CN103031918A - Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof - Google Patents

Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof Download PDF

Info

Publication number
CN103031918A
CN103031918A CN2011102990553A CN201110299055A CN103031918A CN 103031918 A CN103031918 A CN 103031918A CN 2011102990553 A CN2011102990553 A CN 2011102990553A CN 201110299055 A CN201110299055 A CN 201110299055A CN 103031918 A CN103031918 A CN 103031918A
Authority
CN
China
Prior art keywords
mould shell
gypsum
plaster
close rib
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102990553A
Other languages
Chinese (zh)
Inventor
黄勇
刘正平
黄瑞麟
周理
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou University
Original Assignee
Guizhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou University filed Critical Guizhou University
Priority to CN2011102990553A priority Critical patent/CN103031918A/en
Publication of CN103031918A publication Critical patent/CN103031918A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a pin type plaster mould shell and concrete combined dense rib flat slab and a manufacturing method thereof. The manufacturing method comprises the following steps of firstly, preparing a plaster hollow cavity mould shell by using industrial waste plaster or ardealite; pre-embedding a shearing force connecting pin on the plaster hollow cavity mould shell; arraying the plaster hollow cavity mould shell on a pouring supporting bottom plate of a pouring floor system; then carrying out concrete pouring on the plaster hollow cavity mould shell; and after concrete is condensed, removing the pouring supporting bottom plate, so as to obtain the integrated pin type plaster mould shell and concrete combined dense rib flat slab which is formed by connecting the shearing force connecting pin with the plaster hollow cavity mould shell which is used as a permanent formwork, a dense rib and a floor cover plate. The pin type plaster mould shell and concrete combined dense rib flat slab and the manufacturing method thereof not only have the advantages of higher structural strength, fewer used steel products and cement materials and lighter weight, but also have the advantages of small structural height, less occupied space, convenience for construction, and capability of efficiently utilizing a lot of the industrial waste plaster or the ardealite as building materials.

Description

Pin formula gypsum formwork and the close rib arch without beam of Combined concrete and preparation method thereof
Technical field
The present invention relates to a kind of pin formula gypsum formwork and the close rib arch without beam of Combined concrete and preparation method thereof, belong to building superstructure manufacture technology field.
Background technology
The use function of building relies on building cover structure to realize fully, relative vertical structure (post, wall), the area of building cover structure is huge, again owing to its several, tens of inferior reusing, so the material that building cover structure consumes, resource, manpower etc. account for the major part of whole building structure.At present, superstructure in the prior art adopts the superstructure of beam and slab type structure mostly, the superstructure of traditional beam and slab type structure mainly exists many, the shortcoming such as large that takes up room of the material usages such as Heavy Weight, steel and cement, and traditional superstructure preparation method can't effectively utilize industrial waste gypsum or ardealite to use as constructional materials.Therefore, existing building cover structure and preparation method or not ideal enough.
Summary of the invention
The objective of the invention is: provide a kind of structural strength higher, use steel and cement material is less, weight is light, it is less to take up room, and can effectively utilize pin formula gypsum formwork that industrial waste gypsum or ardealite use as constructional materials and the close rib arch without beam of Combined concrete and preparation method thereof, to overcome the deficiencies in the prior art.
The present invention is achieved in that the preparation method of a kind of pin formula gypsum formwork of the present invention and the close rib arch without beam of Combined concrete is, make the gypsum evacuated mould shell with industrial waste gypsum or ardealite first, and on the gypsum evacuated mould shell pre-buried Shear connection pin, then the gypsum evacuated mould shell is arranged in and builds the building on the support baseboard of superstructure, and make the gypsum evacuated mould shell of arranging reserve each other the headspace of the rib of concreting superstructure, then carry out concreting at the gypsum evacuated mould shell, after concrete setting, to build support baseboard and remove, and can obtain like this connecting to form pin formula gypsum formwork and the close rib arch without beam of Combined concrete that is integrated by the Shear connection pin with as the gypsum evacuated mould shell of permanent formwork and close rib and floor structure.
The of the present invention a kind of pin formula gypsum formwork and the close rib arch without beam of Combined concrete that make up according to the method described above are, this superstructure comprises with floor structure builds the close rib that is integrated, and is connected with gypsum evacuated mould shell as permanent formwork by the Shear connection pin in the space that floor structure and close rib surround.
The shape of the π font that two base plates that being shaped as of above-mentioned Shear connection pin become by steel plate bending and door font frame form.
The steel plate thickness of the Shear connection pin of the above-mentioned π of being bent into word shape is 2~10 millimeters; Its steel plate width is 10~150 millimeters.
Above-mentioned Shear connection pin be shaped as the curved planform that the right angle crotch is arranged in two ends at straight steel pole.
Owing to adopted technique scheme, the present invention adopts the gypsum evacuated mould shell as permanent formwork, and by the Shear connection pin rib and the floor structure that gypsum evacuated mould shell and concreting go out being connected to an organic whole structure, this structure is pin formula gypsum formwork of the present invention and the close rib arch without beam of Combined concrete structure.The present invention connects gypsum formwork and concrete with the Shear connection pin, makes them as cooperative shear connector, thereby has effectively improved shearing resistance and the flexural strength of whole superstructure.The present invention has adopted industrial waste gypsum or ardealite as constructional materials effectively, and this has not only reduced building costs, but also has reduced the pollution of industrial waste to environment.Particularly for Guizhou Province, Guizhou Province is one and has the area of enriching phosphate rock resource, be Chinese most important phosphorous chemical industry base, but phosphorous chemical industry produces a large amount of Industry Waste ardealite difficult treatment, contaminated environment.Therefore using all kinds of building materials of gypsum products of ardealite system is the highly effective approach that can process in a large number ardealite.Adopt produced pin formula gypsum formwork and the close rib arch without beam of Combined concrete of the present invention, through experimental test, under the test condition of national building standard defined, every intensity index all meets or exceeds the regulation of national building standard.So, the present invention compared with prior art, the present invention not only have structural strength higher, use steel and cement material is less, weight is lighter advantage, but also have structure height little, occupy little space, construct convenient, and can be effectively and the advantage of utilizing in a large number industrial waste gypsum or ardealite to use as constructional materials.Pin formula gypsum formwork of the present invention and the close rib arch without beam of Combined concrete also have the characteristics that can realize the architectural space flexible partition in use.The present invention can be widely used in huge pillar net parking lot, market and other utilities buildings and use, and its Transformation Application prospect is very wide.
Description of drawings
Fig. 1 is the plan structure schematic diagram of pin formula gypsum formwork of the present invention and the close rib arch without beam of Combined concrete;
Fig. 2 is the A-A sectional structure schematic diagram of Fig. 1;
Fig. 3 is the structural representation of the Shear connection pin of π font of the present invention when being connected with the gypsum evacuated mould shell with floor structure;
Fig. 4 is the another kind of structural representation of Shear connection pin of the present invention.
Description of reference numerals: 1-gypsum evacuated mould shell, 2-Shear connection pin, 2.1-base plate, 2.2-door font frame, the straight steel pole of 2.3-, 2.4-right angle crotch, the close rib of 3-, 4-floor structure, t-steel plate thickness, b-steel plate width.
The specific embodiment
Below in conjunction with drawings and Examples the present invention is done further to say in detail.
Embodiments of the invention: the preparation method of a kind of pin formula gypsum formwork of the present invention and the close rib arch without beam of Combined concrete is, make gypsum evacuated mould shell 1 with industrial waste gypsum or ardealite first, the shape of gypsum evacuated mould shell 1 can be determined according to the needs that use, during making, can be made into the gypsum evacuated mould shell of rectangular closed formula, or be made into the enclosed gypsum evacuated mould shell of other curved or arc surfaced, the part of Shear connection pin 2 is embedded in the gypsum evacuated mould shell 1, then gypsum evacuated mould shell 1 is arranged in and builds the building on the support baseboard of superstructure, and make the gypsum evacuated mould shell 1 of arranging reserve each other the headspace of the rib of concreting superstructure, the width of its headspace can be determined according to the thickness of the rib that designs in the usual way, then the mode by traditional concreting is carried out concreting on gypsum evacuated mould shell 1, at this moment the another part that is embedded in the Shear connection pin 2 on the gypsum evacuated mould shell 1 is wrapped by concrete, after concrete setting, to build support baseboard and remove, and can obtain like this connecting to form pin formula gypsum formwork and the close rib arch without beam of Combined concrete that is integrated by Shear connection pin 2 with as the gypsum evacuated mould shell 1 of permanent formwork and close rib 3 and floor structure 4.
The of the present invention a kind of pin formula gypsum formwork that makes up according to the method described above and the structural representation of the close rib arch without beam of Combined concrete be as depicted in figs. 1 and 2: this superstructure comprises with floor structure 4 builds the close rib 3 that is integrated, and is connected with gypsum evacuated mould shell 1 as permanent formwork by Shear connection pin 2 in the space that floor structure 4 and close rib 3 surround; During making, the shape of Shear connection pin 2 can be made into two base plates 2.1 and a shape (as shown in Figure 3) of the π font that font frame 2.2 forms that are become by steel plate bending, its steel plate thickness t that is bent into the Shear connection pin 2 of π word shape can select the steel plate of 2~10 millimeters thick as required, and its steel plate width b can be controlled in 10~150 millimeters scope; Also the shape of Shear connection pin 2 can be made into by the curved planform (as shown in Figure 4) that right angle crotch 2.4 is arranged in two ends at straight steel pole 2.3, the diameter of its straight steel pole 2.3 can be according to mode of occupation, and selecting diameter is that 6~16 millimeters reinforcing bar or screw-thread steel gets final product.

Claims (5)

1. preparation method of selling formula gypsum formwork and the close rib arch without beam of Combined concrete, it is characterized in that: make gypsum evacuated mould shell (1) with industrial waste gypsum or ardealite first, and at the upper pre-buried Shear connection pin (2) of gypsum evacuated mould shell (1), then gypsum evacuated mould shell (1) is arranged in and builds the building on the support baseboard of superstructure, and make the gypsum evacuated mould shell (1) of arranging reserve each other the headspace of the rib of concreting superstructure, then carry out concreting at gypsum evacuated mould shell (1), after concrete setting, to build support baseboard and remove, and can obtain like this connecting to form pin formula gypsum formwork and the close rib arch without beam of Combined concrete that is integrated by Shear connection pin (2) with as the gypsum evacuated mould shell (1) of permanent formwork and close rib (3) and floor structure (4).
2. sell formula gypsum formwork and the close rib arch without beam of Combined concrete for one kind, comprise with floor structure (4) and build the close rib (3) that is integrated, it is characterized in that: in the space that floor structure (4) and close rib (3) surround, be connected with gypsum evacuated mould shell (1) as permanent formwork by Shear connection pin (2).
3. pin formula gypsum formwork according to claim 2 and the close rib arch without beam of Combined concrete is characterized in that: two base plates (2.1) that being shaped as of Shear connection pin (2) become by steel plate bending and the shape of a π font that font frame (2.2) forms.
4. pin formula gypsum formwork according to claim 3 and the close rib arch without beam of Combined concrete, it is characterized in that: the steel plate thickness (t) that is bent into the Shear connection pin (2) of π word shape is 2~10 millimeters; Its steel plate width (b) is 10~150 millimeters.
5. pin formula gypsum formwork according to claim 2 and the close rib arch without beam of Combined concrete is characterized in that: Shear connection pin (2) be shaped as the curved planform that right angle crotch (2.4) are arranged in two ends at straight steel pole (2.3).
CN2011102990553A 2011-09-29 2011-09-29 Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof Pending CN103031918A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102990553A CN103031918A (en) 2011-09-29 2011-09-29 Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102990553A CN103031918A (en) 2011-09-29 2011-09-29 Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof

Publications (1)

Publication Number Publication Date
CN103031918A true CN103031918A (en) 2013-04-10

Family

ID=48019274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102990553A Pending CN103031918A (en) 2011-09-29 2011-09-29 Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN103031918A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103290967A (en) * 2013-06-28 2013-09-11 中国建筑第四工程局有限公司 Multi-ribbed hollow composite floor slab and manufacturing method thereof
CN106958306A (en) * 2017-04-20 2017-07-18 贵州蓝图新材料股份有限公司 A kind of T fonts ardealite composite exterior wall body
CN106978864A (en) * 2017-04-20 2017-07-25 贵州蓝图新材料股份有限公司 Point load-bearing point family ardealite combined wall in one kind
CN107893500A (en) * 2017-12-22 2018-04-10 贵州大学 A kind of large-span concrete prismatic surface arch grid shell roof structure and preparation method thereof
CN110337519A (en) * 2016-12-21 2019-10-15 法国电力公司 Permanent concrete blinding and the method for manufacturing betonanc composite construction using this formwork
CN114180920A (en) * 2021-11-22 2022-03-15 三峡大学 Preparation method of low-water-cement-ratio phosphogypsum light building block

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2415070Y (en) * 2000-03-31 2001-01-17 何华 Inner thermal insulation board for exterior wall
CN1587575A (en) * 2004-06-30 2005-03-02 清华大学 Steel-concrete folding plate combined beam
CN200985611Y (en) * 2006-12-26 2007-12-05 段庆生 Mounting structure of exterior wall heat insulation decoration board
CN101314935A (en) * 2008-07-17 2008-12-03 南京工业大学 Composite material bridge deck
CN101333832A (en) * 2008-07-02 2008-12-31 新嘉理(江苏)陶瓷有限公司 Wall decoration dry-fastening plate mounting keel and its purpose
JP2009030250A (en) * 2007-07-24 2009-02-12 Hayakawa Rubber Co Ltd Ceiling structure
CN101644082A (en) * 2009-08-21 2010-02-10 贵州金三利科技建材有限公司 Assembling method of gypsum evacuated mould
CN202227554U (en) * 2011-09-29 2012-05-23 贵州大学 Pin-type gypsum formwork and concrete combined multi-ribbed girderless floor

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2415070Y (en) * 2000-03-31 2001-01-17 何华 Inner thermal insulation board for exterior wall
CN1587575A (en) * 2004-06-30 2005-03-02 清华大学 Steel-concrete folding plate combined beam
CN200985611Y (en) * 2006-12-26 2007-12-05 段庆生 Mounting structure of exterior wall heat insulation decoration board
JP2009030250A (en) * 2007-07-24 2009-02-12 Hayakawa Rubber Co Ltd Ceiling structure
CN101333832A (en) * 2008-07-02 2008-12-31 新嘉理(江苏)陶瓷有限公司 Wall decoration dry-fastening plate mounting keel and its purpose
CN101314935A (en) * 2008-07-17 2008-12-03 南京工业大学 Composite material bridge deck
CN101644082A (en) * 2009-08-21 2010-02-10 贵州金三利科技建材有限公司 Assembling method of gypsum evacuated mould
CN202227554U (en) * 2011-09-29 2012-05-23 贵州大学 Pin-type gypsum formwork and concrete combined multi-ribbed girderless floor

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103290967A (en) * 2013-06-28 2013-09-11 中国建筑第四工程局有限公司 Multi-ribbed hollow composite floor slab and manufacturing method thereof
CN103290967B (en) * 2013-06-28 2016-08-10 中国建筑第四工程局有限公司 A kind of multi-ribbed hollow composite floor slab and manufacture method
CN110337519A (en) * 2016-12-21 2019-10-15 法国电力公司 Permanent concrete blinding and the method for manufacturing betonanc composite construction using this formwork
CN106958306A (en) * 2017-04-20 2017-07-18 贵州蓝图新材料股份有限公司 A kind of T fonts ardealite composite exterior wall body
CN106978864A (en) * 2017-04-20 2017-07-25 贵州蓝图新材料股份有限公司 Point load-bearing point family ardealite combined wall in one kind
CN107893500A (en) * 2017-12-22 2018-04-10 贵州大学 A kind of large-span concrete prismatic surface arch grid shell roof structure and preparation method thereof
CN114180920A (en) * 2021-11-22 2022-03-15 三峡大学 Preparation method of low-water-cement-ratio phosphogypsum light building block

Similar Documents

Publication Publication Date Title
CN201206328Y (en) Preform formwork of cast-in-place concrete rib floor
CN103031918A (en) Pin type plaster mould shell and concrete combined dense rib flat slab and manufacturing method thereof
CN105908862B (en) A kind of production method of masonry shell in 3D printing reinforced masonry shear wall
CN204343459U (en) The parapet node structure of overlaid plate type concrete shear wall system
CN105672139B (en) A kind of bridge hollow pier binds construction
CN202644847U (en) CFST (Concrete Filled Steel Tube) combination column
CN101644082A (en) Assembling method of gypsum evacuated mould
CN204059760U (en) A kind of square steel post post core self-compacting concrete pouring construction structure
CN202466927U (en) Aligning type double-opening small-size concrete building block
CN201460212U (en) Arc-shaped plaster cavity die box
CN203022222U (en) Wholly-cast ring beam of brick-concrete building support
CN201713970U (en) Structural system with light multi-ribbed plates and light multi-ribbed floor systems
CN109914667A (en) A kind of overlapping prefabricated hollow floor and preparation method thereof
CN101845797A (en) One-step molding method of vase-shaped columnar pier for urban viaduct bridges
CN202227554U (en) Pin-type gypsum formwork and concrete combined multi-ribbed girderless floor
CN103556755A (en) Single-line reinforcement thermal insulation bearing shear wall with L-shaped hidden posts at end parts and manufacturing method of shear wall
CN207958977U (en) A kind of device to bind for bridge hollow pier
CN204299179U (en) Cast-in-situ reinforced concrete thin-wall rectangular small bore open tubular column template assembly
CN106381956A (en) Concrete prefabricated shell-regenerated mixed concrete combination column and preparation method thereof
CN202266019U (en) Combined structure of building template of building support pillar
CN103046678A (en) Method for constructing BDF (building distribution frame) hollow floorslab
CN208038999U (en) A kind of assembled simple supported box beam end floor beam construction
CN202755532U (en) Pull-lay combination building fabricated wall plate
CN207863236U (en) Overlap wall body structure
CN202299397U (en) Split-type building template

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130410