CN102912978A - One-step forming temporary protection device for floor reserved hole and construction method - Google Patents

One-step forming temporary protection device for floor reserved hole and construction method Download PDF

Info

Publication number
CN102912978A
CN102912978A CN2012104399473A CN201210439947A CN102912978A CN 102912978 A CN102912978 A CN 102912978A CN 2012104399473 A CN2012104399473 A CN 2012104399473A CN 201210439947 A CN201210439947 A CN 201210439947A CN 102912978 A CN102912978 A CN 102912978A
Authority
CN
China
Prior art keywords
floor
cover plate
reserved opening
protection device
structure floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104399473A
Other languages
Chinese (zh)
Inventor
余曦
屠孝军
王永红
罗琦建
董玉平
刘会玲
黄�俊
周蔚文
曹振杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN2012104399473A priority Critical patent/CN102912978A/en
Publication of CN102912978A publication Critical patent/CN102912978A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to a one-step forming temporary protection device for a floor reserved hole and a construction method. The protection device comprises that a bottom die is arranged at the bottom of a structural floor reserved hole, side dies are installed on the periphery of the structural floor reserved hole on the bottom die, a cover board is installed at the tops of the side dies and level with the structural floor surface, and the sizes of the cover plate sides are 2 cm to 5 cm larger than the size of the reserved hole. The one-step forming temporary protection device for the floor reserved hole and the construction method have the advantages that the reserved hole sealing and the floor concrete casting are performed simultaneously and formed through one step, a floor hole blocking protection process is performed after the concrete is casted, and accordingly, time and labor are saved. After the reserved hole is blocked temporarily, an L-shaped water proof structure is formed between the cover plate and concrete, so that rainwater and construction water can be effectively prevented from permeating into a next floor, the environmental protection effect is apparent, secondary pollution reconstruction after decoration is prevented, and the reconstruction cost is saved. Besides, the decoration and the mechanical and electrical installation can be performed in advance, so that the construction period is shortened; and the hole protection upper surface is level with the floor surface, so that the material transportation and the personnel moving are facilitated.

Description

A kind of one-time formed floor slab preformed hole mouth temporary protection device and job practices
Technical field
The invention belongs to building engineering field, particularly a kind of one-time formed floor slab preformed hole mouth temporary protection device and job practices.
Background technology
Existing reserved opening place reinforcing bar disconnects usually, then adopts wooden a tree, used in making timber for boats to do back of the body a tree, used in making timber for boats, and top is laid template the hole is protected.The shortcoming of technique is: could lay the floor protected apron after one, the concrete construction of structure floor is finished, and time-consuming taking a lot of work, and also other constructors have potential safety hazard before laying is finished, and the 2nd, protected apron is higher than floor face, and inconvenient material and personnel carry; The 3rd, when carrying out shutoff, needs bar planting in the reserved opening later stage; The 4th, usually seep water behind the sealing hole, leak, thereby pollute the bottom floor.Technique more and more is not suitable with the trend of green construction.
Summary of the invention
Problem and shortcoming that the present invention exists in order to overcome above-mentioned prior art, a kind of one-time formed floor slab preformed hole mouth temporary protection device and job practices are provided, can guarantee the protection of floor hole and concrete pouring one-step forming, can effectively solve the drawback of pre existing box out mouth guard technology, also be a kind of cutting the waste simultaneously, economize on resources, reduce cost, build a kind of green construction theory.
Technical solution of the present invention is:
A kind of one-time formed floor slab preformed hole mouth temporary protection device, comprise cover plate, side form, bed die, it is characterized in that: bed die is installed in the bottom of structure floor reserved opening, side form is installed respectively around the structure floor reserved opening on bed die, cover plate be installed in the side form top and with structure floor face maintenance level, and the every limit of cover plate size is than the large 2-5cm of reserved opening size.
Described cover plate is wood glue closing lid plate.
Described side form is the comb teeth shape template.
Become " ┛ " type water proof structure between described cover plate and concrete.
Bed die and side form are removed after concrete construction is finished, and described cover plate lower support body is floor hole reserved steel bar.
The job practices of one-time formed floor slab preformed hole mouth provisional protection, it is characterized in that carrying out according to the following steps: for the structure floor reserved opening of the length of side less than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, side form is installed respectively around the structure floor reserved opening on bed die, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 2-5cm cm of reserved opening size, cover reserved opening, cover plate and structure floor face keep level, concreting is smeared water-repellent paint at cover plate and structure floor seam crossing after concreting is finished.Become " ┛ " type water proof structure between described cover plate and concrete.Bed die and side form are removed after concrete construction is finished.
The job practices of one-time formed floor slab preformed hole mouth provisional protection, it is characterized in that carrying out according to the following steps: for the floor reserved opening of the length of side greater than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, difference mounting broach shape side form around the structure floor reserved opening on bed die, before concreting, it is good with muscle at the bottom of the floor and the colligation of floor gluten respectively with the comb teeth shape side form to press the structure floor working drawing, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 2-5cm of reserved opening size, cover plate is placed directly in above the floor gluten and covers reserved opening, concreting is smeared water-repellent paint at cover plate and structure floor seam crossing after concreting is finished.Bed die and side form are removed after concrete construction is finished, and described cover plate lower support body is floor hole reserved steel bar.
Good effect of the present invention is: 1. the sealing of reserved opening and floor concrete casting carry out simultaneously, and one-shot forming is carried out the floor sealing hole after having cancelled pouring concrete and finishing and protected this operation, time and labour saving.2. the hole adopts reserved steel bar to replace wooden a tree, used in making timber for boats back up in the traditional handicraft, and not only intensity is higher, and does not need the later stage that the secondary bar planting is carried out at the hole, has saved the expense of bar planting and wooden a tree, used in making timber for boats.3. become " ┛ " type water proof structure between reserved opening cover plate and concrete.After carrying out temporary plugging, can effectively avoid rainwater and construction water to infiltrate the bottom floor, environment protecting is remarkable, and the secondary pollution after having prevented from fitting up is done over again, and has saved rework cost.And can insert in advance decoration and dynamo-electric installation of bottom floor, save the duration.4. hole protection upper surface and floor face are flat, and transport of materials and flow of personnel are convenient.
Description of drawings
Fig. 1 is floor map of the present invention.
Fig. 2 is that the length of side of the present invention is less than the hole protection generalized section of 300mm.
Fig. 3 is that the length of side of the present invention is greater than the hole protection generalized section of 300mm.
Fig. 4 is that the length of side of the present invention is greater than the hole protection comb teeth shape side form schematic diagram of 300mm.
Among the figure: 1 is that reserved opening, 2 is the comb teeth shape side form for floor gluten, 8 for muscle at the bottom of the floor, 7 for bed die, 6 for side form, 5 for structure floor, 4 for cover plate, 3
The specific embodiment
The invention will be further described by reference to the accompanying drawings.
As shown in Figure 1, a kind of one-time formed floor slab preformed hole mouth temporary protection device of the present invention, comprise cover plate 2, side form 4, bed die 5, bed die 5 is installed in the bottom of structure floor 3 reserved openings 1, side form 4 is installed respectively around structure floor 3 reserved openings 1 on bed die 5, cover plate 2 be installed in side form 4 tops and with 3 maintenance levels of structure floor, and cover plate 2 every limit sizes are than the large 3cm of reserved opening size.Described cover plate 2 is wood glue closing lid plate.
Such as Fig. 1, shown in Figure 2, the job practices of one-time formed floor slab preformed hole mouth provisional protection, for the structure floor reserved opening of the length of side less than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, side form is installed respectively around the structure floor reserved opening on bed die, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 3cm of reserved opening size, cover reserved opening, cover plate and structure floor face keep level, concreting, after concreting is finished, smear water-repellent paint at cover plate and structure floor seam crossing, become " ┛ " type water proof structure between described cover plate and concrete.
Such as Fig. 3, shown in Figure 4, the job practices of one-time formed floor slab preformed hole mouth provisional protection, for the floor reserved opening of the length of side greater than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, difference mounting broach shape side form around the structure floor reserved opening on bed die, before concreting, it is good with muscle at the bottom of the floor 6 and 7 colligations of floor gluten respectively with the comb teeth shape side form to press the structure floor working drawing, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 3cm of reserved opening size, cover plate is placed directly in above the floor gluten and covers reserved opening, concreting is smeared water-repellent paint at cover plate and structure floor seam crossing after concreting is finished, become " ┛ " type water proof structure between described cover plate and concrete.Bed die and side form are removed after concrete construction is finished, and described cover plate lower support body is floor hole reserved steel bar.

Claims (7)

1. one-time formed floor slab preformed hole mouth temporary protection device, comprise cover plate, side form, bed die, it is characterized in that: bed die is installed in the bottom of structure floor reserved opening, side form is installed respectively around the structure floor reserved opening on bed die, cover plate be installed in the side form top and with structure floor face maintenance level, and the every limit of cover plate size is than the large 2-5cm of reserved opening size.
2. one-time formed floor slab preformed hole mouth temporary protection device according to claim 1, it is characterized in that: described cover plate is wood glue closing lid plate.
3. one-time formed floor slab preformed hole mouth temporary protection device according to claim 1, it is characterized in that: described side form is the comb teeth shape template.
4. one-time formed floor slab preformed hole mouth temporary protection device according to claim 1 is characterized in that: become " ┛ " type water proof structure between described cover plate and concrete.
5. one-time formed floor slab preformed hole mouth temporary protection device according to claim 1, it is characterized in that: described cover plate lower support body is floor hole reserved steel bar.
6. the job practices of one-time formed floor slab preformed hole mouth provisional protection, it is characterized in that carrying out according to the following steps: for the structure floor reserved opening of the length of side less than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, side form is installed respectively around the structure floor reserved opening on bed die, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 2-5cm cm of reserved opening size, cover reserved opening, cover plate and structure floor face keep level, concreting is smeared water-repellent paint at cover plate and structure floor seam crossing after concreting is finished.
7. the job practices of one-time formed floor slab preformed hole mouth provisional protection, it is characterized in that carrying out according to the following steps: for the floor reserved opening of the length of side greater than 300mm, when the structure floor is constructed, bed die is installed in the bottom of structure floor reserved opening, difference mounting broach shape side form around the structure floor reserved opening on bed die, before concreting, it is good with muscle at the bottom of the floor and the colligation of floor gluten respectively with the comb teeth shape side form to press the structure floor working drawing, be processed into cover plate with wood plywood, the every limit of cover plate size is than the large 2-5cm of reserved opening size, cover plate is placed directly in above the floor gluten and covers reserved opening, concreting is smeared water-repellent paint at cover plate and structure floor seam crossing after concreting is finished.
CN2012104399473A 2012-11-07 2012-11-07 One-step forming temporary protection device for floor reserved hole and construction method Pending CN102912978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104399473A CN102912978A (en) 2012-11-07 2012-11-07 One-step forming temporary protection device for floor reserved hole and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104399473A CN102912978A (en) 2012-11-07 2012-11-07 One-step forming temporary protection device for floor reserved hole and construction method

Publications (1)

Publication Number Publication Date
CN102912978A true CN102912978A (en) 2013-02-06

Family

ID=47611526

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104399473A Pending CN102912978A (en) 2012-11-07 2012-11-07 One-step forming temporary protection device for floor reserved hole and construction method

Country Status (1)

Country Link
CN (1) CN102912978A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781134A (en) * 2016-05-09 2016-07-20 中国建筑局(集团)有限公司 Horizontal portal protection structure and construction method thereof
CN108756232A (en) * 2018-04-16 2018-11-06 五冶集团上海有限公司 A kind of wooden box makees the construction method of concrete water flat structure hole to be provided
CN109518984A (en) * 2019-01-09 2019-03-26 宁夏第建筑有限公司 A kind of cast-in-situ floor reserved opening protective device and construction technology
CN110552503A (en) * 2019-08-20 2019-12-10 中国一冶集团有限公司 Floor reserved hole protection structure for building construction concrete pouring and construction method thereof
CN115217329A (en) * 2022-08-25 2022-10-21 苏州建设(集团)规划建筑设计院有限责任公司 Concrete floor slab opening plugging structure and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2166992A1 (en) * 1970-05-28 1977-08-25 Butts STEEL BEAM CEILING CONSTRUCTION
CN2359392Y (en) * 1998-10-28 2000-01-19 奇美实业股份有限公司 Forming device for preleave open on concrete floor
JP2004044181A (en) * 2002-07-10 2004-02-12 Yasuyuki Tsuruta Construction method for groove in concrete floor surface, support adjusting device used for construction of the same, and concrete secondary product for forming groove
CN201292665Y (en) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 Concrete floor pre-arranged hole apparatus
CN101575913A (en) * 2009-06-09 2009-11-11 中天建设集团有限公司天津分公司 Construction method for preventing reserved holes of pipes from water leakage
CN201367731Y (en) * 2009-02-05 2009-12-23 中建三局第二建设工程有限责任公司 Reusable cover plate for concrete preformed hole
CN201443203U (en) * 2009-05-18 2010-04-28 青岛市胶州建设集团有限公司 Mold of preformed hole of cast-in-place reinforced concrete slab
CN102359273A (en) * 2011-09-19 2012-02-22 中国十七冶集团有限公司 Method for reinforcing shear wall structure deformation joint template using fixing plate
CN202969967U (en) * 2012-11-07 2013-06-05 中建三局第二建设工程有限责任公司 Temporary protecting device for once formed floor reserved hole

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2166992A1 (en) * 1970-05-28 1977-08-25 Butts STEEL BEAM CEILING CONSTRUCTION
CN2359392Y (en) * 1998-10-28 2000-01-19 奇美实业股份有限公司 Forming device for preleave open on concrete floor
JP2004044181A (en) * 2002-07-10 2004-02-12 Yasuyuki Tsuruta Construction method for groove in concrete floor surface, support adjusting device used for construction of the same, and concrete secondary product for forming groove
CN201292665Y (en) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 Concrete floor pre-arranged hole apparatus
CN201367731Y (en) * 2009-02-05 2009-12-23 中建三局第二建设工程有限责任公司 Reusable cover plate for concrete preformed hole
CN201443203U (en) * 2009-05-18 2010-04-28 青岛市胶州建设集团有限公司 Mold of preformed hole of cast-in-place reinforced concrete slab
CN101575913A (en) * 2009-06-09 2009-11-11 中天建设集团有限公司天津分公司 Construction method for preventing reserved holes of pipes from water leakage
CN102359273A (en) * 2011-09-19 2012-02-22 中国十七冶集团有限公司 Method for reinforcing shear wall structure deformation joint template using fixing plate
CN202969967U (en) * 2012-11-07 2013-06-05 中建三局第二建设工程有限责任公司 Temporary protecting device for once formed floor reserved hole

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105781134A (en) * 2016-05-09 2016-07-20 中国建筑局(集团)有限公司 Horizontal portal protection structure and construction method thereof
CN108756232A (en) * 2018-04-16 2018-11-06 五冶集团上海有限公司 A kind of wooden box makees the construction method of concrete water flat structure hole to be provided
CN109518984A (en) * 2019-01-09 2019-03-26 宁夏第建筑有限公司 A kind of cast-in-situ floor reserved opening protective device and construction technology
CN110552503A (en) * 2019-08-20 2019-12-10 中国一冶集团有限公司 Floor reserved hole protection structure for building construction concrete pouring and construction method thereof
CN110552503B (en) * 2019-08-20 2021-06-29 中国一冶集团有限公司 Floor reserved hole protection structure for building construction concrete pouring and construction method thereof
CN115217329A (en) * 2022-08-25 2022-10-21 苏州建设(集团)规划建筑设计院有限责任公司 Concrete floor slab opening plugging structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN102912978A (en) One-step forming temporary protection device for floor reserved hole and construction method
CN202969967U (en) Temporary protecting device for once formed floor reserved hole
CN104372952A (en) Unstressed permeating washing scabbling technology
CN109025268A (en) Kitchen and toilet concrete flanging construction method
CN211974342U (en) Floor slab reserved hole device with embedded bar planting holes
CN203514793U (en) Equipment reservation template
CN109518960B (en) Shaping mold capable of realizing turnover of reserved hole of cast-in-situ roof and construction method of shaping mold
CN204418229U (en) Poured band of outer wall of basement concrete draw-in groove
CN205024827U (en) Prefabricated plate and roof beam connection structure
CN204800838U (en) A built -up plate for parapet production
CN202064636U (en) Closed stair formwork erecting device
CN201137298Y (en) Post pouring strip, construction joint side steel die
CN212926150U (en) Vertical post-cast strip structure of retaining wall
CN105421780B (en) A kind of construction method of prefabricated concrete structure
CN202672723U (en) Totally closed stair template member
CN206913415U (en) A kind of steel performance steel loose tool for prefabricated component
CN206220057U (en) One-step forming die for open drain
CN108081448B (en) Production process of integrally decorated and electromechanical prefabricated GRC formwork structural column
CN203729581U (en) Novel small-size fast reserved hole
CN111005558A (en) Mould for manufacturing basic cavity concrete mould and using method thereof
CN204126343U (en) A kind of channel-section steel rhone platform
CN205276720U (en) Asphalt shingle roofing eaves mouth structure
CN210857534U (en) Vertical shaft bridge concrete body embedded part
CN218053234U (en) Frame post prefabricated component processingequipment
CN219387408U (en) Pool body structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130206