CN103010239A - Mounting method of end part roof - Google Patents
Mounting method of end part roof Download PDFInfo
- Publication number
- CN103010239A CN103010239A CN2012105651692A CN201210565169A CN103010239A CN 103010239 A CN103010239 A CN 103010239A CN 2012105651692 A CN2012105651692 A CN 2012105651692A CN 201210565169 A CN201210565169 A CN 201210565169A CN 103010239 A CN103010239 A CN 103010239A
- Authority
- CN
- China
- Prior art keywords
- roof
- previous
- sides
- procedure
- mounting method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Connection Of Plates (AREA)
Abstract
The invention provides a mounting method of an end part roof. Two positioning cushion blocks at the two sides of a previous positioning cushion block are maintained to carry out roof pre-assembling; the roof is glued and pushed against, and the roof is temporarily fixed by using a supporting device and an adjustable support rod; the two ends of the supporting device are located at the outer sides of the two positioning cushion blocks; after rivets at the two sides are mounted, the supporting device and the adjustable support rod are detached in time; and procedure self mutual inspection and procedure alternative inspection are carried out. Compared with the previous mounting method, the mounting method disclosed by the invention has the advantages that a two-point one-line principle is used for changing previous multi-point positioning into two-point positioning, so that the mounting flatness of the roof is effectively controlled and the problem of a previous batch opening item is solved; and furthermore, a previous technical process of utilizing the support rod to support the roof all the time and then detach the roof after glue is cured is simplified, and time needed by a roof mounting procedure of each vehicle is shortened from previous 48 hours to 4 hours, so that the procedure assembling period is shortened.
Description
Technical field
The present invention relates to the installation method of the in-built top board of trolley coach, especially relate to the installation method of a kind of end top board.
Background technology
The in-built top board of trolley coach adopts screw or the fixing single mounting structure of glue mostly, only has Australian double deck passenger car to adopt the bonding complicated mounting structure that adds riveted joint.The end mounting of roof plate adopts following process at present: 1, install 5-6 additional and adjust cushion block; 2, play glue, backup top board and be fixed with common strut bar; 3, the top board adhesive curing is waited for; 4, pull down strut bar and riveting lamp in both sides is installed; 5, operation is from inspection and operation are handed over inspection mutually.The method exists multiple spot to cross the location and causes height dimension and the overproof quality of lot problem of whole Pingdu behind the mounting of roof plate, and car is handed in impact; In addition, because the complete cure time of glue is long, need 48 hours, cause operation oversize assembly period.
Summary of the invention
The purpose of this invention is to provide a kind of end top board two point location installation methods, the installation Pingdu of top board is effectively controlled, solved the problem of former batch opening item; Simultaneously each roof hoard installation procedure required time is reduced to 4 hours by original 48 hours, shortens operation assembly period.
For achieving the above object, the invention provides a kind of end mounting of roof plate method, it is characterized in that comprising the following steps:
1) two spacer pads that keep both sides in the cushion block of former location carry out the top board prepackage;
2) play glue, backup top board and carry out temporary fixedly with bracing or strutting arrangement and adjustable supporting pole pair top board, the bracing or strutting arrangement two ends are in the outside of two spacer pads;
3) in time pull down bracing or strutting arrangement and adjustable pole behind the rivet of installation both sides;
4) operation is from inspection and operation are handed over inspection mutually.
The present invention has following advantage with respect to original installation method: utilize the principle of two one lines to change original multipoint positioning into two point locations, the installation Pingdu of top board is effectively controlled, solved the problem of former batch opening item; Simplified in addition originally with the pole technological process after adhesive curing, pulled down again of roof supporting always, each roof hoard installation procedure required time can be reduced to 4 hours by original 48 hours, shortened operation assembly period.
Description of drawings
Accompanying drawing 1 is that the top board middle part installs the lip block scheme drawing additional.
The specific embodiment
With reference to accompanying drawing, end of the present invention mounting of roof plate method is as follows:
1) two spacer pads 1 that keep both sides in the original 5-6 piece spacer pad carry out top board 2 prepackages;
2) beat
SIKAGlue 5, backup top board 2 and carry out with former bracing or strutting arrangement 4 and 3 pairs of top boards of adjustable pole temporary fixed, but will be with former bracing or strutting arrangement lengthening so that two ends in the outside of two spacer pads;
3) in time pull down bracing or strutting arrangement 4 and adjustable pole 3 behind the rivet of installation both sides;
4) operation is from inspection and operation are handed over inspection mutually.
Claims (1)
1. an end mounting of roof plate method is characterized in that comprising the following steps:
1) two spacer pads that keep both sides in the cushion block of former location carry out the top board prepackage;
2) play glue, backup top board and carry out temporary fixedly with bracing or strutting arrangement and adjustable supporting pole pair top board, the bracing or strutting arrangement two ends are in the outside of two spacer pads;
3) in time pull down bracing or strutting arrangement and adjustable pole behind the rivet of installation both sides;
4) operation is from inspection and operation are handed over inspection mutually.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012105651692A CN103010239A (en) | 2012-12-24 | 2012-12-24 | Mounting method of end part roof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012105651692A CN103010239A (en) | 2012-12-24 | 2012-12-24 | Mounting method of end part roof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103010239A true CN103010239A (en) | 2013-04-03 |
Family
ID=47959496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012105651692A Pending CN103010239A (en) | 2012-12-24 | 2012-12-24 | Mounting method of end part roof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103010239A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60102294A (en) * | 1983-11-10 | 1985-06-06 | Kawasaki Heavy Ind Ltd | Method and device for operation in production of structural member for transporting equipment body |
JPH10175543A (en) * | 1996-12-18 | 1998-06-30 | Hitachi Ltd | Ceiling part interior finishing device for rolling stock |
PL178854B1 (en) * | 1995-03-28 | 2000-06-30 | Deutsche Waggonbau Ag | Roof-mounted quiding system for railway cars with sliding walls and those with double roof |
CN201193033Y (en) * | 2008-04-16 | 2009-02-11 | 长春轨道客车股份有限公司 | Installation apparatus for build-in vehicle roof |
CN201400179Y (en) * | 2009-03-27 | 2010-02-10 | 长春轨道客车股份有限公司 | Top plate mounting structure of passenger compartments of high-speed sleeper |
-
2012
- 2012-12-24 CN CN2012105651692A patent/CN103010239A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60102294A (en) * | 1983-11-10 | 1985-06-06 | Kawasaki Heavy Ind Ltd | Method and device for operation in production of structural member for transporting equipment body |
PL178854B1 (en) * | 1995-03-28 | 2000-06-30 | Deutsche Waggonbau Ag | Roof-mounted quiding system for railway cars with sliding walls and those with double roof |
JPH10175543A (en) * | 1996-12-18 | 1998-06-30 | Hitachi Ltd | Ceiling part interior finishing device for rolling stock |
CN201193033Y (en) * | 2008-04-16 | 2009-02-11 | 长春轨道客车股份有限公司 | Installation apparatus for build-in vehicle roof |
CN201400179Y (en) * | 2009-03-27 | 2010-02-10 | 长春轨道客车股份有限公司 | Top plate mounting structure of passenger compartments of high-speed sleeper |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205000778U (en) | Combined structure of automobile external-open handle and door plate | |
CN102991727A (en) | Constraint system of airplane structure test | |
CN102367133A (en) | Adjustable lift car guide rail bracket | |
CN101955106B (en) | Elevator guide rail bracket | |
CN102092394B (en) | Method for assembling railway passenger car modular floors | |
CN201073919Y (en) | Sedan car engine right suspending bracket | |
CN103010239A (en) | Mounting method of end part roof | |
CN104588948B (en) | A kind of electric power wheel self-discharging vehicle front frame assembly tool and assemble method | |
CN205186057U (en) | An automobile | |
CN101092108B (en) | Right suspension installation of saloon car engine | |
CN204355056U (en) | A kind of guideway vehicle and roof inner top thereof and air channel installation component | |
CN102470906B (en) | Device and method for mounting front wings on front wing supports of a vehicle | |
CN103818240A (en) | Assembly securing arrangement | |
CN204367887U (en) | A kind of gear box suspension assembly | |
CN104527686B (en) | Rail vehicle longitudinal direction seat | |
CN201746193U (en) | Elevator guide rail support frame | |
CN208291126U (en) | Support base is used in the installation of electric car headstock outer plaque | |
CN103203702B (en) | In passenger vehicle, glue supporting tool beaten by top board | |
CN202264628U (en) | Engine support frame assembly | |
CN202058754U (en) | Cell panel bracket for solar cell panel | |
CN205292452U (en) | Aircraft wing box transportation trailer's multi -functional pull formula supporter | |
CN205113444U (en) | Connection structure of crossbeam and longeron | |
CN202785121U (en) | Operation panel handle | |
CN104386262B (en) | Transition beam assembly and inspection device | |
CN204505684U (en) | Pulling beam on a kind of three axle Servo Injection Molding Machine manipulators and horizontal go out beam fixed structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130403 |