CN103228841B - Combination isolated column - Google Patents
Combination isolated column Download PDFInfo
- Publication number
- CN103228841B CN103228841B CN201180020897.9A CN201180020897A CN103228841B CN 103228841 B CN103228841 B CN 103228841B CN 201180020897 A CN201180020897 A CN 201180020897A CN 103228841 B CN103228841 B CN 103228841B
- Authority
- CN
- China
- Prior art keywords
- bearing
- lateral isolation
- isolation bar
- bar
- splicing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01F—ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
- E01F8/00—Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic
- E01F8/02—Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic specially adapted for sustaining vegetation or for accommodating plants ; Embankment-type or crib-type noise barriers; Retaining walls specially adapted to absorb or reflect noise
- E01F8/021—Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic specially adapted for sustaining vegetation or for accommodating plants ; Embankment-type or crib-type noise barriers; Retaining walls specially adapted to absorb or reflect noise with integral support structure
- E01F8/022—Crib-type
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Supports For Plants (AREA)
- Cultivation Of Plants (AREA)
- Cultivation Receptacles Or Flower-Pots, Or Pots For Seedlings (AREA)
- Bridges Or Land Bridges (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
A kind of combination isolated column, this isolated column includes bearing (1) and lateral isolation bar (2).Wherein, this bearing (1) and lateral isolation bar (2) are symmetrical structure all around, and lateral isolation bar (2) top is plantation space, and bottom is the double cistern of pipelined channel (3);Bearing (1) has cross through hole (5), lateral isolation bar (2) left and right end face is provided with the double water supply and sewage of connecting hole (4), the arbitrary portion of lateral isolation bar (2) outer surface is enclosed in the interior and built on stilts splicing of through hole (5) of bearing thus bearing (1) arbitrarily can splice on lateral isolation bar (2) outer surface and moves, adjacent transverse spacer bar (2) directly by connecting hole (4) or is added plastic cement sealing gasket and indirectly connects with bolt or hollow tube bolt, and the pipelined channel (3) of adjacent transverse spacer bar (2) is mutually communicated;Part between two adjacent bearings (1) and lateral isolation bar (2) is symmetrical structure.
Description
Technical field
The present invention relates to a kind of isolated column, be related specifically to the combination isolation of a kind of planting plants within it or laying flowerpot
Hurdle.
Background technology
The support of Chinese patent CN2542716 is exactly guardrail or isolated column, and it is utilized in the guardrail itself not having greening
Or be with fixing connector, flower trough to be arranged on guardrail or flower stand on the support of number of patent application 02220331.1 on isolated column,
Being planted in flower trough by flowers and plants, its result is that flower trough makes steel construction guardrail or the scale of construction of flower stand and load make the most greatly guardrail produce again
Turning torque does not has security and stability, the most top-heavy be very easy to tumble collapse, and take up an area width, external irrigation pipe makes it
Guard bar structure is complicated, unsightly and relatively costly, it is often more important that external additional flower trough and irrigation pipe have severely compromised road
Road traffic and the safety of pedestrian, if applying on skyscraper by this technology, being very easy to is fallen by wind endangers the life of people
Life safety.
Summary of the invention
The technical problem to be solved is to provide a kind of combination isolated column, and this combination isolated column has following excellent
Point: 1. make the lateral isolation bar of combination isolated column itself not only have isolation features but also there is direct planting plants within it
Or the greening function of laying flowerpot;2. combination isolated column only needs replacing time or lateral isolation bar just can meet difference simultaneously
Insulation request and greening aesthetic;3. bearing is not only had turning torque by vertical pressure, is i.e. that center of gravity is on the plane of symmetry
The stable and combination isolated column with greening function of safeguard construction;4. simple in construction, installation and easy accessibility, with low cost
The combination isolated column with greening function;5. the bottom Nature Link making lateral isolation bar be formed through whole combination every
Water supply and sewage pouring management maintenance system from hurdle;6. it is spliced into bearing and horizontal stroke that in the combination isolated column of entirety, any two is adjacent
Structure between spacer bar be all support force and be symmetrical rock-steady structure on two adjacent bearings.
The present invention solves above-mentioned technical problem and is adopted the technical scheme that: combination isolated column, including bearing and laterally every
Before and after bar, described bearing and lateral isolation bar appearance profile are all and bilateral symmetry, on described lateral isolation bar
Portion is plantation space, and bottom is that cistern is held concurrently pipelined channel, and water supply and sewage lateral isolation bar left and right end face having position corresponding is held concurrently
Connecting hole, bearing has by the through hole of a side to another side, vertically symmetrical of through hole with vertically symmetrical of bearing
Parallel and distance is in 6 centimetres, and any one section of the whole outer surface of described lateral isolation bar is enclosed in the through hole of bearing also
Built on stilts splicing, its bearing arbitrarily can splice and mobile on the whole outer surface of lateral isolation bar, the end of adjacent transverse spacer bar
Face directly by water supply and sewage connecting hole of holding concurrently or is added plastic cement sealing gasket and is indirectly connected in series with bolt or hollow tube bolt, with
Time lateral isolation bar bottom cistern hold concurrently pipelined channel through become combination isolated column, except adjacent horizontal stroke in described combination isolated column
It is symmetrical structure to the part being connected with each other between the adjacent bearing of part any two and lateral isolation bar of spacer bar.
This combination isolated column makes the lateral isolation bar of isolated column itself not only have isolation features but also has within it
Directly planting plants or the greening function of laying flowerpot, and it is different only to need replacing time or lateral isolation bar just can meet
Insulation request and greening aesthetic, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installs and dismount
Convenient, with low cost, before and after the profile of bearing and lateral isolation bar is all and bilateral symmetry, it is ensured that bearing is only by vertically
Pressure and there is no turning torque, be i.e. the center of gravity stable and safeguard construction on the plane of symmetry, cistern is held concurrently pipelined channel and supply and discharge
Water hold concurrently connecting hole define through whole combination isolated column water supply and sewage pouring management maintenance system, vertically symmetrical of through hole with
The deviation of vertically symmetrical of bearing is effectively protected the safety of a wherein side in 6 centimetres, the whole appearance of lateral isolation bar
Any one section of face is enclosed in the interior and built on stilts splicing of through hole of bearing, and its bearing can on the whole outer surface of lateral isolation bar arbitrarily
Splicing and slip can the most effectively adjust span and adapt to the rugged installation requirement of Different Ground, is spliced into entirety
In combination isolated column part between adjacent bearing and the lateral isolation bar of any two be all support force on two bearings and
Symmetrical rock-steady structure part ensure that overall security and the stability of isolated column.
Combination isolated column, before including bearing and lateral isolation bar, described bearing and lateral isolation bar appearance profile being all
Afterwards and bilateral symmetry, described lateral isolation bar top is plantation space, and bottom is that cistern is held concurrently pipelined channel, laterally every
Two from bar symmetrical outer faces have position corresponding for splicing and the straight pipe of flowing water, bearing has by a side to another
Having for splicing and the clear opening that supports or end face to recessed groove of individual side, for splicing and the clear opening that supports or top
Towards vertically symmetrical of recessed groove is parallel with vertically symmetrical of bearing and distance is in 6 centimetres, lateral isolation bar two
End only need to be inserted directly into or embed left and right bearing for splicing and supporting for the straight pipe of splicing and flowing water along horizontal direction
Clear opening or end face to recessed groove splicing, the empty structure division between two bearings of its lateral isolation bridge is symmetrical
Structure, bearing and lateral isolation bar replace series connection the most continuously and are spliced into combination isolated column, then with bolt or hollow tube bolt
For the straight pipe of splicing and flowing water, two adjacent, left and right is horizontal through two, the left and right on same bearing lateral isolation bar
Spacer bar and bearing three connect fixing, and the cistern of adjacent transverse spacer bar holds concurrently pipelined channel by for splicing and flowing simultaneously
The straight pipe of water is through, and the structure division between two bearings and the lateral isolation bar of described combination isolated column is symmetrical junction
Structure, it provides the benefit that makes the lateral isolation bar of isolated column itself not only have isolation features but also has and the most directly plant
Plant or the greening function of laying flowerpot, and only to need replacing time 1 or lateral isolation bar just can meet different simultaneously
Insulation request and greening aesthetic, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installs and dismount
Convenient, with low cost, before and after the profile of bearing and lateral isolation bar is all and bilateral symmetry, it is ensured that bearing is only by vertically
Pressure and there is no turning torque, be i.e. the center of gravity stable and safeguard construction on the plane of symmetry, cistern hold concurrently pipelined channel and for
Splicing and the straight pipe of flowing water define the water supply and sewage pouring management maintenance system of through whole combination isolated column, through hole vertical
The plane of symmetry deviation with vertically symmetrical of bearing is effectively protected the safety of a wherein side in 6 centimetres, is spliced into entirety
In combination isolated column part between adjacent bearing and the lateral isolation bar of any two be all support force on two bearings and
Symmetrical rock-steady structure part ensure that overall security and the stability of isolated column.
Combination isolated column, before including bearing and lateral isolation bar, described bearing and lateral isolation bar appearance profile being all
Afterwards and bilateral symmetry, described lateral isolation bar top is plantation space, and bottom is that cistern is held concurrently pipelined channel, laterally every
The water supply and sewage having position corresponding on the end face of bar left and right is held concurrently connecting hole, bearing have by a side to another side have for
Splicing and the clear opening supported, parallel with vertically symmetrical of bearing for splicing and vertically symmetrical of clear opening that support and
Distance in 6 centimetres, lateral isolation bar by bolt or hollow tube bolt through bearing for splicing and the clear opening that supports and
Lateral isolation bar hold concurrently for water supply and sewage that connecting hole is built on stilts is fastened on two bearings, its lateral isolation bridge is empty at two
Structure division between bearing is symmetrical structure, and the cistern of two the lateral isolation bars in bearing left and right side is held concurrently pipelined channel simultaneously
Through by water supply and sewage connecting hole of holding concurrently, bearing and lateral isolation bar replace series connection the most continuously and are spliced into combination isolated column, institute
Structure division between combination isolated column any two bearing and the lateral isolation bar stated is symmetrical structure, and it provides the benefit that makes
The lateral isolation bar of isolated column itself not only has isolation features but also has within it direct planting plants or laying flowerpot
Greening function, and only need replacing time or lateral isolation bar just can meet simultaneously different insulation requests and greening attractive in appearance
Requirement, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, bearing
Before and after with the profile of lateral isolation bar being all and bilateral symmetry, it is ensured that bearing is not only had tilting force by vertical pressure
Square, is i.e. the center of gravity stable and safeguard construction on the plane of symmetry, and pipelined channel held concurrently by cistern and water supply and sewage is held concurrently, and connecting hole defines
The water supply and sewage pouring management maintenance system of through whole combination isolated column, is used for vertically symmetrical of the clear opening splicing and supporting
Deviation with vertically symmetrical of bearing is effectively protected the safety of a wherein side in 6 centimetres, be spliced into the combination of entirety every
Part between any two is adjacent in hurdle bearing and lateral isolation bar is all that on two bearings and symmetry is steady for support force
Fixed structure part ensure that overall security and the stability of isolated column.
As the optimization to technique scheme, described bearing at least splices the lateral isolation having two-layer consistency from top to bottom
Bar, and have penetrating plant growth space before and after making the lateral isolation bar of bearing and two-layer consistency from top to bottom, it provides the benefit that
Form more preferable landscape effect and beneficially plant growth.
As the optimization to technique scheme, the end face of described bearing and bottom surface there is the splicing knot being mutually matched
Structure, bearing 1 is connected in series up and down by the splicing construction being mutually matched, and splicing between the same layer of the bearing being connected in series up and down has
Lateral isolation bar, its lateral isolation bar providing the benefit that standardized production and bearing just can realize being desirably combined into respectively
Plant size and the combination isolated column of height.
As the optimization to technique scheme, hold concurrently between connecting hole or use in described adjacent transverse spacer bar supply and discharge water hole
Connect between splicing and the straight pipe of flowing water and have sealing gasket, described supply and discharge water hole to hold concurrently the straight-through of connecting hole or splicing and flowing water
Space between pipe and bolt is pipelined channel, and it provides the benefit that make connection and the pipelined channel of creativeness merge.
As the optimization to technique scheme, planting groove or cistern are arranged at the top of described bearing, its beneficial effect
It is to make full use of the space that bearing takies to become a part for planting plants.
Combination isolated column, including bearing and lateral isolation railing, described bearing and lateral isolation bar appearance profile be all
Front and back and bilateral symmetry, described bearing is hexahedron or cylinder, and described lateral isolation bar top is plantation space,
Bottom is that cistern is held concurrently pipelined channel, and the water supply and sewage that lateral isolation bar left and right end face has position corresponding is held concurrently connecting hole or for spelling
Connect the straight pipe with flowing water, any one section of horizontal top surface at least one bearing of the outer surface of lateral isolation bar or concave
On end face, arbitrarily mobile and splicing is at an arbitrary position, and water supply and sewage is held concurrently connecting hole or straight pipe the most right for splicing and flowing water
Title face is parallel with vertically symmetrical of bearing and distance is in 6 centimetres, and splicing lateral isolation bar at an arbitrary position is by auxiliary even
Fitting or bonding agent are connected with bearing, and connection assist is bolt or inverted U-shaped component, and adjacent transverse spacer bar passes through supply and discharge
Water holds concurrently connecting hole or the straight pipe for splicing and flowing water directly or adds plastic cement sealing gasket indirectly with bolt or hollow tube bolt
Being serially connected in combination isolated column, the cistern of adjacent transverse spacer bar bottom holds concurrently pipelined channel by the double connection of water supply and sewage simultaneously
Hole or through for splicing and the straight pipe of flowing water, bearing that in described combination isolated column, any two is adjacent and laterally every
Being symmetrical structure in addition to the coupling part of adjacent transverse spacer bar between bar, it provides the benefit that the lateral isolation making isolated column
Bar itself not only has isolation features but also has within it direct planting plants or the greening function of laying flowerpot, and only
Needing replacing time or lateral isolation bar just can meet different insulation requests and greening aesthetic, this is prior art simultaneously
The function not having, is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, outside bearing and lateral isolation bar
Before and after shape is all and bilateral symmetry, it is ensured that bearing is not only had turning torque by vertical pressure, is i.e. that center of gravity is in symmetry
Stable and safeguard construction on face, pipelined channel held concurrently by cistern and water supply and sewage is held concurrently connecting hole or for splicing and the straight pipe of flowing water
Defining the water supply and sewage pouring management maintenance system of through whole combination isolated column, water supply and sewage is held concurrently connecting hole or for splicing and flowing
Vertically symmetrical of the straight pipe of water deviation with vertically symmetrical of bearing centimetre in be effectively protected the peace of a wherein side
Entirely, the part being spliced between bearing and the lateral isolation bar that in the combination isolated column of entirety, any two is adjacent is all support force
On two bearings and symmetrical rock-steady structure part ensure that overall security and the stability of isolated column.
Combination isolated column, before including bearing and lateral isolation bar, described bearing and lateral isolation bar appearance profile being all
Afterwards and bilateral symmetry, described bearing is hexahedron or cylinder, and described lateral isolation bar is to separately from an end face
The continuous groove of end face, continuous groove top is plantation space, and bottom is that cistern is held concurrently pipelined channel, outside lateral isolation bar
Arbitrarily move in any one section of horizontal top surface at least one bearing on surface or concave end face and splice at an arbitrary position,
Vertically symmetrical of lateral isolation bar parallel with vertically symmetrical of bearing and distance is in 6 centimetres, and splicing is at an arbitrary position
Lateral isolation bar connection assist or bonding agent are connected with bearing, and connection assist is bolt or inverted U-shaped component, two
Adjacent lateral isolation bar partly overlaps or alignment bolt or bonding agent are connected in series, and combination isolated column is laterally connected in series
Lateral isolation bar in connect and vertically cut off, except vertically cutting off and two adjacent lateral isolation bars in described combination isolated column
The structure division connected between the adjacent bearing of outer any two and lateral isolation bar is symmetrical structure, its provide the benefit that make every
Lateral isolation bar from hurdle itself not only has isolation features but also has within it directly planting plants or laying flowerpot
Greening function, and only need replacing time or lateral isolation bar just can meet different insulation requests simultaneously and afforest attractive in appearance wanting
Asking, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, bearing and
Before and after the profile of lateral isolation bar is all and bilateral symmetry, it is ensured that bearing is not only had turning torque by vertical pressure,
Being i.e. the center of gravity stable and safeguard construction on the plane of symmetry, cistern is held concurrently the water supply and sewage of the through whole combination isolated column of pipelined channel
Pouring management maintenance system, vertically symmetrical of the lateral isolation bar deviation with vertically symmetrical of bearing is effective in 6 centimetres
The safety of a protection wherein side, be spliced into bearing that in the combination isolated column of entirety, any two is adjacent and lateral isolation bar it
Between part be all that on two bearings and symmetrical rock-steady structure part ensure that the overall security of isolated column and steady to support force
Qualitative.
As the optimization to technique scheme, the top and bottom of described lateral isolation bar have mutual with the top and bottom of bearing
The attachment structure of coupling, the top of described bearing has cistern, bearing and lateral isolation bar to be serially connected in alternatively up and down
The combination isolated column of multilayer lateral isolation bar.
As the optimization to technique scheme, described bearing and lateral isolation bar material be metal, plastics, plastic-steel,
Fiberglass or armored concrete, described bearing is V with the horizontal 0 °~90 ° installation, the cross section of described lateral isolation bar
Shape, U-shaped, on have opening rectangle, on have trapezoidal, circular arc or the polygon of opening, described cistern is held concurrently in pipelined channel 3
Being provided with water-stop sheet, it provides the benefit that water soaking part planting medium, makes medium quickly absorb moisture and provides nutrient to plant
Meet demand of plant growth and the pouring efficiency of management is provided.
As the optimization to technique scheme, described lateral isolation bar wall has discharge water hole, discharge water hole it
Between connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
As the optimization to technique scheme, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
As the optimization to technique scheme, the top edge of described lateral isolation bar has level outwardly or inwardly to turn over
Limit or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar, and in-flanges makes it reduce
The moisture disengagement area in plantation space and the intensity of lateral isolation bar.
The lateral isolation bar of the combination isolated column of the present invention itself not only has isolation features but also has the most straight
Connect the function of planting plants or laying flowerpot, only need replacing time or lateral isolation bar just can meet different isolation simultaneously and want
Summation greening aesthetic, bearing is not only had turning torque by vertical pressure, is i.e. the center of gravity stable peace on the plane of symmetry
Full structure, and it is spliced into the part support between bearing and the lateral isolation bar that in the combination isolated column of entirety, any two is adjacent
Power is on two adjacent bearings and is symmetrical rock-steady structure, its simple in construction, easy to loading and unloading, with low cost, lateral isolation
The water supply and sewage irrigation pipe of the attachment structure self-assembling formation through whole combination isolated column greening between bar bottom and lateral isolation bar
Reason maintenance system, it is achieved thereby that the present invention.
The present invention has the advantage that 1. make the lateral isolation bar of combination isolated column itself not only compared with prior art
There is isolation features but also there is within it direct planting plants or the greening function of laying flowerpot;2. can be according to different peaces
Dress condition arbitrarily regulates bearing and installs stitching position or the combination isolated column of span with lateral isolation bar, and combination isolated column is center of gravity
Stable and the structure of safety on the plane of symmetry, its simple in construction, installation and easy accessibility, with low cost, have pouring management dimension
Protecting system, afforestation effect are good;3. can completely industrial flow-line large-scale production bearing and lateral isolation bar, and produce, storage and
The low costs such as transport;4. change any one physical dimension or position in lateral isolation bar and bearing and can change beautification of landscape
Effect, it is possible to reach different use requirements;5. the combination water storage structure of isolated column self-assembling formation, pipelined channel and spilling water
Structure meets the growth requirement of plant;6. take up an area little, green coverage is big, any moulding, release oxygen, absorbing carbon dioxide,
Heat energy, noise, dust, light pollution, does not runs off in can being placed on container because of soil, thus afforestation effect is the best, beautifies
Environment.
Accompanying drawing explanation
Fig. 1 is the schematic perspective view of the lateral isolation bar of a kind of version of the embodiment of the present invention 1.
Fig. 2 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 1.
Fig. 3 is the bearing schematic perspective view of the another kind of version of the embodiment of the present invention 1.
Fig. 4 is the schematic perspective view of the combination isolated column of a kind of combination of the embodiment of the present invention 1.
Fig. 5 is the schematic perspective view of the combination isolated column of the another kind of combination of the embodiment of the present invention 1.
Fig. 6 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 2.
Fig. 7 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 2.
Fig. 8 is the schematic perspective view of the combination isolated column of a kind of combination of the embodiment of the present invention 2.
Fig. 9 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 2.
Figure 10 is the bearing schematic perspective view of the another kind of version of the embodiment of the present invention 2.
Figure 11 is the schematic perspective view of the combination isolated column of the another kind of combination of the embodiment of the present invention 2.
Figure 12 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 2.
Figure 13 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 2.
Figure 14 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 2.
Figure 15 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 16 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 17 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 3.
Figure 18 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 19 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 20 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 3.
Figure 21 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 22 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 3.
Figure 23 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 24 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 3.
Figure 25 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 3.
Figure 26 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 4.
Figure 27 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 4.
Figure 28 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 4.
Figure 29 is the bearing schematic perspective view of a kind of version of the embodiment of the present invention 5.
Figure 30 is the lateral isolation bar schematic perspective view of a kind of version of the embodiment of the present invention 5.
Figure 31 is the schematic perspective view of the combination isolated column of another combination of the embodiment of the present invention 5.
In figure, the parts corresponding to reference are entitled: 1 bearing, 2 lateral isolation bars, 3 cisterns are held concurrently and flowed
Aquaporin, 4 water supply and sewages hold concurrently connecting hole, 5 through holes, 6 for splicing and the straight pipe of flowing water, 7 for splicing and supporting
Clear opening, 8 planting grooves, 9 cisterns, 10 vertically partition, 11 discharge water holes, 12 grooves.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing, the present invention is described in further detail, but embodiments of the present invention are not
It is limited to this.
Embodiment 1: as shown in Figure 1, Figure 2, Fig. 4, as the combination isolated column of a kind of embodiment 1 of this example, including bearing 1 He
Lateral isolation bar 2, it is characterised in that: described bearing 1 and lateral isolation bar 2 appearance profile be all before and after and symmetrical knot
Structure, described lateral isolation bar 2 top is plantation space, and bottom is that cistern is held concurrently pipelined channel 3, and lateral isolation bar about 2 is held
The water supply and sewage having position corresponding on face is held concurrently connecting hole 4, and bearing 1 has by the through hole 5 of a side to another side, through hole 5
Vertically symmetrical parallel with vertically symmetrical of bearing 1 and distance is in 6 centimetres, the whole appearance of described lateral isolation bar 2
Any one section of face is enclosed in the interior and built on stilts splicing of through hole 5 of bearing 1, and its bearing 1 can be on the whole outer surface of lateral isolation bar 2
Arbitrarily splicing and mobile, the end face of adjacent transverse spacer bar 2 is direct or add plastic cement sealing gasket by water supply and sewage connecting hole 4 of holding concurrently
Indirectly being connected in series with bolt or hollow tube bolt, the cistern of lateral isolation bar 2 bottom is held concurrently the through one-tenth of pipelined channel 3 simultaneously
Combination isolated column, that removes adjacent transverse spacer bar 2 in described combination isolated column is connected with each other adjacent the propping up of part any two
Part between seat 1 and lateral isolation bar 2 is symmetrical structure, and it provides the benefit that makes the lateral isolation bar 2 of isolated column itself not
But there is isolation features but also there is within it direct planting plants or the greening function of laying flowerpot, and only need to change and prop up
Seat 1 or lateral isolation bar 2 just can meet different insulation requests and greening aesthetic, and this is the merit that prior art does not has
Can, it is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, before the profile of bearing 1 and lateral isolation bar 2 is all
Afterwards and bilateral symmetry, it is ensured that bearing is not only had turning torque by vertical pressure, it is i.e. steady on the plane of symmetry of center of gravity
Fixed and safeguard construction, the supply and discharge of pipelined channel 3 held concurrently by cistern and water supply and sewage is held concurrently connecting hole 4 defines through whole combination isolated column
Water pouring management maintenance system, vertically symmetrical of through hole 5 deviation with vertically symmetrical of bearing 1 is effective in 6 centimetres
The safety of a protection wherein side, in any one section of the whole outer surface of lateral isolation bar 2 is enclosed in the through hole 5 of bearing 1 and make somebody a mere figurehead
Splicing, its bearing 1 can arbitrarily splice and slide on the whole outer surface of lateral isolation bar 2 and can the most effectively adjust span
With the adaptation rugged installation requirement of Different Ground, it is spliced into the bearing 1 that in the combination isolated column of entirety, any two is adjacent
With the part between lateral isolation bar 2 is all that on two bearings 1 and symmetrical rock-steady structure part ensure that isolated column to support force
Overall security and stability.
Optimization to technique scheme, planting groove 8 or cistern 9 are arranged at the top of described bearing 1, and it provides the benefit that
Make full use of the space that bearing 1 takies and become a part for planting plants.
Such as Fig. 1, Fig. 3, Fig. 5, as the another embodiment of this example, this embodiment is essentially identical with embodiment 1,
The different end faces at described bearing 1 have, on bottom surface, the splicing construction being mutually matched, and bearing 1 is tied by the splicing being mutually matched
Structure is connected in series up and down, and between the same layer of the bearing 1 being connected in series up and down, splicing has lateral isolation bar 2, and it provides the benefit that mark
Lateral isolation bar 2 and bearing 1 that quasi-metaplasia is produced just can realize being desirably combined into the combination isolation of all size and height
Hurdle.
As the optimization to technique scheme, described bearing 1 splicing has the lateral isolation bar 2 of two-layer consistency from top to bottom,
And plant growth space penetrating before and after making the lateral isolation bar 2 of bearing 1 and two-layer consistency from top to bottom, it provides the benefit that formation
Preferably landscape effect and beneficially plant growth.
As the optimization to above two embodiment, hold concurrently connecting hole 4 in described adjacent transverse spacer bar 2 supply and discharge water hole
Between connect have sealing gasket, described supply and discharge water hole hold concurrently connecting hole 4 or splicing with straight pipe 6 and the bolt of flowing water between space
For pipelined channel, it provides the benefit that make connection and the pipelined channel of creativeness merge.
Optimization to above two embodiment, described bearing 1 and lateral isolation bar 2 material are metal, plastics, mould
Steel, fiberglass or armored concrete, described bearing 1 is upper with the horizontal 0 °~90 ° installation, the cross section of lateral isolation bar 2
Having the rectangle of opening, described cistern to hold concurrently in pipelined channel 3 and be provided with water-stop sheet, it provides the benefit that water soaking part is planted
Medium, making medium quickly absorb moisture provides nutrient meet demand of plant growth and provide the pouring efficiency of management to plant.
Optimization to above two embodiment, described lateral isolation bar 2 wall has discharge water hole 11, discharge water hole
Between 11 connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
Optimization to above two embodiment, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
Optimization to above two embodiment, the top edge of described lateral isolation bar 2 has level outwardly or inwardly
Flange or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar 2, and in-flanges makes it subtract
Moisture disengagement area and the intensity of lateral isolation bar 2 in plantation space are lacked.
Embodiment 2: such as Fig. 6, Fig. 7, Fig. 8, as the combination isolated column of a kind of embodiment 1 of this example, including bearing 1 He
Lateral isolation bar 2, it is characterised in that: described bearing 1 and lateral isolation bar 2 appearance profile be all before and after and symmetrical knot
Structure, described lateral isolation bar 2 top is plantation space, and bottom is that cistern is held concurrently pipelined channel 3, and 2 two, lateral isolation bar is right
There is the straight pipe 6 for splicing with flowing water that position is corresponding the outer face claimed, and bearing 1 has by a side to another side
Have for splicing and the clear opening 7 that supports and end face to recessed groove 12, for splicing and the clear opening 7 that supports or end face to
Vertically symmetrical of recessed groove 12 parallel with vertically symmetrical of bearing 1 and distance is in 6 centimetres, upper and lower lateral isolation bar
2 two ends only need to be inserted left and right bearing 1 the most respectively for splicing and the straight pipe 6 of flowing water and are used for splicing and propping up along horizontal direction
The prone groove 12 of clear opening 7 and top of support splices, and the structure division between two bearings 1 maked somebody a mere figurehead by its lateral isolation bar 2
Being symmetrical structure, bearing 1 and lateral isolation bar 2 replace series connection the most continuously and are spliced into combination isolated column, then with bolt or in
Blank pipe bolt is used for the straight pipe 6 of splicing and flowing water by an adjacent left side through two, the left and right lateral isolation bar 2 on same bearing 1
Right two lateral isolation bars 2 and bearing 1 three connect fixing, and the cistern of adjacent transverse spacer bar 2 pipelined channel 3 of holding concurrently leads to simultaneously
Cross the straight pipe 6 for splicing and flowing water through, between two bearings 1 and the lateral isolation bar 2 of described combination isolated column
Structure division is symmetrical structure, its provide the benefit that make the lateral isolation bar 2 of isolated column itself not only have isolation features but also
Also there is within it direct planting plants or the greening function of laying flowerpot, and just only need replacing time 1 or lateral isolation bar 2
Can meet different insulation requests and greening aesthetic, this is the function that prior art does not has, and is simultaneously achieved simultaneously
Simple in construction, installation and easy accessibility, with low cost, before and after the profile of bearing 1 and lateral isolation bar is all and symmetrical knot
Structure, it is ensured that bearing 1 is not only had turning torque by vertical pressure, is i.e. the center of gravity stable and safeguard construction on the plane of symmetry,
Cistern is held concurrently pipelined channel 3 and define the water supply and sewage of through whole combination isolated column for splicing and the straight pipe 6 of flowing water and water
Filling management maintenance system, vertically symmetrical of through hole 5 deviation with vertically symmetrical of bearing 1 is effectively protected in 6 centimetres
The wherein safety of a side, is spliced between bearing 1 and the lateral isolation bar 2 that in the combination isolated column of entirety, any two is adjacent
Part is all that on two bearings 1 and symmetrical rock-steady structure part ensure that the overall security of isolated column and stablizes support force
Property.
As the optimization to technique scheme, described bearing 1 splicing has the lateral isolation bar 2 of two-layer consistency from top to bottom,
And having penetrating plant growth space before and after making the lateral isolation bar 2 of bearing 1 and two-layer consistency from top to bottom, it provides the benefit that shape
Become more preferable landscape effect and beneficially plant growth.
As the optimization to technique scheme, the end face of described bearing 1 and bottom surface can there is the spelling being mutually matched
Access node structure, bearing 1 is connected in series, between the same layer of the bearing 1 being connected in series up and down up and down by the splicing construction being mutually matched
Splicing has lateral isolation bar 2, and it provides the benefit that the lateral isolation bar 2 of standardized production and bearing 1 just can realize according to need
All size to be combined into and the combination isolated column of height.
As the optimization to technique scheme, straight for splicing and flowing water between described adjacent transverse spacer bar 2
Connecting between siphunculus 6 and have sealing gasket, the space between straight pipe 6 and the bolt of described splicing and flowing water is pipelined channel, its
Provide the benefit that make connection and the pipelined channel of creativeness merge.
Such as Fig. 9, Figure 10, Figure 11, as the another embodiment of this example, this embodiment phase basic with embodiment 1
With, the different straight pipes 6 being used for splicing and flowing water at described lateral isolation bar 2 two ends only need to be directly embedded into along horizontal direction
Left and right bearing 1 is splicing in the clear opening 7 of splicing and support.
Such as Figure 12, Figure 13, Figure 14, as another embodiment of this example, this embodiment phase basic with embodiment 1
With, different have planting groove 8 or cistern 9 on the top of described bearing 1, and it provides the benefit that and makes full use of what bearing 1 took
Space becomes a part for planting plants.
Optimization to above-mentioned three kinds of embodiments, described bearing 1 and lateral isolation bar 2 material are metal, plastics, mould
Steel, fiberglass or armored concrete, bearing 1 with the horizontal 90 ° of installations, the cross section of described lateral isolation bar 2 on have out
Mouthful rectangle, described cistern holds concurrently and is provided with water-stop sheet in pipelined channel 3, and it provides the benefit that is having water section to soak plantation
Medium, making medium quickly absorb moisture provides nutrient meet demand of plant growth and provide the pouring efficiency of management to plant.
Optimization to above-mentioned three kinds of embodiments, described lateral isolation bar 2 wall has discharge water hole 11, discharge water hole
Between 11 connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
Optimization to above-mentioned three kinds of embodiments, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
Optimization to above-mentioned three kinds of embodiments, the top edge of described lateral isolation bar 2 has level outwardly or inwardly
Flange or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar 2, and in-flanges makes it subtract
Moisture disengagement area and the intensity of lateral isolation bar 2 in plantation space are lacked.
Embodiment 3: such as Figure 15, Figure 16, Figure 17, as the combination isolated column of a kind of embodiment 1 of this example, including bearing
1 and lateral isolation bar 2, it is characterised in that: before and after described bearing 1 and lateral isolation bar 2 appearance profile are all and symmetrical
Structure, described lateral isolation bar 2 top is plantation space, and bottom is that cistern is held concurrently pipelined channel 3, lateral isolation bar about 2
The water supply and sewage having position corresponding on end face is held concurrently connecting hole 4, bearing 1 have by a side to another side have for splicing and
The clear opening 7 supported, parallel with vertically symmetrical of bearing 1 for splicing and vertically symmetrical of clear opening 7 that support and away from
From in 6 centimetres, lateral isolation bar 2 is used for splicing and clear opening 7 He supported by bolt or hollow tube bolt through bearing 1
Lateral isolation bar 2 hold concurrently for water supply and sewage that connecting hole 4 is built on stilts is fastened on two bearings 1, its lateral isolation bar 2 is maked somebody a mere figurehead
Structure division between two bearings 1 is symmetrical structure, and the cistern of two the lateral isolation bars 2 in bearing 1 left and right side is held concurrently simultaneously
Pipelined channel 3 is through by water supply and sewage connecting hole 4 of holding concurrently, and the most alternately series connection splicing is in groups for bearing 1 and lateral isolation bar 2
Closing isolated column, the described structure division between combination isolated column any two bearing 1 and lateral isolation bar 2 is symmetrical structure,
It provides the benefit that makes the lateral isolation bar 2 of isolated column itself not only have isolation features but also has and the most directly plant
Plant or the greening function of laying flowerpot, and only need replacing time 1 or lateral isolation bar 2 just can meet simultaneously different every
From requiring and afforesting aesthetic, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installs and the side of dismounting
Just, with low cost, before and after the profile of bearing 1 and lateral isolation bar 2 is all and bilateral symmetry, it is ensured that bearing 1 is by perpendicular
Vertical compression power and there is no turning torque, be i.e. the center of gravity stable and safeguard construction on the plane of symmetry, cistern is held concurrently pipelined channel 3 and supplying
Draining hold concurrently connecting hole 4 define through whole combination isolated column water supply and sewage pouring management maintenance system, be used for splicing and supporting
Vertically symmetrical the deviation with vertically symmetrical of bearing 1 of clear opening 7 in 6 centimetres, be effectively protected the peace of a wherein side
Entirely, being spliced into the part between bearing 1 and the lateral isolation bar 2 that in the combination isolated column of entirety, any two is adjacent is all to support
Power is on two bearings 1 and symmetrical rock-steady structure part ensure that overall security and the stability of isolated column.
As the optimization to technique scheme, the end face of described bearing 1 and bottom surface there is the splicing knot being mutually matched
Structure, bearing 1 is connected in series up and down by the splicing construction being mutually matched, and splices between the same layer of the bearing 1 being connected in series up and down
Having lateral isolation bar 2, its lateral isolation bar 2 providing the benefit that standardized production and bearing 1 just can realize group as required
Synthesis all size and the combination isolated column of height.
As the optimization to technique scheme, hold concurrently between connecting hole 4 in described adjacent transverse spacer bar 2 supply and discharge water hole
Connecting that to have sealing gasket, the described supply and discharge water hole space between connecting hole 4 and bolt of holding concurrently be pipelined channel, it provides the benefit that wound
Make connection and the pipelined channel of the property made merge.
It is metal, plastics as the optimization to technique scheme, described bearing 1 and lateral isolation bar 2 material, moulds
Steel, fiberglass or armored concrete, described bearing 1 is with the horizontal 0 °~90 ° installation, cutting of described lateral isolation bar 2
Face has the rectangle of opening, described cistern to hold concurrently in pipelined channel 3 to be provided with water-stop sheet on being, it provides the benefit that water soaking portion
Dividing planting medium, making medium quickly absorb moisture provides nutrient meet demand of plant growth and provide pouring to manage effect to plant
Rate.
As the optimization to technique scheme, described lateral isolation bar 2 wall there are discharge water hole 11, discharge water hole
Between 11 connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
As the optimization to technique scheme, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
As the optimization to technique scheme, the top edge of described lateral isolation bar 2 has level outwardly or inwardly
Flange or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar 2, and in-flanges makes it subtract
Moisture disengagement area and the intensity of lateral isolation bar 2 in plantation space are lacked.
Such as Figure 18, Figure 19, Figure 20, as the another embodiment of this example, this embodiment phase basic with embodiment 1
With, different is the T-shaped structure stood upside down at bearing 1.
Such as Figure 19, Figure 21, Figure 22, as another embodiment of this example, this embodiment phase basic with embodiment 1
With, the different end faces at described bearing 1 have, on bottom surface, the splicing construction being mutually matched, and bearing 1 is by the spelling being mutually matched
Access node structure is connected in series up and down, and between the same layer of the bearing 1 being connected in series up and down, splicing has lateral isolation bar 2, its beneficial effect
It is the lateral isolation bar 2 of standardized production and bearing 1 just can realize being desirably combined into all size and the combination of height
Isolated column.
Embodiment 4: such as Figure 23, Figure 24, Figure 25, as the combination isolated column of an embodiment 1 of this example, including bearing 1
With lateral isolation railing 2, it is characterised in that: described bearing 1 and lateral isolation bar 2 appearance profile be all before and after and symmetrical
Structure, described bearing 1 is hexahedron, described lateral isolation bar 2 top be plantation space, bottom be cistern hold concurrently flowing water lead to
Road 3, lateral isolation bar about 2 end face has the straight pipe 6 for splicing with flowing water that position is corresponding, outside lateral isolation bar 2
Any one section of surface arbitrarily moves in the horizontal top surface of two bearings 1 and splices at an arbitrary position, for splicing and flowing water
Vertically symmetrical of straight pipe 6 parallel with vertically symmetrical of bearing 1 and distance is in 6 centimetres, splicing is at an arbitrary position
Lateral isolation bar 2 connection assist or bonding agent are connected with bearing 1, and connection assist is bolt or inverted U-shaped component, phase
Adjacent lateral isolation bar 2 by for the square straight pipe 6 of splicing and flowing water directly or add plastic cement sealing gasket indirectly with bolt or
Hollow tube bolt is serially connected in combination isolated column, and the cistern of adjacent transverse spacer bar 2 bottom pipelined channel 3 of holding concurrently passes through simultaneously
The square straight pipe 6 for splicing and flowing water is through, and described combines the bearing 1 and horizontal stroke that in isolated column, any two is adjacent
Being symmetrical structure in addition to the coupling part of adjacent transverse spacer bar 2 between spacer bar 2, it provides the benefit that the horizontal stroke making isolated column
Not only there is isolation features to spacer bar 2 itself but also there is within it direct planting plants or the greening merit of laying flowerpot
Can, and only need replacing time 1 or lateral isolation bar 2 just can meet different insulation requests and greening aesthetic simultaneously,
This is the function that prior art does not has, and is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, bearing 1 and horizontal stroke
Before and after the profile of spacer bar 2 is all and bilateral symmetry, it is ensured that bearing 1 is not only had turning torque by vertical pressure,
Being i.e. the center of gravity stable and safeguard construction on the plane of symmetry, cistern is held concurrently pipelined channel 3 and for splicing and the straight pipe 6 of flowing water
Define the water supply and sewage pouring management maintenance system of through whole combination isolated column, be used for the perpendicular of the splicing straight pipe 6 with flowing water
The straight plane of symmetry deviation with vertically symmetrical of bearing 1 is effectively protected the safety of a wherein side in 6 centimetres, is spliced into entirety
Combination isolated column in part between adjacent bearing 1 and the lateral isolation bar 2 of any two be all that support force is at two bearings 1
Upper and symmetrical rock-steady structure part ensure that overall security and the stability of isolated column.
Such as Figure 26, Figure 27, Figure 28, as the another embodiment of this example, this embodiment phase basic with embodiment 1
With, the different straight pipes 6 for splicing and flowing water having position corresponding on lateral isolation bar about 2 end face change water supply and sewage into and hold concurrently
Connecting hole 4.
As the optimization to technique scheme, there is the top and bottom phase with bearing 1 top and bottom of described lateral isolation bar 2
The attachment structure of coupling mutually, cistern 9, bearing 1 and lateral isolation bar 2 company of series connection alternatively up and down are arranged at the top of described bearing 1
It is connected into the combination isolated column of multilayer lateral isolation bar 2.
Optimization to above two embodiment, described bearing 1 and lateral isolation bar 2 material are metal, plastics, mould
Steel, fiberglass or armored concrete, described bearing 1 is with the horizontal 0 °~90 ° installation, cutting of described lateral isolation bar 2
Face has the rectangle of opening, described cistern to hold concurrently in pipelined channel 3 to be provided with water-stop sheet on being, it provides the benefit that water soaking portion
Dividing planting medium, making medium quickly absorb moisture provides nutrient meet demand of plant growth and provide pouring to manage effect to plant
Rate.
Optimization to above two embodiment, described lateral isolation bar 2 wall has discharge water hole 11, discharge water hole
Between 11 connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
Optimization to above two embodiment, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
Optimization to above two embodiment, the top edge of described lateral isolation bar 2 has level outwardly or inwardly
Flange or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar 2, and in-flanges makes it subtract
Moisture disengagement area and the intensity of lateral isolation bar 2 in plantation space are lacked.
Embodiment 5: such as Figure 29, Figure 30, Figure 31, as the combination isolated column of a kind of embodiment of this example, including bearing 1
With lateral isolation bar 2, it is characterised in that: described bearing 1 and lateral isolation bar 2 appearance profile be all before and after and symmetrical knot
Structure, described bearing 1 is hexahedron, and described lateral isolation bar 2 is the continuous groove from an end face to other end, continuously
Groove top is plantation space, and bottom is that cistern is held concurrently pipelined channel 3, and any one section of the outer surface of lateral isolation bar 2 two
Arbitrarily move in the horizontal top surface of individual bearing 1 and splice at an arbitrary position, vertically symmetrical of lateral isolation bar 2 and bearing 1
Vertically symmetrical parallel and distance is in 6 centimetres, splicing lateral isolation bar 2 connection assist or bonding agent at an arbitrary position
Being connected with bearing 1, connection assist is bolt or inverted U-shaped component, two adjacent lateral isolation bar 2 alignment bolts or
Bonding agent is connected in series, and connects to have and vertically cut off 10 in the lateral isolation bar 2 that combination isolated column is laterally connected in series, i.e. two ends
Connect with middle part and have vertical partition 10, described combination isolated column removes vertically partition 10 and two adjacent lateral isolation bars 2
The structure division connected between the adjacent bearing 1 of outer any two and lateral isolation bar 2 is symmetrical structure, and it provides the benefit that makes
The lateral isolation bar of isolated column itself not only has isolation features but also has within it direct planting plants or laying flowerpot
Greening function, and only need replacing time or lateral isolation bar just can meet simultaneously different insulation requests and greening attractive in appearance
Requirement, this is the function that prior art does not has, and is simultaneously achieved simple in construction, installation and easy accessibility, with low cost, bearing
1 and the profile of lateral isolation bar 1 be all before and after and bilateral symmetry, it is ensured that bearing is not only had tilting force by vertical pressure
Square, is i.e. the center of gravity stable and safeguard construction on the plane of symmetry, and the cistern through whole combination isolated column of pipelined channel 3 of holding concurrently is favourable
In pouring management, vertically symmetrical of lateral isolation bar 2 deviation with vertically symmetrical of bearing 1 is effectively protected in 6 centimetres
Protect the safety of a wherein side, be spliced between bearing 1 and the lateral isolation bar 2 that in the combination isolated column of entirety, any two is adjacent
Part be all that on two bearings 1 and symmetrical rock-steady structure part ensure that the overall security of isolated column and stable to support force
Property.
As the optimization to technique scheme, there is the top and bottom phase with bearing 1 top and bottom of described lateral isolation bar 2
The attachment structure of coupling mutually, cistern 9, bearing 1 and lateral isolation bar 2 company of series connection alternatively up and down are arranged at the top of described bearing 1
It is connected into the combination isolated column of multilayer lateral isolation bar 2.
It is metal, plastics as the optimization to technique scheme, described bearing 1 and lateral isolation bar 2 material, moulds
Steel, fiberglass or armored concrete, described bearing 1 is with the horizontal 0 °~90 ° installation, cutting of described lateral isolation bar 2
Face has the rectangle of opening, described cistern to hold concurrently in pipelined channel 3 to be provided with water-stop sheet on being, it provides the benefit that water soaking portion
Dividing planting medium, making medium quickly absorb moisture provides nutrient meet demand of plant growth and provide pouring to manage effect to plant
Rate.
As the optimization to technique scheme, described lateral isolation bar 2 wall there are discharge water hole 11, discharge water hole
Between 11 connected in series or in parallel with flexible pipe or hard tube, it provides the benefit that and realizes the most unified pouring management.
As the optimization to technique scheme, described bearing 1 part is embedded in concrete or is connected with solid
Being scheduled on xoncrete structure, it provides the benefit that and is applied to architecture greening.
As the optimization to technique scheme, the top edge of described lateral isolation bar 2 has level outwardly or inwardly
Flange or level add the most compound flange, and it provides the benefit that flanging strengthens the intensity of lateral isolation bar 2, and in-flanges makes it subtract
Moisture disengagement area and the intensity of lateral isolation bar 2 in plantation space are lacked.
As it has been described above, just can preferably realize the present invention.
Claims (12)
1. combination isolated column, including bearing (1) and lateral isolation bar (2), it is characterised in that: described bearing (1) and horizontal every
Before and after bar (2) appearance profile is all and bilateral symmetry, described lateral isolation bar (2) top is plantation space, bottom
Being that cistern is held concurrently pipelined channel (3), the water supply and sewage that lateral isolation bar (2) left and right end face has position corresponding is held concurrently connecting hole (4),
Seat (1) has by the through hole (5) of a side to another side, and vertically symmetrical of through hole (5) is vertically symmetrical with bearing (1)
Face is parallel and substantially overlapping, and any one section of the whole outer surface of described lateral isolation bar (2) is enclosed in the through hole of bearing (1)
(5) interior and built on stilts splicing, its bearing (1) arbitrarily can splice and mobile on the whole outer surface of lateral isolation bar (2), adjacent horizontal stroke
By water supply and sewage connecting hole (4) of holding concurrently to the end face of spacer bar (2) directly or add plastic cement sealing gasket and indirectly connect with bolt
Connecting, pipelined channel (3) of simultaneously being held concurrently by the cistern of lateral isolation bar (2) bottom is through to be become to combine isolated column, described combination
That removes adjacent transverse spacer bar (2) in isolated column is connected with each other the adjacent bearing of part any two (1) and lateral isolation bar (2)
Between part be symmetrical structure, described lateral isolation bar (2) wall has discharge water hole (11).
2. combination isolated column, including bearing (1) and lateral isolation bar (2), it is characterised in that: described bearing (1) and horizontal every
Before and after bar (2) appearance profile is all and bilateral symmetry, described lateral isolation bar (2) top is plantation space, bottom
That cistern is held concurrently pipelined channel (3), (2) two symmetrical outer faces of lateral isolation bar have position corresponding for splicing and flowing water
Straight pipe (6), bearing (1) have by a side to another side for splicing and support clear opening (7) or end face
To recessed groove (12), it is used for splicing and the clear opening (7) supported or end face to vertically symmetrical of recessed groove (12)
Parallel and substantially overlapping with vertically symmetrical of bearing (1), lateral isolation bar (2) two ends are for splicing and the straight pipe of flowing water
(6) only need to be inserted directly into along horizontal direction or embed left and right bearing (1) for splicing and the clear opening (7) that supports or end face to
Recessed groove (12) splicing, the structure division that its lateral isolation bar (2) is maked somebody a mere figurehead between two bearings (1) is symmetrical structure,
Bearing (1) and lateral isolation bar (2) replace series connection the most continuously and are spliced into combination isolated column, then with bolt through same bearing
(1) two, the left and right on lateral isolation bar (2) is for splicing the straight pipe (6) with flowing water by adjacent two, left and right lateral isolation
Bar (2) and bearing (1) three connect fixing, and the cistern of adjacent transverse spacer bar (2) holds concurrently pipelined channel (3) by being used for simultaneously
The straight pipe (6) of splicing and flowing water is through, between two bearings (1) and the lateral isolation bar (2) of described combination isolated column
Structure division is symmetrical structure, and described lateral isolation bar (2) wall has discharge water hole (11).
3. combination isolated column, including bearing (1) and lateral isolation bar (2), it is characterised in that: described bearing (1) and horizontal every
Before and after bar (2) appearance profile is all and bilateral symmetry, described lateral isolation bar (2) top is plantation space, bottom
Being that cistern is held concurrently pipelined channel (3), the water supply and sewage that lateral isolation bar (2) left and right end face has position corresponding is held concurrently connecting hole (4),
Seat (1) have by a side to another side for splicing and support clear opening (7), for splicing and support lead directly to
Vertically symmetrical of hole (7) is parallel and substantially overlapping with vertically symmetrical of bearing (1), and lateral isolation bar (2) is worn by bolt
Cross built on stilts for water supply and sewage connecting hole (4) of holding concurrently for splicing and the clear opening (7) that supports and lateral isolation bar (2) of bearing (1)
Being fastened on two bearings (1), the structure division between two bearings (1) maked somebody a mere figurehead by its lateral isolation bar (2) is symmetrical
Structure, the cistern of two the lateral isolation bars (2) in bearing (1) left and right side holds concurrently pipelined channel (3) by the double company of water supply and sewage simultaneously
Connecing hole (4) through, bearing (1) and lateral isolation bar (2) replace series connection the most continuously and are spliced into combination isolated column, described group
The structure division closed between isolated column any two bearing (1) and lateral isolation bar (2) is symmetrical structure, described lateral isolation
Discharge water hole (11) is had on bar (2) wall.
4. according to the combination isolated column one of claims 1 to 3 Suo Shu, it is characterised in that: described bearing (1) at least splices to be had
The lateral isolation bar (2) of two-layer consistency from top to bottom, and make the lateral isolation bar (2) of bearing (1) and two-layer consistency from top to bottom front and back have
Penetrating plant growth space.
5. according to the combination isolated column one of claims 1 to 3 Suo Shu, it is characterised in that: the end face of described bearing (1) and the end
Having the splicing construction being mutually matched on face, bearing (1) is connected in series up and down by the splicing construction being mutually matched, the company of series connection up and down
Between the same layer of the bearing (1) connect, splicing has lateral isolation bar (2).
6. according to the combination isolated column one of claims 1 to 3 Suo Shu, it is characterised in that: described adjacent transverse spacer bar (2)
Water supply and sewage hold concurrently between connecting hole (4) or have sealing gasket, described supply and discharge for connection between splicing and the straight pipe (6) of flowing water
Water hold concurrently connecting hole (4) or for splicing with straight pipe (6) and the bolt of flowing water between space be pipelined channel.
7. according to the combination isolated column one of claims 1 to 3 Suo Shu, it is characterised in that: kind is arranged at the top of described bearing (1)
Plant groove (8) or cistern (9).
8. combination isolated column, including bearing (1) and lateral isolation bar (2), it is characterised in that: described bearing (1) and horizontal every
Before and after bar (2) appearance profile is all and bilateral symmetry, described bearing (1) is hexahedron or cylinder, described horizontal stroke
Being plantation space to spacer bar (2) top, bottom is that cistern is held concurrently pipelined channel (3), and lateral isolation bar (2) left and right end face has
Water supply and sewage corresponding to position is held concurrently connecting hole (4) or for splicing and the straight pipe (6) of flowing water, the outer surface of lateral isolation bar (2)
Any one section of horizontal top surface at least one bearing (1) or concave end face on arbitrarily mobile and splicing at an arbitrary position,
Water supply and sewage is held concurrently connecting hole (4) or for splicing and vertically symmetrical of straight pipe (6) of flowing water and vertically symmetrical of bearing (1)
Parallel and substantially overlapping, splicing lateral isolation bar (2) at an arbitrary position connection assist or bonding agent connect with bearing (1)
Connecing, adjacent transverse spacer bar (2) holds concurrently connecting hole (4) by water supply and sewage or the straight pipe (6) for splicing and flowing water directly or adds
Plastic cement sealing gasket is indirectly serially connected in combination isolated column, the simultaneously cistern of adjacent transverse spacer bar (2) bottom with bolt
Pipelined channel (3) of holding concurrently is held concurrently connecting hole (4) or for through, the described combination of splicing and the straight pipe (6) of flowing water by water supply and sewage
Except the coupling part of adjacent transverse spacer bar (2) between bearing (1) and lateral isolation bar (2) that in isolated column, any two is adjacent
It is outward to have discharge water hole (11) on lateral isolation bar (2) wall described in symmetrical structure.
9. combination isolated column, including bearing (1) and lateral isolation bar (2), it is characterised in that: described bearing (1) and horizontal every
Before and after bar (2) appearance profile is all and bilateral symmetry, described bearing (1) is hexahedron or cylinder, described horizontal stroke
Being the continuous groove from an end face to other end to spacer bar (2), continuous groove top is plantation space, and bottom is retaining
Hold concurrently pipelined channel (3) in pond, any one section of the outer surface of lateral isolation bar (2) at least one bearing (1) horizontal top surface or
Arbitrarily moving on concave end face and splice at an arbitrary position, vertically symmetrical of lateral isolation bar (2) is vertical with bearing (1)
The plane of symmetry is parallel and substantially overlapping, splicing lateral isolation bar (2) connection assist or bonding agent and bearing at an arbitrary position
(1) connecting, two adjacent lateral isolation bars (2) partly overlap or alignment bolt or bonding agent are connected in series, combination isolation
Connect in the lateral isolation bar (2) being laterally connected in series on hurdle to have and vertically cut off (10), except vertically in described combination isolated column
Cut off (10) and the adjacent bearing (1) of the outer any two of two adjacent lateral isolation bars (2) connection and lateral isolation bar (2) it
Between structure division be symmetrical structure, described lateral isolation bar (2) wall has discharge water hole (11).
Combination isolated column the most according to claim 8 or claim 9, it is characterised in that: described lateral isolation bar (2) upper and lower
There is the attachment structure that the top and bottom with bearing (1) are mutually matched in face, and cistern (9), bearing are arranged at the top of described bearing (1)
And lateral isolation bar (2) is serially connected in the combination isolated column of multilayer lateral isolation bar (2) alternatively up and down (1).
11. according to the combination isolated column one of claim 1,2,3,8 and 9 Suo Shu, it is characterised in that: described bearing (1) and
Lateral isolation bar (2) material is metal, plastics, plastic-steel, fiberglass or armored concrete, described bearing (1) with the horizontal
Vertical installing, the cross section of described lateral isolation bar (2) is, U-shaped, circular arc or polygon, and described cistern flowing water of holding concurrently leads to
Road is provided with water-stop sheet in (3).
12. according to the combination isolated column one of claim 1,2,3,8 and 9 Suo Shu, it is characterised in that: described bearing (1) portion
Divide and be embedded in concrete or be joined with bolts on xoncrete structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201180020897.9A CN103228841B (en) | 2010-05-11 | 2011-04-29 | Combination isolated column |
Applications Claiming Priority (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010168918.9 | 2010-05-11 | ||
CN2010101689189 | 2010-05-11 | ||
CN201010168918 | 2010-05-11 | ||
CN201180020897.9A CN103228841B (en) | 2010-05-11 | 2011-04-29 | Combination isolated column |
PCT/CN2011/073540 WO2011140935A1 (en) | 2010-05-11 | 2011-04-29 | Combined isolation fence |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103228841A CN103228841A (en) | 2013-07-31 |
CN103228841B true CN103228841B (en) | 2016-08-24 |
Family
ID=44703024
Family Applications (7)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206400999U Expired - Fee Related CN202000279U (en) | 2010-05-11 | 2010-11-26 | Spliced greening isolation barrier |
CN201010572212.9A Active CN102242574B (en) | 2010-05-11 | 2010-11-26 | Spliced greening isolation barrier |
CN201110104295.3A Active CN102251705B (en) | 2010-05-11 | 2011-04-26 | Combined type green isolating railing |
CN2011201246585U Expired - Lifetime CN202055616U (en) | 2010-05-11 | 2011-04-26 | Combined type green isolating railing |
CN201180020897.9A Active CN103228841B (en) | 2010-05-11 | 2011-04-29 | Combination isolated column |
CN2011201462372U Expired - Lifetime CN202298515U (en) | 2010-05-11 | 2011-05-10 | Combined greening isolation fence |
CN201110119986.0A Active CN102278001B (en) | 2010-05-11 | 2011-05-10 | Combination greening wire mesh grating |
Family Applications Before (4)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010206400999U Expired - Fee Related CN202000279U (en) | 2010-05-11 | 2010-11-26 | Spliced greening isolation barrier |
CN201010572212.9A Active CN102242574B (en) | 2010-05-11 | 2010-11-26 | Spliced greening isolation barrier |
CN201110104295.3A Active CN102251705B (en) | 2010-05-11 | 2011-04-26 | Combined type green isolating railing |
CN2011201246585U Expired - Lifetime CN202055616U (en) | 2010-05-11 | 2011-04-26 | Combined type green isolating railing |
Family Applications After (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011201462372U Expired - Lifetime CN202298515U (en) | 2010-05-11 | 2011-05-10 | Combined greening isolation fence |
CN201110119986.0A Active CN102278001B (en) | 2010-05-11 | 2011-05-10 | Combination greening wire mesh grating |
Country Status (2)
Country | Link |
---|---|
CN (7) | CN202000279U (en) |
WO (1) | WO2011140935A1 (en) |
Families Citing this family (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202000279U (en) * | 2010-05-11 | 2011-10-05 | 孙希贤 | Spliced greening isolation barrier |
CN103205946A (en) * | 2012-01-13 | 2013-07-17 | 成都创新景观工程有限公司 | Movable greening guardrail provided with irrigation system |
CN103283519A (en) * | 2012-03-05 | 2013-09-11 | 孙希贤 | Series-wounded and over-headed multi-level green long isolation groove with irrigation system |
CN105369755A (en) * | 2012-06-17 | 2016-03-02 | 苏州汇诚智造工业设计有限公司 | Afforest guardrail pier manufacture method |
CN102733331B (en) * | 2012-06-17 | 2016-05-11 | 苏州汇诚智造工业设计有限公司 | A kind of Green protection fence and manufacture method thereof |
CN102704422A (en) * | 2012-06-17 | 2012-10-03 | 张朝峰 | Guardrail plate with greening groove and manufacturing method for guardrail plate |
CN103563669B (en) * | 2012-07-25 | 2017-07-25 | 上海市政工程设计研究总院(集团)有限公司 | A kind of anticollision barrier greening method |
CN104213524A (en) * | 2013-05-30 | 2014-12-17 | 孙希贤 | Small movable simple greening guard bar convenient to assemble and disassemble |
CN103556869B (en) * | 2013-08-19 | 2016-09-07 | 国家电网公司 | A kind of box-type electric power security tensile fence mesh |
CN103875514A (en) * | 2014-03-04 | 2014-06-25 | 安徽机电职业技术学院 | Road fence with water tanks and flowerpots |
CN105766428A (en) * | 2014-12-23 | 2016-07-20 | 孙希贤 | Flowerpot |
CN104772185A (en) * | 2015-04-01 | 2015-07-15 | 刘银明 | Bilateral protection rack for running water channel |
CN107558317B (en) * | 2017-10-14 | 2019-12-06 | 东阳市琰安建筑工程有限公司 | Road with greenbelt |
CN107905622A (en) * | 2017-10-30 | 2018-04-13 | 湖南诚友绿色建材科技有限公司 | A kind of prefabricated reinforced concrete Green protection fence |
CN108343009B (en) * | 2018-01-15 | 2020-06-05 | 安徽雄风防护设施有限公司 | Guardrail with crashproof function |
CN110318346A (en) * | 2019-06-05 | 2019-10-11 | 成都建工工业化建筑有限公司 | Go slowly bollard and its construction method based on building industrialization product |
CN111877861A (en) * | 2020-08-25 | 2020-11-03 | 临沂市政集团有限公司 | Safety isolation fence is used in road and bridge construction |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1545700A (en) * | 1976-06-17 | 1979-05-10 | Fjeldhammer Brug As | Walls or fences |
CN2441856Y (en) * | 2000-10-12 | 2001-08-08 | 李传将 | Multifuncltion overlap through closure and isolation guard rail flower bed and potted landscape beautifying device |
CN2579159Y (en) * | 2002-11-14 | 2003-10-15 | 赖元俊 | Stereo panel type pant cultivating device |
KR20080000778U (en) * | 2006-10-26 | 2008-04-30 | 주식회사 신흥산업 | Balustrade for Street |
KR20100038826A (en) * | 2008-10-07 | 2010-04-15 | 주식회사 건목 | Middle separation support having a flowerpot |
CN102017874A (en) * | 2009-09-14 | 2011-04-20 | 孙希贤 | Building method of combined-type greening body |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1485939A (en) * | 1976-02-19 | 1977-09-14 | Shell Int Research | Preparation of alkyl chlorides |
DE8903817U1 (en) * | 1989-03-28 | 1989-05-18 | Riedel, Eckard, 7630 Lahr | Kit for plantable noise barriers |
CN2265729Y (en) * | 1995-11-09 | 1997-10-29 | 金荣柱 | Combined stepped flower pot stand |
JP3464887B2 (en) * | 1997-06-02 | 2003-11-10 | 福岡丸本株式会社 | Elevated cultivation container |
JPH1146588A (en) * | 1997-08-05 | 1999-02-23 | Hiroshima Mikado:Kk | Guard fence for planting |
CN2860055Y (en) * | 2005-12-26 | 2007-01-24 | 韩山师范学院 | Automatic drip irrigation greening groove |
CN201156900Y (en) * | 2008-02-22 | 2008-12-03 | 刘旭东 | Plants cultivation frame |
KR20100034434A (en) * | 2008-09-24 | 2010-04-01 | 유지현 | Watering device for hence with hanging flower pot and control method thereof |
WO2011029332A1 (en) * | 2009-09-14 | 2011-03-17 | Sun Xixian | Construction method of combined greening body |
WO2011047641A1 (en) * | 2009-10-23 | 2011-04-28 | Sun Xixian | Combined greening body |
CN202000279U (en) * | 2010-05-11 | 2011-10-05 | 孙希贤 | Spliced greening isolation barrier |
-
2010
- 2010-11-26 CN CN2010206400999U patent/CN202000279U/en not_active Expired - Fee Related
- 2010-11-26 CN CN201010572212.9A patent/CN102242574B/en active Active
-
2011
- 2011-04-26 CN CN201110104295.3A patent/CN102251705B/en active Active
- 2011-04-26 CN CN2011201246585U patent/CN202055616U/en not_active Expired - Lifetime
- 2011-04-29 WO PCT/CN2011/073540 patent/WO2011140935A1/en active Application Filing
- 2011-04-29 CN CN201180020897.9A patent/CN103228841B/en active Active
- 2011-05-10 CN CN2011201462372U patent/CN202298515U/en not_active Expired - Lifetime
- 2011-05-10 CN CN201110119986.0A patent/CN102278001B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1545700A (en) * | 1976-06-17 | 1979-05-10 | Fjeldhammer Brug As | Walls or fences |
CN2441856Y (en) * | 2000-10-12 | 2001-08-08 | 李传将 | Multifuncltion overlap through closure and isolation guard rail flower bed and potted landscape beautifying device |
CN2579159Y (en) * | 2002-11-14 | 2003-10-15 | 赖元俊 | Stereo panel type pant cultivating device |
KR20080000778U (en) * | 2006-10-26 | 2008-04-30 | 주식회사 신흥산업 | Balustrade for Street |
KR20100038826A (en) * | 2008-10-07 | 2010-04-15 | 주식회사 건목 | Middle separation support having a flowerpot |
CN102017874A (en) * | 2009-09-14 | 2011-04-20 | 孙希贤 | Building method of combined-type greening body |
Also Published As
Publication number | Publication date |
---|---|
CN202298515U (en) | 2012-07-04 |
CN102251705B (en) | 2016-03-30 |
CN103228841A (en) | 2013-07-31 |
CN202055616U (en) | 2011-11-30 |
CN102242574B (en) | 2016-04-20 |
WO2011140935A1 (en) | 2011-11-17 |
CN202000279U (en) | 2011-10-05 |
CN102278001B (en) | 2016-04-20 |
CN102242574A (en) | 2011-11-16 |
CN102251705A (en) | 2011-11-23 |
CN102278001A (en) | 2011-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103228841B (en) | Combination isolated column | |
CN203938946U (en) | Modular unit and the matrix that is positioned at load-supporting part below | |
CN102395732B (en) | Module and assembly for managing the flow of water | |
ES2246734A1 (en) | Prefabricated modular tower | |
US20120020746A1 (en) | Modular block | |
CN102484972B (en) | Three-dimensional green planting trough used overhead | |
KR101010730B1 (en) | A greening panel for planting | |
KR100844108B1 (en) | Bending structure for green wall unit and green wall system using the same | |
CN103669261A (en) | Movable combined afforestation fence with irrigation system | |
CN203129048U (en) | Greening isolation rail | |
KR102141237B1 (en) | Assembly type vegetation waterway | |
CN102373665B (en) | Building and overpass afforesting partition fence | |
KR20150019110A (en) | Terraced retaining wall and construction method for slope vegetation | |
CN202759874U (en) | Movable combined type gardening isolation fence with irrigation system | |
CN215421854U (en) | Be used for overpass lateral wall planting technique flower case | |
KR20120017958A (en) | Fixture of block for reinforcing surface | |
CN111972170A (en) | Landscape isolated column can plant | |
CN203755111U (en) | Single modulated cell | |
CN103669260A (en) | Movable combined afforestation guardrail with irrigation system | |
WO2011047641A1 (en) | Combined greening body | |
KR20140000584A (en) | Simplicity pot for damming against floods | |
ES1072313U (en) | Modular deposit for the drainage or storage of rainwater (Machine-translation by Google Translate, not legally binding) | |
CN107548788A (en) | A kind of structure for vegetated wall | |
CN211910007U (en) | Special-shaped bonsai box | |
JP2006000008A (en) | Wall surface greening planter, and method for attaching and watering the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |