CN103113906A - 一种易结焦油品延迟焦化方法 - Google Patents
一种易结焦油品延迟焦化方法 Download PDFInfo
- Publication number
- CN103113906A CN103113906A CN2013100225655A CN201310022565A CN103113906A CN 103113906 A CN103113906 A CN 103113906A CN 2013100225655 A CN2013100225655 A CN 2013100225655A CN 201310022565 A CN201310022565 A CN 201310022565A CN 103113906 A CN103113906 A CN 103113906A
- Authority
- CN
- China
- Prior art keywords
- coking
- coking tower
- tower charging
- process furnace
- heating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Coke Industry (AREA)
Abstract
一种易结焦油品延迟焦化方法,其基本模式是“2炉2塔”,即2台焦化塔进料加热炉作为一组加热炉配置2台焦化塔;当1台焦化塔进料加热炉处于停工、切出焦化塔进料加热生产线、切入除焦生产线、除焦、切出除焦生产线、切入焦化塔进料加热生产线的程序时,另1台焦化塔进料加热炉处于加热焦化塔进料的状态。当焦化塔进料加热炉不需要清焦时焦化塔进料加热炉A与焦化塔进料加热炉B同时加热焦化塔进料,其优点在于:在不大量增加投资和保证焦化塔连续运行的条件下,能够加工残炭值高、结焦率大的油品,实现了焦化原料油的重质化,扩大了加工原料范围。
Description
技术领域
本发明涉及一种易结焦油品延迟焦化方法;特别地讲本发明涉及一种煤焦油重油延迟焦化方法。
背景技术
在油品延迟焦化工艺中,原料油加热和焦化生焦是其核心步骤,常规方法的基本模式是“1炉2塔”,即一台焦化塔进料加热炉配置2台焦化塔,为了实现焦化塔生焦和出焦的总体过程的连续化,焦化塔A与焦化塔B互为备用,切换操作,一台处于清焦工况,另一台处于生焦工况。焦化塔内生成的焦炭通常经水力除焦卸出。排出焦化塔顶部的高温油汽进入焦化分馏塔(进料口位于塔下部、)得到焦化富气、焦化汽油、焦化柴油、焦化蜡油、塔底循环油。该模式的前提条件是焦化塔进料加热炉炉管的生焦速度慢、除焦再生次数少。
在常规油品延迟焦化工艺中,焦化塔进料加热炉炉管的除焦再生方式分为停工烧焦再生方式和在线清焦再生方式。第一种结焦后的焦化塔进料加热炉炉管的再生方式是停工烧焦再生方式,即加热炉全面停工后烧焦,其缺点是焦化装置全线停工,降低了开工率,形成物料浪费和能源浪费。停工烧焦再生过程炉管内通常使用蒸汽、蒸汽+空气。第二种结焦后的焦化塔进料加热炉炉管的再生方式是在线清焦再生方式,即加热炉大部分炉管处于正常加热焦化塔进料状态,通常将一根炉管切出系统进行清焦,完成清焦后切入正常生产状态,其优点是不会导致全装置停工,仅在清焦时期降低装置处理量。由于该方法使焦化塔进料加热炉的再生清焦炉管与正常加热焦化塔进料的炉管处于同一个加热炉炉体内,增加了操作的风险,故通常在线清焦的时间间隔很长,通常一个生产年内为1~2次。恒温法在线清焦再生方法适合于软焦层的清除,炉管内通常使用蒸汽对焦垢层冲刷并进行高温下使焦炭与水蒸气反应生成一氧化碳和氢气。变温法在线清焦再生方法适合于硬焦层的清除,通过快速升高和降低炉管温度,使焦炭层与炉管剥离。
由于煤焦油重油的延迟焦化装置的焦化塔进料加热炉炉管的结焦速度快,如采用停工烧焦再生方式则停工频繁,如采用在线清焦再生方式则劳动强度大、风险大。因此需要提出一种新的再生除焦方式,形成新的延迟焦化工艺。
本发明提出一种易结焦油品延迟焦化方法,其基本模式是“2炉2塔”,即2台焦化塔进料加热炉作为一组加热炉配置2台焦化塔;为了实现焦化塔进料加热过程的连续化,当1台焦化塔进料加热炉处于停工、切出焦化塔进料加热生产线、切入除焦生产线、除焦、切出除焦生产线、切入焦化塔进料加热生产线的程序时,另1台焦化塔进料加热炉处于加热焦化塔进料的状态;为了实现焦化塔生焦和出焦的总体过程的连续化,焦化塔A与焦化塔B互为备用,切换操作,一台处于清焦工况,另一台处于生焦工况。
本发明的优点在于:
①与停工烧焦再生方式相比,避免了全线停工,可提高开工率,减少物料浪费、减少能源浪费;
②与在线烧焦再生方式相比,降低了操作风险,降低了劳动强度,烧焦过程操作条件易于控制;
③能够加工残炭值高、结焦率大的油品,即实现了焦化原料油的重质化,扩大了加工原料范围;当焦化塔进料加热炉不需要清焦时焦化塔进料加热炉A与焦化塔进料加热炉B同时加热焦化塔进料时,仅增加少量投资;
④与降低煤沥青产率的煤焦油减压深拔蒸馏工艺组合,可以提高煤焦油减压分馏过程深拔油品P的拔出率,降低煤沥青产率,降低煤沥青延迟焦化的焦炭产量,煤沥青延迟焦化的油品如沸点低于450℃的煤焦油焦化生成油可以进入油品P的加氢精制过程PHT,可以提高加氢精制过程PHT的原料油总量。
本发明方法未见报道。
因此,本发明的第一目的在于提出一种易结焦油品延迟焦化过程的焦化塔进料加热炉炉管的再生除焦方法。本发明的第二目的在于提出一种易结焦油品延迟焦化方法。本发明的第三目的在于提出一种煤焦油重油延迟焦化方法。本发明的第四目的在于提出一种煤焦油分馏深拔馏分油、煤沥青延迟焦化、煤沥青延迟焦化生成油与煤焦油分馏馏分油共同加氢精制的组合方法。
发明内容
本发明一种易结焦油品的延迟焦化方法,其基本模式是“2炉2塔”,即2台焦化塔进料加热炉作为一组加热炉配置2台焦化塔;为了实现焦化塔进料加热过程的连续化,当1台焦化塔进料加热炉处于停工、切出焦化塔进料加热生产线、切入除焦生产线、除焦、切出除焦生产线、切入焦化塔进料加热生产线的程序时,另1台焦化塔进料加热炉处于加热焦化塔进料的状态;为了实现焦化塔生焦和出焦的总体过程的连续化,焦化塔A与焦化塔B互为备用,切换操作,一台处于清焦工况,另一台处于生焦工况。
当焦化塔进料加热炉不需要清焦时,焦化塔进料加热炉A与焦化塔进料加热炉B加热焦化塔进料的操作方式可以为同时加热或者为一开一备、切换操作。
本发明特别适合于基于煤焦油的油品比如煤沥青的延迟焦化过程。煤沥青可以与高氢含量的溶剂油混合后一并完成延迟焦化过程。
具体实施方式
本发明一种易结焦油品的延迟焦化方法,其基本模式是“2炉2塔”,即2台焦化塔进料加热炉作为一组加热炉配置2台焦化塔;为了实现焦化塔进料加热过程的连续化,当1台焦化塔进料加热炉处于停工、切出焦化塔进料加热生产线、切入除焦生产线、除焦、切出除焦生产线、切入焦化塔进料加热生产线的程序时,另1台焦化塔进料加热炉处于加热焦化塔进料的状态;为了实现焦化塔生焦和出焦的总体过程的连续化,焦化塔A与焦化塔B互为备用,切换操作,一台处于清焦工况,另一台处于生焦工况。
当焦化塔进料加热炉不需要清焦时,焦化塔进料加热炉A与焦化塔进料加热炉B加热焦化塔进料的操作方式可以为同时加热或者为一开一备、切换操作。同时加热方式可以提高焦化塔进料加热炉利用率、降低投资。
本发明特别适合于基于煤焦油的油品比如煤沥青的延迟焦化过程。煤沥青可以与高氢含量的溶剂油混合后一并完成延迟焦化过程。
本发明与降低煤沥青产率的煤焦油减压深拔蒸馏工艺组合,可以提高煤焦油减压分馏过程深拔油品P的拔出率,降低煤沥青产率,降低煤沥青延迟焦化的焦炭产量,煤沥青延迟焦化的油品如沸点低于450℃的煤焦油焦化生成油可以进入油品P的加氢精制过程PHT,可以提高加氢精制过程PHT的原料油总量。
本发明所述焦化塔进料加热炉A与焦化塔进料加热炉B,至少使用不同的辐射室且二者的辐射室能够完全隔断,因此焦化塔进料加热炉A与焦化塔进料加热炉B形式上可以是两台加热炉或者是二合一组合式加热炉。
Claims (6)
1.一种易结焦油品的延迟焦化方法,其基本模式是“2炉2塔”,即2台焦化塔进料加热炉作为一组加热炉配置2台焦化塔;为了实现焦化塔进料加热过程的连续化,当1台焦化塔进料加热炉处于停工、切出焦化塔进料加热生产线、切入除焦生产线、除焦、切出除焦生产线、切入焦化塔进料加热生产线的程序时,另1台焦化塔进料加热炉处于加热焦化塔进料的状态;为了实现焦化塔生焦和出焦的总体过程的连续化,焦化塔A与焦化塔B互为备用,切换操作,一台处于清焦工况,另一台处于生焦工况。
2.根据权利要求1所述的方法,其特征在于:
当焦化塔进料加热炉不需要清焦时,焦化塔进料加热炉A与焦化塔进料加热炉B加热焦化塔进料的操作方式为同时加热。
3.根据权利要求1所述的方法,其特征在于:
当焦化塔进料加热炉不需要清焦时,焦化塔进料加热炉A与焦化塔进料加热炉B加热焦化塔进料的操作方式为一开一备、切换操作。
4.根据权利要求1或2或3所述的方法,其特征在于:
焦化塔进料为基于煤焦油的油品。
5.根据权利要求4所述的方法,其特征在于:
焦化塔进料为煤沥青。
6.根据权利要求5所述的方法,其特征在于:
焦化塔进料为煤沥青和高氢含量油品的混合油。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013100225655A CN103113906A (zh) | 2013-01-08 | 2013-01-08 | 一种易结焦油品延迟焦化方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013100225655A CN103113906A (zh) | 2013-01-08 | 2013-01-08 | 一种易结焦油品延迟焦化方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103113906A true CN103113906A (zh) | 2013-05-22 |
Family
ID=48412325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013100225655A Pending CN103113906A (zh) | 2013-01-08 | 2013-01-08 | 一种易结焦油品延迟焦化方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103113906A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107723023A (zh) * | 2016-08-10 | 2018-02-23 | 中国石油天然气股份有限公司 | 一种油砂沥青的延迟焦化加工方法 |
CN109251758A (zh) * | 2017-07-13 | 2019-01-22 | 鞍钢股份有限公司 | 一种改质沥青停产快速置换的方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87102308A (zh) * | 1987-03-28 | 1988-10-12 | 中国石油化工总公司石油化工科学研究院 | 具有两路进料系统的渣油焦化工艺 |
US4853106A (en) * | 1987-08-19 | 1989-08-01 | Mobil Oil Corporation | Delayed coking process |
CN1246514A (zh) * | 1998-08-27 | 2000-03-08 | 中国石油化工集团公司 | 一种改进的延迟焦化工艺 |
CN1465658A (zh) * | 2002-06-27 | 2004-01-07 | 中国石油化工股份有限公司 | 一种同时提高延迟焦化装置处理量及柴油收率的方法 |
CN1469917A (zh) * | 2000-09-14 | 2004-01-21 | ���ʿ����о�����˾ | 焦化装置中焦化塔蒸汽管路的急冷方法和装置 |
CN102268288A (zh) * | 2010-06-02 | 2011-12-07 | 中国石油化工集团公司 | 一种高酸原料油深度脱酸的延迟焦化工艺 |
-
2013
- 2013-01-08 CN CN2013100225655A patent/CN103113906A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87102308A (zh) * | 1987-03-28 | 1988-10-12 | 中国石油化工总公司石油化工科学研究院 | 具有两路进料系统的渣油焦化工艺 |
US4853106A (en) * | 1987-08-19 | 1989-08-01 | Mobil Oil Corporation | Delayed coking process |
CN1246514A (zh) * | 1998-08-27 | 2000-03-08 | 中国石油化工集团公司 | 一种改进的延迟焦化工艺 |
CN1469917A (zh) * | 2000-09-14 | 2004-01-21 | ���ʿ����о�����˾ | 焦化装置中焦化塔蒸汽管路的急冷方法和装置 |
CN1465658A (zh) * | 2002-06-27 | 2004-01-07 | 中国石油化工股份有限公司 | 一种同时提高延迟焦化装置处理量及柴油收率的方法 |
CN102268288A (zh) * | 2010-06-02 | 2011-12-07 | 中国石油化工集团公司 | 一种高酸原料油深度脱酸的延迟焦化工艺 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107723023A (zh) * | 2016-08-10 | 2018-02-23 | 中国石油天然气股份有限公司 | 一种油砂沥青的延迟焦化加工方法 |
CN107723023B (zh) * | 2016-08-10 | 2020-05-08 | 中国石油天然气股份有限公司 | 一种油砂沥青的延迟焦化加工方法 |
CN109251758A (zh) * | 2017-07-13 | 2019-01-22 | 鞍钢股份有限公司 | 一种改质沥青停产快速置换的方法 |
CN109251758B (zh) * | 2017-07-13 | 2020-10-27 | 鞍钢股份有限公司 | 一种改质沥青停产快速置换的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101514291B (zh) | 一种煤内热低温干馏干熄焦的方法 | |
EP2829589B1 (en) | Method for producing charcoal | |
CN103396820B (zh) | 一种生物质热解制备生物油的方法 | |
CN101824332A (zh) | 废旧塑料、轮胎、废机油的再生能源综合利用生产装备 | |
CN101885977A (zh) | 一种杉木屑提取杉木油联产活性炭的方法 | |
CN101638585A (zh) | 一种延迟焦化方法 | |
CN101724419A (zh) | 一种煤焦油延迟焦化生产针状焦的方法 | |
CN109988548B (zh) | 高温相变蜡及其制备方法 | |
CN103113906A (zh) | 一种易结焦油品延迟焦化方法 | |
CN104232129A (zh) | 一种有机废弃物与煤共热解制取半焦及焦油的方法 | |
CN107586567A (zh) | 一种基于连续干馏、气化重整与烘焙耦合处理的生物质热解气炭清洁联产工艺 | |
CN105087035B (zh) | 一种油砂热解制备清洁燃料油的方法及装置 | |
CN102786953A (zh) | 一种焦炉成组新型桥管荒煤气余热回收装置 | |
CN108728139A (zh) | 一种煤热解无氮工艺方法及系统 | |
CN103756728A (zh) | 生物质炭气联产系统及工作方法 | |
CN203440306U (zh) | 一种针状焦的生产装置 | |
CN102748935A (zh) | 竹屑热解可燃气燃烧尾气直接烘干竹条的方法 | |
CN203307292U (zh) | 一种实现减粘裂化延迟焦化工艺联合的装置 | |
CN106675613B (zh) | 一种苯酚焦油的加工方法 | |
UA96880C2 (ru) | Способ и устройство для переработки угля | |
CN110229683A (zh) | 一种干馏热解生产木醋液生物燃气系统 | |
Azura et al. | Effect of fast pyrolysis operating conditions on product yield of red meranti sawdust | |
CN203307293U (zh) | 一种重油加工装置 | |
CN103725307A (zh) | 废油连续式闪蒸工艺设备 | |
CN105647554B (zh) | 一种煤干馏与煤焦油蒸馏组合工艺方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |