CN110374125A - Metro Deep Excavation side wall interlayer method for treating water - Google Patents

Metro Deep Excavation side wall interlayer method for treating water Download PDF

Info

Publication number
CN110374125A
CN110374125A CN201910693042.0A CN201910693042A CN110374125A CN 110374125 A CN110374125 A CN 110374125A CN 201910693042 A CN201910693042 A CN 201910693042A CN 110374125 A CN110374125 A CN 110374125A
Authority
CN
China
Prior art keywords
well
water
foundation pit
french drain
precipitation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910693042.0A
Other languages
Chinese (zh)
Inventor
任笑谦
陈云飞
董光
李志明
王振东
安刚
范非昨
车广义
卢秀芬
曹金波
程晓龙
冯双龙
郭建军
刘佳兴
林操
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
China Railway No 9 Group Co Ltd
Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 9 Group Co Ltd, Seventh Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical China Railway No 9 Group Co Ltd
Priority to CN201910693042.0A priority Critical patent/CN110374125A/en
Publication of CN110374125A publication Critical patent/CN110374125A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to a kind of Metro Deep Excavation side wall interlayer method for treating water, and steps are as follows: 1), the construction of foundation pit outer dewatering well: embedded casing;Drilling machine pore-forming;Hang well tube filter;Fill out filtrate;Well-flushing;Water pump installation;It is laid with drainage pipeline networks;Water level takes out drop;Water-level observation;Precipitation;It draws water operation;2), precipitation well in foundation pit is constructed;3) tiny node precipitation, is changed to;4), the bright ditch of setting or blind drainage system in foundation pit;5) drainage system is set in pit foundation;6) shut-in well in foundation pit;7) it shunts in a well outside foundation pit.Mutual cooperation precipitation inside and outside foundation pit ensure that engineering is smoothly implemented, and solve the problems, such as that water table aquifer and intermediate water are dry compared with hard-pumped.

Description

Metro Deep Excavation side wall interlayer method for treating water
Technical field
The present invention relates to a kind of method for treating water, especially a kind of Metro Deep Excavation side wall interlayer method for treating water belongs to Metro building construction field.
Background technique
With the development of society, modern Metro station excavation gradually Xiang Geng great more Shenzhen Development Bank, underground water is to deep foundation pit construction Huge security risk is caused, is opened so being increasingly becoming Metro station excavation to the processing of underground water in Deep foundation Pit excavation Essential measure during excavation construction, especially in underground water compared with abundant, the poor stratum of geological conditions, groundwater treatment Scheme and construction quality are even more that can directly affect the security performance of foundation pit.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of Metro Deep Excavation side wall interlayer method for treating water, inside and outside foundation pit Mutual cooperation precipitation ensure that engineering is smoothly implemented, and solve the problems, such as that water table aquifer and intermediate water are dry compared with hard-pumped.
In order to solve the above problem, the specific technical solution of the present invention is as follows: a kind of Metro Deep Excavation side wall interlayer water process Method, steps are as follows: 1), foundation pit outer dewatering well construction: 1.1) bury casing: by casing bottom be embedded to native soil layer;1.2) drilling machine Pore-forming: after step 1.1), drilling machine is in place, carries out dewatering well pore-forming;1.3) hang well tube filter: well casing using no sand cement pipe, In decentralization to well;1.4) it fills out filtrate: inserting filtrate after step 1.3) in chimney filter;1.5) well-flushing: combined using Piston Air Compressor Well-flushing, it is net to water sand removal that with sewage pump and air compressor machine cleaning is repeated in Cheng Jinghou;1.6) water pump is installed: immersible pump nylon rope It is put into well, is laid with cable and switch box;1.7) be laid with drainage pipeline networks: ground is laid with drainpipe, and drainpipe is in each well location Reserved tap is simultaneously connected with high-pressure spiral formula valve;1.8) water level takes out drop: 1.9) water-level observation: static level observation, initial stage Once in the morning and once at night, after stable level once a day;1.10) precipitation;1.11) it draws water operation;2), precipitation well in foundation pit is constructed: collection Well uses hand excavation's form, and sump periphery carries out supporting using steel sleeve, and steel sleeve side wall reserving hole uses simultaneously Double-layer leaching net is wound;3) it, changes to tiny node precipitation: pumping precipitation is carried out using tube well dewatering system;4), setting is bright in foundation pit Ditch or blind drainage system: it is horizontal and vertical to be respectively provided with french drain, 3 ‰ flowing water slope is equipped on french drain;5) setting row in pit foundation Water system;6) shut-in well in foundation pit;7) it shunts in a well outside foundation pit.
In the step 1.10), starts within 15 days before excavation starting dewatering well and draw water, precipitation is down to substrate 1m once.
In the step 1.11), the precipitation time of closing in advance before excavation is no less than 15 days;It draws water sand content: coarse sand Content is less than 1/50000, and middle sand content is less than 1/20000, and fine content is less than 1/10000.
Dewatering well wall casing uses floral tube in the step 3), and borehole wall pipe outside diameter 380mm, floral tube is using concrete prefabricated Chimney filter, the every section 0.9m of chimney filter, when transferring well casing, two chimney filter seam crossings wrapped up with woven bag it is tight, and with three bamboo chip combination iron Silk is 10m with a flow in 8.0-12.0m, each dewatering well upper and lower two sections fixation, well spacing3The immersible pump of/h is dived Water pump is connected with drainpipe using plastic flexible pipe, and plastic flexible pipe diameter is determined by immersible pump jointing, each dewatering well The steel pipe of side setting diameter 273mm is drained by the gradient to rain bilge well.
Longitudinal direction french drain described in the step 4) sets 3 ‰ flowing water slope from west to east, and the transverse direction french drain has north and south two It is lateral intermediate set 3 ‰ flowing water slope, be flowed into inside interim sump, each construction section end is to the place big mileage 4m setting one Transverse drainage french drain, french drain bottom first spread the plastic cloth of a thickness 0.8mm, backfill the cobble of 10cm thickness above, then backfill gradation Rubble is to french drain top surface.
It is managed in the step 5) with the Ф 100PVC with horizontal eye, every long 100cm of section, is inserted into soil body 100cm, exposed On the inside of 90 ° of elbows to reinforced mesh, vertical Ф 100mmPVC pipe is then connect to french drain top;French drain structure size are as follows: wide 30cm is deep 50cm, french drain are built in completion, the backfill good rubble of gradation to french drain top surface;Gauze wraps up pvc pipe and is inserted into soil body part;Ф 100mm infiltration pvc pipe gos deep into soil body part and tilts down preferably 5 ° ~ 15 °, and the serious hole of sand running-down, uses slip casting machine between stake Backfill slip casting is carried out to hole, grouting pressure is 0.3Mpa ~ 0.5Mpa, the slurries ratio of mud=1:1.
In the step 6) before shut-in well, waterproof layer tiles to 5cm on well casing, and enhancement layer tiles to 10cm on well casing, adds Strong layer tile size 20cm, well casing are clinged with waterproof layer and enhancement layer with sealant, and the top of enhancement layer is solid with ferrule It is fixed;Before shut-in well, thickness 8mm is installed, the water flange of long 10cm installs the water-swellable in the section 20mm*10mm on water flange Sealing rod is enclosed along water flange one;When bottom plate and well bore infall installation waterproof layer, with close along the equilateral triangle of dog-ear 5cm Sealing is viscous dead;When shut-in well, with two pieces of 10mm thickness round plates, sandwich rubber seal ring flat-plate, Bian Shangyong bolt is fixed, at shut-in well It is tamped with waterproof mortar.
In the step 7), foundation pit outer dewatering well is that excavation of foundation pit to top plate anti-floating beam construction is completed using the time, is adopted Back fill seals are carried out with plain concrete.
Bring of the present invention has the beneficial effect that mutual cooperation precipitation inside and outside foundation pit, ensure that engineering is smoothly implemented, solves Water table aquifer and intermediate water are compared with the problem that hard-pumped is done.
Detailed description of the invention
Fig. 1 is Metro Deep Excavation side wall interlayer method for treating water Construction Principle schematic diagram.
Specific embodiment
As shown in Figure 1, a kind of Metro Deep Excavation side wall interlayer method for treating water, steps are as follows: 1), foundation pit outer dewatering well applies Work: 1.1) it buries casing: casing bottom is embedded to native soil layer;1.2) drilling machine pore-forming: after step 1.1), drilling machine is in place, is dropped Well pore-forming;1.3) hang well tube filter: well casing is transferred using no sand cement pipe to well;1.4) filtrate is filled out: after step 1.3) Filtrate is inserted in chimney filter;1.5) well-flushing: using Piston Air Compressor combined washing well, Cheng Jinghou sewage pump and air compressor machine repeatedly into Row cleaning is net to water sand removal;1.6) water pump is installed: immersible pump is put into well with nylon rope, is laid with cable and switch box;1.7) it spreads If drainage pipeline networks: ground is laid with drainpipe, and drainpipe reserves tap in each well location and is connected with high-pressure spiral formula valve; When drawing water, first water is extracted into water tank, precipitates the sludge in water, then the water in water tank is discharged in catch-basin, while winter applies Between duration, drainage pipeline takes rubber-plastic sponge heat-insulating plate+Self-controlling-temperature Heating Belt+Insulating aluminium leather hose mode, along pipeline near water One of rubber-plastic sponge heat-insulating plate is first wrapped up in bottom, then one Self-controlling-temperature Heating Belt of laying, outsourcing 70mm thickness Insulating aluminium leather hose, this Kind thermal-insulating scheme can guarantee that for pipeline at subzero 25 degree or so, internal temperature maintains 10-20 degree or so near water;1.8) water level is taken out Drop: 1.9) water-level observation: static level observation, initial stage once in the morning and once at night, after stable level once a day;1.10) precipitation; 1.11) it draws water operation;2), precipitation well in foundation pit is constructed: sump uses hand excavation's form, and sump periphery uses steel sleeve Supporting, steel sleeve side wall reserving hole are carried out, while being wound using double-layer leaching net;3) tiny node precipitation, is changed to: using pipe Well precipitation system carries out pumping precipitation;4), the bright ditch of setting or blind drainage system in foundation pit: it is horizontal and vertical to be respectively provided with french drain, it is blind 3 ‰ flowing water slope is equipped on ditch;5) drainage system is set in pit foundation;6) shut-in well in foundation pit;7) it shunts in a well outside foundation pit.
In the step 1.10), starts within 15 days before excavation starting dewatering well and draw water, precipitation is down to substrate 1m once.
In the step 1.11), the precipitation time of closing in advance before excavation is no less than 15 days;It draws water sand content: coarse sand Content is less than 1/50000, and middle sand content is less than 1/20000, and fine content is less than 1/10000.
Dewatering well wall casing uses floral tube in the step 3), and borehole wall pipe outside diameter 380mm, floral tube is using concrete prefabricated Chimney filter, the every section 0.9m of chimney filter, when transferring well casing, two chimney filter seam crossings wrapped up with woven bag it is tight, and with three bamboo chip combination iron Silk is 10m with a flow in 8.0-12.0m, each dewatering well upper and lower two sections fixation, well spacing3The immersible pump of/h is dived Water pump is connected with drainpipe using plastic flexible pipe, and plastic flexible pipe diameter is determined by immersible pump jointing, each dewatering well The steel pipe of side setting diameter 273mm is drained by the gradient to rain bilge well.
Longitudinal direction french drain described in the step 4) sets 3 ‰ flowing water slope from west to east, and the transverse direction french drain has north and south two It is lateral intermediate set 3 ‰ flowing water slope, be flowed into inside interim sump, each construction section end is to the place big mileage 4m setting one Transverse drainage french drain, french drain bottom first spread the plastic cloth of a thickness 0.8mm, backfill the cobble of 10cm thickness above, then backfill gradation Rubble is to french drain top surface.
It is managed in the step 5) with the Ф 100PVC with horizontal eye, every long 100cm of section, is inserted into soil body 100cm, exposed On the inside of 90 ° of elbows to reinforced mesh, vertical Ф 100mmPVC pipe is then connect to french drain top;French drain structure size are as follows: wide 30cm is deep 50cm, french drain are built in completion, the backfill good rubble of gradation to french drain top surface;Gauze wraps up pvc pipe and is inserted into soil body part;Ф 100mm infiltration pvc pipe gos deep into soil body part and tilts down preferably 5 ° ~ 15 °, and the serious hole of sand running-down, uses slip casting machine between stake Backfill slip casting is carried out to hole, grouting pressure is 0.3Mpa ~ 0.5Mpa, the slurries ratio of mud=1:1.
In the step 6) before shut-in well, waterproof layer tiles to 5cm on well casing, and enhancement layer tiles to 10cm on well casing, adds Strong layer tile size 20cm, well casing are clinged with waterproof layer and enhancement layer with sealant, and the top of enhancement layer is solid with ferrule It is fixed;Before shut-in well, thickness 8mm is installed, the water flange of long 10cm installs the water-swellable in the section 20mm*10mm on water flange Sealing rod is enclosed along water flange one;When bottom plate and well bore infall installation waterproof layer, with close along the equilateral triangle of dog-ear 5cm Sealing is viscous dead;When shut-in well, with two pieces of 10mm thickness round plates, sandwich rubber seal ring flat-plate, Bian Shangyong bolt is fixed, at shut-in well It is tamped with waterproof mortar.
In the step 7), foundation pit outer dewatering well is that excavation of foundation pit to top plate anti-floating beam construction is completed using the time, is adopted Back fill seals are carried out with plain concrete.
Embodiment: Line 1 west side expanding reach and standard paragraphs determine bright row, are exactly bright (blind) the ditch water discharge system of setting in foundation pit, Overall length sets a weeper drain, french drain size in stake are as follows: deep 0.5m, wide 0.3m, longitudinal direction french drain used set 3 ‰ from west to east Flowing water slope, the flowing water slope that all transverse direction french drains have south and north flanks to set 3 ‰ to centre, is flowed into inside interim sump.It is each to apply Workshop section end is to a transverse drainage french drain is arranged at big mileage 4m.The plastic cloth that french drain bottom first spreads a thickness 0.8mm (prevents blind The ditch bottom of trench soil body is by soaking), the cobble of 10cm thickness is backfilled above, then backfills graded broken stone to french drain top surface, transverse drainage is blind An interim catch pit is set among ditch, is evacuated to inside rain bilge well nearest on ground by the immersible pump of 10m3/d.
Before this section of bottom cushion of constructing, the weeper drain of next construction section and interim catch pit are performed, by latent Water pump and french drain are by water ejectment to the interim catch pit of next construction section, this section of bottom cushion of constructing, sump C20 concrete It fills closely knit.When turning over beam as dug, water is drained into interim sump by french drain.It such as digs down when turning over beam, has dug down after turning over beam, stand It digs down and turns over beam beam bottom french drain, linked network then is carried out to french drain and the beam side soil body and sprays C20 pea gravel concreten, C20 microlith coagulation Native match ratio: cement: microlith: sand: water: accelerator=1:2.027:2.37:0.49:0.04 turns under two and sets one among beam beam bottom 3 ‰ french drain of road, manual repair's french drain gradient, french drain bottom first spread the plastic cloth of a thickness 0.8mm, backfill the ovum of 10cm thickness above Then stone backfills graded broken stone to french drain top surface, turns over beam-ends head under two and respectively set an interim sump, guarantee that water is flow to and catchment Hole guarantees that flowing water is smooth, and the water of catch pit is evacuated to rain bilge well the inside nearest on ground by the immersible pump of 10m3/d, under turn over The water that the french drain of beam beam bottom and interim sump size can turn over beam two sides intermediate water under carries out live adjustment.
In Excavation Process, there is infiltration phenomenon in net spray plane individual sites, so using before shotcrete concrete when necessary Two layers of 80 mesh gauze water conservancy diversion are wrapped up in pvc pipe notch, outside, and drainage location is from rises until hole bottom, flows directly into water flow Cheat bright (blind) the ditch water discharge system at bottom.
In the description of the present invention, it is to be understood that, term " vertical ", "upper", "lower", " side ", " one end ", The orientation of the instructions such as " upper end ", "horizontal", " top ", " lower section ", "vertical", " middle part ", " lower end ", " other end ", " longitudinal direction " Or positional relationship describes merely to description is of the invention with simplified to be based on the orientation or positional relationship shown in the drawings, rather than The device or element of indication or suggestion meaning must have a particular orientation, and be constructed and operated in a specific orientation, it is thus impossible to It is interpreted as limitation of the present invention.
In the present invention, it unless otherwise expressly provided and limits, term " installation ", " connects, the arts such as " fixation " " connected " Language shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be mechanical connect It connects, is also possible to be electrically connected;It can be and be directly connected to, can be and be indirectly connected with by intermediary, can be in two elements The interaction relationship of the connection in portion or two elements for the ordinary skill in the art can be according to specific feelings Condition understands the concrete meaning of above-mentioned term in the present invention.
Above-described is only the preferred embodiment of the present invention.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the principle of the present invention, several variations and modifications can also be made, also should be regarded as belonging to guarantor of the invention Protect range.

Claims (8)

1. a kind of Metro Deep Excavation side wall interlayer method for treating water, it is characterised in that following steps: 1), foundation pit outer dewatering well applies Work: 1.1) it buries casing: casing bottom is embedded to native soil layer;1.2) drilling machine pore-forming: after step 1.1), drilling machine is in place, is dropped Well pore-forming;1.3) hang well tube filter: well casing is transferred using no sand cement pipe to well;1.4) filtrate is filled out: after step 1.3) Filtrate is inserted in chimney filter;1.5) well-flushing: using Piston Air Compressor combined washing well, Cheng Jinghou sewage pump and air compressor machine repeatedly into Row cleaning is net to water sand removal;1.6) water pump is installed: immersible pump is put into well with nylon rope, is laid with cable and switch box;1.7) it spreads If drainage pipeline networks: ground is laid with drainpipe, and drainpipe reserves tap in each well location and is connected with high-pressure spiral formula valve; 1.8) water level take out drop: 1.9) water-level observation: static level observation, initial stage once in the morning and once at night, after stable level once a day; 1.10) precipitation;1.11) it draws water operation;2), precipitation well in foundation pit is constructed: sump uses hand excavation's form, sump periphery Supporting, steel sleeve side wall reserving hole are carried out using steel sleeve, while being wound using double-layer leaching net;3) tiny node, is changed to Precipitation: pumping precipitation is carried out using tube well dewatering system;4), the bright ditch of setting or blind drainage system in foundation pit: horizontal and vertical equal French drain is set, 3 ‰ flowing water slope is equipped on french drain;5) drainage system is set in pit foundation;6) shut-in well in foundation pit;7) foundation pit covering Well.
2. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: the step 1.10) in, start within 15 days before excavation starting dewatering well and draw water, precipitation is down to substrate 1m once.
3. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: the step 1.11) in, the precipitation time of closing in advance before excavation is no less than 15 days;Draw water sand content: coarse sand content less than 1/50000, in Sand content is less than 1/20000, and fine content is less than 1/10000.
4. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: in the step 3) Dewatering well wall casing uses floral tube, borehole wall pipe outside diameter 380mm, and floral tube uses concrete prefabricated chimney filter, the every section 0.9m of chimney filter, decentralization When well casing, two chimney filter seam crossings are wrapped up tightly with woven bag, and with three bamboo chip combination iron wires upper and lower two sections fixation, well Away from 8.0-12.0m, each dewatering well is 10m with a flow3The immersible pump of/h, immersible pump and drainpipe are connected using plastics Hose, plastic flexible pipe diameter are determined that the steel pipe of setting diameter 273mm is pressed beside each dewatering well by immersible pump jointing The gradient is drained to rain bilge well.
5. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: in the step 4) The longitudinal direction french drain sets 3 ‰ flowing water slope from west to east, the transverse direction french drain flowing water slope that has south and north flanks to set 3 ‰ to centre, It is flowed into inside interim sump, each construction section end is first to one transverse drainage french drain of setting, french drain bottom at big mileage 4m The plastic cloth of a thickness 0.8mm is spread, backfills the cobble of 10cm thickness above, then backfills graded broken stone to french drain top surface.
6. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: in the step 5) With the Ф 100PVC pipe with horizontal eye, every long 100cm of section is inserted into soil body 100cm, exposes on the inside of 90 ° of elbows to reinforced mesh, so Vertical Ф 100mmPVC pipe is followed by french drain top;French drain structure size are as follows: wide 30cm, deep 50cm, french drain are built in completion, backfill The good rubble of gradation is to french drain top surface;Gauze wraps up pvc pipe and is inserted into soil body part;Ф 100mm infiltration pvc pipe gos deep into soil body portion Divide and tilt down preferably 5 ° ~ 15 °, the serious hole of sand running-down between stake carries out backfill slip casting, slip casting pressure to hole with slip casting machine Power is 0.3Mpa ~ 0.5Mpa, the slurries ratio of mud=1:1.
7. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: in the step 6) Before shut-in well, waterproof layer tiles to 5cm on well casing, and enhancement layer tiles to 10cm on well casing, enhancement layer tile size 20cm, well casing with Waterproof layer and enhancement layer are clinged with sealant, and the top of enhancement layer is fixed with ferrule;Before shut-in well, thickness 8mm is installed, it is long The water flange of 10cm, the water expandable waterstop that the section 20mm*10mm is installed on water flange are enclosed along water flange one;Bottom It is dead with sealing gluing along the equilateral triangle of dog-ear 5cm when plate and well bore infall installation waterproof layer;When shut-in well, with two pieces 10mm thickness round plate, sandwich rubber seal ring flat-plate, Bian Shangyong bolt are fixed, are tamped at shut-in well with waterproof mortar.
8. Metro Deep Excavation side wall interlayer method for treating water as described in claim 1, it is characterised in that: the step 7) In, foundation pit outer dewatering well is that excavation of foundation pit to top plate anti-floating beam construction is completed using the time, backfill using plain concrete close Envelope.
CN201910693042.0A 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water Pending CN110374125A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910693042.0A CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910693042.0A CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Publications (1)

Publication Number Publication Date
CN110374125A true CN110374125A (en) 2019-10-25

Family

ID=68256965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910693042.0A Pending CN110374125A (en) 2019-07-30 2019-07-30 Metro Deep Excavation side wall interlayer method for treating water

Country Status (1)

Country Link
CN (1) CN110374125A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984162A (en) * 2019-11-07 2020-04-10 广西建工集团第五建筑工程有限责任公司 Seepage-proofing and seepage-resisting construction method for foundation pit near river
CN111395995A (en) * 2020-03-19 2020-07-10 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN117403677A (en) * 2023-11-15 2024-01-16 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839691A (en) * 2011-06-22 2012-12-26 南通海洲建设集团有限公司 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN208201896U (en) * 2017-12-31 2018-12-07 中铁十八局集团第五工程有限公司 A kind of underground engineering dewatering well waterproof construction

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839691A (en) * 2011-06-22 2012-12-26 南通海洲建设集团有限公司 Quick sealing method and device for sandless cement pipe deep well dewatering wellhead
CN208201896U (en) * 2017-12-31 2018-12-07 中铁十八局集团第五工程有限公司 A kind of underground engineering dewatering well waterproof construction

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
徐明: "黄土地质条件下的地铁深基坑降水技术探讨", 《科学技术创新》, no. 10, pages 109 - 110 *
车广义: "降水井施工条件与技术", 《石家庄铁道大学学报(自然科学版)》, vol. 31, pages 126 - 129 *
郝建鸿等: "沙钢5m 宽厚板轧机工程基坑降水技术", 《工业建筑》, vol. 37, pages 756 - 758 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984162A (en) * 2019-11-07 2020-04-10 广西建工集团第五建筑工程有限责任公司 Seepage-proofing and seepage-resisting construction method for foundation pit near river
CN111395995A (en) * 2020-03-19 2020-07-10 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN111395995B (en) * 2020-03-19 2021-10-29 丰电阳光(北京)清洁能源技术有限公司 Secondary well completion method for aquifer energy storage well
CN112746624A (en) * 2020-12-22 2021-05-04 中铁九局集团第二工程有限公司 Novel comprehensive water lowering and draining method and device for mudstone subway station
CN117403677A (en) * 2023-11-15 2024-01-16 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method
CN117403677B (en) * 2023-11-15 2024-04-30 中国水利水电第三工程局有限公司 Pump station deep foundation pit double drainage structure and construction method

Similar Documents

Publication Publication Date Title
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN110374125A (en) Metro Deep Excavation side wall interlayer method for treating water
CN107938692B (en) Drainage and recharging construction method and structure
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN103031850B (en) Low-permeability sludge claypan ultra-vacuum dual-pipe unwatering well and construction technology
CN104847010B (en) A kind of miniature groundwater reservoir in city and construction method
CN102383412A (en) Construction method by adopting dewatering and water recharging to control sedimentation surrounding deep foundation pit
LU500273B1 (en) New comprehensive dewatering and drainage method and drainage device for mudstone subway station
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN107044128A (en) Supporting and dewatering construction method in Deep Excavation
CN111139852A (en) Water-rich sandy gravel stratum high-permeability ultra-deep foundation pit dewatering construction method
KR101024787B1 (en) Tunnel abutment precast block structure and drainage structure of new concept and method constructing abutment used by them
CN107100206A (en) A kind of prevention and controls of basement leakage
CN109339059B (en) Comprehensive recycling system and construction method for foundation pit excavation backfill ramming and precipitation recharging water resources
CN107245989A (en) Bear the tunnel structure and its construction technology of external water pressure in height
CN106836232B (en) Deep basal pit pressure-bearing water seal drainage construction technique
CN212506349U (en) Water-logging well sealing device for water-lowering zone of ultra-deep foundation pit pipe well
CN211973796U (en) Novel rainwater underground disconnection system
CN113152425A (en) Combined freezing and reinforcing method for non-drainage excavation of large foundation pit
CN204899978U (en) Shaft excavation to interface water layer drainage system
CN203007963U (en) Ultra-high vacuum double-pipe drained well at low-permeability silt clay course
CN216552030U (en) Basement outer wall fat groove falls drainage structures
CN206477347U (en) The water storage structure of basement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination