CN102953359B - 高效节水现浇排灌暗渠施工方法 - Google Patents

高效节水现浇排灌暗渠施工方法 Download PDF

Info

Publication number
CN102953359B
CN102953359B CN201210434168.4A CN201210434168A CN102953359B CN 102953359 B CN102953359 B CN 102953359B CN 201210434168 A CN201210434168 A CN 201210434168A CN 102953359 B CN102953359 B CN 102953359B
Authority
CN
China
Prior art keywords
water
canal
maintenance
film
sedimentation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210434168.4A
Other languages
English (en)
Other versions
CN102953359A (zh
Inventor
刘伟斌
叶东杰
史广喜
王静
骆望
马跃光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chenglong Construction Group Co ltd
Zhejiang Provincial No 1 Water Conservancy & Electric Power Construction Group Holdings Co ltd
Zhejiang Xinzhongyuan Construction Co ltd
Original Assignee
Zhejiang Province No1 Water Conservancy & Electric Power Construction Group Holdings Co Ltd
Zhejiang Xin Zhongyuan Construction Co Ltd
Chenglong Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Province No1 Water Conservancy & Electric Power Construction Group Holdings Co Ltd, Zhejiang Xin Zhongyuan Construction Co Ltd, Chenglong Construction Group Co Ltd filed Critical Zhejiang Province No1 Water Conservancy & Electric Power Construction Group Holdings Co Ltd
Priority to CN201210434168.4A priority Critical patent/CN102953359B/zh
Publication of CN102953359A publication Critical patent/CN102953359A/zh
Application granted granted Critical
Publication of CN102953359B publication Critical patent/CN102953359B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

本发明公开了一种高效节水现浇排灌暗渠施工方法,包括下渠体设计及配套设施设计、渠体选址及定位放线、土渠体开挖成形、渠体浇筑、渠体养护、泥砂杂物沉淀井施工、闸门施工、覆土回填、运行维护等步骤。本发明施工方便,效果好,具有节水、节能、减少占地、灌水效率高、管理方便、省工省时等优点。

Description

高效节水现浇排灌暗渠施工方法
技术领域
本发明涉及一种现浇排灌暗渠施工方法。
背景技术
目前国内外水土资源供需矛盾不断加剧,国际社会纷纷呼吁保护水土资源、节约用地、用水;国际上不少社会组织及学术团体将保护水土资源、节约用地、用水列入重要的研究课题;我国则是水土资源十分贫乏的国家,因而我国政府把保护水土资源、节约用地、用水列入了国家的基本国策,而农业用水应占社会用水量的50%以上,农业用地占社会用地的70%以上;研究探讨农业节约用地用水则大有可为。
发明内容
本发明的目的在于提供一种施工方便,效果好的高效节水现浇排灌暗渠施工方法。
本发明的技术解决方案是:
一种高效节水现浇排灌暗渠施工方法,其特征是:包括下列步骤:
(一)渠体设计及配套设施设计:
(1)渠体设计:根据时速排水道与灌水量设计渠体管径,确保3小时水面覆盖所灌区域;
(2)杂物砂石沉淀井设计:杂物砂石沉淀井井口平面面积与渠体截面积相同,杂物砂石沉淀井深度为外河底平面深度以上0.5m;
(3)闸门设计:根据支渠管径设置,闸门的底面、顶面、立面均应与支渠平行对齐;
(二)渠体选址及定位放线:
(1)渠体选址:现浇排灌暗渠选址以现行明渠或道路作排灌暗渠选址;
(2)定位放线:按照选址进行定位,每100m设立号桩并按001号,依次编号定位,并通过测试仪测定标高在号桩上注明标高,所设号桩向距渠体中心线向左偏离2m,打入号桩;
(三)土渠体开挖成形:
(1)渠体开挖:开挖时泥土均匀倒在距渠体两侧1m以外;
(2)棱边修整:当渠体开挖后,对棱边、底槽全面进行修整,去除浮土并测底标高,确保底面水平;
(四)渠体浇筑
(1)模机具吊装就位:将模机具吊装就位,吊装时用卷扬机或滑轮机吊装,入槽后进行校正水平度、垂直度,做好开启准备;
(2)开启浇筑:当模机具开启后从进料口投入商品混凝土,所投入的商品混凝土采用C25强度,水灰比应为0.55-0.6,坍落度为6-8cm;
(3)底半槽渠修理:当底半槽渠浇筑后,对裂边、毛边进行修整,并涂刷一层塑性砂浆抹面,确保内壁光滑;
(4)安装内模气囊,内模气囊直径与设计渠体直径相同,并检查气囊是否牢固、是否渗气现象;
(5)进行浇筑成形,抽出气囊,拆除机具;
(五)渠体养护
(1)保养保温膜制作:选用柔性抗晒抗冻0.5mm厚的塑料薄膜和Ф1mm空心塑胶管及Ф5mm空心塑胶管;其中Ф1mm空心塑胶管作支流管,Ф5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;其主流管按2cm距离钻眼孔,孔径为1mm,然后将塑胶纸平铺在制作台上,刷粘合剂,按间距2cm横向铺贴Ф1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根Ф5mm塑胶管,并将Ф1mm空心塑胶管插入Ф5mm孔眼,周边涂入粘合剂,然后再将预先准备的眼状膜覆盖上面,完成保养保温膜制作;
(2)眼状膜制作:混合结构体保养保温膜由底面膜、支流管、主流管、眼状膜组成;眼状膜是覆盖在支流管、主流管上的一层膜,该膜有与支流管相对应的眼孔;制作眼状膜是在商品膜上按横向2cm间距,纵向0.5cm间距,钻Ф0.1孔径眼;钻孔眼时,设与薄膜幅度相等的木板,木板上按横向2cm间距,纵向0.5cm间距,植入Ф0.1mm钢钉,制作眼状膜钻孔板,用眼状膜钻孔板在薄膜上轻轻敲打,即可形成;
(3)保养保温铺贴:将保温保养膜平铺在所需保养的路面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
(4)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;水箱制作后,并当保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混合结构体高度的至少2m,采用蹬式安装或竿式吊装均可;安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
(5)保养保温设施拆除:当保养期满后,拆除保养保温设施;拆除时应先拆除贮水箱,然后掀开保护网,再掀开保护膜,并将保护网、膜,卷叠绑扎,留作再用;
(六)泥砂杂物沉淀井施工
(1)沉淀井区位确定:渠体长度每300-500m设置一个沉淀井,选择近邻河道;
(2)成井机制作:采用3mm厚钢板焊接成圆桶形,桶形直径Φ=井径直径Φ,高度按井径深度确定;
(3)打井:当成井机制作后,配以空压机一次性打井成形;
(4)浇筑:当土井形成后,采用圆桶形钢桶直接浇筑振捣密实,卸模即可;
(七)闸门施工
(1)出水门施工:水门设置为直方形,宽度=支渠直径长度,且制成模板采用C25混凝土浇筑,门框宽度为5cm,厚度为5cm,在内侧设置闸门槽,槽口深度为2cm,宽度为2cm;
(2)闭水门采用2cm钢板或塑胶板或预制板,闭水门规格长宽=出水门长宽,厚度为2cm,在闭水门上安装提门竿,提门竿在固定闭水门部分为扁钢,厚度为1cm,并焊接三个螺栓,套入闭水门孔,用螺母固定,其它部分为圆钢,直径Φ1cm,并绞成丝牙;
(3)闭水圈:采用橡胶制成,圈围在闭门三边上;
(4)固定栓:梁由木质、钢质或混砼土制成,在横梁上固定提门器,并与开音器配合进行开启与关闭;
(八)覆土回填:当混合结构体渠保养期满,沉淀井、闸门浇筑安装完成后进行覆土,覆土时采用分层覆土,每层厚度不超过30cm,且分层夯实,总体覆土厚度≥60cm以上,便于种植或筑路;
(九)运行维护:需要供水时开启闸门,按供水量大小控制开启闸门大小;为保证水流顺畅、关闭灵活,一般每两年进行一次维护,更换闭水圈,对闭水圈不能闭水的及时更换;另外对沉淀井处每两年开启一次沉淀井出水口,将沉淀井中的泥砂杂质冲出,确保水流畅通。
本发明施工方便,效果好,具有节水、节能、减少占地、灌水效率高、管理方便、省工省时等优点。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种高效节水现浇排灌暗渠施工方法,包括下列步骤:
(一)渠体设计及配套设施设计:
(1)渠体设计:根据时速排水道与灌水量设计渠体管径,确保3小时水面覆盖所灌区域;
(2)杂物砂石沉淀井设计:杂物砂石沉淀井井口平面面积与渠体截面积相同,杂物砂石沉淀井深度为外河底平面深度以上0.5m;
(3)闸门设计:根据支渠管径设置,闸门的底面、顶面、立面均应与支渠平行对齐;
(二)渠体选址及定位放线:
(1)渠体选址:现浇排灌暗渠选址以现行明渠或道路作排灌暗渠选址;
(2)定位放线:按照选址进行定位,每100m设立号桩并按001号,依次编号定位,并通过测试仪测定标高在号桩上注明标高,所设号桩向距渠体中心线向左偏离2m,打入号桩;
(三)土渠体开挖成形:
(1)渠体开挖:开挖时泥土均匀倒在距渠体两侧1m以外;
(2)棱边修整:当渠体开挖后,对棱边、底槽全面进行修整,去除浮土并测底标高,确保底面水平;
(四)渠体浇筑
(1)模机具吊装就位:将模机具吊装就位,吊装时用卷扬机或滑轮机吊装,入槽后进行校正水平度、垂直度,做好开启准备;
(2)开启浇筑:当模机具开启后从进料口投入商品混凝土,所投入的商品混凝土采用C25强度,水灰比应为0.55-0.6,坍落度为6-8cm;
(3)底半槽渠修理:当底半槽渠浇筑后,对裂边、毛边进行修整,并涂刷一层塑性砂浆抹面,确保内壁光滑;
(4)安装内模气囊,内模气囊直径与设计渠体直径相同,并检查气囊是否牢固、是否渗气现象;
(5)进行浇筑成形,抽出气囊,拆除机具;
(五)渠体养护
(1)保养保温膜制作:选用柔性抗晒抗冻0.5mm厚的塑料薄膜和Ф1mm空心塑胶管及Ф5mm空心塑胶管;其中Ф1mm空心塑胶管作支流管,Ф5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;其主流管按2cm距离钻眼孔,孔径为1mm,然后将塑胶纸平铺在制作台上,刷粘合剂,按间距2cm横向铺贴Ф1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根Ф5mm塑胶管,并将Ф1mm空心塑胶管插入Ф5mm孔眼,周边涂入粘合剂,然后再将预先准备的眼状膜覆盖上面,完成保养保温膜制作;
(2)眼状膜制作:混合结构体保养保温膜由底面膜、支流管、主流管、眼状膜组成;眼状膜是覆盖在支流管、主流管上的一层膜,该膜有与支流管相对应的眼孔;制作眼状膜是在商品膜上按横向2cm间距,纵向0.5cm间距,钻Ф0.1孔径眼;钻孔眼时,设与薄膜幅度相等的木板,木板上按横向2cm间距,纵向0.5cm间距,植入Ф0.1mm钢钉,制作眼状膜钻孔板,用眼状膜钻孔板在薄膜上轻轻敲打,即可形成;
(3)保养保温铺贴:将保温保养膜平铺在所需保养的路面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
(4)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;水箱制作后,并当保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混合结构体高度的至少2m,采用蹬式安装或竿式吊装均可;安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
(5)保养保温设施拆除:当保养期满后,拆除保养保温设施;拆除时应先拆除贮水箱,然后掀开保护网,再掀开保护膜,并将保护网、膜,卷叠绑扎,留作再用;
(六)泥砂杂物沉淀井施工
(1)沉淀井区位确定:渠体长度每300-500m设置一个沉淀井,选择近邻河道;
(2)成井机制作:采用3mm厚钢板焊接成圆桶形,桶形直径Φ=井径直径Φ,高度按井径深度确定;
(3)打井:当成井机制作后,配以空压机一次性打井成形;
(4)浇筑:当土井形成后,采用圆桶形钢桶直接浇筑振捣密实,卸模即可;
(七)闸门施工
(1)出水门施工:水门设置为直方形,宽度=支渠直径长度,且制成模板采用C25混凝土浇筑,门框宽度为5cm,厚度为5cm,在内侧设置闸门槽,槽口深度为2cm,宽度为2cm;
(2)闭水门采用2cm钢板或塑胶板或预制板,闭水门规格长宽=出水门长宽,厚度为2cm,在闭水门上安装提门竿,提门竿在固定闭水门部分为扁钢,厚度为1cm,并焊接三个螺栓,套入闭水门孔,用螺母固定,其它部分为圆钢,直径Φ1cm,并绞成丝牙;
(3)闭水圈:采用橡胶制成,圈围在闭门三边上;
(4)固定栓:梁由木质、钢质或混砼土制成,在横梁上固定提门器,并与开音器配合进行开启与关闭;
(八)覆土回填:当混合结构体渠保养期满,沉淀井、闸门浇筑安装完成后进行覆土,覆土时采用分层覆土,每层厚度不超过30cm,且分层夯实,总体覆土厚度≥60cm以上,便于种植或筑路;
(九)运行维护:需要供水时开启闸门,按供水量大小控制开启闸门大小;为保证水流顺畅、关闭灵活,一般每两年进行一次维护,更换闭水圈,对闭水圈不能闭水的及时更换;另外对沉淀井处每两年开启一次沉淀井出水口,将沉淀井中的泥砂杂质冲出,确保水流畅通。

Claims (1)

1.一种高效节水现浇排灌暗渠施工方法,其特征是:包括下列步骤:
(一)渠体设计及配套设施设计:
(1)渠体设计:根据时速排水道与灌水量设计渠体管径,确保3小时水面覆盖所灌区域;
(2)杂物砂石沉淀井设计:杂物砂石沉淀井井口平面面积与渠体截面积相同,杂物砂石沉淀井深度为外河底平面深度以上0.5m;
(3)闸门设计:根据支渠管径设置,闸门的底面、顶面、立面均应与支渠平行对齐;
(二)渠体选址及定位放线:
(1)渠体选址:现浇排灌暗渠选址以现行明渠或道路作排灌暗渠选址;
(2)定位放线:按照选址进行定位,每100m设立号桩并按001号,依次编号定位,并通过测试仪测定标高在号桩上注明标高,所设号桩向距渠体中心线向左偏离2m,打入号桩;
(三)土渠体开挖成形:
(1)渠体开挖:开挖时泥土均匀倒在距渠体两侧1m以外;
(2)棱边修整:当渠体开挖后,对棱边、底槽全面进行修整,去除浮土并测底标高,确保底面水平;
(四)渠体浇筑
(1)模机具吊装就位:将模机具吊装就位,吊装时用卷扬机或滑轮机吊装,入槽后进行校正水平度、垂直度,做好开启准备;
(2)开启浇筑:当模机具开启后从进料口投入商品混凝土,所投入的商品混凝土采用C25强度,水灰比应为0.55-0.6,坍落度为6-8cm;
(3)底半槽渠修理:当底半槽渠浇筑后,对裂边、毛边进行修整,并涂刷一层塑性砂浆抹面,确保内壁光滑;
(4)安装内模气囊,内模气囊直径与设计渠体直径相同,并检查气囊是否牢固、是否渗气现象;
(5)进行浇筑成形,抽出气囊,拆除机具;
(五)渠体养护
(1)保养保温膜制作:选用柔性抗晒抗冻0.5mm厚的塑料薄膜和Ф1mm空心塑胶管及Ф5mm空心塑胶管;其中Ф1mm空心塑胶管作支流管,Ф5mm塑胶管作主流管,将支流管侧面按0.5cm距离钻孔,孔径为0.1m;其主流管按2cm距离钻眼孔,孔径为1mm,然后将塑胶纸平铺在制作台上,刷粘合剂,按间距2cm横向铺贴Ф1mm空心胶管,铺贴时眼孔朝上,然后纵向顶面铺贴2-3根Ф5mm塑胶管,并将Ф1mm空心塑胶管插入Ф5mm孔眼,周边涂入粘合剂,然后再将预先准备的眼状膜覆盖上面,完成保养保温膜制作;
(2)眼状膜制作:混合结构体保养保温膜由底面膜、支流管、主流管、眼状膜组成;眼状膜是覆盖在支流管、主流管上的一层膜,该膜有与支流管相对应的眼孔;制作眼状膜是在商品膜上按横向2cm间距,纵向0.5cm间距,钻Ф0.1mm孔径眼;钻孔眼时,设与薄膜幅度相等的木板,木板上按横向2cm间距,纵向0.5cm间距,植入Ф0.1mm钢钉,制作眼状膜钻孔板,用眼状膜钻孔板在薄膜上轻轻敲打,即可形成;
(3)保养保温铺贴:将保养保温膜平铺在所需保养的路面上,铺贴后,在保养保温膜上覆盖保护网;保护网由聚丙烯线编制成,网眼为10×10cm,并将网绷紧压入地面;
(4)贮水箱制作与安装:选择塑胶桶或铁桶,在桶底安装控水阀门和水咀,水咀咀头直径≤5mm;水箱制作后,并当保养保温膜铺贴后,进行水箱安装,水箱高度高于所保养混合结构体高度的至少2m,采用蹬式安装或竿式吊装均可;安装后,将主流管连接贮水箱水咀,然后将水箱灌满水,打开阀门,实施保养;
(5)保养保温设施拆除:当保养期满后,拆除保养保温设施;拆除时应先拆除贮水箱,然后掀开保护网,并将保护网,卷叠绑扎,留作再用;
(六)泥砂杂物沉淀井施工
(1)沉淀井区位确定:渠体长度每300-500m设置一个沉淀井,选择近邻河道;
(2)成井机制作:采用3mm厚钢板焊接成圆桶形,桶形直径Φ=井径直径Φ,高度按井径深度确定;
(3)打井:当成井机制作后,配以空压机一次性打井成形;
(4)浇筑:当土井形成后,采用圆桶形钢桶直接浇筑振捣密实,卸模即可;
(七)闸门施工
(1)出水门施工:水门设置为直方形,宽度=支渠直径长度,且制成模板采用C25混凝土浇筑,门框宽度为5cm,厚度为5cm,在内侧设置闸门槽,槽口深度为2cm,宽度为2cm;
(2)闭水门采用2cm钢板或塑胶板或预制板,闭水门规格长宽=出水门长宽,厚度为2cm,在闭水门上安装提门竿,提门竿在固定闭水门部分为扁钢,厚度为1cm,并焊接三个螺栓,套入闭水门孔,用螺母固定,其它部分为圆钢,直径Φ1cm,并绞成丝牙;
(3)闭水圈:采用橡胶制成,圈围在闭门三边上;
(4)固定栓:梁由木质、钢质或混砼土制成,在横梁上固定提门器,并与开音器配合进行开启与关闭;
(八)覆土回填:当混合结构体渠保养期满,沉淀井、闸门浇筑安装完成后进行覆土,覆土时采用分层覆土,每层厚度不超过30cm,且分层夯实,总体覆土厚度≥60cm,便于种植或筑路;
(九)运行维护:需要供水时开启闸门,按供水量大小控制开启闸门大小;为保证水流顺畅、关闭灵活,每两年进行一次维护,更换闭水圈,对闭水圈不能闭水的及时更换;另外对沉淀井处每两年开启一次沉淀井出水口,将沉淀井中的泥砂杂质冲出,确保水流畅通。
CN201210434168.4A 2012-11-05 2012-11-05 高效节水现浇排灌暗渠施工方法 Expired - Fee Related CN102953359B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210434168.4A CN102953359B (zh) 2012-11-05 2012-11-05 高效节水现浇排灌暗渠施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210434168.4A CN102953359B (zh) 2012-11-05 2012-11-05 高效节水现浇排灌暗渠施工方法

Publications (2)

Publication Number Publication Date
CN102953359A CN102953359A (zh) 2013-03-06
CN102953359B true CN102953359B (zh) 2014-09-03

Family

ID=47762702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210434168.4A Expired - Fee Related CN102953359B (zh) 2012-11-05 2012-11-05 高效节水现浇排灌暗渠施工方法

Country Status (1)

Country Link
CN (1) CN102953359B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103374904B (zh) * 2013-07-02 2015-09-23 东营市黄河三角洲保护与发展研究中心 农田排灌模式转换节地节水方法
CN103498565A (zh) * 2013-10-14 2014-01-08 成军 建筑物混构体自控性节水保养保温施工方法
CN106759126B (zh) * 2017-02-24 2018-08-17 化学工业岩土工程有限公司 一种边坡支护排水渠的施工方法
CN114808859A (zh) * 2022-06-09 2022-07-29 陈利 一种北方高寒地区混凝土渠道结构及施工工艺

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100493339C (zh) * 2007-02-03 2009-06-03 奕永庆 农田排灌系列设施
CN101619570A (zh) * 2008-07-06 2010-01-06 孙加林 一种现浇水泥暗渠施工机具
US8192109B2 (en) * 2010-01-27 2012-06-05 Alsaffar Abdulreidha Abdulrasoul Subsurface irrigation system
CN201898767U (zh) * 2010-06-22 2011-07-20 王鹏 暗渠蓄水渗灌设施
CN201809755U (zh) * 2010-10-09 2011-04-27 王勤 凹槽式农田自动排灌防洪装置
CN201962655U (zh) * 2010-10-14 2011-09-07 中国水利水电科学研究院 一种用于坡耕地灌溉系统的谷坊排水结构
CN202466544U (zh) * 2012-03-12 2012-10-03 江苏省水利科学研究院 一种沿海垦区灌排沟渠
CN102704437A (zh) * 2012-06-14 2012-10-03 中国矿业大学 一种适用复杂山区的采煤塌陷区耕作水源再造方法

Also Published As

Publication number Publication date
CN102953359A (zh) 2013-03-06

Similar Documents

Publication Publication Date Title
CN103758084B (zh) 一种生态河道联锁型砌块及其构筑护坎的施工工法
CN106978843A (zh) 市政排水管道施工工艺
CN106320120B (zh) 一种桩板式无土路基公路施工工艺
CN103669291B (zh) 联接式护坡砖护坡的施工方法
CN102953359B (zh) 高效节水现浇排灌暗渠施工方法
CN105804007B (zh) 一种基于滩涂软基的加筋土岸墙结构
CN109113129A (zh) 一种灌溉与排水系统及输水渠道的施工方法
CN101787701B (zh) 电梯井基坑松木桩支护施工工法
CN103437379B (zh) 地下室底板后浇带施工与排水方法
CN110374181A (zh) 一种雨水收集池及其施工方法
CN100516367C (zh) 跨河大桥水中墩土工充泥管袋围堰及其制备方法
CN203768925U (zh) 一种基坑内降水井的封堵装置
CN114319875A (zh) 一种超大面积混凝土地面无缝施工工艺
CN106120822A (zh) 一种防止泥岩滑坡的支护方法及装置
CN212272234U (zh) 一种大断面斜井明槽段高强度组合模板
CN105756100A (zh) 地下室后浇带系统及其制备方法
CN216075134U (zh) 一种富水区临湖砂性土深基坑坡顶施工道路结构
CN201686965U (zh) 导流隧洞现浇钢筋混凝土闸门
CN206189430U (zh) 用于深覆盖层地基的排水沟
CN206143783U (zh) 一种防止泥岩滑坡的支护装置
CN109024645A (zh) 一体化止水帷幕、海绵城市水循环系统和方法
CN105887760B (zh) 一种生态型的破损护岸修复结构
CN201080616Y (zh) 跨河大桥水中墩土工充泥管袋围堰
CN114855704A (zh) 一种护坡截流抛投用预制砼
CN202073107U (zh) 一种降水井封闭结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: ZHEJIANG NO.1 WATER CONSERVANCY + ELECTRIC POWER C

Effective date: 20140723

Owner name: CHENGLONG CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: GE JIAJUN

Effective date: 20140723

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Liu Weibin

Inventor after: Ye Dongjie

Inventor after: Shi Guangxi

Inventor after: Wang Jing

Inventor after: Luo Wang

Inventor after: Ma Yueguang

Inventor before: Ge Jiajun

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 226400 NANTONG, JIANGSU PROVINCE TO: 322000 JINHUA, ZHEJIANG PROVINCE

Free format text: CORRECT: INVENTOR; FROM: GE JIAJUN TO: LIU WEIBIN YE DONGJIE SHI GUANGXI WANG JING LUO WANG MA YUEGUANG

TA01 Transfer of patent application right

Effective date of registration: 20140723

Address after: 322000 Yiwu Airport Road, Zhejiang, No. 669, No.

Applicant after: CHENGLONG CONSTRUCTION GROUP Co.,Ltd.

Applicant after: ZHEJIANG PROVINCIAL NO. 1 WATER CONSERVANCY & ELECTRIC POWER CONSTRUCTION GROUP HOLDINGS CO.,LTD.

Applicant after: ZHEJIANG XINZHONGYUAN CONSTRUCTION Co.,Ltd.

Address before: Rudong County, Jiangsu province 226400 Nantong juegang Taishan Road East Development Building 1002

Applicant before: Ge Jiajun

C14 Grant of patent or utility model
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20210412

Granted publication date: 20140903

PD01 Discharge of preservation of patent
PD01 Discharge of preservation of patent

Date of cancellation: 20220801

Granted publication date: 20140903

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140903