CN107558311A CN201710829309.5A CN201710829309A CN107558311A CN 107558311 A CN107558311 A CN 107558311A CN 201710829309 A CN201710829309 A CN 201710829309A CN 107558311 A CN107558311 A CN 107558311A
Authority
CN
China
Prior art keywords
linkage section
interlude
connection component
lateral connection
track girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710829309.5A
Other languages
Chinese (zh)
Inventor
刘阳明
彭华春
文望青
耿杰
马明
李靖
余晓燕
洪沁烨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201710829309.5A priority Critical patent/CN107558311A/en
Publication of CN107558311A publication Critical patent/CN107558311A/en
Pending legal-status Critical Current

Links

Landscapes

  • Railway Tracks (AREA)

Abstract

The invention belongs to rail traffic bridge structure correlative technology field, and it discloses a kind of lateral connection component for straddle type monorail rail tracks, the lateral connection component is used to connect adjacent two panels track girder;The lateral connection component includes the first linkage section for being connected to track girder described in two panels and the second linkage section and both ends are removably attachable to the interlude of first linkage section and second linkage section respectively;First linkage section, second linkage section and the interlude are using made of armored concrete, first linkage section and second linkage section are synchronously prefabricated with track girder described in two panels respectively, and it is rear individually prefabricated that the interlude is that the track girder is installed in place.The lateral connection component overcomes the problem of late maintaining cost is high using the relatively low Reinforced Concrete Materials of cost;By the way of prefabricated and on-site consolidation, while ensure construction quality and efficiency of construction, and enhance the lateral stiffness of track girder.

Description

A kind of lateral connection component for straddle type monorail rail tracks
Technical field
The invention belongs to rail traffic bridge structure correlative technology field, is used for straddle-type list more particularly, to one kind The lateral connection component of rail track girder.
Background technology
Load-carrying members and out of shape track of the straddle-type monorail track as train, will not only meet specification on structure stress It is required that and to meet train driving requirement on linear.Track girder lateral dimension is limited general all smaller by vehicle, leads Cause the horizontal integral rigidity of track girder seemingly weaker.
At present, it is domestic to only have 2, No. 3 lines of Chongqing Light Rail that there is straddle-type monorail to run experience, do not have between track girder Using lateral connection component, as shown in figure 1, lateral ties are not provided between two panels track girder, the independent stress of track girder, track It is attached between beam and pier cap beam using pinner and bearing, causes that structure lateral stiffness is weaker, and road-ability is poor.State Outside, the straddle-type track girder on the ground such as Las Vegas, US, St. Paul,Brazil employs steel construction lateral connection component, such as Fig. 2 Shown, wherein steel construction is I-steel, and the both ends of the I-steel are respectively adopted high-strength bolt and are connected with two panels track girder, institute It is be hinged to state between I-steel and the track girder, but the I-steel is not almost contributed the rigidity of track girder, only conduct The supporting member of fire escape, and using I-steel as lateral connection component exist direct cost and later maintenance cost compared with The problem of high.Correspondingly, there is develop a kind of lateral connection for the rigidity that can increase straddle type monorail rail tracks for this area The technical need of component.
The content of the invention
The defects of for prior art, the invention provides a kind of lateral connection structure for straddle type monorail rail tracks Part, its work characteristics based on straddle type monorail rail tracks, study and devise a kind of horizontal stroke for straddle type monorail rail tracks To connecting elements.First linkage section, second linkage section and the interlude of the lateral connection component are adopted Made of armored concrete, the lateral connection component is made of the relatively low armored concrete of cost, reduces cost, and Overcome the defects of late maintaining cost is higher.In addition, first linkage section and second linkage section are connected to two Piece track girder, the both ends of the interlude are removably attachable to first linkage section and second linkage section respectively, On the premise of ensureing track girder and lateral connection component entirety stress, the lateral stiffness of track girder is improved, improves train row Comfortableness is sailed, and is advantageous to track girder later stage LFM signal, simple in construction, flexibility is higher.
To achieve the above object, the invention provides a kind of lateral connection component for straddle type monorail rail tracks, its For connecting adjacent two panels track girder;The lateral connection component includes being connected to the first company of track girder described in two panels Connect section and the second linkage section and both ends are removably attachable in first linkage section and second linkage section respectively Between section;
First linkage section, second linkage section and the interlude are used made of armored concrete, institute It is synchronously prefabricated with track girder described in two panels respectively to state the first linkage section and second linkage section, and the interlude is described Track girder is installed in place rear individually prefabricated.
Further, the size of the interlude be after the track girder is installed in place, according to first linkage section and What the measurement result of the locus of second linkage section determined.
Further, first linkage section is stepped, and, formed with opening, the opening is formed at described first and connected for it Section is connect towards the side of second linkage section.
Further, first linkage section offers the first bolt hole with the opening in communication, the interlude The position of corresponding first bolt hole offers the second bolt hole, and bolt is contained in first bolt hole and second spiral shell In keyhole, so that the interlude is connected with first linkage section.
Further, the structure of first linkage section is identical with the structure of second linkage section, second connection Section is identical with the connected mode between the interlude with the connected mode between the interlude and first linkage section.
Further, the shape at the both ends of the interlude and the size shape and size with first linkage section respectively It is corresponding with the shape and size of second linkage section, so that the both ends of the interlude and first linkage section and described Second linkage section is connected.
Further, first linkage section offers the 3rd bolt hole, the interlude adjacent to the position of the opening One end of neighbouring first linkage section offers the 4th bolt hole, and it is opposite that two steel plates are separately positioned on first linkage section Both sides, and two steel plates cover the junction between first linkage section and the interlude.
Further, high-strength bolt through two steel plates and its be partially housed in the 3rd bolt hole, by two The individual steel plate is connected with first linkage section;It is another have high-strength bolt through two steel plates and its be partially housed in institute The 4th bolt hole is stated, two steel plates are connected with the interlude, thus first linkage section and the centre Section is releasably coupled together.
Further, it is to use on-site consolidation between first linkage section and second linkage section and the interlude Mode be attached.
By the contemplated above technical scheme of the present invention, compared with prior art, provided by the present invention for straddle-type The lateral connection component of monorail track beam mainly has the advantages that:
1. first linkage section, second linkage section and the interlude are used made of armored concrete, The lateral connection component is made of the relatively low armored concrete of cost, reduces cost, and overcome late maintaining cost The defects of higher;
2. first linkage section and second linkage section are synchronously prefabricated with track girder described in two panels respectively, in described Between section to be that the track girder is installed in place rear individually prefabricated, and by the way of on-site consolidation, not only reduce cast-in-site Quantities, and ensure that the workmanship of lateral connection component, while substantially increase efficiency of construction;
3. first linkage section and second linkage section are connected to two panels track girder, the both ends of the interlude First linkage section and second linkage section are removably attachable to respectively, are ensureing that track girder and lateral connection component are whole On the premise of body stress, the lateral stiffness of track girder is improved, improves train driving comfortableness, and is advantageous to the track girder later stage LFM signal, simple in construction, flexibility is higher.
Brief description of the drawings
Fig. 1 is a kind of schematic cross-sectional view of existing straddle type monorail rail tracks;
Fig. 2 is the cross-sectional view of existing another straddle type monorail rail tracks;
Fig. 3 is the cross-section of the lateral connection component for straddle type monorail rail tracks that first embodiment of the invention provides Face schematic diagram;
Fig. 4 is the cross-section of the lateral connection component for straddle type monorail rail tracks that second embodiment of the invention provides Face schematic diagram;
Fig. 5 is the schematic diagram of the lateral connection component for straddle type monorail rail tracks in Fig. 4.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
Referring to Fig. 3, the lateral connection component for straddle type monorail rail tracks that first embodiment of the invention provides, The lateral connection component is used to connect adjacent two panels track girder, and to strengthen the lateral stiffness of track girder, it is comfortable to improve driving Property, while the possibility of reserved track beam later stage LFM signal and flexibility.In addition, the lateral connection component is to straddle-type list The characteristics of rail traffic, is with very strong specific aim and adaptability;Heat of three, the four line cities of the country to cross-saddle single-track traffic at present Feelings are very high, and cross-saddle single-track traffic is being planned and built in multiple cities all, and market potential is huge, the first embodiment party of the same present invention The lateral connection component for straddle type monorail rail tracks that formula provides also has broad application prospects.
The lateral connection component includes the first linkage section, the second linkage section and interlude, the both ends point of the interlude First linkage section and second linkage section are not connected, and fixation connects respectively for first linkage section and second linkage section It is connected to two panels track girder.First linkage section and second linkage section are the synchronously prefabricated mixed with track girder of sign in scheming Solidifying soil section, the interlude are the interior later stage concrete soil section indicated of figure.
First linkage section, second linkage section and the interlude are used made of armored concrete, its Described in the first linkage section and second linkage section it is synchronously prefabricated with two panels track girder respectively, relative to steel construction, using mixed Lateral connection component made of solidifying soil is more easy to conserve, and the later stage does not have to maintenance substantially, reduces cost, and with preferably overall Property, improve the lateral stiffness of track girder.In present embodiment, first linkage section and second linkage section are respectively with two Piece track girder is structure as a whole.
The size of the interlude is after the track girder is installed in place, and is connected according to first linkage section and described second The measurement result of the locus of section is connect to determine, and the interlude be it is prefabricated after carry out it is field erected.
First linkage section is stepped, and it is formed at the first linkage section direction formed with opening, the opening The side of second linkage section.In present embodiment, first linkage section is along perpendicular to the track girder length direction Length is 50 centimetres, and its height along the track girder short transverse is 30 centimetres;The opening is along perpendicular to the track girder The length of length direction is 10 centimetres, and its depth along the track girder short transverse is 15 centimetres;First linkage section is opened Provided with the first bolt hole with the opening in communication, the position that the interlude corresponds to first bolt hole offers second Bolt hole, it is engaged by bolt with first bolt hole and second bolt hole to make the interlude and described first Linkage section is connected.
The structure of first linkage section is identical with the structure of second linkage section, the shape at the both ends of the interlude And size is corresponding with the shape and size of first linkage section and the shape and size of second linkage section respectively, so that The both ends of the interlude are connected with first linkage section and second linkage section.
Refer to Fig. 4 and Fig. 5, the lateral connection for straddle type monorail rail tracks that second embodiment of the invention provides Component, the transverse connection include the first linkage section, the second linkage section and interlude, the both ends activity respectively of the interlude Be connected to first linkage section and second linkage section.First linkage section and second linkage section are fixed respectively It is connected to two panels track girder.
First linkage section, second linkage section and the interlude are used made of armored concrete, its Described in the first linkage section and second linkage section it is synchronously prefabricated with two panels track girder respectively, relative to steel construction, using mixed Lateral connection component made of solidifying soil is more easy to conserve, and the later stage does not have to maintenance substantially, reduces cost, and with preferably overall Property, improve the lateral stiffness of track girder.In present embodiment, first linkage section and second linkage section are respectively with two Piece track girder is structure as a whole.
The size of the interlude is after the track girder is installed in place, and is connected according to first linkage section and described second The measurement result of the locus of section is connect to determine, and the interlude be it is prefabricated after installed.
First linkage section is stepped, and it is formed at the first linkage section direction formed with opening, the opening The side of second linkage section.The structure of first linkage section is identical with the structure of second linkage section, the centre Section both ends shape and size respectively with the shape and size of first linkage section and the shape of second linkage section and Size is corresponding, so that the both ends of the interlude are connected with first linkage section and second linkage section.
First linkage section offers the 3rd bolt hole adjacent to the position of the opening, and the interlude is adjacent to described One end of one linkage section offers the 4th bolt hole, and two steel plates are respectively arranged at the opposite both sides of first linkage section, and Two steel plates cover the junction between first linkage section and the interlude.Wear successively one end of high-strength bolt One in two steel plates, another in the 3rd bolt hole and two steel plates are crossed, by two steel Plate is connected with first linkage section;Separately there is high-strength bolt to sequentially pass through one in two steel plates, the 4th spiral shell Another in keyhole and two steel plates, two steel plates is connected with the interlude, thus by described One linkage section is connected with the interlude.Second linkage section is connected with the interlude in the same way.
In present embodiment, the quantity of the 3rd bolt hole and the quantity of the 4th bolt hole are two, two 3rd bolt hole is arranged at intervals, and two the 4th bolts hole are also arranged at intervals;It is appreciated that in other embodiment In, the quantity of the 3rd bolt hole and the quantity of the 4th bolt hole can increase or reduce according to being actually needed.
Provided by the present invention for the lateral connection component of straddle type monorail rail tracks, the lateral connection component it is described First linkage section, second linkage section and the interlude are used made of armored concrete, the lateral connection structure Part is made of the relatively low armored concrete of cost, reduces cost, and overcome the defects of late maintaining cost is higher.This Outside, first linkage section and second linkage section are connected to two panels track girder, and the both ends of the interlude respectively can First linkage section and second linkage section are releasably connected to, is ensureing track girder and lateral connection component entirety stress On the premise of, the lateral stiffness of track girder is improved, improves train driving comfortableness, and is advantageous to track girder later stage linear tune Whole, simple in construction, flexibility is higher.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, not to The limitation present invention, all any modification, equivalent and improvement made within the spirit and principles of the invention etc., all should be included Within protection scope of the present invention.

Claims (9)

1. a kind of lateral connection component for straddle type monorail rail tracks, it is used to connect adjacent two panels track girder, and it is special Sign is:
The lateral connection component include be connected to track girder described in two panels the first linkage section and the second linkage section and Both ends are removably attachable to the interlude of first linkage section and second linkage section respectively;
First linkage section, second linkage section and the interlude are using made of armored concrete described the One linkage section and second linkage section are synchronously prefabricated with track girder described in two panels respectively, and the interlude is the track Beam is installed in place rear individually prefabricated.
2. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 1, it is characterised in that:The centre The size of section is that the track girder is installed in place afterwards, according to the locus of first linkage section and second linkage section What measurement result determined.
3. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 1, it is characterised in that:Described first Linkage section is stepped, and it is formed at first linkage section towards second linkage section formed with opening, the opening Side.
4. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 3, it is characterised in that:Described first Linkage section offers the first bolt hole with the opening in communication, and the position that the interlude corresponds to first bolt hole is opened Provided with the second bolt hole, bolt is contained in first bolt hole and second bolt hole, so that the interlude and institute The first linkage section is stated to be connected.
5. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 4, it is characterised in that:Described first The structure of linkage section is identical with the structure of second linkage section, the connection side between second linkage section and the interlude Formula and first linkage section are identical with the connected mode between the interlude.
6. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 3, it is characterised in that:The centre Section both ends shape and size respectively with the shape and size of first linkage section and the shape of second linkage section and Size is corresponding, so that the both ends of the interlude are connected with first linkage section and second linkage section.
7. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 3, it is characterised in that:Described first Linkage section offers the 3rd bolt hole adjacent to the position of the opening, and the interlude is opened adjacent to one end of first linkage section Provided with the 4th bolt hole, two steel plates are separately positioned on the opposite both sides of first linkage section, and two steel plates cover The junction covered between first linkage section and the interlude.
8. it is used for the lateral connection component of straddle type monorail rail tracks as claimed in claim 7, it is characterised in that:High-strength bolt Through two steel plates and its be partially housed in the 3rd bolt hole, by two steel plates and first linkage section It is connected;It is another have high-strength bolt through two steel plates and its be partially housed in the 4th bolt hole, by described in two Steel plate is connected with the interlude, and thus first linkage section is releasably coupled together with the interlude.
9. the lateral connection component for straddle type monorail rail tracks as described in claim any one of 1-8, it is characterised in that: Between first linkage section and second linkage section and the interlude it is attached by the way of on-site consolidation.
CN201710829309.5A 2017-09-14 2017-09-14 A kind of lateral connection component for straddle type monorail rail tracks Pending CN107558311A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710829309.5A CN107558311A (en) 2017-09-14 2017-09-14 A kind of lateral connection component for straddle type monorail rail tracks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710829309.5A CN107558311A (en) 2017-09-14 2017-09-14 A kind of lateral connection component for straddle type monorail rail tracks

Publications (1)

Publication Number Publication Date
CN107558311A true CN107558311A (en) 2018-01-09

Family

ID=60980754

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710829309.5A Pending CN107558311A (en) 2017-09-14 2017-09-14 A kind of lateral connection component for straddle type monorail rail tracks

Country Status (1)

Country Link
CN (1) CN107558311A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108221509A (en) * 2018-02-09 2018-06-29 北京交通大学 A kind of cross-saddle single-track traffic pre-track beam of ribbed plate
CN108842530A (en) * 2018-06-29 2018-11-20 中国建筑第五工程局有限公司 A kind of novel straddle-type monorail two-wire combined track girder construction
CN109137642A (en) * 2018-09-03 2019-01-04 北京交通大学 A kind of light-duty straddle-type monorail transportation system
CN109487673A (en) * 2019-01-10 2019-03-19 中建五局土木工程有限公司 Bridge connection structure, track girder and track beam construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040221761A1 (en) * 2001-09-21 2004-11-11 Wu Xiangming Track structure of the rapid track transit
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN103104041A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting transverse connection and construction method thereof
CN103790081A (en) * 2014-01-23 2014-05-14 北京交通大学 Steel rail beam anti-skidding surface layer for straddle type single-rail traffic
CN105568838A (en) * 2015-12-17 2016-05-11 中铁第四勘察设计院集团有限公司 Two-line rail girder of maglev rail-holding rail transit
CN207376378U (en) * 2017-09-14 2018-05-18 中铁第四勘察设计院集团有限公司 A kind of lateral connection component for straddle type monorail rail tracks

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040221761A1 (en) * 2001-09-21 2004-11-11 Wu Xiangming Track structure of the rapid track transit
CN1704537A (en) * 2004-05-27 2005-12-07 同济大学 Totally assembled type prefabricated concrete structure system
CN103104041A (en) * 2013-03-08 2013-05-15 郑州大学 Assembled framework beam-column joint adopting transverse connection and construction method thereof
CN103790081A (en) * 2014-01-23 2014-05-14 北京交通大学 Steel rail beam anti-skidding surface layer for straddle type single-rail traffic
CN105568838A (en) * 2015-12-17 2016-05-11 中铁第四勘察设计院集团有限公司 Two-line rail girder of maglev rail-holding rail transit
CN207376378U (en) * 2017-09-14 2018-05-18 中铁第四勘察设计院集团有限公司 A kind of lateral connection component for straddle type monorail rail tracks

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108221509A (en) * 2018-02-09 2018-06-29 北京交通大学 A kind of cross-saddle single-track traffic pre-track beam of ribbed plate
CN108842530A (en) * 2018-06-29 2018-11-20 中国建筑第五工程局有限公司 A kind of novel straddle-type monorail two-wire combined track girder construction
CN109137642A (en) * 2018-09-03 2019-01-04 北京交通大学 A kind of light-duty straddle-type monorail transportation system
CN109487673A (en) * 2019-01-10 2019-03-19 中建五局土木工程有限公司 Bridge connection structure, track girder and track beam construction method
CN109487673B (en) * 2019-01-10 2024-08-06 中建五局土木工程有限公司 Bridge connection structure, track beam and track beam construction method

Similar Documents

Publication Publication Date Title
CN107558311A (en) A kind of lateral connection component for straddle type monorail rail tracks
CN201144398Y (en) Straddling type track traffic elevated 'bridge-build' structure
CN201843076U (en) Groove-shaped steel bridge deck structure of high-speed railway steel tied arched bridge
CN105821961B (en) A kind of tee girder column connected node
CN203487475U (en) Line suspending and reinforcing structure for existing line jacking bridge and culvert construction
CN103485279A (en) Wet joint for straddle type monorail traffic
CN203654157U (en) Track beam structure supported by double-layer rods
CN101158143A (en) Double-deck bridge floor combined trussed girder bridge
CN204282192U (en) A kind of double deck steel truss girder
CN106978777B (en) A kind of make-shift bridge device
CN103452036A (en) Split streamline steel-concrete composite box girder
CN203639800U (en) Split streamline steel-concrete composite box girder
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN110820609B (en) Roof beam canopy integration dangerous rock rockfall protection shed tunnel
CN206706545U (en) The bridge arrangement of highway and rail traffic building jointly
CN108018772A (en) Non-major P.E.subject flat bed main beam section constructs
CN207376378U (en) A kind of lateral connection component for straddle type monorail rail tracks
CN204676374U (en) A kind of strengthening mechanism of rail track
CN107905043A (en) A kind of suspension type bottom plate open steel web truss combined track girder system system
CN204401479U (en) The novel station of tram
CN203603036U (en) Double-row four-inclined-leg steel structure gate-type pier
CN103556567B (en) Double four battered leg steel work transom piers
CN207891658U (en) A kind of straddle-type monorail curve track girder construction with lateral connection component
CN201762650U (en) Arch bridge with bridge floor having prefabricated, longitudinally-installed and blocked dual suspension cantilever beam
CN209941469U (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180109

RJ01 Rejection of invention patent application after publication