) * 2012-09-17 2013-01-23 中国华冶科工集团有限公司 Rotating chute
CN203452006U (en) * 2013-07-05 2014-02-26 中铁三局集团有限公司 Rainproof construction device poured by precast bridge concrete

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07180367A (en) * 1993-12-22 1995-07-18 Shimizu Corp Movable roof for casting concrete
JP3177127B2 (en) * 1995-05-16 2001-06-18 照夫 羽取 Precast concrete roadside gutters
JP2006188838A (en) * 2004-12-29 2006-07-20 Koji Yomogihara Form coat
CN201850711U (en) * 2010-09-04 2011-06-01 中铁十一局集团第二工程有限公司 Rainproof sun shelter
CN202594209U (en) * 2012-05-24 2012-12-12 青岛港(集团)有限公司 Automatic rain-proof cover for hoppers
CN102888993A (en) * 2012-09-17 2013-01-23 中国华冶科工集团有限公司 Rotating chute
CN203452006U (en) * 2013-07-05 2014-02-26 中铁三局集团有限公司 Rainproof construction device poured by precast bridge concrete

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988262A (en) * 2017-05-12 2017-07-28 孙茂林 Airport runways ice and snow method for quickly eliminating
CN106988262B (en) * 2017-05-12 2019-03-05 孙茂林 Airport runways ice and snow method for quickly eliminating
CN107725075A (en) * 2017-11-09 2018-02-23 洛阳高飞桥隧机械有限公司 A kind of application method of tunnel ditch cable trough chassis walking lining cutting device
CN107725075B (en) * 2017-11-09 2024-05-03 洛阳高飞桥隧机械有限公司 Use method of tunnel ditch cable trough trolley walking lining device
CN109203218A (en) * 2018-11-02 2019-01-15 姚晓宁 A kind of railway prefabricated T beam concreting protection canopy
CN109577198A (en) * 2018-11-07 2019-04-05 同济大学 Fastener Fabricated platform awning skeleton suitable for section assembling construction bridges
CN110306737A (en) * 2019-07-09 2019-10-08 周丽博 A kind of precast bridge concreting rain-proof constructing device
CN113216605A (en) * 2021-05-16 2021-08-06 无锡住信建筑构件有限公司 Assembly type building node based on assembly type building energy-saving component
CN117225838A (en) * 2023-11-13 2023-12-15 中铁三局集团建筑安装工程有限公司 Self-propelled robot for cleaning operation of ultra-long large-diameter heating pipeline
CN117225838B (en) * 2023-11-13 2024-01-23 中铁三局集团建筑安装工程有限公司 Self-propelled robot for cleaning operation of ultra-long large-diameter heating pipeline

Also Published As

Publication number Publication date
CN103306209B (en) 2015-12-23

Similar Documents

Publication Publication Date Title
CN103306209B (en) The rainproof construction method of precast bridge concreting and device thereof
CN105952482B (en) Self-propelled tunnel inverted arch lining trolley
CN108643938B (en) Smooth surface shotcrete supporting structure of deep coal mine tunnel and construction method thereof
CN103302741B (en) Chassis is built in the rainproof movement of precast bridge concrete
CN206428551U (en) A kind of repeatable assembled engagement temporary pavement plate utilized of monoblock type
CN205638490U (en) A portable platform truck that is used for subway station tread wind channel to pour
CN108858723A (en) The novel intensive construction technology of highway prefabricated case beam
CN205618174U (en) Box culvert platform truck
CN203331220U (en) Rainproof moving pouring trolley for prefabricated bridge concrete
CN106223983A (en) A kind of diversion tunnel inclined shaft, flat section tunneling boring primary steel mould trolley
CN104060860B (en) A kind of sectional telescopic rain-proof shelter for precast concrete T-beam and using method
CN203452006U (en) Rainproof construction device poured by precast bridge concrete
CN106050268A (en) Steel mould trolley for concrete lining of rounded rectangle cross section tunnel
JP6636955B2 (en) Portal scraper with carrier structure based on truss structure
CN207671172U (en) A kind of construction rail mounted dumper
CN201546176U (en) Curtain board installing trolley
CN210456001U (en) Clear storehouse device of cement storehouse
CN104527748A (en) Concrete trolley
CN111188633A (en) Rapid construction method for secondary lining of small-section tunnel
CN216193884U (en) Road jar seam device for municipal construction
CN108612127A (en) A kind of construction method of pipe gallery construction
CN212052347U (en) Mountain area segment beam conveyer
CN109986684B (en) Template device and system for streamlined production of concrete twisted blocks
CN205955750U (en) Rounded rectangle cross -section tunnel steel mould trolley for concrete lining
CN209817447U (en) Concrete pouring device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant