CN102839691A - Quick sealing method and device for sandless cement pipe deep well dewatering wellhead - Google Patents

Quick sealing method and device for sandless cement pipe deep well dewatering wellhead Download PDF

Info

Publication number
CN102839691A
CN102839691A CN2011101749837A CN201110174983A CN102839691A CN 102839691 A CN102839691 A CN 102839691A CN 2011101749837 A CN2011101749837 A CN 2011101749837A CN 201110174983 A CN201110174983 A CN 201110174983A CN 102839691 A CN102839691 A CN 102839691A
Authority
CN
China
Prior art keywords
cement pipe
steel sleeve
sand cement
well
flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011101749837A
Other languages
Chinese (zh)
Other versions
CN102839691B (en
Inventor
苏源
孙兴春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Original Assignee
NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd filed Critical NANTONG HAIZHOU CONSTRUCTION GROUP CO Ltd
Priority to CN201110174983.7A priority Critical patent/CN102839691B/en
Publication of CN102839691A publication Critical patent/CN102839691A/en
Application granted granted Critical
Publication of CN102839691B publication Critical patent/CN102839691B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)
  • Joints With Sleeves (AREA)

Abstract

The invention discloses a quick sealing method and a device for a sandless cement pipe deep well dewatering wellhead. A prefabricated steel sleeve is inserted into a sandless cement pipe; at least one water stop plate is arranged on an outer side wall of the steel sleeve; materials such as polyurethane sealants and SBS (styrene-butadiene-styrene) waterproof coiled materials are adopted among the steel sleeve, the sandless cement pipe and a foundation concrete cushion for comprehensive water resistance; hard concrete is poured into the steel sleeve; and the upper part of the steel sleeve is connected by a sealing plate, a waterproof rubber mat and a flange for once quick sealing, so that the problem of water seepage inside and outside a pipe well after being sealed is avoided.

Description

No sand cement pipe deep-well precipitation well head rapid plugging method and device thereof
Technical field
The present invention relates to precipitation well blocking technology field, relate in particular to a kind of no sand cement pipe deep-well precipitation well head rapid plugging method and device thereof.
Background technology
In the middle of the process of the deep foundation pit precipitation well of basement in high rise building, underground garage and civil air defense constructions and installations excavation; Because the infiltration of underground water in soil, the phenomenon of quicksand and gush takes place through regular meeting, gush on cheating that subsoil will not stop along with excavation; Side slope also will constantly be caved in; So not only can influence the excavation construction of the earthwork, and will have influence on the safety of adjacent building, structure and foundation pit supporting construction, also can have influence on the normal construction and the workmanship of building foundation simultaneously.
Deep foundation pit precipitation well adopts no sand cement pipe deep-well precipitation usually at present; Obtained using widely in fields such as building, railway, culverts, deep foundation pit precipitation well has plurality of advantages such as precipitation has quick construction, displacement is big, precipitation is dark, drainage effect is good, well spacing is big.
Current deep foundation pit precipitation well is when its area is bigger, owing to receive the restriction of the precipitation depth and the precipitation radius of influence, deep foundation pit precipitation well must be embedded in the foundation ditch; But this moment, the shutoff of well head became a difficult problem, and the phenomenon of seepage often appears in conventional sale monopoly method for blocking easily in the middle of the process of shutoff or after shutoff, take a lot of work during handling; And leak stopping is not thorough; And conventional method for blocking can cause the cross-operation of work post, can influence the duration, and construction cost is high; Shutoff is got up also more difficult, is difficult to guarantee the quality and the effect of shutoff.
Summary of the invention
In order to solve the problem of above-mentioned existence; The object of the present invention is to provide that a kind of technology is simple, speed of application is fast, the cycle is short, can not influence construction speed, and good no sand cement pipe deep-well precipitation well head rapid plugging method and the used device of this method of disposable plugging effect.
To achieve these goals, the present invention adopts following technical scheme:
No sand cement pipe deep-well precipitation well head rapid plugging method, concrete steps are:
Step 1, the mouth of pipe are handled: laying base concrete bed course makes has certain intensity, makes that simultaneously no sand cement pipe well open height is higher than the base concrete bed course;
Step 2, steel sleeve are made: on the lateral wall of circular steel sleeve pipe, be welded with at least one seal plate; Welded top at steel sleeve has a flange; Several screws are set on the flange; The configuration corresponding bolts is provided with shrouding at the top of steel sleeve, and the rubber waterproof pad is set between shrouding and flange;
Step 3, steel sleeve are inserted fixing in advance: before the sole plate assembling reinforcement, steel sleeve is inserted in the no sand cement mouth of pipe, and near the bottom welded reinforcement support of one seal plate of no sand cement pipe import, make this seal plate be higher than no sand cement pipe well mouth;
Step 4, sealing joint waterproof: at steel sleeve with there is not between the sand cement pipe well mouth waterproof sealing of filling cream; After treating waterproof sealing cream drying; Adopt waterproof cement mortar will be near fill plug seal between one seal plate of no sand cement pipe import and the no sand cement pipe well mouth, make arc chord angle in the junction of no sand cement pipe and base concrete bed course with cement mortar, on arc chord angle, do waterproofing course one; Waterproofing course joins with following seal plate, and interface adopts the hot melt sealing;
Step 5, foundation construction: colligation basis end placing of reinforcement; Break off at no sand cement pipe well mouth place; Periphery is provided with reinforcing rib; Concreting around no sand cement pipe well mouth, no sand cement pipe well mouth top are that the back cast gate is kept somewhere at the center with the well head, after the well head quick blocking, adopt than the higher leveled expansive concrete teeming of circumferential concrete grade;
Step 6, at interval stop precipitation successively: stop precipitation should be a plurality of no sand cement pipe precipitation wells at interval progressively stop precipitation, individual well stops to take out water pump immediately behind the precipitation;
Step 7, fill out core and seal: no sand cement Guan Zhongyong fine sand is backfilling into the height of concrete cushion, drops in the steel sleeve vibration compacting again with the harsh concrete that is mixed with early strength admixture; And be poured into the top of steel sleeve always; On the flange at steel sleeve top, place the rubber waterproof pad immediately, cover shrouding, shrouding is fixed on the flange with bolt; Use the top of expansive concrete teeming again in steel sleeve; Make it to maintain an equal level vibration compacting, covering protection mutually with the concrete surface that does not have around the sand cement pipe well mouth.
Preferably, the sealing compound in the said step 4 adopts polyurethane water-proof sealing compound.
Preferably, the waterproofing course in the said step 4 adopts the SBS coil waterproof layer.
No sand cement pipe deep-well precipitation well head fast plugging device, it comprises no sand cement pipe and steel sleeve, steel sleeve comprises that steel tube body, flange, shrouding, bolt, rubber waterproof pad are with seal plate at least; Said no sand cement pipe is embedded in the middle of the base concrete bed course; Insert in the no sand cement pipe bottom of said steel sleeve, and said flange is positioned at the top of steel sleeve, and said shrouding is positioned at the top of flange; Be equipped with at least three screws on said flange and the shrouding; Said rubber waterproof pad is between flange and shrouding, and through the firm connection of bolt, said seal plate is positioned on the lateral wall of steel sleeve between said flange and the shrouding.
Preferably, be equipped with 12 screws on said flange and the shrouding.
Preferably, the lateral wall of said steel sleeve is provided with the twice seal plate, is positioned at the last seal plate that is at steel sleeve middle part, is positioned at the following seal plate that is of steel sleeve bottom.
Preferably, said steel sleeve and do not have filled polyurethane waterproof sealing cream between the sand cement pipe well mouth.
Preferably, fill waterproof cement mortar between said no sand cement pipe well mouth and the following seal plate.
Preferably, arc chord angle is made with cement mortar in said junction at no sand cement pipe and base concrete bed course, on arc chord angle, is provided with waterproofing course one, and waterproofing course joins with following seal plate, and interface adopts the hot melt sealing.
Preferably, said waterproofing course is the SBS coil waterproof layer.
Advantage of the present invention is: the steel sleeve that insertion is made in advance in the no sand cement pipe; On the lateral wall of steel sleeve, be provided with at least one seal plate; Between steel sleeve, no sand cement pipe and base concrete bed course, adopt materials such as polyurethane sealant, SBS coiled material to carry out comprehensive waterproof, build harsh concrete in the inside of steel sleeve, top couples together with shrouding, rubber waterproof pad and flange; Carry out disposable quick blocking, stopped the difficult problem of the inside and outside infiltration of shut-in well back pipe well.
Description of drawings
Fig. 1 is the schematic flow sheet of method among the present invention;
Fig. 2 is the structural representation that installs among the present invention.
Among the figure 1, no sand cement pipe, 2, steel sleeve, 201, steel tube body, 202, flange; 203, shrouding, 204, bolt, 205, the rubber waterproof pad, 206, go up seal plate; 207, following seal plate, 3, waterproof sealing cream, 4, waterproof cement mortar, 5, the SBS coil waterproof layer.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the present invention is done further to describe in detail explanation.
Of Fig. 1 to 2; No sand cement pipe deep-well precipitation well head rapid plugging method; The flow process of entire method is that the mouth of pipe is handled---the steel sleeve making---and steel sleeve is inserted fixing in advance---the sealing joint waterproof---foundation construction---stops precipitation---successively at interval, and fill out core and seal, wherein concrete steps are:
Step 1, the mouth of pipe are handled: laying base concrete bed course makes has certain intensity, makes that simultaneously no sand cement pipe 1 well head height is higher than base concrete bed course 220mm, and the external diameter of the no sand cement pipe 1 that uses in the present embodiment is 380mm, and internal diameter is 320mm;
Step 2, steel sleeve 2 are made: outside the hole, make circular steel sleeve pipe 2 on the ground, the external diameter of steel sleeve 2 is 300mm, and steel sleeve 2 wall thickness are 6.5mm; Welding twice steel plate for sealing water is respectively seal plate 206 and following seal plate 207 on the lateral wall of circular steel sleeve pipe 2, and last seal plate 206 is positioned at 1/2 height of steel sleeve 2; Following seal plate 207 is positioned at apart from 300mm place, steel sleeve 2 lower end, and the thickness of seal plate is 4mm, and width is 100mm; At flange 202 of welded top of steel sleeve 2, the thickness of flange 202 is 10mm, and width is that 12 screws are set on the 70mm flange 202; Dispose 12 corresponding bolts 204, the diameter of screw is 14mm, at the top of steel sleeve 2 shrouding 203 is set; The thickness of shrouding 203 is 10mm, between shrouding 203 and flange 202, rubber waterproof pad 205 is set, and the thickness of rubber waterproof pad 205 is 6mm.;
Step 3, steel sleeve 2 inserted fixing in advance: before the sole plate assembling reinforcement, steel sleeve 2 is inserted in 1 mouthful of the no sand cement pipe, and in the bottom welded reinforcement support of seal plate 207 down, make down seal plate 207 be higher than no sand cement pipe 1 well head 80mm;
Step 4, sealing joint waterproof: at steel sleeve 2 with there is not between sand cement pipe 1 well head waterproof sealing of filling cream 3; Waterproof sealing cream 3 in the present embodiment adopts polyurethane water-proof sealing compound 3; After treating waterproof sealing cream 3 dryings, adopt waterproof cement mortar 4 will descend the 80mm fill plug seal between seal plate 207 and no sand cement pipe 1 well head, make arc chord angle with cement mortar in the no sand cement pipe 1 and the junction of base concrete bed course; The radius of arc chord angle is 5cm; On arc chord angle, do SBS coil waterproof layer 5 one, SBS coil waterproof layer 5 is accomplished to join with following seal plate 207 always, and interface adopts the hot melt sealing;
Step 5, foundation construction: colligation basis end placing of reinforcement; Break off at no sand cement pipe 1 well head place; Periphery is provided with reinforcing rib; Concreting around no sand cement pipe 1 well head, no sand cement pipe 1 well head top are that the back cast gate is kept somewhere at the center with the well head, after the well head quick blocking, adopt than the higher leveled expansive concrete teeming of circumferential concrete grade;
Step 6, at interval stop precipitation successively: stop precipitation should be a plurality of no sand cement pipe 1 precipitation wells at interval progressively stop precipitation; Individual well stops to take out water pump immediately behind the precipitation; The adverse effect that minimizing pressure of return water that like this can maximum efficiency produces, the effect of the sealing that also can guarantee simultaneously to shunt in a well;
Step 7, fill out core and seal: the height that is backfilling into concrete cushion in the no sand cement pipe 1 with fine sand; Drop in the steel sleeve 2 with the harsh concrete that is mixed with early strength admixture again, vibration compacting, and be poured into the top of steel sleeve 2 always; On the flange 202 at steel sleeve 2 tops, place rubber waterproof pad 205 immediately; Cover shrouding 203, with 12 bolts 204 shrouding 203 is fixed on the flange 202, the screwing force distance is 50N.m-60N.m; Use the top of expansive concrete teeming again, make reinforcing rib interior fair with the reinforcing rib foreign minister in steel sleeve 2.
Construction is accomplished back reply waterproofing course, steel sleeve and is not had positions such as sand cement pipe junction surface, seal plate, shrouding and check that also next step construction can be carried out in qualified rear.
The present invention does not have the device that uses in the sand cement pipe deep-well precipitation well head rapid plugging method, a kind of no sand cement pipe deep-well precipitation well head fast plugging device, and it comprises no sand cement pipe 1 and steel sleeve 2; Steel sleeve comprises steel tube body 201, flange 201, shrouding 203, bolt 204, rubber waterproof pad 205 and twice seal plate, does not wherein have sand cement pipe 1 and is embedded in the middle of the base concrete bed course, and insert in the no sand cement pipe 1 bottom of steel sleeve 2; At steel sleeve 2 with there is not filled polyurethane waterproof sealing cream 3 between sand cement pipe 1 well head; Flange 202 is positioned at the top of steel sleeve 2, and shrouding 203 is positioned at the top of flange 202, on flange 202 and shrouding 203, is equipped with 12 screws; Be provided with rubber waterproof pad 205 between flange 202 and the shrouding 203; Through bolt 204 firm connections, seal plate is positioned on the lateral wall of steel sleeve 2 between flange 202 and the shrouding 203, and the road number of seal plate can be confirmed according to the height of steel sleeve; It in the present embodiment twice seal plate; Wherein be positioned at the last seal plate 206 that is at steel sleeve 2 middle parts, be positioned at the following seal plate 207 that is of steel sleeve 2 bottoms, fill waterproof cement mortar 4 between no sand cement pipe 1 well head and the following seal plate 207; Make arc chord angle in the no sand cement pipe 1 and the junction of base concrete bed course with cement mortar; On arc chord angle, be provided with SBS coil waterproof layer 5 one, SBS coil waterproof layer 5 joins with following seal plate 207, and interface adopts the hot melt sealing.
The above only is a preferred implementation of the present invention; Should be pointed out that to those skilled in the art, under the prerequisite that does not break away from the invention design; Can also make some similar distortion and improvement, these also should be regarded as within protection scope of the present invention.

Claims (10)

1. do not have sand cement pipe deep-well precipitation well head rapid plugging method, it is characterized in that concrete steps are:
Step 1, the mouth of pipe are handled: laying base concrete bed course makes has certain intensity, makes that simultaneously no sand cement pipe well open height is higher than the base concrete bed course;
Step 2, steel sleeve are made: on the lateral wall of circular steel sleeve pipe, be welded with at least one seal plate; Welded top at steel sleeve has a flange; Several screws are set on the flange; The configuration corresponding bolts is provided with shrouding at the top of steel sleeve, and the rubber waterproof pad is set between shrouding and flange;
Step 3, steel sleeve are inserted fixing in advance: before the sole plate assembling reinforcement, steel sleeve is inserted in the no sand cement mouth of pipe, and near the bottom welded reinforcement support of one seal plate of no sand cement pipe import, make this seal plate be higher than no sand cement pipe well mouth;
Step 4, sealing joint waterproof: at steel sleeve with there is not between the sand cement pipe well mouth waterproof sealing of filling cream; After treating waterproof sealing cream drying; Adopt waterproof cement mortar will be near fill plug seal between one seal plate of no sand cement pipe import and the no sand cement pipe well mouth, make arc chord angle in the junction of no sand cement pipe and base concrete bed course with cement mortar, on arc chord angle, do waterproofing course one; Waterproofing course joins with following seal plate, and interface adopts the hot melt sealing;
Step 5, foundation construction: colligation basis end placing of reinforcement; Break off at no sand cement pipe well mouth place; Periphery is provided with reinforcing rib; Concreting around no sand cement pipe well mouth, no sand cement pipe well mouth top are that the back cast gate is kept somewhere at the center with the well head, after the well head quick blocking, adopt than the higher leveled expansive concrete teeming of circumferential concrete grade;
Step 6, at interval stop precipitation successively: stop precipitation should be a plurality of no sand cement pipe precipitation wells at interval progressively stop precipitation, individual well stops to take out water pump immediately behind the precipitation;
Step 7, fill out core and seal: no sand cement Guan Zhongyong fine sand is backfilling into the height of concrete cushion, drops in the steel sleeve vibration compacting again with the harsh concrete that is mixed with early strength admixture; And be poured into the top of steel sleeve always; On the flange at steel sleeve top, place the rubber waterproof pad immediately, cover shrouding, shrouding is fixed on the flange with bolt; Use the top of expansive concrete teeming again in steel sleeve; Make it to maintain an equal level vibration compacting, covering protection mutually with the concrete surface that does not have around the sand cement pipe well mouth.
2. no sand cement pipe deep-well precipitation well head rapid plugging method according to claim 1 is characterized in that, the waterproof sealing cream in the said step 4 adopts polyurethane water-proof sealing compound.
3. no sand cement pipe deep-well precipitation well head rapid plugging method according to claim 1 is characterized in that, the waterproofing course in the said step 4 adopts the SBS coil waterproof layer.
4. do not have sand cement pipe deep-well precipitation well head fast plugging device, it is characterized in that it comprises no sand cement pipe and steel sleeve; Steel sleeve comprises steel tube body, flange, shrouding, bolt, rubber waterproof pad with seal plate at least, and said no sand cement pipe is embedded in the middle of the base concrete bed course, and insert in the no sand cement pipe bottom of said steel sleeve; Said flange is positioned at the top of steel sleeve; Said shrouding is positioned at the top of flange, is equipped with at least three screws on said flange and the shrouding, and said rubber waterproof pad is between flange and shrouding; Through the firm connection of bolt, said seal plate is positioned on the lateral wall of steel sleeve between said flange and the shrouding.
5. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 4 is characterized in that, is equipped with 12 screws on said flange and the shrouding.
6. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 5 is characterized in that the lateral wall of said steel sleeve is provided with the twice seal plate, is positioned at the last seal plate that is at steel sleeve middle part, is positioned at the following seal plate that is of steel sleeve bottom.
7. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 6 is characterized in that, said steel sleeve and do not have filled polyurethane waterproof sealing cream between the sand cement pipe well mouth.
8. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 7 is characterized in that, fills waterproof cement mortar between said no sand cement pipe well mouth and the following seal plate.
9. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 8; It is characterized in that; Arc chord angle is made with cement mortar in said junction at no sand cement pipe and base concrete bed course; On arc chord angle, be provided with waterproofing course one, waterproofing course joins with following seal plate, and interface adopts the hot melt sealing.
10. no sand cement pipe deep-well precipitation well head fast plugging device according to claim 9 is characterized in that said waterproofing course is the SBS coil waterproof layer.
CN201110174983.7A 2011-06-22 2011-06-22 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead Active CN102839691B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110174983.7A CN102839691B (en) 2011-06-22 2011-06-22 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110174983.7A CN102839691B (en) 2011-06-22 2011-06-22 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead

Publications (2)

Publication Number Publication Date
CN102839691A true CN102839691A (en) 2012-12-26
CN102839691B CN102839691B (en) 2015-04-15

Family

ID=47367393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110174983.7A Active CN102839691B (en) 2011-06-22 2011-06-22 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead

Country Status (1)

Country Link
CN (1) CN102839691B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362145A (en) * 2013-08-02 2013-10-23 江苏正方园建设集团有限公司 Steel sleeve for basement tube well plugging
CN103898920A (en) * 2012-12-27 2014-07-02 上海建工七建集团有限公司 Foundation pit dewatering and drainage method
CN104563144A (en) * 2014-12-04 2015-04-29 成都迅德科技有限公司 Plugging structure
WO2018214143A1 (en) * 2017-05-26 2018-11-29 南通八建集团有限公司 Construction method for plugging dewatering well having penetrating bottom plate in foundation pit
CN110374125A (en) * 2019-07-30 2019-10-25 中铁九局集团第七工程有限公司 Metro Deep Excavation side wall interlayer method for treating water
CN111441374A (en) * 2020-01-14 2020-07-24 中建六局建设发展有限公司 Quick plugging construction method for high-water-pressure deep foundation pit dewatering well
CN116537238A (en) * 2023-07-04 2023-08-04 北京建工集团有限责任公司 Plugging method for dry well under water-carrying operation environment

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148884A (en) * 2007-10-30 2008-03-26 山东天齐置业集团股份有限公司 Waterproof and plugging construction method for precipitation well in foundation pit
DE102006059044A1 (en) * 2006-12-14 2008-06-19 Fischerwerke Gmbh & Co. Kg Method e.g. for sealing buildings, involves sealing buildings inside from outside against pressurized water with device and sealing layer is applied and plug with plug head is provided
CN201144424Y (en) * 2008-01-11 2008-11-05 江苏南通二建集团有限公司 Fast plugging device for deep foundation pit dewatering well
CN201212148Y (en) * 2008-07-07 2009-03-25 中建八局第二建设有限公司 Precipitation Well seal structure in foundation slab
CN201517218U (en) * 2009-07-09 2010-06-30 朱奎 Basement bottom board water-proof conformation
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006059044A1 (en) * 2006-12-14 2008-06-19 Fischerwerke Gmbh & Co. Kg Method e.g. for sealing buildings, involves sealing buildings inside from outside against pressurized water with device and sealing layer is applied and plug with plug head is provided
CN101148884A (en) * 2007-10-30 2008-03-26 山东天齐置业集团股份有限公司 Waterproof and plugging construction method for precipitation well in foundation pit
CN201144424Y (en) * 2008-01-11 2008-11-05 江苏南通二建集团有限公司 Fast plugging device for deep foundation pit dewatering well
CN201212148Y (en) * 2008-07-07 2009-03-25 中建八局第二建设有限公司 Precipitation Well seal structure in foundation slab
CN201517218U (en) * 2009-07-09 2010-06-30 朱奎 Basement bottom board water-proof conformation
CN202124865U (en) * 2011-06-22 2012-01-25 南通海洲建设集团有限公司 Quick plugging device for dewatering wellhead of sand-free cement pipe deep well

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李昌成: "降水井封堵施工方法", 《建材技术与应用》, no. 12, 1 April 2009 (2009-04-01) *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898920A (en) * 2012-12-27 2014-07-02 上海建工七建集团有限公司 Foundation pit dewatering and drainage method
CN103362145A (en) * 2013-08-02 2013-10-23 江苏正方园建设集团有限公司 Steel sleeve for basement tube well plugging
CN104563144A (en) * 2014-12-04 2015-04-29 成都迅德科技有限公司 Plugging structure
WO2018214143A1 (en) * 2017-05-26 2018-11-29 南通八建集团有限公司 Construction method for plugging dewatering well having penetrating bottom plate in foundation pit
CN110374125A (en) * 2019-07-30 2019-10-25 中铁九局集团第七工程有限公司 Metro Deep Excavation side wall interlayer method for treating water
CN111441374A (en) * 2020-01-14 2020-07-24 中建六局建设发展有限公司 Quick plugging construction method for high-water-pressure deep foundation pit dewatering well
CN116537238A (en) * 2023-07-04 2023-08-04 北京建工集团有限责任公司 Plugging method for dry well under water-carrying operation environment

Also Published As

Publication number Publication date
CN102839691B (en) 2015-04-15

Similar Documents

Publication Publication Date Title
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN102839691B (en) Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN204343312U (en) A kind of plugging device of precipitation well in foundation pit
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN104846841B (en) Anti-floating construction method for basements without uplift piles
CN105178344A (en) Built-in anti-floating anchor blocking structure used in foundation mat for deep-well dewatering well and construction method
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN206090653U (en) Anchor rod static pressure pile slip casting structure
CN206916753U (en) A kind of water sealing structure of diaphram wall and its seam crossing
CN109519150B (en) Dewatering well plugging device and method for large water yield
CN204530733U (en) Underground construction deep-well precipitation well head plugging structure
CN202730786U (en) Well-sealing waterproof construction structure of dewatering well
CN102220764B (en) Construction method of deep foundation pit bracing system
CN212837843U (en) IV-class and V-class surrounding rock tunnel concrete lining anti-cracking structure
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN203768925U (en) Seal device for dewatering well in foundation pit
CN212506349U (en) Water-logging well sealing device for water-lowering zone of ultra-deep foundation pit pipe well
CN212052717U (en) Structure for penetrating karst cave of precast tubular pile
CN212129150U (en) Deep basal pit precipitation well block structure
CN210712963U (en) Drainage structure of basement bottom plate post-cast strip
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN105442528B (en) A kind of cement injection sheet pile with sealing ring
CN114607386A (en) Single-layer well wall with connecting and water stopping structure and grouting system and construction method thereof
CN216788363U (en) Well head block structure of deep tube well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant