CN103266614A - Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum - Google Patents

Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum Download PDF

Info

Publication number
CN103266614A
CN103266614A CN2013101799093A CN201310179909A CN103266614A CN 103266614 A CN103266614 A CN 103266614A CN 2013101799093 A CN2013101799093 A CN 2013101799093A CN 201310179909 A CN201310179909 A CN 201310179909A CN 103266614 A CN103266614 A CN 103266614A
Authority
CN
China
Prior art keywords
grouting
liquid
slurries
pipe
water glass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101799093A
Other languages
Chinese (zh)
Other versions
CN103266614B (en
Inventor
王文正
孔恒
杨建华
郑雪梅
刘彦林
刘明
姚毅
任有旺
李博凯
张德华
安声镛
安善福
李达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANSEI CHINA TRADING Co Ltd
Beijing Jiaotong University
Beijing Municipal Construction Co Ltd
Original Assignee
HANSEI CHINA TRADING Co Ltd
Beijing Jiaotong University
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANSEI CHINA TRADING Co Ltd, Beijing Jiaotong University, Beijing Municipal Construction Co Ltd filed Critical HANSEI CHINA TRADING Co Ltd
Priority to CN201310179909.3A priority Critical patent/CN103266614B/en
Publication of CN103266614A publication Critical patent/CN103266614A/en
Application granted granted Critical
Publication of CN103266614B publication Critical patent/CN103266614B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种砂卵石地层深基坑分段后退式双液复合注浆工法,具体步骤是:确定注浆加固方案;现场测量放线;钻孔,成孔后,下放双重注浆管,然后安装拔管器,拔出钻杆;浆液配制;注浆,采用隔孔注入方式,将水泥-水玻璃浆液和改性水玻璃浆液双液复合注入,浆液的转换根据注浆压力、流量和注浆位置的变化综合考虑,注浆量超过设计值的80%同时注浆压力达到2MPa,或者注浆压力超过3MPa,双重管上提后,重复上述注浆过程,直到注浆完成。本发明能够防止因为塌孔而无法安设注浆管的现象发生;两种浆液的复合注入,综合两种浆液的优点,实现止水帷幕同时满足渗透系数低、凝结强度高的优点;克服了因为浆液回流而出现拔管困难的现象。

Figure 201310179909

The invention discloses a subsection retreat double-liquid composite grouting construction method for deep foundation pits in sand and pebble formations. The specific steps are: determining the grouting reinforcement scheme; measuring and setting out lines on site; drilling holes, and lowering the double grouting pipes after the holes are formed , and then install the pipe puller and pull out the drill pipe; grout preparation; grouting, using the injection method of the septum hole, the cement-water glass slurry and the modified water glass slurry are injected in combination, and the conversion of the grout is based on the grouting pressure and flow rate. Considering the change of the grouting position comprehensively, the grouting amount exceeds 80% of the design value and the grouting pressure reaches 2MPa, or the grouting pressure exceeds 3MPa. After the double pipe is lifted, repeat the above grouting process until the grouting is completed. The invention can prevent the occurrence of the phenomenon that the grouting pipe cannot be installed due to hole collapse; the compound injection of the two kinds of grout combines the advantages of the two kinds of grout to realize the water-stop curtain while satisfying the advantages of low permeability coefficient and high coagulation strength; Difficulty extubating due to reflux of serous fluid.

Figure 201310179909

Description

砂卵石地层深基坑分段后退式双液复合注浆施工方法Segment-retreat double-fluid composite grouting construction method for deep foundation pit in sandy pebble formation

技术领域technical field

本发明属于基坑工程技术领域,涉及一种针对砂卵石地层深基坑注浆防水加固工程的分段后退式双液复合注浆的施工方法。The invention belongs to the technical field of foundation pit engineering, and relates to a construction method of segmented retreat double-liquid composite grouting for deep foundation pit grouting and waterproof reinforcement projects in sandy pebble formations.

背景技术Background technique

就目前我国的隧道与地下工程注浆的现状而言,针对双液注浆,双层管钻杆注浆法和袖阀管注浆法是目前采用较多、注浆效果较好的施工工法。As far as the current situation of tunnel and underground engineering grouting in my country is concerned, for double-liquid grouting, double-pipe drill pipe grouting method and sleeve valve pipe grouting method are the construction methods that are currently used more and have better grouting effects. .

现有的双重管注浆施工一般采用双重管钻杆,端头安装管内混合器。钻进采用清水作为循环液,达到设计深度或位置时,封闭端点进行横向喷射切换。然后用注浆泵分别将两种浆液压入外管和内管,浆液在二重管的端头混合器内混合,通过滤网在水平方向实行喷射,将浆液注入地层中。注浆采用分段后退注浆,达到土层加固效果。该工法的缺点是采用钻杆注浆,钻杆与注浆孔之间必然会存在间隙,注浆时极易造成浆液回流,对于固结强度高的浆液造成拔管困难,且施工工期较长。Existing double-pipe grouting construction generally adopts double-pipe drill pipe, and an in-pipe mixer is installed at the end. Clean water is used as the circulating fluid for drilling, and when the design depth or position is reached, the closed end point is used for lateral jet switching. Then use a grouting pump to inject the two kinds of slurry into the outer pipe and the inner pipe respectively, and the slurry is mixed in the end mixer of the double pipe, and sprayed in the horizontal direction through the filter screen to inject the slurry into the formation. The grouting adopts step-back grouting to achieve the effect of soil layer reinforcement. The disadvantage of this construction method is that when the drill pipe is used for grouting, there will inevitably be a gap between the drill pipe and the grouting hole, which will easily cause the grout to flow back during grouting, and it will be difficult to pull out the pipe for the grout with high consolidation strength, and the construction period will be longer .

袖阀管后退式注浆是在浆液经过注浆泵加压后,通过连接管进入注浆管,聚集到袖阀管注浆管段,然后通过钻有泄浆孔的PVC管(即袖阀管),在压力作用下,将包裹在PVC管外地橡胶圈胀开。当压力逐渐增大到一定程度,被加压的浆液就会沿着地层结构产生填充、渗透、压密、劈裂流动,浆液在地层中形成固结体,从而达到增加地层强度,降低地层渗透性的目的。该工法的缺点是遇砂卵石地层,成孔比较困难,钻杆拔出后,容易塌孔,无法安设袖阀管。Sleeve valve pipe retreat grouting is that after the grout is pressurized by the grouting pump, it enters the grouting pipe through the connecting pipe, gathers at the sleeve valve pipe grouting pipe section, and then passes through the PVC pipe drilled with grout holes (that is, the sleeve valve pipe ), under pressure, expand the rubber ring wrapped around the PVC pipe. When the pressure gradually increases to a certain level, the pressurized slurry will flow along the formation structure to fill, infiltrate, compact, and split, and the slurry will form a consolidated body in the formation, thereby increasing the strength of the formation and reducing the penetration of the formation. sexual purpose. The disadvantage of this construction method is that it is difficult to form a hole in the sand and pebble formation. After the drill pipe is pulled out, the hole is easy to collapse, and the sleeve valve cannot be installed.

现有注浆项目通常采用单种浆液注入,但单种浆液相比较而言通常会存在突出性缺点,如水泥-水玻璃浆液凝结体渗透系数大、可注性较差,酸性水玻璃浆液凝结体强度低。Existing grouting projects usually use a single type of grout to inject, but the single type of grout usually has prominent shortcomings in comparison, such as the cement-water glass grout has a large permeability coefficient and poor injectability, and the acidic water glass grout condenses Body strength is low.

针对现有技术存在的上述不足,提出本发明。The present invention is proposed aiming at the above-mentioned deficiencies existing in the prior art.

发明内容Contents of the invention

为了克服现有双重管注浆工法浆液回流、拔管困难、工期较长的缺点,袖阀管后退式注浆容易塌孔、无法安设袖阀管的不足,以及单种浆液的存在的突出缺点,本发明提供一种砂卵石地层深基坑分段后退式双液复合注浆工法。In order to overcome the disadvantages of the existing double-pipe grouting method, such as grout backflow, difficulty in pulling out the pipe, and a long construction period, the retreating grouting of the sleeve valve pipe is easy to collapse the hole, the sleeve valve pipe cannot be installed, and the existence of a single type of grout is prominent. Disadvantages, the present invention provides a step-back two-liquid composite grouting construction method for deep foundation pits in sand and pebble formations.

为实现上述目的,本发明的砂卵石地层深基坑分段后退式双液复合注浆工法,具体步骤是:In order to achieve the above-mentioned purpose, the step-back two-liquid composite grouting construction method of the deep foundation pit in the sand and pebble stratum of the present invention, the specific steps are:

1、确定注浆加固方案1. Determine the grouting reinforcement plan

确定注浆孔的位置、孔的布置方式、孔间距、孔排距以及钻孔深度,确定钻机型号、注浆泵型号。其中,双排采用孔梅花形布置形成了一定厚度的止水帷幕以实现止水加固的目的。Determine the location of the grouting holes, the layout of the holes, the hole spacing, the hole row spacing and the drilling depth, and determine the model of the drilling rig and the model of the grouting pump. Among them, the double row is arranged in a plum blossom shape with holes to form a water-stop curtain of a certain thickness to achieve the purpose of water-stop reinforcement.

2、现场测量放线2. Field measurement and setting out

根据测量控制网用全站仪进行主要定位工作,再由放线班按图纸进行细部尺寸的放线工作。According to the measurement control network, the total station is used for the main positioning work, and then the laying-out team performs the laying-out work of the detailed dimensions according to the drawings.

3、钻孔3. Drilling

针对砂卵石地层成孔困难的特点,钻孔使用进口RPD-130C全液压钻机和韩国SH5000、SH6000、SH8000钻机成孔,该钻机具有液压全自动操作,作业扭矩大,能够克服各种地层,成孔效率高,定位快捷,准确。Aiming at the characteristics of difficult hole forming in sand and pebble strata, the imported RPD-130C full hydraulic drilling rig and Korean SH5000, SH6000, SH8000 drilling rigs are used to drill holes. High hole efficiency, fast and accurate positioning.

成孔后,下放双重注浆管,然后安装拔管器,拔出钻杆。After the hole is formed, the double grouting pipe is lowered, and then the pipe puller is installed to pull out the drill pipe.

钻孔前需对钻孔周围宽2m范围内地面进行硬化,硬化采用C20混凝土,厚度30cm。Before drilling, it is necessary to harden the ground within a width of 2m around the drilling hole. The hardening is made of C20 concrete with a thickness of 30cm.

4、浆液配制4. Serum preparation

A液:水泥浆液,采用普通硅酸盐P.O42.5水泥,加水,取水灰比为0.8-1.3。Liquid A: cement slurry, using ordinary Portland P.O42.5 cement, adding water, the water-cement ratio is 0.8-1.3.

B液:水玻璃浆液,采用浓度42Be’水玻璃与水1:1混合。Liquid B: water glass slurry, mixed with water glass and water at a concentration of 42Be' 1:1.

C液:磷酸溶液,加水,取溶液浓度为3%-8%。Solution C: Phosphoric acid solution, add water, and the concentration of the solution is 3%-8%.

A、B、C液分别搅拌均匀,根据浆液要求的固结时间调节各浆液的浓度。其中等体积比A液与B液混合后形成水泥-水玻璃浆液,等体积比的A液与B液混合形成酸性水玻璃浆液。A, B, and C liquids are stirred evenly, and the concentration of each slurry is adjusted according to the consolidation time required by the slurry. Wherein equal volume ratio A liquid and B liquid are mixed to form cement-water glass slurry, and equal volume ratio A liquid and B liquid are mixed to form acidic water glass slurry.

5、注浆5. Grouting

(a)地层的注浆量是否合适是地层加固及止水效果的体现,采用隔孔注入方式,这样既避免注浆孔互相影响,又使后注孔起到补充先注孔的作用,保证土体浆液扩散均匀。将水泥-水玻璃浆液和改性水玻璃浆液双液复合注入,具体为:注浆时,先注改性水玻璃浆液,再注水泥-水玻璃浆液;注浆过程中两种浆液混合注浆,内排注浆孔注入改性水玻璃浆液(B液和C液),外排则注入水泥-水玻璃浆液(A液和B液);注浆时要实时观察注浆压力,压力较大时可注水泥-水玻璃双液浆(A液和B液),压力较小时可注改性水玻璃浆液(B液和C液)以迅速填充;(a) Whether the amount of grouting in the formation is appropriate is the embodiment of the reinforcement of the formation and the water-stopping effect. The method of injecting through holes is used to avoid the mutual influence of the grouting holes, and to make the post-injection holes supplement the first-injection holes to ensure The soil slurry spreads evenly. The cement-water glass slurry and the modified water glass slurry are double-liquid compositely injected, specifically: when grouting, the modified water glass slurry is injected first, and then the cement-water glass slurry is injected; the two types of slurry are mixed during the grouting process. , inject modified water glass slurry (liquid B and liquid C) into the inner row of grouting holes, and inject cement-water glass slurry (liquid A and liquid B) into the outer row; when grouting, observe the grouting pressure in real time, the pressure is relatively high Cement-water glass double liquid slurry (liquid A and liquid B) can be injected when the pressure is low, and modified water glass slurry (liquid B and liquid C) can be injected to quickly fill when the pressure is low;

浆液的转换根据注浆压力、流量和注浆位置的变化综合考虑,通过吸浆管的阀门开关更改浆液,可以随时进行。The conversion of grout is considered comprehensively according to the change of grouting pressure, flow rate and grouting position, and the grout can be changed at any time through the valve switch of the grouting pipe.

(b)注浆压力控制在1.5-3MPa、注浆速度为60L/min、注浆分段长度为5-10cm、浆液固结时间控制在20s-90s;(b) The grouting pressure is controlled at 1.5-3MPa, the grouting speed is 60L/min, the length of the grouting section is 5-10cm, and the grouting time is controlled at 20s-90s;

(c)当注浆量超过设计值的80%同时注浆压力达到2MPa,或者注浆压力超过3MPa,双重管上提后,重复上述注浆过程,直到注浆完成。(c) When the grouting volume exceeds 80% of the design value and the grouting pressure reaches 2MPa, or the grouting pressure exceeds 3MPa, after the double pipe is lifted up, repeat the above grouting process until the grouting is completed.

本发明对比已有技术具有以下优点:Compared with the prior art, the present invention has the following advantages:

1、先下放注浆管再拔钻杆,可以防止因为塌孔而无法安设注浆管的现象发生。1. Lowering the grouting pipe first and then pulling out the drill pipe can prevent the phenomenon that the grouting pipe cannot be installed due to hole collapse.

2、两种浆液的复合注入,可以实现注浆凝结体综合两种浆液的优点,克服因为浆液回流而出现拔管困难的现象,同时又不影响注浆质量。2. The composite injection of the two kinds of grout can realize the advantages of the two kinds of grout in the grouting condensate, overcome the phenomenon of difficult extubation due to the backflow of the grout, and at the same time not affect the quality of the grouting.

3、钻孔和注浆同步交叉进行,缩短了工期。3. Drilling and grouting are carried out synchronously and crosswise, which shortens the construction period.

附图说明Description of drawings

当结合附图考虑时,通过参照下面的详细描述,能够更完整更好地理解本发明以及容易得知其中许多伴随的优点,但此处所说明的附图用来提供对本发明的进一步理解,构成本发明的一部分,本发明的示意性实施例及其说明用于解释本发明,并不构成对本发明的不当限定,其中:A more complete and better understanding of the invention, and many of its attendant advantages, will readily be learned by reference to the following detailed description when considered in conjunction with the accompanying drawings, but the accompanying drawings illustrated herein are intended to provide a further understanding of the invention and constitute A part of the present invention, the exemplary embodiment of the present invention and its description are used to explain the present invention, and do not constitute an improper limitation of the present invention, wherein:

图1为本发明施工工艺流程图;Fig. 1 is a construction process flow chart of the present invention;

图2为本发明注浆系统布置图。Fig. 2 is a layout diagram of the grouting system of the present invention.

具体实施方式Detailed ways

为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。In order to make the above objects, features and advantages of the present invention more comprehensible, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

本发明的砂卵石地层深基坑分段后退式双液复合注浆工法,其施工工艺流程及操作要点如图1所示。Figure 1 shows the construction process and operating points of the step-back two-liquid composite grouting method for deep foundation pits in sand and pebble formations of the present invention.

1)确定注浆加固方案1) Determine the grouting reinforcement scheme

注浆孔孔位分布在围护桩中间及外边,共两排,孔间距900mm,两排间距600mm梅花型交错布设,采用孔梅花形布置形成了一定厚度的止水帷幕以实现止水加固的目的,共设注浆孔1138个,φ89mm钻杆成孔,钻孔深度为现状地面高程(46.65m)至砾岩层下0.5m,砾岩层标高为10.62m,钻孔深36.53m,总钻孔量为41572m。注浆深度为现况水位21.89以上2m至砾岩层以下0.5m,注浆深度为13.77m。The grouting holes are distributed in the middle and outside of the retaining piles, in two rows, with a hole spacing of 900mm, and a quincunx pattern with a spacing of 600mm. Purpose: A total of 1,138 grouting holes are to be set up with φ89mm drill pipes. The drilling depth is from the current ground elevation (46.65m) to 0.5m below the conglomerate layer. The conglomerate layer elevation is 10.62m. The volume is 41572m. The grouting depth is 2m above the current water level of 21.89 to 0.5m below the conglomerate layer, and the grouting depth is 13.77m.

2)现场测量放线2) On-site measurement and setting out

根据测量控制网用全站仪进行主要定位工作,再由放线班按图纸进行细部尺寸的放线工作。测量仪器必须经检测合格后方可使用。According to the measurement control network, the total station is used for the main positioning work, and then the laying-out team performs the laying-out work of the detailed dimensions according to the drawings. Measuring instruments can only be used after passing the test.

3)钻孔3) drilling

针对砂卵石地层成孔困难的特点,钻孔使用进口RPD-130C全液压钻机和韩国SH5000、SH6000、SH8000钻机成孔,该钻机具有液压全自动操作,作业扭矩大,能够克服各种地层,成孔效率高,定位快捷,准确。Aiming at the characteristics of difficult hole forming in sand and pebble strata, the imported RPD-130C full hydraulic drilling rig and Korean SH5000, SH6000, SH8000 drilling rigs are used to drill holes. High hole efficiency, fast and accurate positioning.

本工程采用φ89钻杆钻孔,钻孔直径同钻杆。钻孔前需对钻孔周围宽2m范围内地面进行硬化,硬化采用C20混凝土,厚度30cm。This project adopts φ89 drill pipe for drilling, and the diameter of the hole is the same as that of the drill pipe. Before drilling, it is necessary to harden the ground within a width of 2m around the drilling hole. The hardening is made of C20 concrete with a thickness of 30cm.

钻孔保证措施:Drilling Guarantee Measures:

1)、应严格按照设计参数进行钻孔。钻孔孔位及角度偏差符合相关规范规定,若现场钻孔孔位因为客观条件限制不能满足设计要求,应进行移位并进行计算确定参数,必要时应进行补孔。1) Drilling should be carried out in strict accordance with the design parameters. The position and angle deviation of the drilling hole complies with the relevant specifications. If the drilling hole position on site cannot meet the design requirements due to objective conditions, it should be shifted and calculated to determine the parameters, and the hole should be repaired if necessary.

2)、在钻孔施工过程中要稳定钻机,稳步钻进,要求有丰富经验的钻机手进行操作,杜绝无经验的新手贸然进行操作。2) During the drilling construction process, it is necessary to stabilize the drilling rig and drill steadily. It requires experienced drillers to operate, and prevents inexperienced novices from rashly operating.

3)、每班上班前对机械设备进行检查,严禁机械带病作业;同时对钻具进行检查,使用质量性能良好的钻杆和钻头,严禁使用有缺陷的钻具。3) Check the mechanical equipment before going to work every shift, and it is strictly forbidden to operate the machine with a disease; at the same time, check the drilling tools, use drill pipes and drill bits with good quality and performance, and strictly prohibit the use of defective drilling tools.

成孔后,下放直径为42mm的双重注浆管,完成后,安装拔管器,拔出钻杆。After the hole is formed, the double grouting pipe with a diameter of 42mm is lowered. After completion, the pipe puller is installed to pull out the drill pipe.

4、浆液配制4. Serum preparation

控制浆液的凝结时间为水泥-水玻璃浆液在30-90s,改性水玻璃浆液控制在2-10s范围内。The setting time of the slurry is controlled to be within 30-90s for the cement-water glass slurry, and 2-10s for the modified water glass slurry.

A液:水泥浆液,采用普通硅酸盐P.O42.5水泥,配合比为水:水泥=1:1.2。Liquid A: cement slurry, using ordinary Portland P.O42.5 cement, the mix ratio is water: cement = 1:1.2.

B液:水玻璃浆液,采用波美度42Be’水玻璃,配合比为水:水玻璃=1:1。Liquid B: water glass slurry, using Baumedo 42Be' water glass, the mixing ratio is water: water glass = 1:1.

C液:速凝剂磷酸溶液,配合比为水:磷酸=1:0.05。Liquid C: quick-setting agent phosphoric acid solution, the mixing ratio is water: phosphoric acid = 1:0.05.

为了满足注浆固结的目的,需要按照一定的次序进行浆液配制。例如,水泥浆稀释应在搅拌桶中按每次搅拌体加入所需的水量,开动搅拌机,再加入水泥搅拌3分钟以上。In order to meet the purpose of grouting consolidation, it is necessary to prepare grout in a certain order. For example, to dilute the cement slurry, add the required amount of water into the mixing tank according to each mixing body, start the mixer, and then add cement and stir for more than 3 minutes.

5、注浆5. Grouting

注浆泵试运转Grouting pump test run

确定注浆系统各部分连接无误后,开动注浆泵压水试验,检查注浆泵液压情况,系统管路有否漏浆,管路是否畅通。After confirming that all parts of the grouting system are connected correctly, start the grouting pump pressure water test to check the hydraulic pressure of the grouting pump, whether there is any grout leakage in the system pipeline, and whether the pipeline is unblocked.

浆液注入Serous injection

系统就绪后,如图2所示,配比好的A液通过吸浆管1连接至注浆泵4,配比好的B液通过吸浆管2连接至注浆泵4,配比好的C液通过吸浆管3连接至注浆泵4,注浆泵4通过输浆管5将浆液输送至注浆管6。After the system is ready, as shown in Figure 2, the well-proportioned liquid A is connected to the grouting pump 4 through the grout suction pipe 1, and the well-proportioned liquid B is connected to the grouting pump 4 through the grout suction pipe 2. Liquid C is connected to the grouting pump 4 through the grouting pipe 3 , and the grouting pump 4 delivers the grout to the grouting pipe 6 through the grouting pipe 5 .

首先开通吸浆管2、吸浆管3,同时关闭吸浆管1,浆液通过双重管压入地层中。完成100L的设计注浆量后或者注浆压力突然增大时,开通吸浆管1、吸浆管2,关闭吸浆管3,浆液通过双重管压入地层中,随着注浆管6上拔,注浆压力突然减小时重复开通吸浆管2、吸浆管3、关闭吸浆管1的操作。采用隔孔注入方式,这样既避免注浆孔互相影响,又使后注孔起到补充先注孔的作用,保证土体浆液扩散均匀。First open the slurry suction pipe 2 and the slurry suction pipe 3, and close the slurry suction pipe 1 at the same time, and the slurry is pressed into the formation through the double pipes. After completing the designed grouting volume of 100L or when the grouting pressure suddenly increases, open the grouting pipe 1 and the grouting pipe 2, close the grouting pipe 3, the grout is pressed into the formation through the double pipes, and as the grouting pipe 6 goes up When the grouting pressure suddenly decreases, repeat the operation of opening the grout suction pipe 2, grout suction pipe 3, and closing the grout suction pipe 1. The method of injecting through holes is adopted, which not only avoids the mutual influence of the grouting holes, but also makes the post-grouting holes play the role of supplementing the first-grouting holes, so as to ensure that the soil grout spreads evenly.

压力、注浆量控制Pressure and grouting volume control

通过压力表7观察注浆压力,检查随注浆量的增加,压力变化情况。注浆过程中采用压力控制,注浆压力控制在1.5-3MPa、注浆速度为60L/min,当注浆时间达到15分钟同时注浆压力达到2.0Mpa时,或者注浆压力超过3MPa,双重管往上提0.1m后,继续注浆,直到注浆完成。Observe the grouting pressure through the pressure gauge 7, and check the pressure change with the increase of the grouting amount. Pressure control is adopted during the grouting process, the grouting pressure is controlled at 1.5-3MPa, and the grouting speed is 60L/min. When the grouting time reaches 15 minutes and the grouting pressure reaches 2.0Mpa, or the grouting pressure exceeds 3MPa, double pipe After lifting up 0.1m, continue grouting until the grouting is complete.

本发明虽然以较佳实施例公开如上,但其并不是用来限定本发明,任何本领域技术人员在不脱离本发明的精神和范围内,都可以做出可能的变动和修改,因此本发明的保护范围应当以本发明权利要求所界定的范围为准。如上所述,对本发明的实施例进行了详细地说明,但是只要实质上没有脱离本发明的发明点及效果可以有很多的变形,这对本领域的技术人员来说是显而易见的。因此,这样的变形例也全部包含在本发明的保护范围之内。Although the present invention is disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make possible changes and modifications without departing from the spirit and scope of the present invention. Therefore, the present invention The scope of protection should be based on the scope defined by the claims of the present invention. As mentioned above, although the Example of this invention was demonstrated in detail, it is obvious to those skilled in the art that many modifications can be made as long as the inventive point and effect of this invention are not substantially deviated. Therefore, all such modified examples are also included in the protection scope of the present invention.

Claims (2)

1. a sand-pebble layer deep foundation ditch segmentation retrusive biliquid combined casting job practices is characterized in that, may further comprise the steps:
1) determines the grouting and reinforcing scheme, determine the position of injected hole, arrangement, injected hole spacing, injected hole array pitch and the drilling depth of injected hole, determine rig model, grouting pump model; Wherein, position, injected hole hole is distributed in the middle of the fender post and the outside, totally two arranges, and injected hole adopts quincuncial arrangement;
2) in-site measurement unwrapping wire is mainly located work according to SURVEYING CONTROL NETWORK with total powerstation, is carried out the setting-out work of thin portion size again by drawing by unwrapping wire class;
3) boring behind the pore-forming, is transferred dual Grouting Pipe, and pipe extractor is installed then, extracts drilling rod;
4) slurries preparation,
A liquid: cement grout, adopt normal silicate P.O42.5 cement, add water, the water intaking gray scale is 0.8-1.3;
B liquid: the water glass slurries, adopt concentration 42Be ' water glass to mix with water 1:1;
C liquid: phosphoric acid solution, add water, getting solution concentration is 3%-8%;
A liquid, B liquid, C liquid stir respectively, the concentration that the consolidation time that requires according to slurries is regulated each slurries; Wherein equal-volume mixes back formation cement-sodium silicate slurries than A liquid with B liquid, and the B liquid of equal-volume ratio mixes formation modified water glass slurries with C liquid;
5) slip casting,
(a) mode of injecting every the hole is adopted in slip casting, with cement-sodium silicate slurries and the compound injection of modified water glass slurries biliquid, is specially: during slip casting, annotate modified water glass slurries, cementing again-water glass slurries earlier; Two kinds of slurries mixing slip castings in the slip casting process, interior row's injected hole injects modified water glass slurries (B liquid and C liquid), effluxes and then injects cement-sodium silicate slurries (A liquid and B liquid); Want the Real Time Observation grouting pressure during slip casting, but cementing-water glass biliquid slurry (A liquid and B liquid) when pressure is big, and pressure hour can be annotated modified water glass slurries (B liquid and C liquid) with rapid filling;
(b) grouting pressure control is that 60L/min, slip casting section length are to control at 20s-90s 5-10cm, slurry consolidation time at 1.5-3MPa, injection speed;
(c) when grouting amount surpass design load 80% simultaneously grouting pressure reach 2MPa, perhaps grouting pressure surpasses 3MPa, after carrying on the dual pipe, repeats above-mentioned slip casting process, finishes up to slip casting.
2. a kind of sand-pebble layer deep foundation ditch segmentation retrusive biliquid combined casting job practices according to claim 1, it is characterized in that, in the step 3), need before the boring to be hardened in ground in the wide 2m scope around the boring, C20 concrete, thickness 30cm are adopted in sclerosis.
CN201310179909.3A 2013-05-15 2013-05-15 Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum Expired - Fee Related CN103266614B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310179909.3A CN103266614B (en) 2013-05-15 2013-05-15 Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310179909.3A CN103266614B (en) 2013-05-15 2013-05-15 Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum

Publications (2)

Publication Number Publication Date
CN103266614A true CN103266614A (en) 2013-08-28
CN103266614B CN103266614B (en) 2015-04-29

Family

ID=49010268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310179909.3A Expired - Fee Related CN103266614B (en) 2013-05-15 2013-05-15 Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum

Country Status (1)

Country Link
CN (1) CN103266614B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485345A (en) * 2013-09-26 2014-01-01 葛洲坝集团基础工程有限公司 Construction method for covering layer closed porthole high-pressure curtain grouting
CN104533448A (en) * 2014-11-06 2015-04-22 海南大学 Construction method for stopping water and reinforcing end of shield tunnel in lithosphere
CN104674831A (en) * 2015-02-11 2015-06-03 中国水利水电第四工程局有限公司 Water-stopping curtain construction method
CN105155541A (en) * 2015-08-21 2015-12-16 中铁城建集团第三工程有限公司 Double-slurry closing construction method for sump
CN105155544A (en) * 2015-08-04 2015-12-16 中铁建大桥工程局集团第五工程有限公司 Grouting construction method for radius-controllable deep holes
CN105220695A (en) * 2015-08-21 2016-01-06 中铁建大桥工程局集团第五工程有限公司 Close sand ovum layer moves water slip casting solidification construction
CN105971638A (en) * 2015-03-12 2016-09-28 中铁隆工程集团有限公司 Application of WSS construction method in shield tool changing reinforcement of water-rich sand layer
CN105971637A (en) * 2015-03-12 2016-09-28 中铁隆工程集团有限公司 Application of WSS construction method in shield end reinforcement of water-rich sand layer
CN106677190A (en) * 2017-01-24 2017-05-17 中交第二公路工程局有限公司 Grouting construction method for underwater pebble bed foundation pit curtain
CN107288658A (en) * 2017-08-04 2017-10-24 河北天理环保科技有限公司 Underground concrete water-proof engineering connects the casting method of stubble seam
CN107795021A (en) * 2016-08-30 2018-03-13 盛世安泰建筑工程(北京)有限公司 Minimally invasive leak stopping system and its construction technology
CN108797621A (en) * 2018-07-20 2018-11-13 中铁十八局集团有限公司 A kind of water sealing structure and its construction method in rich water depth ovum gravel erratic boulder stratum front pre-grouting
CN109723468A (en) * 2019-01-14 2019-05-07 北京建工土木工程有限公司 The method that slip casting is carried out to power shallow-buried tunnel engineering based on remote control slip casting trolley
CN110529155A (en) * 2019-09-26 2019-12-03 中铁隧道局集团有限公司 A kind of drill bit only starches drilling rod and is segmented retrusive grouting method
CN111036660A (en) * 2019-12-31 2020-04-21 北京高能时代环境技术股份有限公司 In-situ curing method for heavy metal polluted sandy gravel soil layer
CN111648748A (en) * 2020-07-01 2020-09-11 广州海洋地质调查局 A method for in-situ heating and depressurization exploitation of marine natural gas hydrate with stable formation
CN112963158A (en) * 2021-05-18 2021-06-15 北京城建道桥建设集团有限公司 Double-liquid grouting method and slurry for pore stratum
CN118686046A (en) * 2024-06-25 2024-09-24 山东高速集团有限公司创新研究院 A two-component polymer extraction grouting reinforcement device and method for deep-seated highway damage

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04318096A (en) * 1991-04-17 1992-11-09 Dai Ichi Kogyo Seiyaku Co Ltd Grouting liquid composition for stabilizing soil, etc., and stabilization and reinforcement of soil using the same
CN102296600A (en) * 2011-09-01 2011-12-28 北京交通大学 Method for positioning middle pile of spread built subway station
CN102493498A (en) * 2011-12-29 2012-06-13 荣盛建设工程有限公司 Construction process for foundation
CN102606167A (en) * 2012-03-16 2012-07-25 西安理工大学 Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04318096A (en) * 1991-04-17 1992-11-09 Dai Ichi Kogyo Seiyaku Co Ltd Grouting liquid composition for stabilizing soil, etc., and stabilization and reinforcement of soil using the same
CN102296600A (en) * 2011-09-01 2011-12-28 北京交通大学 Method for positioning middle pile of spread built subway station
CN102493498A (en) * 2011-12-29 2012-06-13 荣盛建设工程有限公司 Construction process for foundation
CN102606167A (en) * 2012-03-16 2012-07-25 西安理工大学 Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485345A (en) * 2013-09-26 2014-01-01 葛洲坝集团基础工程有限公司 Construction method for covering layer closed porthole high-pressure curtain grouting
CN104533448A (en) * 2014-11-06 2015-04-22 海南大学 Construction method for stopping water and reinforcing end of shield tunnel in lithosphere
CN104674831A (en) * 2015-02-11 2015-06-03 中国水利水电第四工程局有限公司 Water-stopping curtain construction method
CN105971638A (en) * 2015-03-12 2016-09-28 中铁隆工程集团有限公司 Application of WSS construction method in shield tool changing reinforcement of water-rich sand layer
CN105971637A (en) * 2015-03-12 2016-09-28 中铁隆工程集团有限公司 Application of WSS construction method in shield end reinforcement of water-rich sand layer
CN105155544A (en) * 2015-08-04 2015-12-16 中铁建大桥工程局集团第五工程有限公司 Grouting construction method for radius-controllable deep holes
CN105155541A (en) * 2015-08-21 2015-12-16 中铁城建集团第三工程有限公司 Double-slurry closing construction method for sump
CN105220695A (en) * 2015-08-21 2016-01-06 中铁建大桥工程局集团第五工程有限公司 Close sand ovum layer moves water slip casting solidification construction
CN105155541B (en) * 2015-08-21 2017-03-01 中铁城建集团第三工程有限公司 A kind of dual slurry closure construction method of catch pit
CN105220695B (en) * 2015-08-21 2017-05-10 中铁建大桥工程局集团第五工程有限公司 Compact sandy-pebble layer dynamic grouting curing construction method
CN107795021A (en) * 2016-08-30 2018-03-13 盛世安泰建筑工程(北京)有限公司 Minimally invasive leak stopping system and its construction technology
CN106677190A (en) * 2017-01-24 2017-05-17 中交第二公路工程局有限公司 Grouting construction method for underwater pebble bed foundation pit curtain
CN107288658A (en) * 2017-08-04 2017-10-24 河北天理环保科技有限公司 Underground concrete water-proof engineering connects the casting method of stubble seam
CN107288658B (en) * 2017-08-04 2019-04-26 中煤第一建设有限公司 Underground concrete water-proof engineering connects the casting method of stubble seam
CN108797621A (en) * 2018-07-20 2018-11-13 中铁十八局集团有限公司 A kind of water sealing structure and its construction method in rich water depth ovum gravel erratic boulder stratum front pre-grouting
CN109723468A (en) * 2019-01-14 2019-05-07 北京建工土木工程有限公司 The method that slip casting is carried out to power shallow-buried tunnel engineering based on remote control slip casting trolley
CN110529155A (en) * 2019-09-26 2019-12-03 中铁隧道局集团有限公司 A kind of drill bit only starches drilling rod and is segmented retrusive grouting method
CN110529155B (en) * 2019-09-26 2020-11-06 中铁隧道局集团有限公司 Drill bit grout stopping drill rod sectional retreating type grouting method
CN111036660A (en) * 2019-12-31 2020-04-21 北京高能时代环境技术股份有限公司 In-situ curing method for heavy metal polluted sandy gravel soil layer
CN111648748A (en) * 2020-07-01 2020-09-11 广州海洋地质调查局 A method for in-situ heating and depressurization exploitation of marine natural gas hydrate with stable formation
CN112963158A (en) * 2021-05-18 2021-06-15 北京城建道桥建设集团有限公司 Double-liquid grouting method and slurry for pore stratum
CN112963158B (en) * 2021-05-18 2021-10-08 北京城建道桥建设集团有限公司 Double-liquid grouting method and slurry for pore stratum
CN118686046A (en) * 2024-06-25 2024-09-24 山东高速集团有限公司创新研究院 A two-component polymer extraction grouting reinforcement device and method for deep-seated highway damage

Also Published As

Publication number Publication date
CN103266614B (en) 2015-04-29

Similar Documents

Publication Publication Date Title
CN103266614B (en) Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum
CN110230309B (en) Karst area bridge karst cave pile foundation construction method
CN101638987B (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
CN100580188C (en) Construction method of decompression double-liquid rotary spraying in quadruple pipe formation
CN105178326B (en) Upper soft lower hard water rich strata base pit engineering building enclosure water-stopping method
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN103410182B (en) Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN103953365A (en) Tunnel single-liquid and double-liquid alternate grouting reinforcement process and device
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN111119940B (en) Grouting construction treatment method
CN103388338B (en) A kind of method of novel quick sealing and soil improvement
CN105351001B (en) A method of strengthening gas drainage based on gob-side entry retaining area
CN109881696A (en) A kind of HPPG back cover construction method
CN102011591A (en) Grouting process for working surface of deep well
CN107060821A (en) A kind of many lithology method for protecting support of face
CN102838325A (en) Hole sealing grout stop material and grouting hole sealing process
CN109826635B (en) Construction method for reinforcing shield receiving space peripheral soil body constructed by subsurface excavation method
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN110700842A (en) An advanced grouting reinforcement method suitable for the water-rich sand layer at the shield end
CN102817361B (en) Double bushing top cover for broken rock curtain grouting and construction method of double bushing top cover
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN102995647B (en) A Groundwater Control Method for Pile Hole Grouting and Seepage Isolation
CN203161250U (en) Deep hole grouting reinforcing system for tunnel

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20130828

Assignee: Beijing Geotechnical Engineering Association

Assignor: Hansei China Trade Co.,Ltd.|BEIJING MUNICIPAL CONSTRUCTION Group Co.,Ltd.|Beijing Jiaotong University

Contract record no.: 2015990000893

Denomination of invention: Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum

Granted publication date: 20150429

License type: Exclusive License

Record date: 20151026

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150429