CN103089280B - 一种隧道内地下水疏堵结合的注浆止水加固施工工艺 - Google Patents

一种隧道内地下水疏堵结合的注浆止水加固施工工艺 Download PDF

Info

Publication number
CN103089280B
CN103089280B CN201110339243.4A CN201110339243A CN103089280B CN 103089280 B CN103089280 B CN 103089280B CN 201110339243 A CN201110339243 A CN 201110339243A CN 103089280 B CN103089280 B CN 103089280B
Authority
CN
China
Prior art keywords
water
tunnel
liquid
grouting
grout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110339243.4A
Other languages
English (en)
Other versions
CN103089280A (zh
Inventor
韩化龙
朱玉明
王赢泽
魏之奇
王永华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201110339243.4A priority Critical patent/CN103089280B/zh
Publication of CN103089280A publication Critical patent/CN103089280A/zh
Application granted granted Critical
Publication of CN103089280B publication Critical patent/CN103089280B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明为一种隧道内地下水疏堵结合的注浆止水加固施工工艺,包括如下步骤:(1),在隧道内侧向外侧设置注浆管,同时,配合设置疏水管,疏水管与真空泵连接实现局部抽水;(2),将原浆39Be’的水玻璃稀释至28Be’,TGRM灌浆料与水泥按1∶3的比例混合,以上两种浆液1∶1混合制成A液;将原浆39Be’的水玻璃用水稀释至30Be’,浓磷酸按照1∶6用水稀释成稀磷酸,以上两种浆液1∶1混合制成B液;(3),将A、B液交替通过注浆管注入隧道开挖范围外加固土层,从而完成隧道四周的注浆;(4),在开挖面四周1.5m的范围内,将A液和B液交替通过小导管注入。本发明的施工工艺通过“疏、堵”结合、双管齐下,从而避免了地下水向注浆薄弱处扩散渗透,使隧道施工的难度降低,从而提高了施工安全程度。

Description

一种隧道内地下水疏堵结合的注浆止水加固施工工艺
【技术领域】
本发明涉及一种建筑施工方法,具体涉及隧道内地下水疏堵结合的注浆止水加固施工工艺。
【背景技术】
隧道的暗挖施工,关键在于隧道在地下水下、松散地层内,通过注浆止水、加固,使隧道初衬施工在保证质量的前提下安全进行。在不能降水的情况下隧道施工中,以往都是单纯的注浆封堵,由于注浆加固地层容易受到地下水压力的影响,造成局部水压力增大,这直接加剧了水层向隧道注浆薄弱处扩散渗透的趋势,无形中提升了施工难度。
为解决上述技术问题,确有必要在地下水环境下提供一种暗挖隧道安全、可靠注浆加固的施工工艺,以克服现有技术中的所述缺陷。
【发明内容】
为解决上述问题,本发明的目的在于提供一种“疏、堵”结合、双管齐下的隧道内地下水疏堵结合的注浆止水加固施工工艺。
为实现上述目的,本发明采取的技术方案为:一种隧道内地下水疏堵结合的注浆止水加固施工工艺,其包括如下工艺步骤:
(1),首先在隧道内向外侧设置注浆管,同时,配合设置疏水管,将疏水管与真空泵连接实现局部抽水;
(2),将原浆39Be’的水玻璃用水稀释至28Be’,TGRM灌浆料与水泥按照1∶3的比例混合,以上两种浆液1∶1混合制成A液;将原浆39Be’的水玻璃用水稀释至30B e’,浓磷酸按照1∶6用水稀释成稀磷酸,以上两种浆液1∶1混合制成B液;
(3),采用高压风将小导管送入竖井四周1.5m的范围内,将A液和B液交替通过小导管注入竖井四周;
(4),将A液和B液交替通过注浆管注入隧道的开挖面以外疏松地层内,两种材料注入的压力为0.3Mpa~0.6Mpa,从而完成隧道四周的疏水及注浆。
本发明的隧道内地下水疏堵结合的注浆止水加固施工工艺进一步为:所述注浆管竖向倾斜35°,疏水管竖向倾斜22°,二者配合。
本发明的隧道内地下水疏堵结合的注浆止水加固施工工艺进一步为:所述注浆管和疏水管均选用Φ32*3.5钻孔无缝钢管。
与现有技术相比,本发明具有如下有益效果:本发明的隧道的注浆加固施工工艺通过“疏、堵”结合、双管齐下,从而避免了水层向注浆薄弱处扩散渗透的趋势;同时,对于疏导出来的地下水将在施工完成段范围内择处进行回灌,以保证土层内含水量稳定,避免地表下沉。
【具体实施方式】
本发明为一种隧道内地下水疏堵结合的注浆止水加固施工工艺,其包括如下工艺步骤:
(1),隧道施工遇富含地下水疏松地质时,首先在隧道内向外侧设置注浆管,同时,配合设置疏水管,将疏水管与真空泵连接,实现局部抽水。所述注浆管竖向倾斜35°,疏水管竖向倾斜22°。所述注浆管和疏水管均选用Φ32*3.5钻孔无缝钢管。
(2),将原浆39Be’的水玻璃用水稀释至28Be’,TGRM灌浆料与水泥按照1∶3的比例混合,以上两种浆液1∶1混合制成A液;将原浆39Be’的水玻璃用水稀释至30Be’,浓磷酸按照1∶6用水稀释成稀磷酸,以上两种浆液1∶1混合制成B液。
(3),采用高压风将小导管送入竖井四周1.5m的范围内,将A液和B液交替通过小导管注入竖井四周。
(4),将A液和B液交替通过注浆管注入隧道的开挖面以外疏松地层内,两种材料注入的压力为0.3Mpa~0.6Mpa,从而完成隧道四周的疏水及注浆。
本发明的隧道内地下水疏堵结合的注浆止水加固施工工艺通过“疏、堵”结合、双管齐下,从而避免了地下水向注浆薄弱处扩散渗透的趋势,使隧道施工的难度大大降低,提高了施工安全程度;同时,对于疏导出来的地下水将在施工完成段范围内择处进行回灌,以保证土层内含水量稳定,避免地表下沉。
以上的具体实施方式仅为本创作的较佳实施例,并不用以限制本创作,凡在本创作的精神及原则之内所做的任何修改、等同替换、改进等,均应包含在本创作的保护范围之内。

Claims (1)

1.一种隧道内地下水疏堵结合的注浆止水加固施工工艺,其特征在于:包括如下工艺步骤:
(1),首先在隧道内向外侧设置注浆管,同时,配合设置疏水管,将疏水管与真空泵连接实现局部抽水;所述注浆管竖向倾斜35°,疏水管竖向倾斜22°,二者配合;所述注浆管和疏水管均选用Φ32*3.5钻孔无缝钢管;
(2),将原浆39Be’的水玻璃用水稀释至28Be’,TGRM灌浆料与水泥按照1∶3的比例混合,以上两种浆液1∶1混合制成A液;将原浆39Be’的水玻璃用水稀释至30Be’,浓磷酸按照1∶6用水稀释成稀磷酸,以上两种浆液1∶1混合制成B液;
(3),采用高压风将小导管送入竖井四周1.5m的范围内,将A液和B液交替通过小导管注入竖井四周;
(4),将A液和B液交替通过注浆管注入隧道的开挖面以外疏松地层内,两种材料注入的压力为0.3Mpa~0.6Mpa,从而完成隧道四周的疏水及注浆。
CN201110339243.4A 2011-11-01 2011-11-01 一种隧道内地下水疏堵结合的注浆止水加固施工工艺 Expired - Fee Related CN103089280B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110339243.4A CN103089280B (zh) 2011-11-01 2011-11-01 一种隧道内地下水疏堵结合的注浆止水加固施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110339243.4A CN103089280B (zh) 2011-11-01 2011-11-01 一种隧道内地下水疏堵结合的注浆止水加固施工工艺

Publications (2)

Publication Number Publication Date
CN103089280A CN103089280A (zh) 2013-05-08
CN103089280B true CN103089280B (zh) 2015-02-04

Family

ID=48202349

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110339243.4A Expired - Fee Related CN103089280B (zh) 2011-11-01 2011-11-01 一种隧道内地下水疏堵结合的注浆止水加固施工工艺

Country Status (1)

Country Link
CN (1) CN103089280B (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103422868B (zh) * 2013-08-06 2015-10-21 同济大学 一种消散超孔隙水压、加固盾构隧道土体的结构及方法
CN104033164B (zh) * 2014-05-26 2016-07-06 江苏鼎泰工程材料有限公司 对隧道内拱的脱空及渗水害进行修复的方法
CN109555559B (zh) * 2018-11-16 2020-06-16 北京中煤矿山工程有限公司 一种金属矿山千米级盲竖井防治水技术方法
CN109736824A (zh) * 2018-12-10 2019-05-10 中交一公局桥隧工程有限公司 一种t76高强度自钻式螺旋管棚施工工艺
CN112281878B (zh) * 2020-08-28 2021-07-09 浙大城市学院 用于基坑工程地下水渗透破坏治理的定位注浆加固方法
CN115012953B (zh) * 2022-06-17 2023-06-02 北京瑞诺安科新能源技术有限公司 煤矿或隧道工程中富水流沙围岩的注浆加固工艺及设备

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1158938A (zh) * 1996-08-02 1997-09-10 北京市地下铁道建设公司 一种地下铁道排水施工方法
CN1139718C (zh) * 2002-05-14 2004-02-25 何益寿 地下工程经络防排水结构及施工方法
ITGE20030005A1 (it) * 2003-01-24 2004-07-25 Ferrari De Nobili S R L Metodo continuo di realizzazione di opere in sotterraneo,
CN100410492C (zh) * 2005-11-29 2008-08-13 长安大学 隧道工程的集中泄水装置及其泄水方法
KR100823103B1 (ko) * 2007-02-22 2008-04-18 고려대학교 산학협력단 터널 수처리 시스템의 시공방법 및 이에 사용되는도수파이프
CN100591866C (zh) * 2008-01-23 2010-02-24 湖南省建筑工程集团总公司 流砂层及砂砾层动水双液高压注浆堵水施工方法
CN101761346B (zh) * 2009-12-30 2012-10-03 中铁十二局集团第二工程有限公司 一种变质岩承压水隧道的施工方法

Also Published As

Publication number Publication date
CN103089280A (zh) 2013-05-08

Similar Documents

Publication Publication Date Title
CN103089301B (zh) 一种竖井内地下水疏堵结合的注浆加固施工工艺
CN103089280B (zh) 一种隧道内地下水疏堵结合的注浆止水加固施工工艺
CN101914917B (zh) 软土地区地铁基坑开挖用防渗堵漏施工方法
CN103306684A (zh) 盾构管片背后注浆工艺
CN105041325A (zh) 一种高压富水特大断层软弱角砾岩隧道的施工方法
CN102660952B (zh) 可控粘土膏浆灌浆方法
CN101694096B (zh) 一种用于动水条件下砂层地基的注浆处理方法
CN107605498A (zh) 富水砂卵石地层盾构隧道端头水平注浆加固结构施工方法
CN107120121A (zh) 一种盾构施工实时补充注浆防沉降控制方法
CN112095647B (zh) 一种快速封堵止水帷幕泄漏点的堵漏方法
CN102400694A (zh) 盾构隧道与矿山法隧道结合部的加固方法
CN105386458B (zh) 一种嵌入式塑性搅拌桩加固地下连续墙槽壁施工方法
CN105155541A (zh) 一种集水坑的双液浆封闭施工方法
CN104141314A (zh) 在岩、土两种介质中形成完整防渗帷幕的方法
CN108716410A (zh) 机械法联络通道高强弹性壁后注浆浆液及注浆方法
CN104314106A (zh) 一种带接缝止水和补缺结构的地下连续墙及其施工方法
CN105862872B (zh) 一种深基坑围护结构接缝止水施工方法
CN103742162B (zh) 盾尾顶部设置有同步注浆装置的盾构机及同步注浆装置
CN103174135B (zh) 不达标后注浆灌注桩的修补方法
CN106089245B (zh) 一种用于单护盾tbm壁后延迟注浆方法
CN102535518B (zh) 一种地下连续墙大接缝的封堵方法
CN110468828A (zh) 一种基坑支护止水连续墙的施工方法
CN109881696B (zh) 一种hppg封底施工方法
CN102518450A (zh) 浅埋暗挖法地层加固普通水泥注浆取代超细水泥的注浆方法
CN105586978A (zh) 基于砾石的换土搅拌止水帷幕施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150204

Termination date: 20151101

EXPY Termination of patent right or utility model