CN103161476A - 一种隧道和地下工程中盾构刀盘检修井机械成井的方法 - Google Patents

一种隧道和地下工程中盾构刀盘检修井机械成井的方法 Download PDF

Info

Publication number
CN103161476A
CN103161476A CN2012104146179A CN201210414617A CN103161476A CN 103161476 A CN103161476 A CN 103161476A CN 2012104146179 A CN2012104146179 A CN 2012104146179A CN 201210414617 A CN201210414617 A CN 201210414617A CN 103161476 A CN103161476 A CN 103161476A
Authority
CN
China
Prior art keywords
shield
pile
tunnel
construction
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104146179A
Other languages
English (en)
Other versions
CN103161476B (zh
Inventor
许维清
翟志国
赵宝华
杨志永
张长强
杨泽平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201210414617.9A priority Critical patent/CN103161476B/zh
Publication of CN103161476A publication Critical patent/CN103161476A/zh
Application granted granted Critical
Publication of CN103161476B publication Critical patent/CN103161476B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及竖井施作技术领域,公开一种隧道和地下工程中盾构刀盘检修井机械成井的方法,首先在盾构隧道需要检修刀盘的位置做好标记,对钻孔灌注桩加固范围内进行注浆加固,再以预停机位置为中心对盾构隧道加固范围采用玻璃纤维筋灌注桩(1);并在盾构(6)隧道轴线(3)上群桩中间施作灌注桩(2),然后在灌注桩中间旋挖钻钻出一个中空孔(4)形成盾构刀盘检修竖井(8),并在井口预埋钢护筒;再对群桩中间的土体地层进行补偿注浆,最后在灌注桩桩顶施做盖梁(9),将所有的桩连成一个整体。本发明施工方便、快捷、安全,能够大大的减少开挖工程数量,缩短施工工期、降低工程成本和施工风险,达到为盾构刀盘刀具检修提供作业空间的目的。

Description

一种隧道和地下工程中盾构刀盘检修井机械成井的方法
技术领域
本发明涉及竖井施作技术领域,主要涉及一种隧道和地下工程中盾构刀盘检修井机械成井的方法。
背景技术
在采用的盾构法施工的城市地下铁路隧道和地铁工程中,由于盾构机长距离掘进、刀盘刀具与工程地质条件适应性差等原因,常导致刀盘刀具磨损破坏严重,因此经常需施作工作竖井,对盾构刀盘刀具改造修复。以保证工程顺利进行。
目前国内外采用的传统工作竖井施工方法,施工场地大、施工工艺复杂经常需要进行施工降水、管线改移、长时间交通导改等工作,极大的增加了施工成本和施工工期,另外传统竖井施工采用人工开挖且常伴带水作业,施工场地周边临近建筑物,施工安全风险非常大。
发明内容
为克服现有技术的不足,本发明提出一种隧道和地下工程中盾构刀盘检修井机械成井的方法,尤其适用于城市繁忙地区工作井施工,减少开挖工程数量,缩短施工工期、降低工程成本和施工风险,达到为盾构刀盘刀具改造修复提供作业空间的目的。
为实现上述发明目的,本发明采用如下技术方案:
一种隧道和地下工程中盾构刀盘检修井机械成井的方法,其步骤如下:
1)、首先在盾构隧道需要检修刀盘的位置,采用物探和人工挖探的方法,探明施工区域地下管线(11),并对地下管线(11)做好标记;
2)、然后对钻孔灌注桩加固范围内5m深的地层进行后退式注浆加固,
3)、再以预停机位置为中心对盾构隧道加固范围采用旋挖钻施作3排φ1.0m玻璃纤维筋灌注桩(1);
4)、最后在盾构(6)隧道轴线(3)上,群桩中间施作1根大直径(φ2.0m-φ3.0m)灌注桩(2),灌注桩施工过程:桩位测量放线、埋设护筒、钻机就位、钻孔、终孔、清孔、下玻璃纤维筋笼、水下灌的混凝土采用缓凝混凝土(5)灌注; 
5)、待φ2.0m的灌注桩砼达到1天凝固强度后,在灌注桩顶中心位置画出一个φ1.0m的圆, 
6)、然后在φ2.0m灌注桩(2)中间位置根据作业需要采用旋挖钻钻出一个较小直径(如φ1.0m)中空孔(4)形成盾构刀盘检修竖井(8),并在井口预埋一段钢护筒;
a)、先采用φ1.0m的旋挖钻进行钻孔,钻孔时孔内仍然装满高质量泥浆,起到护壁和支撑桩壁的作用;
b)、保持好旋挖钻杆的垂直度,防止偏钻,造成井壁薄厚不均,根据工作需要确定工作井钻孔设计标高,并保证工作井底部有7m厚左右砼底板;
c)、钻孔完成后,孔内仍充满泥浆,
d)、待砼达到7天强度后,将孔内泥浆全部抽排干净,形成工作竖井(8)。
e)、井口预埋一段2m高的钢护筒,使钢护筒和盖板钢筋连接牢固一起浇筑盖板,成为一个整体,确保安全。
7)、灌注桩完成后对群桩中间的土体地层进行补偿注浆(6);
8)、最后在灌注桩桩顶施做C30砼盖梁(9),将所有的桩连成一个整体,盖梁中间将工作井孔口留出,并加盖一个封闭的井盖。
由于采用如上所述的技术方案,本发明具有如下优越性:
一种隧道和地下工程中盾构刀盘检修井机械成井的方法,是在隧道和地下工程领域的盾构法隧道施工中,采用机械法施工盾构刀盘检修井的方法,尤其适用于城市中心区周边环境复杂的区域进行竖井施工,可以大大的减少开挖工程数量,缩短施工工期、降低工程成本和施工风险,达到为盾构刀盘刀具检修提供作业空间的目的。本发明施作的工作竖井同时还可以应用于长大隧道测量、轨下结构施工投料孔作用。采用本发明的新工艺方法,施工方便、快捷、安全,可以大大降低工程成本和施工风险。经施工工程试验取得了良好的效果,具有很好的推广应用前景。
附图说明
图1 灌注桩和注浆孔位平面布置图
图2旋挖钻孔桩施工流程图。
图3 灌注桩施工顺序图。
图4盾构刀盘与工作竖井下部位置关系纵侧面示意图。
图5盾构刀盘与工作竖井下部位置关系纵正面示意图。
图中,1、φ1.0m玻纤灌注桩,2、φ2.0m玻纤灌注桩,3、隧道中线,4、φ1.0m中空桩,5、C20缓凝混凝土,6、盾构机,7、补偿注浆孔,8、工作空间, 9、C30砼盖梁,10、盾构机刀盘, 11管线
具体实施方式
结合附图对本发明实施例加以说明:
如图1、2、3、4、5所示,一种隧道和地下工程中盾构刀盘检修井机械成井的方法,其步骤如下:
1)、首先在盾构隧道需要检修刀盘的位置,采用物探和人工挖探的方法,探明施工区域地下管线(11),并对地下管线(11)做好标记;
2)、然后对钻孔灌注桩加固范围内5m深的地层进行后退式注浆加固,
3)、再以预停机位置为中心对盾构隧道加固范围采用旋挖钻施作3排φ1.0m玻璃纤维筋灌注桩(1);
4)、最后在盾构(6)隧道轴线(3)上,群桩中间施作1根大直径(φ2.0m-φ3.0m)灌注桩(2),灌注桩施工过程:桩位测量放线、埋设护筒、钻机就位、钻孔、终孔、清孔、下玻璃纤维筋笼、水下灌的混凝土采用缓凝混凝土(5)灌注; 
5)、待φ2.0m的灌注桩砼达到1天凝固强度后,在灌注桩顶中心位置画出一个φ1.0m的圆, 
6)、然后在φ2.0m灌注桩(2)中间位置根据作业需要采用旋挖钻钻出一个较小直径(如φ1.0m)中空孔(4)形成盾构刀盘检修竖井(8),并在井口预埋一段钢护筒;
a)、先采用φ1.0m的旋挖钻进行钻孔,钻孔时孔内仍然装满高质量泥浆,起到护壁和支撑桩壁的作用;
b)、保持好旋挖钻杆的垂直度,防止偏钻,造成井壁薄厚不均,根据工作需要确定工作井钻孔设计标高,并保证工作井底部有7m厚左右砼底板;
c)、钻孔完成后,孔内仍充满泥浆,
d)、待砼达到7天强度后,将孔内泥浆全部抽排干净,形成工作竖井(8)。
e)、井口预埋一段2m高的钢护筒,使钢护筒和盖板钢筋连接牢固一起浇筑盖板,成为一个整体,确保安全。
7)、灌注桩完成后对群桩中间的土体地层进行补偿注浆(6);
8)、最后在灌注桩桩顶施做C30砼盖梁(9),将所有的桩连成一个整体,盖梁中间将工作井孔口留出,并加盖一个封闭的井盖。
即本发明采用机械法施工盾构刀盘检修井工艺步骤为:如图4所示,
步骤1:管线探查、注浆加固。采用物探和人工挖探方法,探明设计施工区地下管线,并对地下管线做好标记。
然后对钻孔灌注桩加固范围内5m深的地层进行后退式注浆加固
如图2、3所示,步骤2:施作周边及中心φ2.0m玻纤灌注桩。以预停机位置为中心施做3排φ1.0m玻璃纤维筋灌注桩,旋挖钻孔桩施工流程见图2
旋挖钻孔桩施工时应分排跳孔施工,具体施工顺序如下:
第一排桩施工顺序:1#—5#—3#—7#——2#—4#—6#—8#;
第二排桩施工顺序:15#—11#—13#—9#—14#—12#—10#;
第三排桩施工顺序:16#—20#—18#—22#—17#—19#—21#—23#;
最后施工24#桩。
如图3、4所示,步骤3:施作φ1.0m中空孔及工作竖井。φ2.0m的灌注桩砼达到1天凝固强度后,在桩顶中心位置画出一个φ1.0m的圆,然后埋设护筒,先采用φ1.0m的旋挖钻进行钻孔。待砼达到7天强度后,将孔内泥浆全部抽排干净,形成工作竖井。井口预埋一段2m高的钢护筒,使钢护筒和盖板钢筋连接牢固一起浇筑盖板,成为一个整体,最后加盖井盖。
如图1所示,步骤4:施作补偿注浆和盖梁。灌注桩完成后对群桩中间的土体地层进行补偿注浆,最后在桩顶施做盖梁将所有的桩连成一个整体,盖梁中间将工作井孔口留出,并加盖封闭的井盖。
虽然上面已经参考附图描述了本发明的实施例,但是本领域技术人员可以理解,在不脱离本发明和精神的情况下,可以对本发明做出各种不同的修改和变化。因此,应该理解上述的实施案例不是限制,而是各个方面的举例说明。

Claims (1)

1.一种隧道和地下工程中盾构刀盘检修井机械成井的方法,其特征在于:其步骤如下:
1)、首先在盾构隧道需要检修刀盘的位置,采用物探和人工挖探的方法,探明施工区域地下管线(11),并对地下管线(11)做好标记;
2)、然后对钻孔灌注桩加固范围内5m深的地层进行后退式注浆加固,
3)、再以预停机位置为中心对盾构隧道加固范围采用旋挖钻施作3排φ1.0m玻璃纤维筋灌注桩(1);
4)、最后在盾构(6)隧道轴线(3)上,群桩中间施作1根大直径φ2.0m-φ3.0m的灌注桩(2),灌注桩施工过程:桩位测量放线、埋设护筒、钻机就位、钻孔、终孔、清孔、下玻璃纤维筋笼、水下灌的混凝土采用缓凝混凝土(5)灌注; 
5)、待φ2.0m的灌注桩砼达到1天凝固强度后,在灌注桩顶中心位置画出一个φ1.0m的圆, 
6)、然后在φ2.0m灌注桩(2)中间位置根据作业需要采用旋挖钻钻出一个小直径φ1.0m的中空孔(4)形成盾构刀盘检修竖井(8),并在井口预埋一段钢护筒;
a)、先采用φ1.0m的旋挖钻进行钻孔,钻孔时孔内仍然装满高质量泥浆,起到护壁和支撑桩壁的作用;
b)、保持好旋挖钻杆的垂直度,防止偏钻,造成井壁薄厚不均,根据工作需要确定工作井钻孔设计标高,并保证工作井底部有7m厚左右砼底板;
c)、钻孔完成后,孔内仍充满泥浆,
d)、待砼达到7天强度后,将孔内泥浆全部抽排干净,形成工作竖井(8):
e)、井口预埋一段2m高的钢护筒,使钢护筒和盖板钢筋连接牢固一起浇筑盖板,成为一个整体,确保安全;
7)、灌注桩完成后对群桩中间的土体地层进行补偿注浆(6);
8)、最后在灌注桩桩顶施做C30砼盖梁(9),将所有的桩连成一个整体,盖梁中间将工作井孔口留出,并加盖一个封闭的井盖。
CN201210414617.9A 2012-10-26 2012-10-26 一种隧道和地下工程中盾构刀盘检修井机械成井的方法 Active CN103161476B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210414617.9A CN103161476B (zh) 2012-10-26 2012-10-26 一种隧道和地下工程中盾构刀盘检修井机械成井的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210414617.9A CN103161476B (zh) 2012-10-26 2012-10-26 一种隧道和地下工程中盾构刀盘检修井机械成井的方法

Publications (2)

Publication Number Publication Date
CN103161476A true CN103161476A (zh) 2013-06-19
CN103161476B CN103161476B (zh) 2014-05-21

Family

ID=48584971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210414617.9A Active CN103161476B (zh) 2012-10-26 2012-10-26 一种隧道和地下工程中盾构刀盘检修井机械成井的方法

Country Status (1)

Country Link
CN (1) CN103161476B (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060997A (zh) * 2014-07-11 2014-09-24 北京建筑大学 盾构穿越检查井的施工方法
CN105569666A (zh) * 2016-01-20 2016-05-11 铁道第三勘察设计院集团有限公司 一种盾构长距离掘进常压换刀配套的地层加固方法
CN106907157A (zh) * 2017-02-09 2017-06-30 广东水电二局股份有限公司 一种盾构机常压开舱作业施工方法
CN108643917A (zh) * 2018-05-16 2018-10-12 北京中地盾构工程技术研究院有限公司 半回填式盾构刀盘检修井装配式施工方法
CN108678751A (zh) * 2018-05-16 2018-10-19 北京中地盾构工程技术研究院有限公司 先顶进后开挖的盾构刀盘检修井装配式施工方法
CN108708727A (zh) * 2018-05-16 2018-10-26 北京中地盾构工程技术研究院有限公司 半开挖后顶进的盾构刀盘检修井装配式施工方法
CN108708736A (zh) * 2018-05-16 2018-10-26 北京中地盾构工程技术研究院有限公司 盾构刀盘检修井装配式施工方法
CN109113746A (zh) * 2018-07-24 2019-01-01 北京隧盾市政建设有限公司 盾构检修井的施工方法
CN109322672A (zh) * 2018-11-08 2019-02-12 中交二航局成都城市建设工程有限公司 一种基于辅助桩的盾构机正侧面维保空间系统及方法
CN109403993A (zh) * 2018-12-04 2019-03-01 中交隧道工程局有限公司 一种用于盾构机刀盘正面检修清理的玻璃纤维筋中孔桩及施工方法
CN110259473A (zh) * 2019-05-24 2019-09-20 中交一公局第三工程有限公司 富水砂卵石地层空心桩施作刀盘检修井检修工艺
CN110685700A (zh) * 2019-10-16 2020-01-14 中建铁路投资建设集团有限公司 一种地面钻孔清理盾体表面附着砂浆的施工方法
CN112459785A (zh) * 2020-12-01 2021-03-09 中冶赛迪工程技术股份有限公司 利用市政井进行超浅埋暗挖隧道下穿既有管线的加固方法
CN112576267A (zh) * 2021-02-22 2021-03-30 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4369627B2 (ja) * 2001-02-16 2009-11-25 清水建設株式会社 トンネル築造方法及びそれに用いるシールド掘削機
CN102418531A (zh) * 2011-12-14 2012-04-18 中铁十二局集团有限公司 一种盾构直接截除立交桥群桩掘进施工方法
CN102654056A (zh) * 2012-05-08 2012-09-05 上海市基础工程有限公司 盾构遇岩层段冲孔清障施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4369627B2 (ja) * 2001-02-16 2009-11-25 清水建設株式会社 トンネル築造方法及びそれに用いるシールド掘削機
CN102418531A (zh) * 2011-12-14 2012-04-18 中铁十二局集团有限公司 一种盾构直接截除立交桥群桩掘进施工方法
CN102654056A (zh) * 2012-05-08 2012-09-05 上海市基础工程有限公司 盾构遇岩层段冲孔清障施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨保琦等: "《盾构检修井快速施工方法探讨》", 《铁道建筑技术》, no. 2, 31 December 2011 (2011-12-31), pages 72 - 73 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060997A (zh) * 2014-07-11 2014-09-24 北京建筑大学 盾构穿越检查井的施工方法
CN104060997B (zh) * 2014-07-11 2016-03-30 北京建筑大学 盾构穿越检查井的施工方法
CN105569666A (zh) * 2016-01-20 2016-05-11 铁道第三勘察设计院集团有限公司 一种盾构长距离掘进常压换刀配套的地层加固方法
CN106907157B (zh) * 2017-02-09 2019-01-04 广东水电二局股份有限公司 一种盾构机常压开舱作业施工方法
CN106907157A (zh) * 2017-02-09 2017-06-30 广东水电二局股份有限公司 一种盾构机常压开舱作业施工方法
CN108643917A (zh) * 2018-05-16 2018-10-12 北京中地盾构工程技术研究院有限公司 半回填式盾构刀盘检修井装配式施工方法
CN108678751A (zh) * 2018-05-16 2018-10-19 北京中地盾构工程技术研究院有限公司 先顶进后开挖的盾构刀盘检修井装配式施工方法
CN108708727A (zh) * 2018-05-16 2018-10-26 北京中地盾构工程技术研究院有限公司 半开挖后顶进的盾构刀盘检修井装配式施工方法
CN108708736A (zh) * 2018-05-16 2018-10-26 北京中地盾构工程技术研究院有限公司 盾构刀盘检修井装配式施工方法
CN108708727B (zh) * 2018-05-16 2019-12-31 北京中地盾构工程技术研究院有限公司 半开挖后顶进的盾构刀盘检修井装配式施工方法
CN108678751B (zh) * 2018-05-16 2020-04-07 北京中地盾构工程技术研究院有限公司 先顶进后开挖的盾构刀盘检修井装配式施工方法
CN108708736B (zh) * 2018-05-16 2019-12-27 北京中地盾构工程技术研究院有限公司 盾构刀盘检修井装配式施工方法
CN109113746A (zh) * 2018-07-24 2019-01-01 北京隧盾市政建设有限公司 盾构检修井的施工方法
CN109113746B (zh) * 2018-07-24 2020-02-18 北京隧盾市政建设有限公司 盾构检修井的施工方法
CN109322672A (zh) * 2018-11-08 2019-02-12 中交二航局成都城市建设工程有限公司 一种基于辅助桩的盾构机正侧面维保空间系统及方法
CN109403993A (zh) * 2018-12-04 2019-03-01 中交隧道工程局有限公司 一种用于盾构机刀盘正面检修清理的玻璃纤维筋中孔桩及施工方法
CN110259473A (zh) * 2019-05-24 2019-09-20 中交一公局第三工程有限公司 富水砂卵石地层空心桩施作刀盘检修井检修工艺
CN110685700A (zh) * 2019-10-16 2020-01-14 中建铁路投资建设集团有限公司 一种地面钻孔清理盾体表面附着砂浆的施工方法
CN110685700B (zh) * 2019-10-16 2021-01-01 中建铁路投资建设集团有限公司 一种地面钻孔清理盾体表面附着砂浆的施工方法
CN112459785A (zh) * 2020-12-01 2021-03-09 中冶赛迪工程技术股份有限公司 利用市政井进行超浅埋暗挖隧道下穿既有管线的加固方法
CN112576267A (zh) * 2021-02-22 2021-03-30 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法
CN112576267B (zh) * 2021-02-22 2021-12-21 中铁九局集团第四工程有限公司 富水砂卵石地层高效常压换刀施工方法

Also Published As

Publication number Publication date
CN103161476B (zh) 2014-05-21

Similar Documents

Publication Publication Date Title
CN103161476B (zh) 一种隧道和地下工程中盾构刀盘检修井机械成井的方法
CN102704957B (zh) 一种用于浅埋大型地下结构建造的棚架法
CN107130613B (zh) 大跨隧道正穿既有挡墙的支挡结构及其施工方法
CN100588816C (zh) 一种水平钻孔的施工方法
CN104763449B (zh) 一种地下水封洞库水幕系统设计方法
CN202707075U (zh) 基于柱拱法施工成型的地铁大跨度车站主体结构
CN104120731B (zh) 一种隧道沉降防护装置及其施工方法
CN102748040B (zh) 地铁大跨度车站主体结构及其柱拱法施工方法
CN101737061A (zh) 既有单洞隧道改扩建为连拱隧道的施工方法
CN205876348U (zh) 一种复杂地质条件下横通道拱顶多层次超前支护结构
CN103206219A (zh) 偏压状态下明暗交界段隧道进洞开挖支护结构及施工工法
CN105239598A (zh) 井式全自动立体车库的整体下沉施工方法
CN103711492B (zh) 一种顶进式电缆套管通道施工方法
CN103899318B (zh) 中硬地层隧道铣挖及配套机械化施工工法
CN107119669A (zh) 用于盾构在富水砂层中侧穿房屋的预注浆加固地基方法
CN104790978A (zh) 小净距立体交叉隧道环形导坑施工方法
CN109736811A (zh) 一种竖井机械掘进施工方法
CN109488202A (zh) 一种含漂卵石层的砂砾岩层桩基成孔施工工法
CN103410522A (zh) 浅埋暗挖法连续近距离下穿铁路桥的施工方法
CN112832802B (zh) 一种针对非对称压力的大底板块支护结构及支护方法
CN105673025A (zh) 一种地下工程黄土隧道控制地表沉降施工工艺
CN205748469U (zh) 一种水库滑坡多场信息现场监测系统
CN109577991A (zh) 一种多隧洞并行的隧道结构及其施工方法
CN104863183B (zh) 大断面隧道近接建筑物施工隔离减震桩结构及施工方法
CN110055973A (zh) 施工空间受限时的高铁桥下基坑围护结构与止水方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Xu Weiqing

Inventor after: Di Zhiguo

Inventor after: Zhao Baohua

Inventor after: Yang Zhiyong

Inventor after: Zhang Changqiang

Inventor after: Yang Zeping

Inventor before: Xu Weiqing

Inventor before: Di Zhiguo

Inventor before: Zhao Baohua

Inventor before: Yang Zhiyong

Inventor before: Zhang Changqiang

Inventor before: Yang Zeping