CN103255768A - Grouting construction method of engineering well after bottom wall in pipe is sealed - Google Patents

Grouting construction method of engineering well after bottom wall in pipe is sealed Download PDF

Info

Publication number
CN103255768A
CN103255768A CN2013101781808A CN201310178180A CN103255768A CN 103255768 A CN103255768 A CN 103255768A CN 2013101781808 A CN2013101781808 A CN 2013101781808A CN 201310178180 A CN201310178180 A CN 201310178180A CN 103255768 A CN103255768 A CN 103255768A
Authority
CN
China
Prior art keywords
grouting
pipe
well casing
well
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101781808A
Other languages
Chinese (zh)
Inventor
聂庆科
孙运青
张军旗
杨海朋
杨征
冯立民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Prospecting Research Institute Co Ltd
Original Assignee
Hebei Construction Prospecting Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Prospecting Research Institute Co Ltd filed Critical Hebei Construction Prospecting Research Institute Co Ltd
Priority to CN2013101781808A priority Critical patent/CN103255768A/en
Publication of CN103255768A publication Critical patent/CN103255768A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a grouting construction method of an engineering well after the bottom wall in a pipe is sealed. The method includes the steps of firstly installing a floating plate on the bottom of a bottom joint well pipe of the engineering well in a welding mode, carrying out welding and reinforcement through a cross-shaped steel plate, and welding and reinforcing a connection portion of the bottom of the bottom joint well pipe and the inner wall of the well pipe, secondly arranging at least two sets of grouting pipes in a symmetrical mode along the outer side of the well pipe, inserting one set of grouting pipes into the bottom of the well pipe, arranging other sets of grouting pipes on positions with the distance of 1m from the bottom of the well pipe, welding the grouting pipes through pipe hoops, and welding the grouting pipes with the well pipe firmly, thirdly, welding a steel plate protection device on a pipe opening of the grouting pipe at the bottom joint, preforming a grouting hole in the side face of the protection device, and connecting the grouting pipes and a grouting pump on a well opening through a high-pressure rubber pipe, fourthly, determining grouting filling sections and grouting filling times, fifthly, installing and connecting the grouting pump, carrying out grouting filling operation till design demands are met, and completing grouting and cementing. A grouting system is simple in structure, convenient to operate, improves construction efficiency and reduces construction risks.

Description

Back cover grouting behind shaft or drift lining job practices in a kind of engineering well casing
 
Technical field
The present invention relates to back cover grouting behind shaft or drift lining job practices in a kind of engineering well support with backfilling grouting construction method, particularly a kind of engineering well casing, belong to mine and municipal engineering construction technical field.
Background technology
In the engineering construction construction, the mechanical boring method drilling construction of the many employings of diameter 0.8~1.5m engineering well, after well casing is laid and is put in place, traditional cement slurry cementing method mainly contains two kinds: a kind of is in the well casing bottom kickboard to be installed to make well casing become a semi-enclosed floating body, one way valve is installed at the kickboard top, and is connected with Grouting Pipe, adopts the floating and dropping method of cylindrical shaft wall method, utilize in the well and carry out slip casting behind the buoyancy of liquid effect sinking well casing, realize well cementation.The shortcoming of this method is that the impurity in the slurries stops up one way valve easily, causes grouting pipeline obstructed, or because Grouting Pipe connects the insecure cement paste that causes to be leaked in the well casing, causes the slip casting accident.Another kind method is that mouth does not seal at the bottom of the well casing, adopts nature sinking method to lay well casing, and well casing is laid Grouting Pipe after sinking to finishing in well casing, and the sealing well casing is suitable for reading to carry out slip casting.The shortcoming of this method is when the well casing deadweight is big, can't implement owing to the lifting appliance capabilities limits causes the nature sinking scheme.
Summary of the invention
The purpose of this invention is to provide back cover grouting behind shaft or drift lining job practices in a kind of engineering well casing, be used for the interior back cover grouting behind shaft or drift lining construction of pipe of diameter 0.8~1.5m engineering well, realized well casing mortar depositing construction safety.
The object of the present invention is achieved like this: back cover grouting behind shaft or drift lining job practices in a kind of engineering well casing may further comprise the steps:
(1) thickness being installed in the bottom of coxopodite well casing is 25~30mm steel kickboard, and uses the cross steel plate reinforcement of weld, and kickboard and well casing inwall are fastenedly connected, and makes well casing and kickboard form a semi-enclosed integral body;
(2) be no less than 2 cover Grouting Pipe along well casing outer wall symmetric arrangement, wherein a cover stretches into the well casing bottom, all the other place high 1m place at the bottom of the well casing, the Grouting Pipe internal diameter is 40~60mm, wall thickness 3~5mm, the single-unit Grouting Pipe is welded to connect by pipe collar, Grouting Pipe and well casing firmly weld, sink to laying simultaneously with well casing, for preventing that the mud skin stops up Grouting Pipe in the well casing sinking installation course, protector in the making of coxopodite Grouting Pipe mouth of pipe welding 10mm steel plate, guard sideways is reserved grout outlet, and Grouting Pipe is connected by high-pressure rubber pipe with grouting pump at well head, in conjunction with well casing suspender crane capacity, adjust the ballast water height in the well casing, utilize the floating and dropping method of cylindrical shaft wall method to lay well casing to projected depth;
(3) calculate definite grouting filling section and grouting filling number of times, avoid the excessive well casing come-up that causes of grouting filling height, the first section high grouting filling in well casing bottom carries out in whole well casings sank to finishing back 3 days;
(4) adopt vehicle-mounted can cement, directly be connected with automatic mixing drum, the mixer configuration is no less than 2, the configuration requirement of mixer is that its stirring capacity is finished primary filling in 6 ~ 8 hours, adopts and stirs slurry systems produce cement paste automatically, air-supply earlier before the water supply mud, after send cement, the mud of cutting off the water earlier when stopping, it is out-of-blast again to treat in the pipeline that cement all enters when stirring slurry jar, and the setting of agitator tank cement pipeline entrance prevents the device that stops up;
(5) installation and connection grouting pump, the grouting filling operation, the pressure limit of grouting pump is 0.1~1.0MPa, be provided with valve between each grouting pump and the grouting pipeline, to prevent that grouting pipeline from stopping up, slip casting is carried out continuously, and the time of at every turn resting is no more than 0.5 hour, meet design requirement until slip casting, finish the slip casting well cementing operation.
The present invention is specially adapted to diameter 0.8~1.5m engineering well support with backfilling mortar depositing construction.
The beneficial effect that the present invention obtains is:
The steel kickboard is installed at the bottom of the well casing, has reduced the risk of well casing bottom slurries seepage, improved the slip casting safety.Grouting pipeline is external, and protector is set, and lays simultaneously with well casing, has improved the quality of connection of grouting pipeline and the reliability of laying, and has reduced construction risk.
Description of drawings
Fig. 1 is filling schematic diagram of the present invention.
The implication of number in the figure representative is: 1, borehole wall 2, valve 3, well casing 4, annular gap 5, kickboard 6, Grouting Pipe 7, protected apron 8, pipe collar 9, one way valve 10, high-pressure rubber pipe 11, grouting pump.
The specific embodiment
Following examples are used for explanation the present invention.
Embodiment
Certain ground boring gas pipeline engineering, bore diameter 1200mm, hole depth 412.5m, well casing are the seamless steel pipe of external diameter 820mm, adopt floating method to lay, and the outer Grouting Pipe of twice is installed when well casing is laid.This engineering adopts back cover support with backfilling cement slurry cementing in the pipe, and theory is filled amount of fill 248m 3, actual support with backfilling amounts to 269m 3Utilize grouting construction method of the present invention, concrete steps are as follows:
1, steel kickboard 5 is installed in the bottom of coxopodite well casing 3, thickness 30mm is processed into the plectane of diameter 830mm, is welded to connect with well casing 3.Kickboard 5 adopts thick 30mm, high 200mm steel plate to carry out " ten " reinforcement of weld, and arrange at the bottom of four 200mm() * the 200mm(height) the triangle gusset welds well casing 3 inwalls and kickboard 5.Weld seam should be full, and the weldering of leakage, slag inclusion, seminess must not be arranged.
2, Grouting Pipe 6 is external diameter 60mm, wall thickness 3mm hot rolled seamless steel tube, and the long 6m of single-unit, by internal diameter 62mm, the pipe collar 8 of thick 5mm is welded to connect.Stretch into well casing 1 bottom along well casing 3 outer wall symmetric arrangement two cover Grouting Pipe 2, one covers, one is placed on above 1m place, 1 end of well casing, and one way valve 9 is installed in Grouting Pipe 6 bottoms, and Grouting Pipe 6 and well casing 3 firm welding are laid simultaneously.
3, pipe collar 8 places add the high 70mm of weldering, thick 10mm steel protected apron 7 protection Grouting Pipe 6, can prevent that the mud skin from stopping up Grouting Pipe.
4, adopt the once grouting well cementation, for preventing the well casing come-up, apply the counterweight that is not less than 40t in the well casing.
5, the used cement of slip casting, materials such as flyash adopt vehicle-mounted can cement, and cement grout is mechanical agitation in the automatic mixing drum of special use, and this engineering is calculated total grouting amount according to 1.2 fullness coefficient and is about 303 m 3, each every can be stirred 6m 3, mixing time is 10 minutes, can finish cement paste and stir in 5 hours, satisfies construction requirement.
6, the pressure limit of grouting pump 11 is 0.1~1.0MPa during slip casting, and mortar depositing construction carries out continuously, between each grouting pump and the grouting pipeline valve is set, and the time of at every turn resting must not surpass 0.5 hour, prevent that grouting pipeline from stopping up.
7, connect Grouting Pipe 6 and grouting pump 11 with high-pressure rubber pipe 10, valve 2 is set, finish back cover grouting behind shaft or drift lining device in the pipe.
8, mix up cement grout, open valve 2, open grouting pump 11, carry out the slip casting operation according to design parameters, until reaching designing requirement, finish the slip casting work in well casing outer ring-like gap 4.

Claims (1)

1. back cover grouting behind shaft or drift lining job practices in the engineering well casing is characterized in that may further comprise the steps:
(1) thickness being installed in the bottom of coxopodite well casing is 25~30mm steel kickboard, and uses the cross steel plate reinforcement of weld, and kickboard and well casing inwall are fastenedly connected, and makes well casing and kickboard form a semi-enclosed integral body;
(2) be no less than 2 cover Grouting Pipe along well casing outer wall symmetric arrangement, wherein a cover stretches into the well casing bottom, all the other place high 1m place at the bottom of the well casing, the Grouting Pipe internal diameter is 40~60mm, wall thickness 3~5mm, the single-unit Grouting Pipe is welded to connect by pipe collar, Grouting Pipe and well casing firmly weld, sink to laying simultaneously with well casing, at the protector that coxopodite Grouting Pipe mouth of pipe welding 10mm steel plate is made, guard sideways is reserved grout outlet, Grouting Pipe is connected by high-pressure rubber pipe with grouting pump at well head, in conjunction with well casing suspender crane capacity, adjust the ballast water height in the well casing, utilize the floating and dropping method of cylindrical shaft wall method to lay well casing to projected depth;
(3) calculate definite grouting filling section and grouting filling number of times, avoid the excessive well casing come-up that causes of grouting filling height, the first section high grouting filling in well casing bottom carries out in whole well casings sank to finishing back 3 days;
(4) adopt vehicle-mounted can cement, directly be connected with automatic mixing drum, the mixer configuration is no less than 2, the configuration requirement of mixer is that its stirring capacity is finished primary filling in 6 ~ 8 hours, adopts and stirs slurry systems produce cement paste automatically, air-supply earlier before the water supply mud, after send cement, the mud of cutting off the water earlier when stopping, it is out-of-blast again to treat in the pipeline that cement all enters when stirring slurry jar, and the setting of agitator tank cement pipeline entrance prevents the device that stops up;
(5) installation and connection grouting pump, the pressure limit of grouting pump is 0.1~1.0MPa, is provided with valve between each grouting pump and the grouting pipeline, slip casting is carried out continuously, the time of at every turn resting is no more than 0.5 hour, meets design requirement until slip casting, finishes the slip casting well cementing operation.
CN2013101781808A 2013-05-15 2013-05-15 Grouting construction method of engineering well after bottom wall in pipe is sealed Pending CN103255768A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101781808A CN103255768A (en) 2013-05-15 2013-05-15 Grouting construction method of engineering well after bottom wall in pipe is sealed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101781808A CN103255768A (en) 2013-05-15 2013-05-15 Grouting construction method of engineering well after bottom wall in pipe is sealed

Publications (1)

Publication Number Publication Date
CN103255768A true CN103255768A (en) 2013-08-21

Family

ID=48959952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101781808A Pending CN103255768A (en) 2013-05-15 2013-05-15 Grouting construction method of engineering well after bottom wall in pipe is sealed

Country Status (1)

Country Link
CN (1) CN103255768A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883348A (en) * 2014-04-02 2014-06-25 淮北矿业(集团)勘探工程有限责任公司 Method for welding well ground pipeline for gas extraction in mining area
CN105756066A (en) * 2016-04-22 2016-07-13 江苏巨鑫石油钢管有限公司 Grouting system used for wharf and bridge piling steel pipe and processing technology thereof
CN107780879A (en) * 2017-09-15 2018-03-09 核工业北京化工冶金研究院 A kind of reverse inlet well well formation device and method
CN109629573A (en) * 2019-01-15 2019-04-16 中交哈尔滨地铁投资建设有限公司 A kind of pouch slip casting borehole wall water sealing structure
CN109723070A (en) * 2018-12-28 2019-05-07 上海二十冶建设有限公司 Concrete well mounting device and application method for underground tube well dewatering
CN111322075A (en) * 2019-10-28 2020-06-23 中国铁建重工集团股份有限公司 Backfill slip casting system behind wall for shaft boring machine
CN113789803A (en) * 2021-10-28 2021-12-14 北京中地恒基建筑工程有限公司 Construction method of slender open caisson and slender open caisson structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288292A (en) * 1986-06-09 1987-12-15 株式会社竹中工務店 Method for confirming water escape preventing effect of deepboring hole by chemical solution of isocyanate compound
CN101705823A (en) * 2009-11-03 2010-05-12 徐英 Delayed coagulation well cementation method of high-pressure gas underground gas storage wells
CN201883435U (en) * 2010-09-17 2011-06-29 广州市建筑科学研究院有限公司 Preburied pipe pile grouting device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288292A (en) * 1986-06-09 1987-12-15 株式会社竹中工務店 Method for confirming water escape preventing effect of deepboring hole by chemical solution of isocyanate compound
CN101705823A (en) * 2009-11-03 2010-05-12 徐英 Delayed coagulation well cementation method of high-pressure gas underground gas storage wells
CN201883435U (en) * 2010-09-17 2011-06-29 广州市建筑科学研究院有限公司 Preburied pipe pile grouting device

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张永成等: "《钻井技术》", 31 August 2008, 煤炭工业出版社 *
王梦恕: "《大瑶山隧道:20世纪隧道修建新技术》", 31 December 1994, 广东科技出版社 *
程荷兰等: "竖井井壁漂浮下沉过程的力学行为", 《北京交通大学学报》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103883348A (en) * 2014-04-02 2014-06-25 淮北矿业(集团)勘探工程有限责任公司 Method for welding well ground pipeline for gas extraction in mining area
CN103883348B (en) * 2014-04-02 2016-04-20 淮北矿业(集团)勘探工程有限责任公司 The welding method of a kind of minery gas pumping well ground pipeline
CN105756066A (en) * 2016-04-22 2016-07-13 江苏巨鑫石油钢管有限公司 Grouting system used for wharf and bridge piling steel pipe and processing technology thereof
CN107780879A (en) * 2017-09-15 2018-03-09 核工业北京化工冶金研究院 A kind of reverse inlet well well formation device and method
CN109723070A (en) * 2018-12-28 2019-05-07 上海二十冶建设有限公司 Concrete well mounting device and application method for underground tube well dewatering
CN109723070B (en) * 2018-12-28 2021-03-26 上海二十冶建设有限公司 Concrete well pipe installation device for underground pipe well precipitation and use method
CN109629573A (en) * 2019-01-15 2019-04-16 中交哈尔滨地铁投资建设有限公司 A kind of pouch slip casting borehole wall water sealing structure
CN111322075A (en) * 2019-10-28 2020-06-23 中国铁建重工集团股份有限公司 Backfill slip casting system behind wall for shaft boring machine
CN111322075B (en) * 2019-10-28 2021-11-23 中国铁建重工集团股份有限公司 Backfill slip casting system behind wall for shaft boring machine
CN113789803A (en) * 2021-10-28 2021-12-14 北京中地恒基建筑工程有限公司 Construction method of slender open caisson and slender open caisson structure

Similar Documents

Publication Publication Date Title
CN103255768A (en) Grouting construction method of engineering well after bottom wall in pipe is sealed
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN104389623B (en) Shield tunnel prefabricated tunnel segment lining back stratum grouting device
CN107059903A (en) Bottom plate plugging dewatering well construction method is worn in foundation ditch
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN101333812A (en) Grouter for back side grouting and its construction method
CN109519150B (en) Dewatering well plugging device and method for large water yield
CN109763483A (en) A kind of thick 4th is buried excavation collapse broken formation upstriker segmenting slip casting technique
CN106978821A (en) A kind of soft soil layer reduces shield driving and applies method to the retaining design that building foundation influences
CN106522252A (en) Seepage-proofing blocking mechanism and method for deep foundation pit raft dewatering well
CN203145029U (en) Plugging structure for deep foundation pit dewatering well
CN201795223U (en) Internal repair expansion device for pipeline cracking
CN206636579U (en) A kind of subway shield tunnel construction feeding device
CN102839691A (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN208563315U (en) A kind of pile foundation grouting behind shaft or drift lining constructing device
CN111206610A (en) Construction method for treating piping of exploration hole of foundation pit by curtain grouting method
CN103205986A (en) Concrete raft foundation construction-joint grouting device and construction method
CN108360542A (en) Waterproof between piles curtain combination stake side sleeve valve barrel grouting water stop construction method
CN104564105B (en) A kind of apparatus and method of two grades of sleeve pipes of seat earth grouting and reinforcing
CN204780962U (en) Built -in anti sea anchor pole block structure of deep well precipitation well in soleplate
CN110469338A (en) A kind of artesian water stratum shield method of reseptance
CN203880321U (en) Grouting device for repairing blank pipe empty shell of lining type prestressed concrete cylinder pipeline
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN103174154A (en) Underground building bottom plate water burst well pit solid seal method and auxiliary water lowering device
CN210946855U (en) Plugging device for dewatering well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130821