CN103104041B - A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method - Google Patents

A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method Download PDF

Info

Publication number
CN103104041B
CN103104041B CN201310074280.6A CN201310074280A CN103104041B CN 103104041 B CN103104041 B CN 103104041B CN 201310074280 A CN201310074280 A CN 201310074280A CN 103104041 B CN103104041 B CN 103104041B
Authority
CN
China
Prior art keywords
prefabricated
precast beam
hidden bracket
bolt
corbel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310074280.6A
Other languages
Chinese (zh)
Other versions
CN103104041A (en
Inventor
王艳
陈淮
葛素娟
陈代海
李�杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou University
Original Assignee
Zhengzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou University filed Critical Zhengzhou University
Priority to CN201310074280.6A priority Critical patent/CN103104041B/en
Publication of CN103104041A publication Critical patent/CN103104041A/en
Application granted granted Critical
Publication of CN103104041B publication Critical patent/CN103104041B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点,包括预制柱的梁上所设置的暗牛腿,暗牛腿上横向预留暗牛腿螺栓孔;预制梁端部连接处的前/后侧面上设有与暗牛腿配合的缺口槽,缺口槽为从预制梁竖向轴线开始向一侧挖去一个缺口,缺口和暗牛腿的截面形状相同,在缺口槽底部的对应位置上沿横向预留预制梁螺栓孔;暗牛腿沿横向的宽度是预制梁沿横向的宽度的一半,暗牛腿沿横向方向嵌固在预制梁的缺口槽内且嵌入后的结合体的前后两侧设有螺栓垫板,螺栓沿横向穿过螺栓垫板、暗牛腿螺栓孔、预制梁螺栓孔进行固定。相应的施工方法包括预制、安装、缝隙填浆。本发明使预制梁柱之间的内力传递明确,节点连接可靠,施工操作简单,加快了施工进度。

A prefabricated reinforced concrete frame beam-column joint connected by transverse bolts, including hidden corbels set on the beams of prefabricated columns, and hidden corbel bolt holes are reserved horizontally on the dark corbels; / There is a notch on the rear side to match with the hidden corbel. The notch is a notch dug from the vertical axis of the prefabricated beam to one side. The cross-sectional shape of the notch and the concealed corbel is the same. Bolt holes for prefabricated beams are reserved along the upper horizontal direction; the width of the concealed corbel along the transverse direction is half of the width of the prefabricated beam along the transverse direction, and the concealed corbel is embedded in the notch groove of the prefabricated beam along the transverse direction and the front and rear of the combination after being embedded There are bolt backing plates on both sides, and the bolts pass through the bolt backing plate, the bolt holes of the concealed corbel and the bolt holes of the prefabricated beam along the transverse direction for fixing. The corresponding construction methods include prefabrication, installation, and gap filling. The invention makes the transmission of internal force between the prefabricated beams and columns clear, the node connection is reliable, the construction operation is simple, and the construction progress is accelerated.

Description

一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点及施工方法A prefabricated reinforced concrete frame beam-column joint connected by transverse bolts and its construction method

技术领域 technical field

本发明涉及一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点及施工方法。 The invention relates to an assembled reinforced concrete frame beam-column node connected by transverse bolts and a construction method.

背景技术 Background technique

预制装配式钢筋混凝土框架结构可以提高机械化施工水平,加快施工进度,降低劳动强度,实现建筑工业化生产,而且有利于保护环境。这种结构体系已在发达国家得到了广泛应用,并已成为一些国家新建建筑的主要形式。连接方式是预制装配式钢筋混凝土结构的核心问题,也是结构的薄弱环节,只要预制构件的接合部位有可靠的连接,才能保证结构的安全可靠。 The prefabricated reinforced concrete frame structure can improve the level of mechanized construction, speed up the construction progress, reduce labor intensity, realize industrialized production of buildings, and help protect the environment. This structural system has been widely used in developed countries and has become the main form of new buildings in some countries. The connection method is the core issue of the prefabricated reinforced concrete structure, and it is also the weak link of the structure. Only when the joint parts of the prefabricated components are reliably connected can the safety and reliability of the structure be guaranteed.

我国现有的装配式钢筋混凝土框架节点连接可靠性差,难以满足结构抗裂和整体性、抗震性能等方面的要求,这就需要开发新的便于整体性连接的干式节点,以加快我国建筑工业化生产的进程。新型的装配式钢筋混凝土框架连接技术需要可靠的连接质量来实现按设计要求传递规定的内力,并保证整体结构安全性、整体性的要求;然后尽量简化连接构造和施工工艺,降低施工中不确定性对结构性能的影响,以提高节点连接的施工效率;最后装配式节点不会引起使用和观感上的问题。 The connection reliability of the existing prefabricated reinforced concrete frame joints in my country is poor, and it is difficult to meet the requirements of structural crack resistance, integrity, and seismic performance. production process. The new prefabricated reinforced concrete frame connection technology requires reliable connection quality to achieve the specified internal force transmission according to the design requirements, and to ensure the safety and integrity of the overall structure; then try to simplify the connection structure and construction process to reduce construction uncertainty In order to improve the construction efficiency of node connection, the influence of sex on structural performance; finally, the prefabricated node will not cause problems in use and perception.

发明内容 Contents of the invention

本发明提供一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点及施工方法,使预制梁柱之间的内力传递明确,节点连接可靠;节点施工操作简单,加快了施工进度,能够有效地提高生产效率;节点连接后不占用多余的建筑空间、保持了建筑室内的美观。 The invention provides an assembled reinforced concrete frame beam-column node connected by transverse bolts and a construction method, which makes the internal force transmission between the prefabricated beams and columns clear and the node connection is reliable; the node construction operation is simple, the construction progress is accelerated, and the production can be effectively improved Efficiency; After the nodes are connected, no extra building space is occupied, and the beauty of the building interior is maintained.

为了解决上述技术问题,本发明采用如下技术方案:一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点,包括预制柱的悬臂梁上所设置的暗牛腿,暗牛腿上横向预留暗牛腿螺栓孔;预制梁端部连接处的前/后侧面上设有与暗牛腿配合的缺口槽,所述缺口槽为从预制梁竖向轴线开始向一侧挖去一个缺口,缺口和暗牛腿的截面形状相同,在缺口槽底部的对应位置上沿横向预留预制梁螺栓孔;暗牛腿沿横向的宽度是预制梁沿横向的宽度的一半,暗牛腿沿横向方向嵌固在预制梁的缺口槽内且嵌入后的结合体的前后两侧设有螺栓垫板,螺栓沿横向穿过螺栓垫板、暗牛腿螺栓孔、预制梁螺栓孔进行固定。 In order to solve the above-mentioned technical problems, the present invention adopts the following technical scheme: an assembled reinforced concrete frame beam-column node connected by transverse bolts, including the concealed corbel set on the cantilever beam of the prefabricated column, and the transverse reserve on the concealed corbel Hidden corbel bolt hole; the front/rear side of the prefabricated beam end connection is provided with a notch matching with the dark corbel, the notch is a gap dug from the vertical axis of the prefabricated beam to one side, the notch The cross-sectional shape of the concealed corbel is the same as that of the prefabricated beam bolt holes along the transverse direction at the corresponding position at the bottom of the notch; the transverse width of the concealed corbel is half of the transverse width of the prefabricated beam, and The combination fixed in the notch groove of the prefabricated beam and embedded is provided with bolt backing plates on the front and rear sides, and the bolts pass through the bolt backing plate, the concealed corbel bolt holes and the prefabricated beam bolt holes in the transverse direction for fixing.

暗牛腿横截面为矩形或梯形。 The cross section of the dark corbel is rectangular or trapezoidal.

预制梁端部的缺口槽四周与暗牛腿截面四周设置倒角构造。 Chamfering structures are provided around the notch groove at the end of the prefabricated beam and around the section of the concealed corbel.

在相互嵌固的暗牛腿和预制梁之间设有结合层,结合层为细石混凝土或水泥砂浆。 A bonding layer is provided between the concealed corbels embedded in each other and the prefabricated beams, and the bonding layer is fine stone concrete or cement mortar.

外露的螺栓和螺栓垫板用防锈涂料封盖。 Exposed bolts and bolt backers are capped with anti-rust paint.

一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点的施工方法,具体步骤如下: A construction method for a fabricated reinforced concrete frame beam-column joint connected by transverse bolts, the specific steps are as follows:

(1)根据建筑结构等级、荷载、跨径、层高设计参数进行装配式钢筋混凝土框架结构分析,确定预制梁和预制柱的截面尺寸、钢筋用量;根据节点处抗剪设计要求计算确定预制梁缺口槽处梁内部的配筋数量;暗牛腿是短悬臂结构;根据节点受力确定螺栓数量、布置形式和螺栓垫板尺寸,螺栓采用普通螺栓或摩擦型高强螺栓; (1) Analyze the prefabricated reinforced concrete frame structure according to the design parameters of building structure grade, load, span, and storey height, and determine the cross-sectional dimensions and steel bar consumption of prefabricated beams and prefabricated columns; calculate and determine the prefabricated beams according to the shear design requirements at nodes The number of reinforcements inside the beam at the notch groove; the hidden corbel is a short cantilever structure; the number of bolts, the layout form and the size of the bolt backing plate are determined according to the force of the node, and the bolts are ordinary bolts or friction-type high-strength bolts;

(2)预制装配式钢筋混凝土的预制柱与预制梁:按设计要求在预制厂预制预制梁和带暗牛腿的预制柱,其中预制柱的暗牛腿的一侧边与预制梁竖向轴线平齐,仅保留预制梁竖向轴线一侧的暗牛腿部分,在暗牛腿内预留横穿暗牛腿的暗牛腿螺栓孔;预制梁的梁端做成相应的缺口槽,即从预制梁竖向轴线开始向一侧挖去一个缺口槽,缺口槽与暗牛腿的截面形状完全相同,在缺口槽底部对应位置也横向预留相同数量的预制梁螺栓孔;按照传统的梁柱预制方法进行预制,仅对预制梁端部侧模进行相应调整,待模板支护完后,精确定位预制梁螺栓孔位置,并埋设螺栓孔管道,随后浇筑混凝土、养护,预制完成; (2) Prefabricated columns and prefabricated beams of prefabricated reinforced concrete: prefabricated prefabricated beams and prefabricated columns with hidden corbels in the prefabricated factory according to the design requirements, wherein one side of the hidden corbels of the prefabricated columns is in line with the vertical axis of the prefabricated beams flush, only retain the hidden corbel part on one side of the vertical axis of the prefabricated beam, and reserve the hidden corbel bolt holes crossing the dark corbel in the dark corbel; the beam end of the prefabricated beam is made into a corresponding notch, that is Dig a notch from the vertical axis of the prefabricated beam to one side, the notch and the corbel have exactly the same cross-sectional shape, and the same number of prefabricated beam bolt holes are reserved horizontally at the corresponding position at the bottom of the notch; according to the traditional beam The column prefabrication method is prefabricated, and only the side formwork at the end of the prefabricated beam is adjusted accordingly. After the formwork is supported, the position of the bolt hole of the prefabricated beam is accurately positioned, and the bolt hole pipe is buried, and then the concrete is poured and maintained, and the prefabrication is completed;

(3)装配式钢筋混凝土的预制梁与预制柱采用横向螺栓节点安装:将预制完成的钢筋混凝土的预制梁、预制柱运输到建设场地,先安装带暗牛腿的预制柱,安装就位后,然后将预制梁吊装到与暗牛腿同一水平面后,在预制梁的缺口槽内均匀铺设一层结合层,结合层为细石混凝土或水泥砂浆,以增强暗牛腿和预制梁的结合度,随后缓慢横向移动预制梁梁体,使梁端缺口槽包裹暗牛腿,实现二者结合,安装误差应满足允许误差;梁端缺口槽与暗牛腿的周边设置倒角构造防止节点应力集中;最后,调整预制梁位置使暗牛腿内预留的暗牛腿螺栓孔与预制梁缺口槽处剩余梁体内预留的预制梁螺栓孔水平对齐,然后安装螺栓垫板,穿设螺栓,随后将螺母拧紧,即将预制梁与暗牛腿连接成整体; (3) Prefabricated reinforced concrete prefabricated beams and prefabricated columns are installed with transverse bolt joints: transport the prefabricated reinforced concrete prefabricated beams and prefabricated columns to the construction site, first install the prefabricated columns with concealed corbels, and install them in place , then hoist the prefabricated beam to the same level as the concealed corbel, and evenly lay a layer of bonding layer in the notch groove of the prefabricated beam, the bonding layer is fine stone concrete or cement mortar, so as to enhance the bonding degree of the concealed corbel and the prefabricated beam , and then slowly move the prefabricated beam body laterally so that the notch groove at the beam end wraps the hidden corbel to realize the combination of the two, and the installation error should meet the allowable error; the chamfering structure is set around the notch groove at the beam end and the dark corbel to prevent the stress concentration of the joints ;Finally, adjust the position of the prefabricated beam so that the bolt holes reserved in the concealed corbel are horizontally aligned with the reserved prefabricated beam bolt holes in the remaining beam body at the notch of the prefabricated beam, then install the bolt backing plate, pass the bolts, and then Tighten the nuts to connect the prefabricated beams with the concealed corbels as a whole;

(4)装配式钢筋混凝土预制梁与预制柱采用横向螺栓连接节点安装后续工作:待预制梁与暗牛腿连接成整体后,将预制梁梁端缺口槽与暗牛腿之间的缝隙用水泥砂浆填满,并将所有外露螺栓、螺母和螺栓垫板用防锈涂料封盖。 (4) Prefabricated reinforced concrete prefabricated beams and prefabricated columns are connected by transverse bolts. Follow-up installation work: After the prefabricated beams and concealed corbels are connected as a whole, the gap between the notch groove at the end of the prefabricated beam beam and the concealed corbel is filled with cement Mortar fill and cover all exposed bolts, nuts and bolt backers with anti-rust paint.

本发明节点强度可靠,预制柱的暗牛腿与相应预制梁端部的缺口组成卯榫结构,并采用横向穿螺栓连接成整体等构造措施解决了预制梁柱之间的平顺竖向传力问题,安装后结构立即能够承受荷载。同时预制柱带有一定长度的梁,梁与柱不在梁柱节点核心区域上进行装配式连接,而是在节点位置外的梁上进行装配连接体现强节点弱构件、强柱弱梁原则,保证了梁柱节点的整体性。 The joint strength of the present invention is reliable, the concealed corbel of the prefabricated column and the gap at the end of the corresponding prefabricated beam form a mortise and tenon structure, and the structural measures such as connecting the bolts horizontally to form a whole solve the problem of smooth vertical force transmission between the prefabricated beams and columns. Immediately after the structure is able to bear the load. At the same time, the prefabricated columns have beams of a certain length, and the beams and columns are not assembled in the core area of the beam-column joints, but are assembled and connected on the beams outside the joint positions, reflecting the principles of strong joints and weak components, strong columns and weak beams, ensuring Integrity of beam-column joints.

本发明具体的有益效果为: Concrete beneficial effects of the present invention are:

1.采用矩形(或梯形)暗牛腿与预制梁缺口槽的相互嵌固,再用螺栓将二者连接成整体,使预制梁柱之间传力明确,节点连接安全可靠; 1. Rectangular (or trapezoidal) hidden corbels and prefabricated beam notch grooves are embedded into each other, and then the two are connected into a whole with bolts, so that the force transmission between prefabricated beams and columns is clear, and the node connection is safe and reliable;

2.该螺栓连接节点构造简单,施工操作简单,加快了施工进度,能够有效地提高生产效率; 2. The bolt connection node has simple structure and simple construction operation, which speeds up the construction progress and can effectively improve production efficiency;

3.设置暗牛腿嵌固在预制梁缺口槽内的形式,不占用建筑空间,也不影响结构使用和美观; 3. Set the form that the hidden corbel is embedded in the notch groove of the prefabricated beam, which does not occupy the building space and does not affect the use and appearance of the structure;

4.该节点适用于不同跨径的多层或高层装配式钢筋混凝土框架结构。 4. This node is suitable for multi-storey or high-rise prefabricated reinforced concrete frame structures with different spans.

附图说明 Description of drawings

图1为本发明的结构示意图; Fig. 1 is a structural representation of the present invention;

图2为图1的A-A剖面图; Fig. 2 is the A-A sectional view of Fig. 1;

图3为带暗牛腿的预制柱的正立面图; Fig. 3 is the front elevation view of the prefabricated column with dark corbels;

图4为图3的侧立面图; Fig. 4 is a side elevation view of Fig. 3;

图5为预制梁正立面图; Figure 5 is a front elevation view of the prefabricated beam;

图6为图5的B-B剖面图。 Fig. 6 is a B-B sectional view of Fig. 5 .

具体实施方式 Detailed ways

实施例:如图1-6所示,一种采用横向螺栓连接的装配式钢筋混凝土框架梁柱节点,包括预制柱1的悬臂梁上所设置的暗牛腿2,暗牛腿2横截面为矩形或梯形,暗牛腿2上横向预留暗牛腿螺栓孔9;预制梁3端部连接处的前/后侧面上设有与暗牛腿2配合的缺口槽6,所述缺口槽6为从预制梁3竖向轴线开始向一侧挖去一个缺口,缺口和暗牛腿2的截面形状相同,缺口尺寸略大于暗牛腿,以方便二者嵌固,在缺口槽6底部的对应位置上沿横向预留预制梁螺栓孔10;暗牛腿2沿横向的宽度是预制梁3沿横向的宽度的一半,暗牛腿2沿横向方向嵌固在预制梁3的缺口槽6内且嵌入后的结合体的前后两侧设有螺栓垫板4,螺栓5沿横向穿过螺栓垫板4、暗牛腿螺栓孔9、预制梁螺栓孔10通过螺母8进行固定,使牛腿2与预制梁3连成整体,可传递梁端竖向剪力和弯矩。预制梁3端部的缺口槽6四周与暗牛腿2截面四周设置倒角构造,避免接头部分受力时发生应力集中。在相互嵌固的暗牛腿2和预制梁3之间设有结合层7,结合层7为细石混凝土或水泥砂浆,使暗牛腿2与预制梁3结合更紧密。外露的螺栓5、螺母8和螺栓垫板4用防锈涂料封盖。 Embodiment: As shown in Figures 1-6, a prefabricated reinforced concrete frame beam-column node connected by transverse bolts includes a concealed corbel 2 set on the cantilever beam of the prefabricated column 1, and the cross section of the concealed corbel 2 is Rectangular or trapezoidal, concealed corbel bolt holes 9 are reserved horizontally on the concealed corbel 2; a notch 6 matching with the concealed corbel 2 is provided on the front/rear side of the prefabricated beam 3 end connection, and the notch 6 In order to dig a gap from the vertical axis of the prefabricated beam 3 to one side, the cross-sectional shape of the gap and the hidden corbel 2 is the same, and the size of the gap is slightly larger than the hidden corbel, so as to facilitate the embedding of the two. Prefabricated beam bolt holes 10 are reserved in the transverse direction; the width of the dark corbel 2 along the transverse direction is half of the width of the prefabricated beam 3 along the transverse direction, and the dark corbel 2 is embedded in the notch groove 6 of the prefabricated beam 3 along the transverse direction and Bolt backing plates 4 are provided on the front and rear sides of the embedded combination, and bolts 5 pass through the bolt backing plate 4, the concealed corbel bolt holes 9, and the prefabricated beam bolt holes 10 through nuts 8 to fix the corbel 2 and the The prefabricated beams 3 are connected as a whole, which can transmit the vertical shear force and bending moment at the beam ends. Chamfering structures are provided around the notch groove 6 at the end of the prefabricated beam 3 and the section around the concealed corbel 2 to avoid stress concentration when the joint is stressed. A bonding layer 7 is provided between the concealed corbels 2 and the prefabricated beams 3 embedded in each other, and the bonding layer 7 is fine stone concrete or cement mortar, so that the concealed corbels 2 and the prefabricated beams 3 are combined more tightly. Exposed bolts 5, nuts 8 and bolt backing plates 4 are sealed with antirust paint.

预制梁螺栓孔10和暗牛腿螺栓孔9的螺栓孔位置要定位精确,以保证二者结合后,螺栓孔左右对齐,方便顺利穿螺栓。在运输和吊装预制构件过程中需注意保护螺栓孔,避免孔内受损或开裂。螺栓可采用普通螺栓或摩擦型高强螺栓,根据受力要求确定螺栓数量、布置形式和垫板尺寸。暗牛腿2是短悬臂结构,受力较为复杂,应进行纵向受力筋的配筋设计,并在全长度范围内加密箍筋。 The positions of the bolt holes of the prefabricated beam bolt holes 10 and the concealed corbel bolt holes 9 should be accurately positioned to ensure that after the two are combined, the bolt holes are aligned left and right, so that the bolts can be threaded smoothly. During the transportation and hoisting of prefabricated components, care should be taken to protect the bolt holes to avoid damage or cracking in the holes. Bolts can be ordinary bolts or friction-type high-strength bolts, and the number, layout and size of the backing plate are determined according to the force requirements. Concealed corbel 2 is a short cantilever structure, and the force is relatively complicated. The longitudinal reinforcement design should be carried out, and the stirrups should be thickened throughout the entire length.

将预制梁3吊装至与暗牛腿2同一高程,使暗牛腿2横向嵌固在预制梁3的缺口槽6内,并保证暗牛腿2内预留的暗牛腿螺栓孔9与预制梁3内预留的预制梁螺栓孔10左右对齐,然后安装螺栓垫板4,穿螺栓5,随后将螺母8拧紧,使暗牛腿2与预制梁3连成整体,随后即可承受荷载。 Hoist the prefabricated beam 3 to the same elevation as the concealed corbel 2, so that the concealed corbel 2 is horizontally embedded in the notch 6 of the prefabricated beam 3, and ensure that the concealed corbel bolt holes 9 reserved in the concealed corbel 2 are in line with the prefabricated The bolt holes 10 reserved in the beam 3 are aligned left and right, then the bolt backing plate 4 is installed, the bolt 5 is threaded, and then the nut 8 is tightened, so that the concealed corbel 2 and the prefabricated beam 3 are connected as a whole, and then the load can be carried.

一种横向连接的装配式钢筋混凝土框架梁柱节点的施工方法,具体步骤如下: A construction method of a laterally connected assembled reinforced concrete frame beam-column joint, the specific steps are as follows:

(1)根据建筑结构等级、荷载、跨径、层高设计参数进行装配式钢筋混凝土框架结构分析,确定预制梁3和预制柱1的截面尺寸、钢筋用量;根据节点处抗剪设计要求计算确定预制梁3缺口槽6处梁内部的配筋数量;暗牛腿2是短悬臂结构;根据节点受力确定螺栓5数量、布置形式和螺栓垫板4尺寸,螺栓5采用普通螺栓或摩擦型高强螺栓; (1) Analyze the prefabricated reinforced concrete frame structure according to the design parameters of building structure grade, load, span, and storey height, and determine the cross-sectional size and steel bar consumption of prefabricated beam 3 and prefabricated column 1; calculate and determine according to the shear design requirements at nodes The number of reinforcements inside the beam at the 6 notch slots of the prefabricated beam 3; the hidden corbel 2 is a short cantilever structure; the number and arrangement of bolts 5 and the size of the bolt backing plate 4 are determined according to the force of the nodes, and the bolts 5 are ordinary bolts or friction-type high-strength bolts bolt;

(2)预制装配式钢筋混凝土的预制柱与预制梁:按设计要求在预制厂预制预制梁3和带暗牛腿2的预制柱1,其中预制柱1的暗牛腿2的一侧边与预制梁3竖向轴线平齐,仅保留预制梁3竖向轴线一侧的暗牛腿2部分,在暗牛腿2内预留横穿暗牛腿2的暗牛腿螺栓孔9;预制梁3的梁端做成相应的缺口槽6,即从预制梁3竖向轴线开始向一侧挖去一个缺口槽6,缺口槽6与暗牛腿2的截面形状完全相同,其横截面尺寸比暗牛腿2略大,以方便二者装配,在缺口槽6底部对应位置也横向预留相同数量的预制梁螺栓孔10;按照传统的梁柱预制方法进行预制,仅对预制梁3端部侧模进行相应调整,待模板支护完后,精确定位预制梁螺栓孔10位置,并埋设螺栓孔管道,随后浇筑混凝土、养护,预制完成; (2) Prefabricated columns and prefabricated beams of prefabricated reinforced concrete: prefabricated prefabricated beams 3 and prefabricated columns 1 with hidden corbels 2 in the prefabricated factory according to the design requirements, wherein one side of the hidden corbels 2 of the prefabricated column 1 is connected to The vertical axis of the prefabricated beam 3 is even, and only the concealed corbel 2 part on one side of the vertical axis of the prefabricated beam 3 is reserved, and the concealed corbel bolt hole 9 crossing the concealed corbel 2 is reserved in the concealed corbel 2; the prefabricated beam The beam end of 3 is made into a corresponding notch 6, that is, a notch 6 is dug from the vertical axis of the prefabricated beam 3 to one side. The concealed corbel 2 is slightly larger to facilitate the assembly of the two, and the same number of prefabricated beam bolt holes 10 are reserved horizontally at the corresponding position at the bottom of the notch groove 6; prefabrication is carried out according to the traditional beam and column prefabrication method, and only the end of the prefabricated beam 3 is prefabricated. Adjust the side formwork accordingly. After the formwork is supported, accurately locate the position of the bolt hole 10 of the prefabricated beam, and bury the bolt hole pipe, then pour concrete and maintain it, and the prefabrication is completed;

(3)装配式钢筋混凝土的预制梁与预制柱采用横向螺栓节点安装:将预制完成的钢筋混凝土的预制梁3、预制柱1运输到建设场地,先安装带暗牛腿2的预制柱1,安装就位后,然后将预制梁3吊装到与暗牛腿2同一水平面后,在预制梁3的缺口槽6内均匀铺设一层结合层7,结合层为细石混凝土或水泥砂浆,以增强暗牛腿2和预制梁3的结合度,随后缓慢横向移动预制梁3梁体,使梁端缺口槽6包裹暗牛腿2,实现二者结合,安装误差应满足允许误差;梁端缺口槽6与暗牛腿2的周边设置倒角构造防止节点应力集中;最后,调整预制梁3位置使暗牛腿内预留的暗牛腿螺栓孔9与预制梁3缺口槽6处剩余梁体内预留的预制梁螺栓孔10水平对齐,然后安装螺栓垫板4,穿设螺栓5,随后将螺母8拧紧,即将预制梁3与暗牛腿2连接成整体; (3) Prefabricated reinforced concrete prefabricated beams and prefabricated columns are installed with transverse bolt joints: transport the prefabricated reinforced concrete prefabricated beams 3 and prefabricated columns 1 to the construction site, and install the prefabricated columns 1 with concealed corbels 2 first, After the installation is in place, after the prefabricated beam 3 is hoisted to the same level as the dark corbel 2, a bonding layer 7 is evenly laid in the notch groove 6 of the prefabricated beam 3. The bonding layer is fine stone concrete or cement mortar to strengthen The combination degree of the hidden corbel 2 and the prefabricated beam 3, and then slowly move the prefabricated beam 3 beam body laterally, so that the beam end notch 6 wraps the concealed corbel 2 to realize the combination of the two, and the installation error should meet the allowable error; the beam end notch groove 6 and the surroundings of the hidden corbel 2 are provided with chamfering structures to prevent joint stress concentration; finally, the position of the prefabricated beam 3 is adjusted so that the reserved hidden corbel bolt holes 9 in the hidden corbel 2 are prefabricated Align the remaining prefabricated beam bolt holes 10 horizontally, then install the bolt backing plate 4, pass through the bolt 5, and then tighten the nut 8, that is, the prefabricated beam 3 and the dark corbel 2 are connected as a whole;

(4)装配式钢筋混凝土预制梁与预制柱采用横向螺栓连接节点安装后续工作:待预制梁3与暗牛腿2连接成整体后,将预制梁3梁端缺口槽6与暗牛腿2之间的缝隙用水泥砂浆填满,并将所有外露螺栓5、螺母8和螺栓垫板4用防锈涂料封盖。 (4) The assembled reinforced concrete prefabricated beam and the prefabricated column are connected by transverse bolts. Follow-up work: after the prefabricated beam 3 and the concealed corbel 2 are connected as a whole, the notch groove 6 at the beam end of the prefabricated beam 3 and the concealed corbel 2 are connected. Fill the gaps between them with cement mortar, and seal all exposed bolts 5, nuts 8 and bolt backing plates 4 with antirust paint.

本发明适用于多层或高层装配式钢筋混凝土框架结构,也适用于不同跨径的装配式钢筋混凝土框架结构。 The invention is applicable to multi-layer or high-rise assembled reinforced concrete frame structures, and is also suitable for assembled reinforced concrete frame structures with different spans.

采用将预制柱的暗牛腿与相应预制梁端部的缺口组成卯榫结构,并采用横向穿螺栓连接成整体等构造措施,使预制梁柱之间的内力传递明确,节点连接可靠;该节点施工操作简单,加快了施工进度,能够有效地提高生产效率。节点连接后不占用多余的建筑空间、保持了建筑室内的美观。 The concealed corbels of the prefabricated columns and the gaps at the ends of the corresponding prefabricated beams are used to form a mortise and tenon structure, and the transverse bolts are used to connect them into a whole, so that the internal force transmission between the prefabricated beams and columns is clear and the joint connection is reliable; the construction operation of this joint It is simple, speeds up the construction progress, and can effectively improve production efficiency. After the nodes are connected, it does not take up extra building space and maintains the beauty of the building interior.

Claims (6)

1. the assembled steel reinforced concrete frame bean column node adopting cross bolts to connect, is characterized in that: comprise hidden bracket set on the semi girder of prefabricated post, hidden bracket laterally reserves hidden bracket bolt hole; The front/rear side of junction, precast beam end is provided with the gap slot coordinated with hidden bracket, described gap slot for cut out a breach from precast beam vertical axis to side, breach is identical with the cross sectional shape of hidden bracket, and the correspondence position bottom gap slot transversely reserves precast beam bolt hole; Hidden bracket width is transversely the half of precast beam width transversely, hidden bracket transversely direction be mounted in precast beam gap slot in and the both sides, front and back of combination after embedding are provided with bolt backing plate, bolt is transversely fixed through bolt backing plate, hidden bracket bolt hole, precast beam bolt hole.
2. the assembled steel reinforced concrete frame bean column node of employing cross bolts connection according to claim 1, is characterized in that: hidden bracket cross section is rectangle or trapezoidal.
3. the assembled steel reinforced concrete frame bean column node of employing cross bolts connection according to claim 2, is characterized in that: gap slot surrounding and the hidden bracket cross section surrounding of precast beam end arrange chamfer configuration.
4. the assembled steel reinforced concrete frame bean column node of employing cross bolts connection according to claim 3, it is characterized in that: between the hidden bracket and precast beam of mutual build-in, be provided with setting course, setting course is pea gravel concreten or cement mortar.
5. the assembled steel reinforced concrete frame bean column node of employing cross bolts connection according to claim 4, is characterized in that: the bolt exposed, the capping of nuts and bolt backing plate antirusting paint.
6. a construction method for the assembled steel reinforced concrete frame bean column node adopting cross bolts to connect, concrete steps are as follows:
(1) according to building structure grade, load, carry out the analysis of assembled steel tendon concrete frame structure across footpath, storey height design parameter, the sectional dimension of precast beam and prefabricated post, amount of reinforcement is determined; Require according to Nodes shear Design to calculate the arrangement of reinforcement quantity determining beam inside, precast beam gap slot place; Hidden bracket is short cantilever construction; According to joints determination bolt quantity, arrangement form and bolting pad board size, bolt adopts plain bolt or frictional high-strength bolts;
(2) prefabricated post of prefabricated assembling type reinforced concrete and precast beam: by designing requirement in the prefabricated precast beam of precast yard and the prefabricated post being with hidden bracket, wherein a side of the hidden bracket of prefabricated post is concordant with precast beam vertical axis, only retain the hidden bracket part of precast beam vertical axis side, the reserved hidden bracket bolt hole crossing hidden bracket in hidden bracket; The beam-ends of precast beam makes corresponding gap slot, and namely from precast beam vertical axis, cut out a gap slot to side, gap slot is identical with the cross sectional shape of hidden bracket, and bottom gap slot, correspondence position also laterally reserves the precast beam bolt hole of equal number; Beam column method for prefabricating traditionally carries out prefabricated, only adjusts accordingly precast beam end side form, and after template support is complete, accurately precast beam bolt hole position, location, and bury bolt hole pipeline underground, concreting, maintenance subsequently, prefabricatedly completes;
(3) assembled steel reinforced concrete precast beam and prefabricated post adopt cross bolts node installation: by the precast beam of the prefabricated steel concrete completed, prefabricated post is transported to builds place, the prefabricated post of first mounting strap hidden bracket, after installation in position, then precast beam is lifted into hidden bracket same level after, evenly one deck setting course is laid in the gap slot of precast beam, setting course is pea gravel concreten or cement mortar, to strengthen the conjugation of hidden bracket and precast beam, slow transverse shifting Prefabricated bar body subsequently, beam-ends gap slot is made to wrap up hidden bracket, both realizations combine, alignment error should meet allowable error, the periphery of beam-ends gap slot and hidden bracket arranges chamfer configuration and prevents node stress from concentrating, finally, adjustment precast beam position makes hidden bracket bolt hole reserved in hidden bracket and precast beam gap slot place remain precast beam bolt hole horizontal alignment reserved in beam body, and then erection bolt backing plate, wears bolt, subsequently by nut screwing clamping, connect into entirety by precast beam and hidden bracket,
(4) assembled steel reinforced concrete prefabricated beam and prefabricated post adopt cross bolts connected node to install follow-up work: after precast beam and hidden bracket connect into entirety, gap cement mortar between prefabricated beam end gap slot and hidden bracket is filled up, and by all exerted bolts, the capping of nuts and bolt backing plate antirusting paint.
CN201310074280.6A 2013-03-08 2013-03-08 A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method Expired - Fee Related CN103104041B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310074280.6A CN103104041B (en) 2013-03-08 2013-03-08 A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310074280.6A CN103104041B (en) 2013-03-08 2013-03-08 A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method

Publications (2)

Publication Number Publication Date
CN103104041A CN103104041A (en) 2013-05-15
CN103104041B true CN103104041B (en) 2015-09-30

Family

ID=48312212

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310074280.6A Expired - Fee Related CN103104041B (en) 2013-03-08 2013-03-08 A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method

Country Status (1)

Country Link
CN (1) CN103104041B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235638A (en) * 2018-10-23 2019-01-18 王虹 A kind of anti-seismic prefabricated bean column node and its construction method for assembled architecture

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603435B (en) * 2013-12-06 2015-11-04 金陵科技学院 A prefabricated concrete anti-seismic beam-column frame and its construction method
CN104032967B (en) * 2014-06-30 2016-06-29 龙信建设集团有限公司 Prefabricated assembled frame structure component construction method for hanging
CN106285015A (en) * 2015-05-28 2017-01-04 五冶集团上海有限公司 Steel structural roof beam method for rapidly mounting based on location-plate
CN105155773B (en) * 2015-08-18 2017-08-25 同济大学 A kind of removable concrete component construction method
CN105133726A (en) * 2015-09-25 2015-12-09 郑州大学 Assembled monolithic concrete frame structure system and frame shear structure system formed by assembled monolithic concrete frame structure system
CN105951985B (en) * 2016-06-17 2024-05-10 华东建筑设计研究院有限公司 Precast concrete frame beam node
CN106499054A (en) * 2016-11-30 2017-03-15 上海建工二建集团有限公司 Prefabricated assembled frame beam column structure and its construction method
CN107447920B (en) * 2017-09-06 2019-06-25 广东弘信建设有限公司 Assembled lintel
CN107558311A (en) * 2017-09-14 2018-01-09 中铁第四勘察设计院集团有限公司 A kind of lateral connection component for straddle type monorail rail tracks
CN109162354A (en) * 2018-10-25 2019-01-08 安徽建筑大学 Assembled connected node of two brackets
CN109098282A (en) * 2018-11-08 2018-12-28 安徽建筑大学 A kind of connecting node of assembly concrete frame beam column
CN109296076B (en) * 2018-12-04 2024-04-30 安徽建筑大学 Hidden type connecting node of beam column with assembled frame structure
CN109898653A (en) * 2019-03-30 2019-06-18 中国二十二冶集团有限公司 Box beam joint connection in site method
CN109881778B (en) * 2019-04-15 2024-05-14 上海应用技术大学 Prefabricated steel structure hidden bracket node and construction method thereof
CN110145023B (en) * 2019-06-25 2024-10-22 安徽建筑大学 Prefabricated assembled concrete rectangular beam column connection node
CN112942945A (en) * 2021-02-05 2021-06-11 绍兴文理学院 Assembled tenon fourth of twelve earthly branches bracket type beam column node connecting device
CN113699869A (en) * 2021-08-13 2021-11-26 浙江瓯越交建科技股份有限公司 Prefabricated bridge plate connecting structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004068569A (en) * 2002-08-08 2004-03-04 Yukio Adachi Super-strong/high yield-strength column
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN101113604A (en) * 2007-06-22 2008-01-30 东南大学 Fully prefabricated concrete frame structure
CN102086677A (en) * 2009-12-02 2011-06-08 张吉华 Prefabricated reinforced concrete beam and connection joint of reinforced concrete column and beam
JP2012149464A (en) * 2011-01-21 2012-08-09 Mikio Tashiro Rigid junction structure of modified column and beam of laminated lumber

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004068569A (en) * 2002-08-08 2004-03-04 Yukio Adachi Super-strong/high yield-strength column
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN101113604A (en) * 2007-06-22 2008-01-30 东南大学 Fully prefabricated concrete frame structure
CN102086677A (en) * 2009-12-02 2011-06-08 张吉华 Prefabricated reinforced concrete beam and connection joint of reinforced concrete column and beam
JP2012149464A (en) * 2011-01-21 2012-08-09 Mikio Tashiro Rigid junction structure of modified column and beam of laminated lumber

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235638A (en) * 2018-10-23 2019-01-18 王虹 A kind of anti-seismic prefabricated bean column node and its construction method for assembled architecture
CN109235638B (en) * 2018-10-23 2020-05-05 中贤建设集团有限公司 Anti-seismic prefabricated beam-column joint for prefabricated building and construction method thereof

Also Published As

Publication number Publication date
CN103104041A (en) 2013-05-15

Similar Documents

Publication Publication Date Title
CN103104041B (en) A kind of adopt cross bolts to connect assembled steel reinforced concrete frame bean column node and construction method
CN103104040B (en) A kind of assembling frame bean column node and construction method adopting vertical connection
CN103104039B (en) Assembled framework beam-column joint adopting cover plate connection and construction method thereof
CN108049498B (en) Prefabricated column and prefabricated beam connection structure and method of prefabricated building frame structure
CN105839846A (en) Prefabricated reinforced concrete composite beam
CN105484151B (en) The construction and its construction method connected between a kind of enhancing precast concrete segment
CN106968381B (en) Prefabricated precast shear wall and composite panel joints connected by combined grouting sleeves
CN107100290A (en) A kind of prefabricated shear wall and overlapping plate node
CN103104053A (en) Assembled concrete shear wall and construction method thereof
CN106836479A (en) A kind of prefabricated PC concrete frame structure
CN104594523A (en) Prestress splicing method for fabricated shear wall
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN203475598U (en) Shock-proof prefabricated building of steel bar truss shearing wall composite structure
CN205329526U (en) Pier is assembled to precast concrete
CN202559384U (en) Prefabricated assembled pipe-jacking working well
CN110565797B (en) Hidden corbel type beam-column joint connection method for shock absorption
CN102644296A (en) Prefabricate assembly type pipe jacking working well
CN104499568A (en) Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN111749365A (en) A prefabricated composite wall based on H-beam and its construction method
CN112627391A (en) Construction process of prefabricated double-steel-plate-concrete combined shear wall
CN212295166U (en) A prefabricated wall connection structure based on a ribbed box
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN108999281A (en) A kind of novel precast concrete bean column node and its construction method
CN206736696U (en) A kind of prefabricated assembled anchor bolts steel reinforced concrete combination beam
CN103603435A (en) Assembled concrete seismic beam-column frame and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150930

Termination date: 20160308

CF01 Termination of patent right due to non-payment of annual fee