CN102927863B - A kind of new method of total rock tunnel blasting construction - Google Patents

A kind of new method of total rock tunnel blasting construction Download PDF

Info

Publication number
CN102927863B
CN102927863B CN201110237848.2A CN201110237848A CN102927863B CN 102927863 B CN102927863 B CN 102927863B CN 201110237848 A CN201110237848 A CN 201110237848A CN 102927863 B CN102927863 B CN 102927863B
Authority
CN
China
Prior art keywords
cannelure
borehole
stemming
explosive
priming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110237848.2A
Other languages
Chinese (zh)
Other versions
CN102927863A (en
Inventor
李立华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201110237848.2A priority Critical patent/CN102927863B/en
Publication of CN102927863A publication Critical patent/CN102927863A/en
Application granted granted Critical
Publication of CN102927863B publication Critical patent/CN102927863B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The new method of a kind of total rock tunnel blasting construction, the present invention relates to the technical field of roadway blast working, and it includes cannelure, borehole, electric cap, mining explosive, rapid hardening glue, stemming, blows out line, exploder etc..It is characterized in that: be respectively arranged the borehole parallel with the bus of cannelure cell wall being perpendicular to, with extraordinary rig, the inside and outside of cannelure that work surface gets out.During powder charge, for the borehole within cannelure, first fill priming and the explosive of instant electric detonator, breeching mud, rapid hardening glue and stemming the most successively, or first fill priming and the explosive of instant electric detonator, then breeching mud, rapid hardening glue, stemming, the priming of delay electric detonator, explosive and stemming successively;For the borehole outside cannelure, first the dress extension time is more than the priming of the electric cap of electric cap extension time, breech-loading gun mud in the internal borehole of cannelure.Connect big gun by common serial or parallel connection method after powder charge and detonate.Can be by the rock pillar in cannelure or dish out and collapse broken after explosion, explosion in this way, the broken swollen space of rock that not only can provide necessary realizes medium-length hole blasting, it is also possible to improve driving speed more than 0.5 1 times.

Description

A kind of new method of total rock tunnel blasting construction
Technical field:
The present invention relates to roadway blasting construction method.
Background technology:
At present both at home and abroad total rock tunnel blasting technology construction jewel hole amount is big, time-consuming, laborious, take gunpowder, and driving speed is low, many Number coal mine excavation imbalance, adjust difficulty, particularly medium-length hole and deep hole blasting technology solve slotting problem owing to having no idea and Can not well apply, as a whole, existing total rock tunnel blasting has a disadvantage in that
1, jewel hole quantity is many, and powder charge is many, detonates often.
2, waste gunpowder is many.
3, the harmful gas produced is many.
4, blasting energy is big, is easily caused rock crusher, roof fall wall caving.
5, the engineering time is long, and efficiency is low.
Summary of the invention:
The invention reside in and design a kind of total rock tunnel blasting speed of application soon, efficiency is high, it is achieved medium-length hole blasting is easy, Save gunpowder, the new method that protection country rock is effective.
The technical scheme is that the new method that a kind of total rock tunnel blasting is constructed, it includes cannelure, borehole, wink Electric detonator, delay electric detonator, mining explosive, rapid hardening glue, stemming, blow out line, exploder, earpick, punching water pipe and tamper Deng.It is characterized in that: be respectively arranged and cannelure being perpendicular to, with extraordinary rig, the inside and outside of cannelure that work surface gets out The parallel borehole of bus.Borehole depth within cannelure more than the degree of depth of cannelure, borehole depth cannelure outside and The deep equality of cannelure.After earpick and the clear hole of water pipe, clear hole, the borehole within cannelure first fills carry out the coffin upon burial in wink medicine and explosive, Breeching mud, rapid hardening glue, stemming the most successively.Borehole outside cannelure, first fills priming and the explosive of delay electric detonator, then breeching Mud, uses common serial or parallel connection method connect big gun and can make the borehole once detonation inside and outside cannelure after installing big gun.Explosion Time the detonation wave that produces of carry out the coffin upon burial in wink medicine and explosive within cannelure the rock pillar of cannelure inner bottom part is broken, and by high-temperature gas Rock pillar in cannelure is dished out outside groove by the pressure produced, and the borehole outside cannelure detonates subsequently, outside avalanche cannelure Rock.
The present invention can also be achieved in that:
A kind of new method of stone head blast working, it include cannelure, borehole, instant electric detonator, delay electric detonator, Mining explosive, rapid hardening glue, stemming, blow out line, exploder, earpick, punching water pipe and tamper etc..It is characterized in that: by special type Rig is perpendicular to the inside and outside of cannelure that work surface gets out and is respectively arranged the borehole parallel with the bus of cannelure.Annular Borehole depth within groove is more than the deep equality of the degree of depth of cannelure, the borehole depth outside cannelure and cannelure.With drawing After ear picker and the clear hole of water pipe, clear hole, the borehole within cannelure first fills carry out the coffin upon burial in wink medicine and explosive, more successively breeching mud, rapid hardening glue, Stemming, explosive, the priming of delay electric detonator and stemming, the borehole outside cannelure, first the dress extension time is more than inside cannelure In borehole, the delay priming of time and the explosive of electric cap, refill stemming, uses common method to connect big gun can after installing stemming So that the borehole once detonation inside and outside cannelure.The detonation wave that during explosion, carry out the coffin upon burial in wink medicine and explosive within cannelure produces is by ring The rock pillar of shape groove inner bottom part breaks, and the pressure produced by high-temperature gas groove of being dished out by the rock pillar in cannelure is outer and collapse broken.Ring Borehole outside shape groove detonates subsequently, the rock outside avalanche cannelure.
The main feature of the present invention:
1, first arrange cannelure at work surface, work surface rock mass is divided into cylindrical-shaped structure, shape around borehole Become the omnibearing scope of freedom, the stress of rock when changing explosion, it is possible to reach a big gun cavitation, the effect of two big gun grooving Really.
2, provide, for deep hole blasting, the free space that fractured rock expands.
3, straight eye explosion can be realized, improve blast hole utilization factor.
4, the efficiency of borehole avalanche rock is high.
5, reducing borehole number, shorten drilling time, save gunpowder consumption, the harmful gas produced during explosion is few, reduces Ventilate and dispel the time used by blasting fume.
6, driving speed can be greatly improved, reduce excavation cost, open up make new advances for solving coal mine excavation imbalance Approach.
Accompanying drawing illustrates:
Fig. 1: cannelure of the present invention and borehole arrange the structural representation of detailed description of the invention
Fig. 2: the detailed description of the invention schematic diagram of borehole (2) charge constitution in cannelure of the present invention
Fig. 3: the detailed description of the invention schematic diagram of borehole (2) charge constitution in cannelure of the present invention
The detailed description of the invention schematic diagram of outer borehole (3) charge constitution of Fig. 4: cannelure of the present invention
Fig. 5: bursting work detailed description of the invention schematic diagram of the present invention
1, the borehole 3 within cannelure 2, cannelure, the borehole outside cannelure
4, explosive 5, instant electric detonator 6, rapid hardening glue 7, stemming
8, delay time shorter electric cap 9, time of delaying longer electric cap 10, detonator payment to a porter
11, connecting line 12, bus 13, blow out line 14, blaster
The invention will be further described below in conjunction with the accompanying drawings
Detailed description of the invention:
1, seeing Fig. 1, a figure is that the master of the borehole (2) within cannelure (1), cannelure and the outside borehole (3) of cannelure regards Figure, b figure is its side view.
Seeing the charge constitution figure that Fig. 2, Fig. 2 are borehole (2), wherein (5) are instant electric detonator, and (4) are explosive, and (6) are Rapid hardening glue, (7) are stemming, and (9) are detonator payment to a porter.
Seeing the charge constitution figure that Fig. 4, Fig. 4 are borehole (3), wherein (10) are extension time longer electric cap, and (4) are Explosive, (7) are stemming, and (9) are detonator payment to a porter.
Seeing Fig. 5, Fig. 5 is bursting work figure, wherein the borehole (2) within 2 cannelures and the big gun outside 3 cannelures Eye (3) is parallel on connecting line (11) a, b 2 by payment to a porter (10), and connecting line is in c, d 2 and bus (12) one end phase Connect, the other end of bus e point with blow out one end of line (13) and be connected, the other end of line of blowing out passes through to connect with blaster (14) Terminal f, g connect.Start blaster energising explosion.
2, seeing Fig. 1, a figure is that the master of the borehole (2) within cannelure (1), cannelure and the outside borehole (3) of cannelure regards Figure, b figure is its side view.
Seeing the charge constitution figure that Fig. 3, Fig. 3 are borehole (2), wherein (5) are instant electric detonator, and (4) are explosive, and (6) are Rapid hardening glue, (7) are stemming, and (8) are extension time shorter electric cap, and (9) are detonator payment to a porter.
Seeing the charge constitution figure that Fig. 4, Fig. 4 are borehole (3), (4) are explosive, and (7) are stemming, and (9) are detonator payment to a porter, (10) it is extension time longer electric cap.
Seeing Fig. 5, Fig. 5 is that wherein the borehole (2) within 2 cannelures and the borehole (3) outside 3 cannelures pass through foot Line (10) is parallel on connecting line (11) a, b 2, and connecting line is connected with bus (12) one end c, d 2, bus The other end e point with blow out one end of line (13) and be connected, blow out line the other end with blaster (14) by binding post f, g even Connect.Start blaster energising explosion.

Claims (3)

1. a method for total rock tunnel blasting construction, it includes being perpendicular to, with extraordinary rig, cannelure, the big gun that work surface gets out Eye, electric cap, mining explosive, rapid hardening glue, stemming, blowing out line, earpick, punching water pipe, tamper and exploder, its feature exists In, inside and outside at cannelure is respectively arranged the borehole parallel with the bus of cannelure cell wall, annular of first detonating when detonating Borehole within groove, after detonate the borehole outside cannelure.
The method of a kind of total rock tunnel blasting the most according to claim 1 construction, it is characterised in that the internal borehole of cannelure Loading method be: first fill priming and the explosive of instant electric detonator, then breeching mud, rapid hardening glue, stemming successively.
The method of a kind of total rock tunnel blasting the most according to claim 1 construction, it is characterised in that the internal borehole of cannelure Loading method be: first fill priming and the explosive of instant electric detonator, then breeching mud, rapid hardening glue, stemming, delay electric detonator successively Priming, stemming.
CN201110237848.2A 2011-08-11 2011-08-11 A kind of new method of total rock tunnel blasting construction Expired - Fee Related CN102927863B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110237848.2A CN102927863B (en) 2011-08-11 2011-08-11 A kind of new method of total rock tunnel blasting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110237848.2A CN102927863B (en) 2011-08-11 2011-08-11 A kind of new method of total rock tunnel blasting construction

Publications (2)

Publication Number Publication Date
CN102927863A CN102927863A (en) 2013-02-13
CN102927863B true CN102927863B (en) 2016-08-24

Family

ID=47642724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110237848.2A Expired - Fee Related CN102927863B (en) 2011-08-11 2011-08-11 A kind of new method of total rock tunnel blasting construction

Country Status (1)

Country Link
CN (1) CN102927863B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178389B (en) * 2017-06-21 2018-12-21 永城煤电控股集团有限公司 Coal mine gas drainage Deephole pre-splitting blasting permeability improvement device and its method
CN107762399A (en) * 2017-11-24 2018-03-06 中交第二航务工程局有限公司 Explosion coordinates rotary drilling rig deep layer one-step pore-creating construction method
CN108692622A (en) * 2018-03-28 2018-10-23 中交公局第三工程有限公司 A kind of method of tunnel photoface exploision

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101266123A (en) * 2007-03-15 2008-09-17 鞍钢集团矿业公司 Crushing station pit digging method
CN101441055A (en) * 2008-12-31 2009-05-27 中煤平朔煤业有限责任公司 Presplit blasting method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100323151B1 (en) * 1999-12-31 2002-02-06 조영동 Tunnel blasting method with large empty holes and pre-splitting of circular cut

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101266123A (en) * 2007-03-15 2008-09-17 鞍钢集团矿业公司 Crushing station pit digging method
CN101441055A (en) * 2008-12-31 2009-05-27 中煤平朔煤业有限责任公司 Presplit blasting method

Also Published As

Publication number Publication date
CN102927863A (en) 2013-02-13

Similar Documents

Publication Publication Date Title
CN103940309B (en) A kind of method of underground blasting Cheng Jing
CN108007285B (en) A kind of efficient Cut Blasting method of stone head deep hole sublevel segmentation
CN103321669B (en) Method for increasing permeability of low-permeability coal seam by means of deep-hole directional pre-splitting blasting
CN105333778A (en) Medium-deep hole large-section composite cut blasting structure and method
CN104634199B (en) Utilize primacord and Nonel detonator to realize the method for tunnel perimeter eye photoface exploision
CN103195466A (en) Directional water pressure blasting method for improving coal bed gas permeability
CN103244180B (en) Gob-side entry driving surrounding rock control method using remaining small pillars
CN101419040A (en) Deep hole blasting method in large aperture composite undermine
CN103063094A (en) Channeling method in rapid roadway explosion
CN202630821U (en) Directional energy collection fracture blasting device of lancing pipe
CN101864961B (en) Method for actively preventing and controlling rock burst
CN104482816B (en) A kind of vertical periphery segment algorithm gradient presplit blasting method and device
CN104819670B (en) Pre-drilling mesopore shaft excavation blasting method
CN103575172A (en) Novel roadway blasting construction method
CN104406470B (en) Western Cretaceous System Soft Rock Area major diameter freezing shaft deep hole Cut Blasting method
CN102168543A (en) Method and apparatus of improving recovery efficiency of shale gas through a blast mode
CN104154830A (en) Medium-length hole blasting method for underground mining
CN105823387A (en) Rapid construction method for deep hole blasting of vertical shaft frozen bedrock
CN106643355B (en) A kind of overhead caving method of the huge thick tight roof of deep coalmine
CN102927863B (en) A kind of new method of total rock tunnel blasting construction
CN103697775A (en) Method of loose blasting by high-pressure water jet helical cutting
CN106121644B (en) The water-filling pressure-bearing unloading pressure by blasting of cellular structure and supporting reinforcement are crosslinked based on drilling in coal and rock plane
CN108362179A (en) A kind of energy saving cut shot method of star
CN209230424U (en) A kind of compound burn cut
CN104847350A (en) Method for treating suspended roof by medium-length hole blasting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 302 room 3, unit 49, Xiangyang District, pointed mountain, Heilongjiang, Shuangyashan 155100, China

Applicant after: Li Lihua

Address before: 155100 Shuangyashan Province, sharp mountain city, the emerging street, No. 60

Applicant before: Li Lihua

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Li Lihua

Document name: Notification to Pay the Fees

DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Li Lihua

Document name: Notice of termination of patent right

DD01 Delivery of document by public notice
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160824

Termination date: 20210811

CF01 Termination of patent right due to non-payment of annual fee