CN110374125A - Metro Deep Excavation side wall interlayer method for treating water - Google Patents

Metro Deep Excavation side wall interlayer method for treating water Download PDF

Info

Publication number
CN110374125A
CN110374125A CN201910693042.0A CN201910693042A CN110374125A CN 110374125 A CN110374125 A CN 110374125A CN 201910693042 A CN201910693042 A CN 201910693042A CN 110374125 A CN110374125 A CN 110374125A
Authority
CN
China
Prior art keywords
well
water
pipe
foundation pit
dewatering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910693042.0A
Other languages
Chinese (zh)
Inventor
任笑谦
陈云飞
董光
李志明
王振东
安刚
范非昨
车广义
卢秀芬
曹金波
程晓龙
冯双龙
郭建军
刘佳兴
林操
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 9 Group Co Ltd, Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical China Railway No 9 Group Co Ltd
Priority to CN201910693042.0A priority Critical patent/CN110374125A/en
Publication of CN110374125A publication Critical patent/CN110374125A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明涉及一种地铁深基坑侧壁夹层水处理方法,步骤如下:1)、基坑外降水井施工:埋设护筒;钻机成孔;吊放井管滤管;填滤料;洗井;水泵安装;铺设排水管网;水位抽降;水位观测;降水;抽水运行;2)、基坑内降水井施工;3)、换乘站节点降水;4)、基坑内设置明沟或盲沟排水系统;5)坑基内设置排水系统;6)基坑内封井;7)基坑外封井。基坑内外相互配合降水,保证了工程顺利实施,解决了潜水层及夹层水较难抽干的问题。

The invention relates to a method for treating interlayer water on the side wall of a deep foundation pit of a subway. The steps are as follows: 1) Construction of a dewatering well outside the foundation pit: burying a casing; drilling a rig to form a hole; hanging the well pipe and filter tube; filling filter material; washing the well ;Water pump installation; laying drainage pipe network; water level pumping down; water level observation; precipitation; pumping operation; 2), construction of dewatering wells in foundation pits; 5) Drainage system is installed in the pit foundation; 6) Well closure inside the foundation pit; 7) Well closure outside the foundation pit. The coordination of precipitation inside and outside the foundation pit ensures the smooth implementation of the project and solves the problem that the aquifer and interlayer water are difficult to drain.

Description

地铁深基坑侧壁夹层水处理方法Water Treatment Method for Side Wall Interlayer of Subway Deep Foundation Pit

技术领域technical field

本发明涉及一种水处理方法,特别是一种地铁深基坑侧壁夹层水处理方法,属于地铁建筑施工领域。The invention relates to a water treatment method, in particular to a method for treating interlayer water on the side wall of a subway deep foundation pit, and belongs to the field of subway building construction.

背景技术Background technique

随着社会的发展,现代地铁车站基坑逐渐向更大更深发展,地下水对深基坑施工造成了巨大安全隐患,所以深基坑施工过程中对地下水的处理逐渐成为了地铁车站基坑开挖施工过程中必不可少的措施,尤其是在地下水较丰富、地质条件较差地层,地下水处理的方案及施工质量更是能够直接影响基坑的安全性能。With the development of society, the foundation pits of modern subway stations are gradually becoming larger and deeper, and groundwater poses a huge safety hazard to the construction of deep foundation pits. Indispensable measures in the construction process, especially in strata with rich groundwater and poor geological conditions, the scheme of groundwater treatment and construction quality can directly affect the safety performance of the foundation pit.

发明内容Contents of the invention

本发明要解决的技术问题是提供一种地铁深基坑侧壁夹层水处理方法,基坑内外相互配合降水,保证了工程顺利实施,解决了潜水层及夹层水较难抽干的问题。The technical problem to be solved by the present invention is to provide a method for treating the interlayer water on the side wall of the deep foundation pit of the subway. The inside and outside of the foundation pit cooperate with each other to dewater, which ensures the smooth implementation of the project and solves the problem that the aquifer and interlayer water are difficult to drain.

为解决以上问题,本发明的具体技术方案如下:一种地铁深基坑侧壁夹层水处理方法,步骤如下:1)、基坑外降水井施工:1.1)埋设护筒:将护筒底部埋入原土层;1.2)钻机成孔:步骤1.1)后,钻机就位,进行降水井成孔;1.3)吊放井管滤管:井管采用无砂水泥管,下放至井内;1.4)填滤料:步骤1.3)后在滤管内填入滤料;1.5)洗井:采用活塞空压机联合洗井,成井后用污水泵与空压机反复进行清洗至水清砂净;1.6)水泵安装:潜水泵用尼龙绳放入井内,铺设电缆和电闸箱;1.7)铺设排水管网:地面铺设排水管,排水管在每一个井位预留分接头并连接有高压螺旋式阀门;1.8)水位抽降:1.9)水位观测:静止水位观测,初期早晚各一次,水位稳定后每天一次;1.10)降水;1.11)抽水运行;2)、基坑内降水井施工:集水井采用人工开挖形式,集水井周边采用钢套管进行支护,钢套管侧壁预留孔洞,同时采用双层滤网进行缠绕;3)、换乘站节点降水:采用管井降水系统进行抽降水;4)、基坑内设置明沟或盲沟排水系统: 横向和纵向均设置盲沟,盲沟上均设有3‰的流水坡;5)坑基内设置排水系统;6)基坑内封井;7)基坑外封井。In order to solve the above problems, the specific technical scheme of the present invention is as follows: a method for treating interlayer water on the side wall of a deep foundation pit of a subway, the steps are as follows: 1), the construction of the dewatering well outside the foundation pit: 1.1) burying the casing: bury the bottom of the casing into the original soil layer; 1.2) Drilling rig to form a hole: After step 1.1), the drilling rig is in place to form a dewatering well; 1.3) Hanging the well pipe and filter tube: the well pipe is made of sand-free cement pipe and lowered into the well; 1.4) Filling Filter material: after step 1.3), fill the filter tube with filter material; 1.5) Well washing: Use a piston air compressor to wash the well, and after the well is completed, use a sewage pump and an air compressor to clean it repeatedly until the water is clean and the sand is clean; 1.6) The water pump Installation: Put the submersible pump into the well with nylon rope, lay cables and electric switch box; 1.7) Lay drainage pipe network: Lay drainage pipes on the ground, reserve taps for each well position and connect high-pressure screw valves; 1.8) Water level pumping and lowering: 1.9) Water level observation: static water level observation, once in the morning and evening at the initial stage, once a day after the water level stabilizes; 1.10) Precipitation; 1.11) Pumping operation; The surroundings of the water collection wells are supported by steel casings, holes are reserved on the side walls of the steel casings, and double-layer filter screens are used for winding; 3) Dewatering at transfer station nodes: use tube well dewatering system for pumping and dewatering; 4), base Set open ditch or blind ditch drainage system in the pit: Blind ditch is set horizontally and vertically, and a 3‰ flow slope is set on the blind ditch; 5) Drainage system is set in the pit foundation; 6) Well is sealed inside the foundation pit; 7) Outside the foundation pit Seal the well.

所述的步骤1.10)中,在开挖前15天开始启动降水井抽水,降水降至基底一下1m。In the above step 1.10), the precipitation well pumping was started 15 days before the excavation, and the precipitation dropped to 1m below the basement.

所述的步骤1.11)中,开挖前的提前封闭降水时间不少于15天;抽水含砂量:粗砂含量小于1/50000,中砂含量小于1/20000,细砂含量小于1/10000。In the above step 1.11), the pre-sealed precipitation time before excavation shall not be less than 15 days; pumping sand content: the content of coarse sand is less than 1/50000, the content of medium sand is less than 1/20000, and the content of fine sand is less than 1/10000 .

所述的步骤3)中降水井井壁管采用花管,井壁管外径380mm,花管采用混凝土预制滤管,滤管每节0.9m,下放井管时,两滤管接缝处用编织袋包扎严实,并用三根竹片结合铁丝把上下两节固定牢固,井距在8.0-12.0m,每个降水井配一台流量为10m3/h的潜水泵,潜水泵和排水管连接采用塑料软管,塑料软管直径大小按潜水泵连接接头确定,每个降水井旁边设置直径273mm的钢管按坡度进行排水至雨污水井里面。In the step 3) the well wall pipe of the middle dewatering well adopts flower pipes, the outer diameter of the well wall pipe is 380mm, and the flower pipes adopt concrete prefabricated filter pipes, and each section of the filter pipes is 0.9m. When the well pipes are lowered, the joints of the two filter pipes are The woven bag is wrapped tightly, and the upper and lower sections are fixed firmly with three bamboo pieces combined with iron wire. The well spacing is 8.0-12.0m. Each dewatering well is equipped with a submersible pump with a flow rate of 10m 3 /h. The submersible pump and the drainage pipe are connected by Plastic hose, the diameter of the plastic hose is determined by the connection joint of the submersible pump, and a steel pipe with a diameter of 273mm is installed next to each dewatering well to drain water into the rainwater well according to the slope.

所述的步骤4)中所述纵向盲沟由西向东设3‰的流水坡,所述横向盲沟有南北两侧向中间设3‰的流水坡,流入到临时集水井里面,每一施工段端头向大里程4m处设置一条横向排水盲沟,盲沟底先铺一层厚0.8mm的塑料布,上面回填10cm厚的卵石,然后回填级配碎石至盲沟顶面。In the step 4), the vertical blind ditch has a water slope of 3‰ from west to east, and the horizontal blind ditch has a water slope of 3‰ from the north and south sides to the middle, and flows into the temporary water collection well. A horizontal drainage blind ditch is set at the end of the section 4m to the maximum mileage. First, a layer of 0.8mm thick plastic cloth is laid on the bottom of the blind ditch, and 10cm thick pebbles are backfilled on it, and then backfilled with graded gravel to the top of the blind ditch.

所述的步骤5)中用带水平眼的Ф100PVC管,每节长100cm,插入土体100cm,露出90°弯头至钢筋网片内侧,然后接竖向Ф100mmPVC管到盲沟顶;盲沟结构尺寸为:宽30cm,深50cm,盲沟修筑完成内,回填级配良好的碎石至盲沟顶面;纱布包裹PVC管插入土体部分;Ф100mm渗水PVC管深入土体部分向下倾斜宜为5°~15°,桩间砂土流失严重的孔洞,用注浆机对孔洞进行回填注浆,注浆压力为0.3Mpa~0.5Mpa,浆液水灰比=1:1。In step 5), use a Ф100 PVC pipe with a horizontal eye, each section is 100cm long, insert 100cm into the soil, expose a 90° elbow to the inside of the steel mesh, and then connect a vertical Ф100mm PVC pipe to the top of the blind ditch; blind ditch structure Dimensions: 30cm wide and 50cm deep. After the blind ditch is built, backfill well-graded gravel to the top of the blind ditch; wrap the PVC pipe with gauze and insert it into the soil; 5°~15°, for holes with severe sand loss between piles, use a grouting machine to backfill the holes with grouting, the grouting pressure is 0.3Mpa~0.5Mpa, and the grout water-cement ratio=1:1.

所述的步骤6)中封井前,防水层平铺至井管上5cm,加强层平铺至井管上10cm,加强层平铺尺寸20cm,井管与防水层、与加强层用密封胶粘紧,加强层的最上面用金属箍固定;封井前,安装厚8mm,长10cm的止水法兰,在止水法兰上安装20mm*10mm截面的遇水膨胀止水条沿止水法兰一圈;底板与井身交叉处安装防水层时,沿折角5cm的等边三角形内用密封胶粘死;封井时,用两块10mm厚圆钢板,中间夹着橡胶密封环板,边上用螺栓固定,封井处用防水砂浆填实。Step 6) Before sealing the well, spread the waterproof layer to 5cm above the well pipe, spread the reinforcement layer to 10cm above the well pipe, and spread the reinforcement layer to a size of 20cm, and use sealant for the well pipe, waterproof layer, and reinforcement layer Adhesively, the top of the reinforcement layer is fixed with a metal hoop; before sealing the well, install a water-stop flange with a thickness of 8mm and a length of 10cm, and install a water-swellable water-stop strip with a cross-section of 20mm*10mm on the water-stop flange along the water-stop One circle around the flange; when installing the waterproof layer at the intersection of the bottom plate and the well body, use sealing glue to seal the inside of an equilateral triangle along the knuckle angle of 5cm; when sealing the well, use two 10mm thick round steel plates with a rubber sealing ring plate in the middle, The sides are fixed with bolts, and the sealing place is filled with waterproof mortar.

所述的步骤7)中,基坑外降水井使用时间为基坑开挖至顶板抗浮梁施工完成,采用素混凝土进行回填密封。In the above step 7), the use time of the dewatering well outside the foundation pit is from the excavation of the foundation pit to the completion of the construction of the anti-floating beam on the roof, and plain concrete is used for backfilling and sealing.

本发明带来的有益效果为:基坑内外相互配合降水,保证了工程顺利实施,解决了潜水层及夹层水较难抽干的问题。The beneficial effects brought by the invention are: the inside and outside of the foundation pit cooperate with each other for dewatering, which ensures the smooth implementation of the project and solves the problem that the water in the submerged layer and the interlayer is difficult to drain.

附图说明Description of drawings

图1为地铁深基坑侧壁夹层水处理方法施工原理示意图。Figure 1 is a schematic diagram of the construction principle of the interlayer water treatment method for the side wall of the subway deep foundation pit.

具体实施方式Detailed ways

如图1所示,一种地铁深基坑侧壁夹层水处理方法,步骤如下:1)、基坑外降水井施工:1.1)埋设护筒:将护筒底部埋入原土层;1.2)钻机成孔:步骤1.1)后,钻机就位,进行降水井成孔;1.3)吊放井管滤管:井管采用无砂水泥管,下放至井内;1.4)填滤料:步骤1.3)后在滤管内填入滤料;1.5)洗井:采用活塞空压机联合洗井,成井后用污水泵与空压机反复进行清洗至水清砂净;1.6)水泵安装:潜水泵用尼龙绳放入井内,铺设电缆和电闸箱;1.7)铺设排水管网:地面铺设排水管,排水管在每一个井位预留分接头并连接有高压螺旋式阀门;抽水时,先将水抽到水箱中,沉淀水中的污泥,再将水箱中的水排到雨水井中,同时冬季施工期间,排水管道采取橡塑海绵保温板+自控温加热带+保温铝皮管的方式,沿着临水管道底部先包裹一道橡塑海绵保温板,然后布设一条自控温加热带,外包70mm厚保温铝皮管,此种保温方案可保证临水管道在零下25度左右,内部温度维持在10-20度左右;1.8)水位抽降:1.9)水位观测:静止水位观测,初期早晚各一次,水位稳定后每天一次;1.10)降水;1.11)抽水运行;2)、基坑内降水井施工:集水井采用人工开挖形式,集水井周边采用钢套管进行支护,钢套管侧壁预留孔洞,同时采用双层滤网进行缠绕;3)、换乘站节点降水:采用管井降水系统进行抽降水;4)、基坑内设置明沟或盲沟排水系统: 横向和纵向均设置盲沟,盲沟上均设有3‰的流水坡;5)坑基内设置排水系统;6)基坑内封井;7)基坑外封井。As shown in Figure 1, a method for treating interlayer water on the side wall of a subway deep foundation pit, the steps are as follows: 1) Construction of the dewatering well outside the foundation pit: 1.1) Embedding the casing: bury the bottom of the casing into the original soil layer; 1.2) Drilling rig to form a hole: After step 1.1), the drilling rig is in place to form a dewatering well; 1.3) Hanging the well pipe and filter tube: the well pipe is made of sand-free cement pipe and lowered into the well; 1.4) Filling the filter material: after step 1.3) Fill the filter tube with filter material; 1.5) Well cleaning: use a piston air compressor to clean the well, and after the well is completed, use a sewage pump and an air compressor to clean it repeatedly until the water and sand are clean; 1.6) Water pump installation: use nylon rope for submersible pumps Put it into the well, lay cables and electric switch boxes; 1.7) Lay the drainage pipe network: lay drainage pipes on the ground, and the drainage pipes reserve taps at each well position and connect with high-pressure screw valves; when pumping water, first pump the water to the water tank During the construction period in winter, the drainage pipe adopts the method of rubber and plastic sponge insulation board + self-temperature control heating belt + heat preservation aluminum pipe, along the waterfront The bottom of the pipeline is first wrapped with a rubber-plastic sponge insulation board, and then a self-temperature-controlling heating belt is laid out, which is outsourced with a 70mm thick thermal insulation aluminum tube. 1.8) Water level pumping down: 1.9) Water level observation: static water level observation, once in the morning and evening at the beginning, once a day after the water level stabilizes; 1.10) Precipitation; 1.11) Pumping operation; In the form of manual excavation, the surrounding of the water collection well is supported by steel casings, holes are reserved on the side walls of the steel casings, and double-layer filters are used for winding; 3) Dewatering at transfer station nodes: use tube well dewatering system for pumping and dewatering ;4) Set up open ditch or blind ditch drainage system in the foundation pit: Blind ditch is set horizontally and vertically, and a 3‰ flow slope is set on the blind ditch; 5) Drainage system is set in the pit foundation; 6) The well is closed in the foundation pit; 7) Well sealing outside the foundation pit.

所述的步骤1.10)中,在开挖前15天开始启动降水井抽水,降水降至基底一下1m。In the above step 1.10), the precipitation well pumping was started 15 days before the excavation, and the precipitation dropped to 1m below the basement.

所述的步骤1.11)中,开挖前的提前封闭降水时间不少于15天;抽水含砂量:粗砂含量小于1/50000,中砂含量小于1/20000,细砂含量小于1/10000。In the above step 1.11), the pre-sealed precipitation time before excavation shall not be less than 15 days; pumping sand content: the content of coarse sand is less than 1/50000, the content of medium sand is less than 1/20000, and the content of fine sand is less than 1/10000 .

所述的步骤3)中降水井井壁管采用花管,井壁管外径380mm,花管采用混凝土预制滤管,滤管每节0.9m,下放井管时,两滤管接缝处用编织袋包扎严实,并用三根竹片结合铁丝把上下两节固定牢固,井距在8.0-12.0m,每个降水井配一台流量为10m3/h的潜水泵,潜水泵和排水管连接采用塑料软管,塑料软管直径大小按潜水泵连接接头确定,每个降水井旁边设置直径273mm的钢管按坡度进行排水至雨污水井里面。In the step 3) the well wall pipe of the middle dewatering well adopts flower pipes, the outer diameter of the well wall pipe is 380mm, and the flower pipes adopt concrete prefabricated filter pipes, and each section of the filter pipes is 0.9m. When the well pipes are lowered, the joints of the two filter pipes are The woven bag is wrapped tightly, and the upper and lower sections are fixed firmly with three bamboo pieces combined with iron wire. The well spacing is 8.0-12.0m. Each dewatering well is equipped with a submersible pump with a flow rate of 10m 3 /h. The submersible pump and the drainage pipe are connected by Plastic hose, the diameter of the plastic hose is determined by the connection joint of the submersible pump, and a steel pipe with a diameter of 273mm is installed next to each dewatering well to drain water into the rainwater well according to the slope.

所述的步骤4)中所述纵向盲沟由西向东设3‰的流水坡,所述横向盲沟有南北两侧向中间设3‰的流水坡,流入到临时集水井里面,每一施工段端头向大里程4m处设置一条横向排水盲沟,盲沟底先铺一层厚0.8mm的塑料布,上面回填10cm厚的卵石,然后回填级配碎石至盲沟顶面。In the step 4), the vertical blind ditch has a water slope of 3‰ from west to east, and the horizontal blind ditch has a water slope of 3‰ from the north and south sides to the middle, and flows into the temporary water collection well. A horizontal drainage blind ditch is set at the end of the section 4m to the maximum mileage. First, a layer of 0.8mm thick plastic cloth is laid on the bottom of the blind ditch, and 10cm thick pebbles are backfilled on it, and then backfilled with graded gravel to the top of the blind ditch.

所述的步骤5)中用带水平眼的Ф100PVC管,每节长100cm,插入土体100cm,露出90°弯头至钢筋网片内侧,然后接竖向Ф100mmPVC管到盲沟顶;盲沟结构尺寸为:宽30cm,深50cm,盲沟修筑完成内,回填级配良好的碎石至盲沟顶面;纱布包裹PVC管插入土体部分;Ф100mm渗水PVC管深入土体部分向下倾斜宜为5°~15°,桩间砂土流失严重的孔洞,用注浆机对孔洞进行回填注浆,注浆压力为0.3Mpa~0.5Mpa,浆液水灰比=1:1。In step 5), use a Ф100 PVC pipe with a horizontal eye, each section is 100cm long, insert 100cm into the soil, expose a 90° elbow to the inside of the steel mesh, and then connect a vertical Ф100mm PVC pipe to the top of the blind ditch; blind ditch structure Dimensions: 30cm wide and 50cm deep. After the blind ditch is built, backfill well-graded gravel to the top of the blind ditch; wrap the PVC pipe with gauze and insert it into the soil; 5°~15°, for holes with severe sand loss between piles, use a grouting machine to backfill the holes with grouting, the grouting pressure is 0.3Mpa~0.5Mpa, and the grout water-cement ratio=1:1.

所述的步骤6)中封井前,防水层平铺至井管上5cm,加强层平铺至井管上10cm,加强层平铺尺寸20cm,井管与防水层、与加强层用密封胶粘紧,加强层的最上面用金属箍固定;封井前,安装厚8mm,长10cm的止水法兰,在止水法兰上安装20mm*10mm截面的遇水膨胀止水条沿止水法兰一圈;底板与井身交叉处安装防水层时,沿折角5cm的等边三角形内用密封胶粘死;封井时,用两块10mm厚圆钢板,中间夹着橡胶密封环板,边上用螺栓固定,封井处用防水砂浆填实。Step 6) Before sealing the well, spread the waterproof layer to 5cm above the well pipe, spread the reinforcement layer to 10cm above the well pipe, and spread the reinforcement layer to a size of 20cm, and use sealant for the well pipe, waterproof layer, and reinforcement layer Adhesively, the top of the reinforcement layer is fixed with a metal hoop; before sealing the well, install a water-stop flange with a thickness of 8mm and a length of 10cm, and install a water-swellable water-stop strip with a cross-section of 20mm*10mm on the water-stop flange along the water-stop One circle around the flange; when installing the waterproof layer at the intersection of the bottom plate and the well body, use sealing glue to seal the inside of an equilateral triangle along the knuckle angle of 5cm; when sealing the well, use two 10mm thick round steel plates with a rubber sealing ring plate in the middle, The sides are fixed with bolts, and the sealing place is filled with waterproof mortar.

所述的步骤7)中,基坑外降水井使用时间为基坑开挖至顶板抗浮梁施工完成,采用素混凝土进行回填密封。In the above step 7), the use time of the dewatering well outside the foundation pit is from the excavation of the foundation pit to the completion of the construction of the anti-floating beam on the roof, and plain concrete is used for backfilling and sealing.

实施例:1号线西侧扩大段及标准段定明排,就是基坑内设置明(盲)沟排水系统,靠桩内全长设一条排水盲沟,盲沟尺寸为:深0.5m,宽0.3m,所用纵向盲沟由西向东设3‰的流水坡,所有横向盲沟有南北两侧向中间设3‰的流水坡,流入到临时集水井里面。每一施工段端头向大里程4m处设置一条横向排水盲沟。盲沟底先铺一层厚0.8mm的塑料布(防止盲沟沟底土体被侵泡),上面回填10cm厚的卵石,然后回填级配碎石至盲沟顶面,横向排水盲沟中间设一个临时集水坑,通过10m³/d的潜水泵抽至地面上最近的雨污水井里面。Example: The expanded section on the west side of Line 1 and the standard section are designated as clear rows, that is, an open (blind) ditch drainage system is installed in the foundation pit, and a drainage blind ditch is installed along the entire length of the pile. The size of the blind ditch is: 0.5m deep and 0.3m wide , the longitudinal blind ditches used have a water slope of 3‰ from west to east, and all horizontal blind ditches have a water slope of 3‰ from the north and south sides to the middle, and flow into the temporary water collection well. A horizontal drainage blind ditch is set at the end of each construction section 4m away from the maximum mileage. First lay a layer of 0.8mm thick plastic sheeting on the bottom of the blind ditch (to prevent the soil at the bottom of the blind ditch from being soaked), backfill 10cm thick pebbles on it, and then backfill graded gravel to the top of the blind ditch, and drain the middle of the blind ditch horizontally Set up a temporary sump, pump it to the nearest rainwater well on the ground through a 10m³/d submersible pump.

当施工此段底板垫层前,将下一施工段的排水盲沟和临时集水坑施做好,通过潜水泵和盲沟将水引排至下一施工段临时集水坑内,施工此段底板垫层,集水井用C20混凝土填充密实。如挖上翻梁时,水通过盲沟排至临时集水井里。如挖下翻梁时,挖完下翻梁后,立即挖下翻梁梁底盲沟,然后对盲沟和梁边土体进行挂网喷射C20细石混凝土,C20细石混凝土配合比:水泥:细石:砂:水:速凝剂=1:2.027:2.37:0.49:0.04,两条下翻梁梁底中间设一道3‰盲沟,人工修理盲沟坡度,盲沟底先铺一层厚0.8mm的塑料布,上面回填10cm厚的卵石,然后回填级配碎石至盲沟顶面,两条下翻梁端头各设一个临时集水井,保证水流至集水坑,保证流水顺畅,集水坑的水通过10m³/d的潜水泵抽至地面上最近的雨污水井里面,下翻梁梁底的盲沟及临时集水井大小可根据下翻梁两侧夹层水的水量进行现场调整。Before constructing the floor cushion of this section, the drainage blind ditch and temporary sump of the next construction section shall be completed, and the water shall be drained into the temporary sump of the next construction section through the submersible pump and blind ditch, and the floor of this section shall be constructed Cushion, water collection wells are filled with C20 concrete. For example, when the overturning beam is dug, the water will be drained into the temporary sump well through the blind ditch. For example, when digging the downturned beam, after the downturned beam is dug, immediately dig the blind ditch at the bottom of the downturned beam, and then spray C20 fine stone concrete on the blind ditch and the soil beside the beam, and the mix ratio of C20 fine stone concrete: cement : fine stone: sand: water: accelerator = 1:2.027:2.37:0.49:0.04, a 3‰ blind ditch is set in the middle of the bottom of the two downturn beams, the slope of the blind ditch is manually repaired, and a layer is first laid at the bottom of the blind ditch Plastic cloth with a thickness of 0.8mm is backfilled with 10cm thick pebbles, and then backfilled with graded gravel to the top of the blind ditch. A temporary water collection well is installed at each end of the two downturning beams to ensure that the water flows to the sump and the water flows smoothly. , the water in the sump is pumped to the nearest rainwater well on the ground through a 10m³/d submersible pump. Adjustment.

基坑开挖过程中,网喷面个别部位存在渗水现象,所以必要时在锚喷砼之前采用PVC管切口,外侧包扎两层80目纱网导流,引流位置从渗水处一直到坑底,使水流直接流入坑底的明(盲)沟排水系统。During the excavation of the foundation pit, there is water seepage in some parts of the net sprayed surface, so if necessary, use PVC pipe cutouts before the anchor sprayed concrete, and wrap two layers of 80-mesh gauze on the outside for drainage. The drainage position is from the seepage to the bottom of the pit. Make the water flow directly into the open (blind) ditch drainage system at the bottom of the pit.

在本发明的描述中,需要理解的是,术语“垂直”、“上”、“下”、“一侧端”、“一端”、“上端”、“水平”、“上方”、“下方”、“竖直”、“中部”、“下端”、 “另一端”、“纵向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位,以特定的方位构造和操作,因此,不能理解为对本发明的限制。In describing the present invention, it is to be understood that the terms "vertical", "upper", "lower", "side end", "one end", "upper end", "horizontal", "above", "below" , "vertical", "middle", "lower end", "other end", "longitudinal" and other indicated orientations or positional relationships are based on the orientations or positional relationships shown in the drawings, and are only for describing the present invention and simplifying the description , rather than indicating or implying that the device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore, should not be construed as limiting the invention.

在本发明中,除非另有明确规定和限定,术语“安装”、“ 相连”、“连接、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接连接,可以是通过中间媒介间接连接,可以是两个元件内部的连通或两个元件的相互作用关系,对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本发明中的具体含义。In the present invention, terms such as "installation", "connection", "connection" and "fixation" should be interpreted in a broad sense unless otherwise clearly specified and limited, for example, it may be a fixed connection or a detachable connection, or Integrate; it can be mechanical connection or electrical connection; it can be direct connection, it can be indirect connection through an intermediary, it can be the internal communication of two components or the interaction relationship between two components, for ordinary skills in the art Personnel can understand the specific meanings of the above terms in the present invention according to specific situations.

以上所述的仅是本发明的优选实施例。应当指出,对于本领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以作出若干变型和改进,也应视为属于本发明的保护范围。What has been described above are only preferred embodiments of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, some modifications and improvements can be made, which should also be considered as belonging to the protection scope of the present invention.

Claims (8)

1.一种地铁深基坑侧壁夹层水处理方法,其特征在于如下步骤:1)、基坑外降水井施工:1.1)埋设护筒:将护筒底部埋入原土层;1.2)钻机成孔:步骤1.1)后,钻机就位,进行降水井成孔;1.3)吊放井管滤管:井管采用无砂水泥管,下放至井内;1.4)填滤料:步骤1.3)后在滤管内填入滤料;1.5)洗井:采用活塞空压机联合洗井,成井后用污水泵与空压机反复进行清洗至水清砂净;1.6)水泵安装:潜水泵用尼龙绳放入井内,铺设电缆和电闸箱;1.7)铺设排水管网:地面铺设排水管,排水管在每一个井位预留分接头并连接有高压螺旋式阀门;1.8)水位抽降:1.9)水位观测:静止水位观测,初期早晚各一次,水位稳定后每天一次;1.10)降水;1.11)抽水运行;2)、基坑内降水井施工:集水井采用人工开挖形式,集水井周边采用钢套管进行支护,钢套管侧壁预留孔洞,同时采用双层滤网进行缠绕;3)、换乘站节点降水:采用管井降水系统进行抽降水;4)、基坑内设置明沟或盲沟排水系统: 横向和纵向均设置盲沟,盲沟上均设有3‰的流水坡;5)坑基内设置排水系统;6)基坑内封井;7)基坑外封井。1. A method for treating interlayer water on the side wall of a subway deep foundation pit, characterized by the following steps: 1), construction of a dewatering well outside the foundation pit: 1.1) Embedding the casing: bury the bottom of the casing into the original soil layer; 1.2) Drilling rig Hole forming: After step 1.1), the drilling rig is in place, and the dewatering well is formed; 1.3) Hanging the well pipe and filter pipe: the well pipe is made of sand-free cement pipe and lowered into the well; 1.4) Filling filter material: after step 1.3) Fill the filter tube with filter material; 1.5) Well cleaning: Use a piston air compressor to clean the well, and after the well is completed, use a sewage pump and an air compressor to clean it repeatedly until the water and sand are clean; Enter the well, lay cables and electric switch boxes; 1.7) Lay the drainage pipe network: lay drainage pipes on the ground, and the drainage pipes reserve taps at each well position and connect with high-pressure screw valves; 1.8) Water level pumping down: 1.9) Water level observation : Static water level observation, once in the morning and evening at the beginning, once a day after the water level stabilizes; 1.10) precipitation; For support, holes are reserved on the side wall of the steel casing, and double-layer filter screens are used for winding; 3) Dewatering at transfer station nodes: tube well dewatering system is used for pumping and dewatering; 4) Open ditch or blind ditch drainage system is set in the foundation pit : Blind ditches are installed both horizontally and vertically, and a 3‰ flowing water slope is provided on the blind ditches; 5) Drainage systems are installed in the pit foundation; 6) Wells are sealed inside the pit; 7) Wells are closed outside the pit. 2.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤1.10)中,在开挖前15天开始启动降水井抽水,降水降至基底一下1m。2. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: in the step 1.10), the dewatering well pumping is started 15 days before the excavation, and the dewatering drops to 1m below the base . 3.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤1.11)中,开挖前的提前封闭降水时间不少于15天;抽水含砂量:粗砂含量小于1/50000,中砂含量小于1/20000,细砂含量小于1/10000。3. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: in the step 1.11), the pre-sealed precipitation time before excavation is not less than 15 days; : The coarse sand content is less than 1/50000, the medium sand content is less than 1/20000, and the fine sand content is less than 1/10000. 4.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤3)中降水井井壁管采用花管,井壁管外径380mm,花管采用混凝土预制滤管,滤管每节0.9m,下放井管时,两滤管接缝处用编织袋包扎严实,并用三根竹片结合铁丝把上下两节固定牢固,井距在8.0-12.0m,每个降水井配一台流量为10m3/h的潜水泵,潜水泵和排水管连接采用塑料软管,塑料软管直径大小按潜水泵连接接头确定,每个降水井旁边设置直径273mm的钢管按坡度进行排水至雨污水井里面。4. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: in the step 3), the well wall pipe of the dewatering well adopts flower pipes, the outer diameter of the well wall pipes is 380mm, and the flower pipes adopt Concrete prefabricated filter pipe, each section of the filter pipe is 0.9m. When the well pipe is lowered, the joints of the two filter pipes are tightly wrapped with woven bags, and the upper and lower sections are fixed firmly with three bamboo pieces combined with iron wire. The well spacing is 8.0-12.0m. Each dewatering well is equipped with a submersible pump with a flow rate of 10m 3 /h. The connection between the submersible pump and the drainage pipe is made of a plastic hose. Drainage is carried out according to the slope to the inside of the rainwater well. 5.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤4)中所述纵向盲沟由西向东设3‰的流水坡,所述横向盲沟有南北两侧向中间设3‰的流水坡,流入到临时集水井里面,每一施工段端头向大里程4m处设置一条横向排水盲沟,盲沟底先铺一层厚0.8mm的塑料布,上面回填10cm厚的卵石,然后回填级配碎石至盲沟顶面。5. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: in the step 4), the vertical blind ditch is provided with a running water slope of 3‰ from west to east, and the horizontal blind ditch The ditch has a slope of 3‰ in the middle of the north and south sides, and flows into the temporary water collection well. A horizontal drainage blind ditch is set at the end of each construction section 4m away from the maximum mileage. The bottom of the blind ditch is first paved with a layer of 0.8mm thick Plastic sheet, backfill with 10cm thick pebbles, and then backfill with graded gravel to the top of the blind ditch. 6.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤5)中用带水平眼的Ф100PVC管,每节长100cm,插入土体100cm,露出90°弯头至钢筋网片内侧,然后接竖向Ф100mmPVC管到盲沟顶;盲沟结构尺寸为:宽30cm,深50cm,盲沟修筑完成内,回填级配良好的碎石至盲沟顶面;纱布包裹PVC管插入土体部分;Ф100mm渗水PVC管深入土体部分向下倾斜宜为5°~15°,桩间砂土流失严重的孔洞,用注浆机对孔洞进行回填注浆,注浆压力为0.3Mpa~0.5Mpa,浆液水灰比=1:1。6. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: in the step 5), a Ф100 PVC pipe with a horizontal eye is used, each section is 100 cm long, inserted into the soil body for 100 cm, and exposed 90° elbow to the inner side of the steel mesh, and then connect the vertical Ф100mm PVC pipe to the top of the blind ditch; the structural size of the blind ditch is: width 30cm, depth 50cm, after the blind ditch is completed, backfill with well-graded gravel to the top of the blind ditch Surface; the gauze-wrapped PVC pipe is inserted into the soil part; the Ф100mm permeable PVC pipe penetrates into the soil part and the downward slope should be 5°~15°. For holes with serious sand loss between piles, use a grouting machine to backfill the holes. The grouting pressure is 0.3Mpa~0.5Mpa, and the grout water-cement ratio=1:1. 7.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤6)中封井前,防水层平铺至井管上5cm,加强层平铺至井管上10cm,加强层平铺尺寸20cm,井管与防水层、与加强层用密封胶粘紧,加强层的最上面用金属箍固定;封井前,安装厚8mm,长10cm的止水法兰,在止水法兰上安装20mm*10mm截面的遇水膨胀止水条沿止水法兰一圈;底板与井身交叉处安装防水层时,沿折角5cm的等边三角形内用密封胶粘死;封井时,用两块10mm厚圆钢板,中间夹着橡胶密封环板,边上用螺栓固定,封井处用防水砂浆填实。7. The method for treating interlayer water on the side wall of subway deep foundation pit as claimed in claim 1, characterized in that: before the well is sealed in step 6), the waterproof layer is tiled to 5 cm above the well pipe, and the reinforcement layer is tiled to The top of the well pipe is 10cm, and the size of the reinforcement layer is 20cm. The well pipe, the waterproof layer, and the reinforcement layer are glued tightly with sealant, and the top of the reinforcement layer is fixed with a metal hoop. Before sealing the well, install a water stop with a thickness of 8mm and a length of 10cm. For the flange, install a water-swelling water-stop strip with a cross-section of 20mm*10mm on the water-stop flange and make a circle around the water-stop flange; when installing a waterproof layer at the intersection of the bottom plate and the well body, use a seal along an equilateral triangle with a knuckle angle of 5cm Glue to death; when sealing the well, use two 10mm thick round steel plates with a rubber sealing ring plate sandwiched between them, and fix them with bolts on the sides, and fill the well sealing place with waterproof mortar. 8.如权利要求1所述的地铁深基坑侧壁夹层水处理方法,其特征在于:所述的步骤7)中,基坑外降水井使用时间为基坑开挖至顶板抗浮梁施工完成,采用素混凝土进行回填密封。8. The method for treating interlayer water on the side wall of subway deep foundation pit according to claim 1, characterized in that in step 7), the use time of the dewatering well outside the foundation pit is from excavation of the foundation pit to the construction of the anti-floating beam on the roof Completed, backfill and seal with plain concrete.
CN201910693042.0A 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water Pending CN110374125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910693042.0A CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910693042.0A CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Publications (1)

Publication Number Publication Date
CN110374125A true CN110374125A (en) 2019-10-25

Family

ID=68256965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910693042.0A Pending CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Country Status (1)

Country Link
CN (1) CN110374125A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984162A (en) * 2019-11-07 2020-04-10 广西建工集团第五建筑工程有限责任公司 Seepage-proofing and seepage-resisting construction method for foundation pit near river
CN111395995A (en) * 2020-03-19 2020-07-10 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN117403677A (en) * 2023-11-15 2024-01-16 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method
CN120421282A (en) * 2025-07-09 2025-08-05 山西阳煤千军汽车部件有限责任公司 Sand cleaning device for sand casting of automobile cylinder cover and operation method of sand cleaning device

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839691A (en) * 2011-06-22 2012-12-26 南通海洲建设集团有限公司 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN208201896U (en) * 2017-12-31 2018-12-07 中铁十八局集团第五工程有限公司 A kind of underground engineering dewatering well waterproof construction

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839691A (en) * 2011-06-22 2012-12-26 南通海洲建设集团有限公司 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN208201896U (en) * 2017-12-31 2018-12-07 中铁十八局集团第五工程有限公司 A kind of underground engineering dewatering well waterproof construction

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
徐明: "黄土地质条件下的地铁深基坑降水技术探讨", 《科学技术创新》, no. 10, pages 109 - 110 *
车广义: "降水井施工条件与技术", 《石家庄铁道大学学报(自然科学版)》, vol. 31, pages 126 - 129 *
郝建鸿等: "沙钢5m 宽厚板轧机工程基坑降水技术", 《工业建筑》, vol. 37, pages 756 - 758 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984162A (en) * 2019-11-07 2020-04-10 广西建工集团第五建筑工程有限责任公司 Seepage-proofing and seepage-resisting construction method for foundation pit near river
CN111395995A (en) * 2020-03-19 2020-07-10 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN111395995B (en) * 2020-03-19 2021-10-29 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN117403677A (en) * 2023-11-15 2024-01-16 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method
CN117403677B (en) * 2023-11-15 2024-04-30 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method
CN120421282A (en) * 2025-07-09 2025-08-05 山西阳煤千军汽车部件有限责任公司 Sand cleaning device for sand casting of automobile cylinder cover and operation method of sand cleaning device

Similar Documents

Publication Publication Date Title
CN110374125A (en) Metro Deep Excavation side wall interlayer method for treating water
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN105002913B (en) A kind of highly permeable stratum deep basal pit back cover water sealing structure and its construction method
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN112049115A (en) Anti-seepage treatment method for deep foundation pit excavation of water-rich silt stratum
CN111139852A (en) Water-rich sandy gravel stratum high-permeability ultra-deep foundation pit dewatering construction method
CN104878771B (en) The construction method of vacuum tube well precipitation system
CN115012452A (en) Post-casting belt construction technology and basement drainage and pressure relief structure
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN107100206A (en) A kind of prevention and controls of basement leakage
CN114592911A (en) A super-span open-cut tunnel waterproof and drainage structure
CN212506349U (en) A device for water sealing well in the dewatering zone of ultra-deep foundation pit tube well
CN114164869A (en) Magnetic-attraction impermeable film vertical concealed laying device and water-intercepting curtain construction method
CN107724405A (en) A kind of underground pipe construction middle pipe dewatering of foundation construction method
CN211312564U (en) Groundwater control structure of deep foundation pit in highly permeable stratum based on pressure reduction and seepage reduction
CN106638641B (en) Base pit dewatering well structure and its construction method
CN216275788U (en) Drainage device used after failure of water interception curtain of deep foundation pit
CN204825916U (en) Highly permeable stratum deep basal pit back cover stagnant water structure
CN116537269A (en) Seepage pressure-reducing anti-floating structure of underground building and construction method thereof
CN204551507U (en) A kind of rock foundation ductule local dewatering device
CN108755724A (en) The external water drainage waterproof method of pipe gallery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191025

RJ01 Rejection of invention patent application after publication