CN103291322A - 一种双线铁路隧道冬季混凝土施工供热防冻方法 - Google Patents
一种双线铁路隧道冬季混凝土施工供热防冻方法 Download PDFInfo
- Publication number
- CN103291322A CN103291322A CN2013101653072A CN201310165307A CN103291322A CN 103291322 A CN103291322 A CN 103291322A CN 2013101653072 A CN2013101653072 A CN 2013101653072A CN 201310165307 A CN201310165307 A CN 201310165307A CN 103291322 A CN103291322 A CN 103291322A
- Authority
- CN
- China
- Prior art keywords
- floor heating
- feed bin
- heat supply
- main
- boiler
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Road Paving Structures (AREA)
Abstract
一种双线铁路隧道冬季混凝土施工供热防冻方法,涉及一种供热防冻方法,由原料仓、地暖供热管道、锅炉房(11)、循环泵(14)、风机(18)和风管(6),在原料仓底下设置地暖供热管(7),通过锅炉房(11)内的循环泵(14)使热水在地暖供热管(7)内进行循环,再利用风机(18)和风管(6)的排烟,以此来达到混凝土材料的保温和改善隧道内空气的目的;本发明实用性极强,而且安全可靠,操作极为方便,能持续对隧道内的原料仓及工作环境进行保温,避免了混凝土的长途运输,保证了冬季隧道工程大规模的混凝土施工,有效的解决了保温和改善作业环境的问题。
Description
【技术领域】
本发明涉及一种供热防冻方法,尤其是涉及一种双线铁路隧道冬季混凝土施工供热防冻方法。
【背景技术】
已知的,我国冻土面积分布非常广泛,其中多年冻土的面积约有207万平方公里,约占国土面积的21.5%,在这些地区进行隧道修建时,特别是隧道工程冬期施工时需要采取相应的防冻措施,如在混凝土拌合站内建立预热保温棚对混凝土原材料进行加热,对混凝土输送设备进行改造使之达到保温效果,在隧道的洞口安设保温门帘等等。
但混凝土拌合站属于临建工程,一般采用彩钢板施工,即使采取保温措施也存在严重的热量耗散,热能利用率低。另外,几个施工点共用一个拌合站也是非常多的现象,有的施工点距离拌合站达20公里以上,采用一般的砼输送车保温措施也是很难满足混凝土运输保温的要求,而在洞口设置保温门帘不仅不利于施工通风排烟而且也不能从根本上保证隧道工程二衬混凝土养护的温度要求,同时采用该措施是以牺牲洞内作业环境即空气质量为条件的,对工作人员的生命造成影响,从而为工程带来安全隐患。
【发明内容】
为了克服背景技术中的不足,本发明公开了一种双线铁路隧道冬季混凝土施工供热防冻方法,本发明通过在隧道内原料仓、地暖供热管道、锅炉房、循环泵、风机和风管,在原料仓底下设置地暖供热管,通过锅炉房内的循环泵使热水在地暖供热管内进行循环,再利用风机和风管的排烟,以此来达到混凝土材料的保温和改善隧道内空气的目的。
为了实现所述发明目的,本发明采用如下技术方案:
一种双线铁路隧道冬季混凝土施工供热防冻方法,包括原料仓、地暖供热管道、锅炉房、循环泵、风机和风管,在隧道贴着隧道边墙的一侧设有原料仓,另一侧设有风机,风机与风管相连接,原料仓包括水泥仓、已检碎石料仓、已检砂子料仓、待检碎石料仓和待检砂子料仓,在隧道洞口处设有锅炉房,锅炉房一侧设有门帘,锅炉房内设有锅炉,水箱设在原料仓的一侧,锅炉分别与地暖供热干管和地暖回水干管相连接,地暖供热干管的一端与锅炉相连接,地暖供热干管的另一端与水箱相连接,地暖回水干管的一端与水箱相连接,地暖回水干管的另一端与锅炉相连接,水箱上设有水箱供水管,水箱供水管一端与水箱相连接,水箱供水管另一端与地暖供热干管相连接,通过原料仓的地暖供热干管、地暖回水干管和水箱供水管设置在地下;在水泥仓、已检碎石料仓、已检砂子料仓、待检碎石料仓和待检砂子料仓的下面分别铺设有一根地暖供热管,所述的地暖供热管一端与地暖供热干管相连接,地暖供热管的另一端与地暖回水干管相连接,在锅炉房内的地暖回水干管上设有循环泵,循环泵和锅炉之间的地暖回水干管上设有旁通阀。
进一步,所述原料仓的地面上铺设有地板,地板由导热材料制作而成。
进一步,所述地暖供热管呈S形铺设在原料仓的地板下。
进一步,所述水箱供水管上设有第一调节阀。
进一步,所述地暖供热干管上设有止回阀。
进一步,所述地暖回水干管上设有第二调节阀。
由于采用了上述技术方案,本发明具有如下有益效果:
本发明所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,包括原料仓、地暖供热管道、锅炉房、循环泵、风机和风管,在原料仓底下设置地暖供热管,通过锅炉房内的循环泵使热水在地暖供热管内进行循环,再利用风机和风管的排烟,以此来达到混凝土材料的保温和改善隧道内空气的目的;本发明实用性极强,而且安全可靠,操作也极为方便,能持续对隧道内的原料仓及工作环境进行保温,避免了混凝土的长途运输,保证了冬季隧道工程大规模的混凝土施工,有效的解决了保温和改善作业环境的问题。
【附图说明】
图1是本发明的平面结构及供热管道布置示意图。
图2是本发明的立体结构结构示意图。
图中:1、水箱;2、隧道边墙;3、搅拌机;4、未开凿岩体; 5、地暖回水干管;6、风管;7、地暖供热管;8、地暖供热干管;9、第一调节阀门;10、水箱供水管;11、锅炉房;12、锅炉;13、止回阀;14、循环泵;15、第二调节阀门;16、旁通阀;17、门帘;18、风机;19、水泥仓;20、已检碎石料仓;21、已检砂子料仓;22、待检碎石料仓;23、待检砂子料仓;24、地板。
【具体实施方式】
通过下面的实施例可以详细的解释本发明,公开本发明的目的旨在保护本发明范围内的一切技术改进。
结合附图1~2所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,包括一种双线铁路隧道冬季混凝土施工供热防冻方法,包括原料仓、地暖供热管道、锅炉房11、循环泵14、风机18和风管6,在隧道贴着隧道边墙2的一侧设有原料仓,另一侧设有风机18,风机18与风管6相连接,原料仓包括水泥仓19、已检碎石料仓20、已检砂子料仓21、待检碎石料仓22和待检砂子料仓23,在隧道洞口处设有锅炉房11,锅炉房11一侧设有门帘17,锅炉房11内设有锅炉12,水箱1设在原料仓的一侧,锅炉12分别与地暖供热干管8和地暖回水干管5相连接,地暖供热干管8的一端与锅炉12相连接,地暖供热干管8的另一端与水箱1相连接,地暖回水干管5的一端与水箱1相连接,地暖回水干管5的另一端与锅炉12相连接,水箱1上设有水箱供水管10,水箱供水管10一端与水箱1相连接,水箱供水管10另一端与地暖供热干管8相连接,通过原料仓的地暖供热干管8、地暖回水干管5和水箱供水管10设置在地下;在水泥仓19、已检碎石料仓20、已检砂子料仓21、待检碎石料仓22和待检砂子料仓23的下面分别铺设有一根地暖供热管7,所述的地暖供热管7一端与地暖供热干管8相连接,地暖供热管的7另一端与地暖回水干管5相连接,在锅炉房11内的地暖回水干管5上设有循环泵14,循环泵14和锅炉12之间的地暖回水干管5上设有旁通阀16,所述原料仓的地面上铺设有地板24,地板24由导热材料制作而成,所述地暖供热管7呈S形铺设在原料仓的地板24下,所述水箱供水管10上设有第一调节阀9,所述地暖供热干管8上设有止回阀13,所述地暖回水干管5上设有第二调节阀15。
实施本发明所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,在工作时,将锅炉房11内的锅炉12烧成设定温度,打开循环泵14,使热水沿着地暖供热干管8内进行流动,地暖供热干管8上设置有止回阀13,防止热水回流,打开第一调节阀门9,可以调节水箱供水管10的热水供水量,使供水量达到保温温度的需要,热水经过水箱1再从地暖回水干管5流入到锅炉12内,地暖回水干管5设有第二调节阀门15和旁通阀16,第二调节阀门15可以对水量进行调节,旁通阀16可以缓解水的压力,从而保护好循环泵14,在原料仓的地板下面都设置有一根地暖供热管7,地暖供热管7铺满整个原料仓的地下,热水从地暖供热干管8和地暖供热管7 的连接端口处流入,从地暖供热管7 的另一端口流出到地暖回水干管5内,形成循环热水;在原料仓内放入相应的原料,在使用时将原料仓的原料用铲车等工具拉出来,在隧道内的搅拌机3内进行搅拌,从而可以对隧道内的未开凿岩体4进行施工;在锅炉房11一侧设置门帘17,防止隧道内的热量过快的流逝,隧道洞口的风机18通过风管6对隧道内的空气进行调节,风管从隧道口直接通入到隧道内的未开凿岩体4处,通过风机18能很好的对隧道内的空气以及掘进工作面的温度进行调节。
本发明未详述部分为现有技术。
Claims (6)
1.一种双线铁路隧道冬季混凝土施工供热防冻方法,包括原料仓、地暖供热管道、锅炉房(11)、循环泵(14)、风机(18)和风管(6),其特征是:在隧道贴着隧道边墙(2)的一侧设有原料仓,另一侧设有风机(18),风机(18)与风管(6)相连接,原料仓包括水泥仓(19)、已检碎石料仓(20)、已检砂子料仓(21)、待检碎石料仓(22)和待检砂子料仓(23),在隧道洞口处设有锅炉房(11),锅炉房(11)一侧设有门帘(17),锅炉房(11)内设有锅炉(12),水箱(1)设在原料仓的一侧,锅炉(12)分别与地暖供热干管(8)和地暖回水干管(5)相连接,地暖供热干管(8)的一端与锅炉(12)相连接,地暖供热干管(8)的另一端与水箱(1)相连接,地暖回水干管(5)的一端与水箱(1)相连接,地暖回水干管(5)的另一端与锅炉(12)相连接,水箱(1)上设有水箱供水管(10),水箱供水管(10)一端与水箱(1)相连接,水箱供水管(10)另一端与地暖供热干管(8)相连接,通过原料仓的地暖供热干管(8)、地暖回水干管(5)和水箱供水管(10)设置在地下;在水泥仓(19)、已检碎石料仓(20)、已检砂子料仓(21)、待检碎石料仓(22)和待检砂子料仓(23)的下面分别铺设有一根地暖供热管(7),所述的地暖供热管(7)一端与地暖供热干管(8)相连接,地暖供热管的(7)另一端与地暖回水干管(5)相连接,在锅炉房(11)内的地暖回水干管(5)上设有循环泵(14),循环泵(14)和锅炉(12)之间的地暖回水干管(5)上设有旁通阀(16)。
2.根据权利要求1所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,其特征是:所述原料仓的地面上铺设有地板(24),地板(24)由导热材料制作而成。
3.根据权利要求1或2所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,其特征是:所述地暖供热管(7)呈S形铺设在原料仓的地板(24)下。
4.根据权利要求1所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,其特征是:所述水箱供水管(10)上设有第一调节阀(9)。
5.根据权利要求1所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,其特征是:所述地暖供热干管(8)上设有止回阀(13)。
6.根据权利要求1所述的一种双线铁路隧道冬季混凝土施工供热防冻方法,其特征是:所述地暖回水干管(5)上设有第二调节阀(15)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310165307.2A CN103291322B (zh) | 2013-05-08 | 2013-05-08 | 一种双线铁路隧道冬季混凝土施工供热防冻方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310165307.2A CN103291322B (zh) | 2013-05-08 | 2013-05-08 | 一种双线铁路隧道冬季混凝土施工供热防冻方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103291322A true CN103291322A (zh) | 2013-09-11 |
CN103291322B CN103291322B (zh) | 2016-01-20 |
Family
ID=49092784
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310165307.2A Active CN103291322B (zh) | 2013-05-08 | 2013-05-08 | 一种双线铁路隧道冬季混凝土施工供热防冻方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103291322B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103552155A (zh) * | 2013-10-30 | 2014-02-05 | 中国神华能源股份有限公司 | 骨料保温系统及混凝土的搅拌方法 |
CN105926385A (zh) * | 2016-04-26 | 2016-09-07 | 中铁六局集团有限公司 | 低温环境道岔放散锁定的施工方法 |
CN107310045A (zh) * | 2017-07-07 | 2017-11-03 | 中铁大桥局集团第二工程有限公司 | 一种全封闭地暖保温式混凝土工厂 |
CN109441481A (zh) * | 2018-11-21 | 2019-03-08 | 中铁十局集团第五工程有限公司 | 一种高海拔寒冷地区抗冻融灾害的隧道衬砌结构 |
CN109610894A (zh) * | 2018-12-10 | 2019-04-12 | 中交公局桥隧工程有限公司 | 一种拌和站保温施工工艺 |
CN109989770A (zh) * | 2019-03-12 | 2019-07-09 | 中交一公局桥隧工程有限公司 | 一种高速公路隧道冬季施工方法 |
CN112627889A (zh) * | 2020-12-21 | 2021-04-09 | 中铁二院工程集团有限责任公司 | 利用围岩地下水热能的高寒长大铁路隧道防冻结构及方法 |
CN113719144A (zh) * | 2021-07-13 | 2021-11-30 | 中铁十九局集团有限公司 | 梁体冬期施工养护的方法 |
CN115822640A (zh) * | 2022-11-04 | 2023-03-21 | 中国科学院西北生态环境资源研究院 | 冻土隧道洞口防护系统 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1055419A (zh) * | 1991-03-30 | 1991-10-16 | 青海矿山机械厂 | 无压无膨胀水箱热水锅炉网路系统 |
JP2001200699A (ja) * | 2000-01-20 | 2001-07-27 | Maeda Corp | フレッシュ混練材料吹付けシステム |
CN1645002A (zh) * | 2003-10-10 | 2005-07-27 | 马环宇 | 双循环可计量采暖方法与系统 |
CN2858419Y (zh) * | 2005-12-01 | 2007-01-17 | 中铁一局集团有限公司新运工程公司 | 高寒地区铁路宿营车集中采暖系统 |
CN103017211A (zh) * | 2013-01-08 | 2013-04-03 | 钟殿玺 | 土炕自烧锅炉及其供暖系统 |
-
2013
- 2013-05-08 CN CN201310165307.2A patent/CN103291322B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1055419A (zh) * | 1991-03-30 | 1991-10-16 | 青海矿山机械厂 | 无压无膨胀水箱热水锅炉网路系统 |
JP2001200699A (ja) * | 2000-01-20 | 2001-07-27 | Maeda Corp | フレッシュ混練材料吹付けシステム |
CN1645002A (zh) * | 2003-10-10 | 2005-07-27 | 马环宇 | 双循环可计量采暖方法与系统 |
CN2858419Y (zh) * | 2005-12-01 | 2007-01-17 | 中铁一局集团有限公司新运工程公司 | 高寒地区铁路宿营车集中采暖系统 |
CN103017211A (zh) * | 2013-01-08 | 2013-04-03 | 钟殿玺 | 土炕自烧锅炉及其供暖系统 |
Non-Patent Citations (1)
Title |
---|
王峰: "冬季隧道衬砌混凝土暖棚法施工", 《公路交通科技(应用技术版)》, no. 5, 15 May 2012 (2012-05-15) * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103552155A (zh) * | 2013-10-30 | 2014-02-05 | 中国神华能源股份有限公司 | 骨料保温系统及混凝土的搅拌方法 |
CN105926385A (zh) * | 2016-04-26 | 2016-09-07 | 中铁六局集团有限公司 | 低温环境道岔放散锁定的施工方法 |
CN107310045A (zh) * | 2017-07-07 | 2017-11-03 | 中铁大桥局集团第二工程有限公司 | 一种全封闭地暖保温式混凝土工厂 |
CN107310045B (zh) * | 2017-07-07 | 2020-05-12 | 中铁大桥局集团第二工程有限公司 | 一种全封闭地暖保温式混凝土工厂 |
CN109441481A (zh) * | 2018-11-21 | 2019-03-08 | 中铁十局集团第五工程有限公司 | 一种高海拔寒冷地区抗冻融灾害的隧道衬砌结构 |
CN109610894A (zh) * | 2018-12-10 | 2019-04-12 | 中交公局桥隧工程有限公司 | 一种拌和站保温施工工艺 |
CN109989770A (zh) * | 2019-03-12 | 2019-07-09 | 中交一公局桥隧工程有限公司 | 一种高速公路隧道冬季施工方法 |
CN112627889A (zh) * | 2020-12-21 | 2021-04-09 | 中铁二院工程集团有限责任公司 | 利用围岩地下水热能的高寒长大铁路隧道防冻结构及方法 |
CN112627889B (zh) * | 2020-12-21 | 2023-01-20 | 中铁二院工程集团有限责任公司 | 利用围岩地下水热能的高寒长大铁路隧道防冻结构及方法 |
CN113719144A (zh) * | 2021-07-13 | 2021-11-30 | 中铁十九局集团有限公司 | 梁体冬期施工养护的方法 |
CN115822640A (zh) * | 2022-11-04 | 2023-03-21 | 中国科学院西北生态环境资源研究院 | 冻土隧道洞口防护系统 |
CN115822640B (zh) * | 2022-11-04 | 2023-11-28 | 中国科学院西北生态环境资源研究院 | 冻土隧道洞口防护系统 |
Also Published As
Publication number | Publication date |
---|---|
CN103291322B (zh) | 2016-01-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103291322B (zh) | 一种双线铁路隧道冬季混凝土施工供热防冻方法 | |
CN106246209B (zh) | 一种隧道内衬混凝土保温养护施工装置及其施工方法 | |
CN100595420C (zh) | 隧道辅助导坑洞内调压分配室通风施工方法 | |
CN202768046U (zh) | 单斜井双正洞隧道施工射流通风结构 | |
CN105134278B (zh) | 高海拔高寒地区隧道通风升温系统及通风升温施工方法 | |
CN101672188A (zh) | 隧道洞口段衬砌加热系统 | |
WO2021078306A1 (zh) | 中深层地下岩热型供热系统及供热方法 | |
CN103216879A (zh) | 一种隧道供热防冻系统 | |
CN106948856A (zh) | 一种矿井局部降温装置及方法 | |
CN102322276A (zh) | 季节性冻土地区的隧道工程防冻结构 | |
WO2020143066A1 (zh) | 一种地热开发系统及其施工方法 | |
CN110359930A (zh) | 一种用于极易破碎巷道围岩的注浆系统及其防灭火方法 | |
CN105649668A (zh) | 巷帮截流式矿井降温方法及降温系统 | |
CN108952806A (zh) | 高寒严寒地区隧道排水防冻集成系统 | |
CN107034874A (zh) | 双螺旋式注浆型冻结装置及施工方法 | |
KR20110002376A (ko) | 지중 열교환기를 이용한 열원저장식 지열 히트펌프 시스템 | |
CN104264657B (zh) | 处理公路冻土地基的方法 | |
CN203869493U (zh) | 隧道窑炉 | |
CN103437779B (zh) | 整治隧道衬砌渗水病害的施工方法 | |
CN203427158U (zh) | 一种新型混凝土管桩蒸养系统 | |
CN103774677A (zh) | 地源井灌浆回填方法 | |
CN104533462A (zh) | 一种隧道衬砌混凝土保温系统 | |
CN206408485U (zh) | 一种用于沥青及沥青混合料的加热系统 | |
CN103387835B (zh) | 焦炉热态泵送灌浆施工方法 | |
CN109209496A (zh) | 煤矿井筒防冻装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |