CN102995666A - 减少振动对周边建(构)筑物影响的施工方法 - Google Patents
减少振动对周边建(构)筑物影响的施工方法 Download PDFInfo
- Publication number
- CN102995666A CN102995666A CN2011102687128A CN201110268712A CN102995666A CN 102995666 A CN102995666 A CN 102995666A CN 2011102687128 A CN2011102687128 A CN 2011102687128A CN 201110268712 A CN201110268712 A CN 201110268712A CN 102995666 A CN102995666 A CN 102995666A
- Authority
- CN
- China
- Prior art keywords
- grouting
- root pile
- hole
- grouting pipe
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明涉及一种减少振动对周边建(构)筑物影响的施工方法,包括采用树根桩形成一道隔离墙对建筑物的保护,具体步骤是:1.定位放线;2.钻进成孔;3.清孔;4.安放钢筋笼;5.下注浆管;6.投入碎石;7.第一次压浆;8.第二次压浆;9.加固树根桩与施工区域。本发明的施工方法,可以有效对建(构)筑物进行保护,在施工过程中对周围土体扰动小,桩位偏差控制在20mm内,垂直度不超过1/100。适用于振动施工区域附近存在相邻建(构)筑物的保护。
Description
技术领域
本发明涉及一种用于保护正在施工建(构)筑物的施工方法,尤其是一种采用树根桩形成隔离墙对建(构)筑物进行保护的施工工艺。
背景技术
在建筑施工领域,经常会遇到有施工区域周边有紧邻的建(构)筑物,由于施工时机械产生振动,会引起对周边建(构)筑物的影响,比如沉降、开裂、倾斜,有些甚至倒塌等,所以必须采取一定的保护措施对已有的建(构)筑物进行保护,避免造成不利影响。有一些需要保护的文物建筑尤其更需要注意,这些建筑往往都是浅基础、砖混结构,而且建筑时间都比较长,其主体结构的强度或者稳定性已经比较差,存在一定的倾斜或者墙体开裂的情况,在其周边进行施工时候,需要采取有效的措施对其进行相关的保护。
发明内容
本发明是要提供一种减少振动对周边建(构)筑物影响的施工方法,该方法主要在建筑物及施工区域中间设置树根桩形成一道隔离墙,用于隔离施工产生的振动对建筑物的不利影响。
为实现上述目的,本发明的技术方案是:一种减少振动对周边建(构)筑物影响的施工方法,包括采用树根桩形成一道隔离墙对建筑物的保护,具体步骤是:
(1)定位放线
用钢尺沿设计要求测放树根桩位;钻机就位前,先平整场地,铺好枕木并用水平尺校正,保证钻机平稳、牢固;
(2)钻进成孔
经测量平面放样后,对树根桩中心点作好护桩工作,然后开钻,树根桩成孔时根据土质情况采用天然泥浆或者人造泥浆进行护壁;
(3)清孔
当钻至设计深度后,拔出钻头进行清孔,清孔直至孔口泛清水为止;
(4)安放钢筋笼
成孔后垂直下放钢筋笼,并在孔口固定钢筋笼,钢筋笼接头错开;吊放钢筋笼和注浆管时节间钢筋搭接焊缝长度不小于10倍钢筋直径;
(5)下注浆管
每根树根桩孔内布置两根注浆管,并且注浆管直插到孔底;
(6)投入碎石
在放置注浆管的树根桩孔内投入粒径10~25mm小碎石,投石量为桩的计算体积的80%~90%;
(7)第一次压浆
采用P.O42.5级普通硅酸盐水泥,水灰比0.55注浆,注浆压力0.5~1.0MPa。注浆时控制压力,使浆液均匀上冒,直至泛出孔口为止;
(8)第二次压浆
在第一次注浆初凝之后,在第二根注浆管内进行二次注浆,浆液的水灰比为0.55,注浆压力为2.0~4.0MPa;
(9)加固树根桩与施工区域
在树根桩内部区域土体采用压密注浆方式进行加固施工。
上述步骤一中,用钢尺沿设计要求测放树根桩位,桩位偏差≤20mm。
第一、二压浆中所用的注浆泵最大工作压力应≥1.5MPa。
在树根桩内部区域土体采用压密注浆方式进行加固施工的具体方法:浆液采用P.O42.5的普通硅酸盐水泥,浆液配合比为:水泥:水玻璃为1:0.03,注浆量≥2m3,注浆管每米分三次拔管,每次拔管高度为1/3m,注浆顺序采用跳孔间隔注浆的方式。
本发明的有益效果是:
本发明的施工方法,可以有效对建(构)筑物进行保护,在施工过程中对周围土体扰动小,桩位偏差控制在20mm内,垂直度不超过1/100。适用于振动施工区域附近存在相邻建(构)筑物的保护。
附图说明
图1是树根桩隔离墙平面图示意图;
图2是本发明的施工流程图。
具体实施方式
下面结合附图与实施例对本发明作进一步的说明。
如图1所示,为了保护施工区域的建(构)筑物1,需在建(构)筑物和正在施工的区域2之间施工一道隔离墙,用来隔离施工时候产生的振动对周边的建(构)筑物的影响,减小或降低对其的不利危害,从而起到保护周边建(构)筑物的作用。
如图2所示,本发明主要采用树根桩作为隔离桩的施工方法对建(构)筑物进行保护的施工方法,主要施工流程如下:
(1)测放桩位:用钢尺沿设计要求测放树根桩3桩位,桩位偏差不大于20mm。
(2)钻机就位前,先平整场地,铺好枕木并用水平尺校正,保证钻机平稳、牢固。
(3)钻孔:经测量平面放样后,对桩中心点作好护桩工作,然后开钻。树根桩3成孔时根据土质情况采用天然泥浆或者人造泥浆进行护壁。
(4)清孔:当钻至设计深度后,拔出钻头进行清孔,清孔直至孔口基本上泛清水为止。
(5)钢筋笼制作安放:按设计和规范要求制作钢筋笼。成孔后垂直下放钢筋笼,在孔口固定好。钢筋笼接头按照设计要求错开,吊放钢筋笼和注浆管时节间钢筋搭接焊缝长度不小于10倍钢筋直径。
(6)下注浆管:每根树根桩孔内应布置两根注浆管4,注浆管4应直插到孔底,施工时应尽量缩短吊放和焊接时间,注浆管4末端临时封好。
(7)投石:根桩孔内投入粒径10~25mm小碎石,投石量为计算体积的80%~90%,碎石应先用水冲洗,在填灌过程中应始终利用注浆管注水清孔孔口流浆后。
(8)第一次压浆:注浆采用P.O42.5级普通硅酸盐水泥,水灰比0.55。注浆泵最大工作压力应不小于1.5MPa。第一次注浆压力在0.5~1.0MPa。注浆时应控制压力,使浆液均匀上冒,直至泛出孔口为止。
(9)第二次压浆:二次注浆应在第一次注浆初凝之后,在第二根注浆管4内进行二次注浆,注浆量应按设计要求控制,要求注浆压力为2.0~4.0MPa(具体视土层条件而定)。止浆标准:当浆压达1.0MPa时,灌浆量0.5L/min,稳压15min。浆液的水灰比为0.55。
(10)拔注浆管、移位:拔管后应填补桩顶混凝土至设计标高。
(11)在树根桩内部区域土体采用压密注浆方式进行加固施工。浆液采用新鲜42.5的普通硅酸盐水泥,浆液配合比为:水泥:水玻璃为1:0.03,注浆量不得少于2m3。注浆压力与土性相关:砂性土一般为0.2~0.5MPa,粘性土一般为0.2~0.3MPa,具体根据现场实施情况调整。注浆管每米分三次拔管,每次拔管高度为1 /3m,注浆顺序采用跳孔间隔注浆的方式。
Claims (4)
1.一种减少振动对周边建(构)筑物影响的施工方法,包括采用树根桩形成一道隔离墙对建筑物的保护,其特征在于:具体步骤是:
(1)定位放线
用钢尺沿设计要求测放树根桩位;钻机就位前,先平整场地,铺好枕木并用水平尺校正,保证钻机平稳、牢固;
(2)钻进成孔
经测量平面放样后,对树根桩中心点作好护桩工作,然后开钻,树根桩成孔时采用天然泥浆或者人造泥浆进行护壁;
(3)清孔
当钻至设计深度后,拔出钻头进行清孔,清孔直至孔口泛清水为止;
(4)安放钢筋笼
成孔后垂直下放钢筋笼,并在孔口固定钢筋笼,钢筋笼接头错开;吊放钢筋笼和注浆管时节间钢筋搭接焊缝长度不小于10倍钢筋直径;
(5)下注浆管
每根树根桩孔内布置两根注浆管,并且注浆管直插到孔底;
(6)投入碎石
在放置注浆管的树根桩孔内投入粒径10~25mm小碎石,投石量为桩的计算体积的80%~90%;
(7)第一次压浆
采用P.O42.5级普通硅酸盐水泥,水灰比0.55注浆,注浆压力0.5~1.0Mpa;
注浆时控制压力,使浆液均匀上冒,直至泛出孔口为止;
(8)第二次压浆
在第一次注浆初凝之后,在第二根注浆管内进行二次注浆,浆液的水灰比为0.55,注浆压力为2.0~4.0MPa;
(9)加固树根桩与施工区域
在树根桩内部区域土体采用压密注浆方式进行加固施工。
2.根据权利要求1所述的减少振动对周边建(构)筑物影响的施工方法,其特征在于:上述步骤一中,用钢尺沿设计要求测放树根桩位,桩位偏差≤20mm。
3.根据权利要求1所述的减少振动对周边建(构)筑物影响的施工方法,其特征在于:第一、二压浆中所用的注浆泵最大工作压力应≥1.5MPa。
4.根据权利要求1所述的减少振动对周边建(构)筑物影响的施工方法,其特征在于:在树根桩内部区域土体采用压密注浆方式进行加固施工的具体方法:浆液采用P.O42.5的普通硅酸盐水泥,浆液配合比为:水泥:水玻璃为1:0.03,注浆量≥2m3,注浆管每米分三次拔管,每次拔管高度为1 /3m,注浆顺序采用跳孔间隔注浆的方式。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102687128A CN102995666A (zh) | 2011-09-13 | 2011-09-13 | 减少振动对周边建(构)筑物影响的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102687128A CN102995666A (zh) | 2011-09-13 | 2011-09-13 | 减少振动对周边建(构)筑物影响的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102995666A true CN102995666A (zh) | 2013-03-27 |
Family
ID=47924722
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102687128A Pending CN102995666A (zh) | 2011-09-13 | 2011-09-13 | 减少振动对周边建(构)筑物影响的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102995666A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104389308A (zh) * | 2014-10-17 | 2015-03-04 | 中建四局第六建筑工程有限公司 | 一种基坑支护用现浇劲性桩施工方法 |
CN107882020A (zh) * | 2017-11-24 | 2018-04-06 | 苏州枫石堂工程科技有限公司 | 一种小直径树根桩施工方法及清洗注浆装置 |
CN109440545A (zh) * | 2018-11-30 | 2019-03-08 | 中铁第四勘察设计院集团有限公司 | 一种下穿运营高速铁路的路基结构及施工方法 |
CN110117953A (zh) * | 2019-05-13 | 2019-08-13 | 燕山大学 | 一种土层接触面扰动剧烈程度检测方法及系统 |
CN112726563A (zh) * | 2020-12-14 | 2021-04-30 | 宁波市轨道交通集团有限公司 | 一种用于轨道上盖物业减振的多重门型地基注浆结构及其施工方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1088587A (ja) * | 1996-09-13 | 1998-04-07 | Taisei Corp | 構造物基礎の地盤側方流動圧に対する抵抗構造 |
CN101761237A (zh) * | 2009-12-24 | 2010-06-30 | 上海隧道工程股份有限公司 | 盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法 |
-
2011
- 2011-09-13 CN CN2011102687128A patent/CN102995666A/zh active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1088587A (ja) * | 1996-09-13 | 1998-04-07 | Taisei Corp | 構造物基礎の地盤側方流動圧に対する抵抗構造 |
CN101761237A (zh) * | 2009-12-24 | 2010-06-30 | 上海隧道工程股份有限公司 | 盾构隧道近距离穿越建(构)筑物变形控制的隔离桩施工方法 |
Non-Patent Citations (2)
Title |
---|
孙友良: "树根桩在涵洞地基加固中的应用", 《江苏水利》 * |
陈金巧等: "减轻地下工程施工对环境影响的施工方案", 《青岛理工大学学报》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104389308A (zh) * | 2014-10-17 | 2015-03-04 | 中建四局第六建筑工程有限公司 | 一种基坑支护用现浇劲性桩施工方法 |
CN107882020A (zh) * | 2017-11-24 | 2018-04-06 | 苏州枫石堂工程科技有限公司 | 一种小直径树根桩施工方法及清洗注浆装置 |
CN109440545A (zh) * | 2018-11-30 | 2019-03-08 | 中铁第四勘察设计院集团有限公司 | 一种下穿运营高速铁路的路基结构及施工方法 |
CN110117953A (zh) * | 2019-05-13 | 2019-08-13 | 燕山大学 | 一种土层接触面扰动剧烈程度检测方法及系统 |
CN112726563A (zh) * | 2020-12-14 | 2021-04-30 | 宁波市轨道交通集团有限公司 | 一种用于轨道上盖物业减振的多重门型地基注浆结构及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106641440B (zh) | 一种横向穿越铁路线地下管道顶进施工方法 | |
CN104846829B (zh) | 预留盾构穿越复合式基坑围护墙及其施工方法 | |
CN104747088B (zh) | 一种钻孔灌注桩单腰多叶筒式钻头及成孔施工方法 | |
CN102146672B (zh) | 一种在岩溶地区的桩基施工方法 | |
CN105064328B (zh) | 桩基础施工装置及其方法 | |
CN104120716A (zh) | 一种泥浆护壁钻孔灌注桩施工方法 | |
CN104631470A (zh) | 高水位大粒径砂砾石地质深基坑组合支护施工方法 | |
CN106894422B (zh) | 复杂环境深基坑支护施工方法 | |
CN109505229A (zh) | 公路高陡边坡应力平衡及减振防灾高桥墩结构及施工方法 | |
CN102995666A (zh) | 减少振动对周边建(构)筑物影响的施工方法 | |
CN105696550A (zh) | 一种辅助加固地下连续墙成槽的三轴搅拌桩施工方法 | |
CN103741963A (zh) | 一种工业厂房基础加固方法 | |
CN105569051A (zh) | 一种砂卵石漂石地质层基坑支护体系及施工方法 | |
CN108842764B (zh) | 一种旋转搅拌式锚管施工方法 | |
CN106677168A (zh) | 一种超流态混凝土灌注桩的施工方法 | |
CN106988305A (zh) | 一种地下一体化成型的桩柱式桥墩施工方法 | |
CN106245655A (zh) | 利用微型钢管桩的深基坑支护施工方法 | |
CN101798823B (zh) | 通道法远程纠偏工法 | |
CN115539048A (zh) | 一种用于浅埋偏压隧道洞口施工方法 | |
CN108385669A (zh) | 一种cfg桩施工工法 | |
CN112855029B (zh) | 一种采空区钻孔外扩管施工方法 | |
CN109944251A (zh) | 软质岩层钢板桩打入的引孔施工方法 | |
CN106758759A (zh) | 一种用于深水裸岩河床的栈桥桩基及其锚固方法 | |
CN113431097A (zh) | 一种紧邻深基坑工程浅基础建筑保护结构及施工方法 | |
CN205712144U (zh) | 一种岩溶岩堆锚杆补强支挡结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130327 |