CN102865592A - Middle combination bunker formed between two boilers through connection beam and arranging method thereof - Google Patents

Middle combination bunker formed between two boilers through connection beam and arranging method thereof Download PDF

Info

Publication number
CN102865592A
CN102865592A CN2012104097172A CN201210409717A CN102865592A CN 102865592 A CN102865592 A CN 102865592A CN 2012104097172 A CN2012104097172 A CN 2012104097172A CN 201210409717 A CN201210409717 A CN 201210409717A CN 102865592 A CN102865592 A CN 102865592A
Authority
CN
China
Prior art keywords
boiler
coal bunker
bunker
starboard
port side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012104097172A
Other languages
Chinese (zh)
Inventor
张彦军
于泽忠
孟宪国
尹向梅
徐栋
王文浒
宋景阳
朱焱
郑乐宇
刘启军
陈炼非
宫柯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Boiler Co Ltd
Original Assignee
Harbin Boiler Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Boiler Co Ltd filed Critical Harbin Boiler Co Ltd
Priority to CN2012104097172A priority Critical patent/CN102865592A/en
Publication of CN102865592A publication Critical patent/CN102865592A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Combustion Of Fluid Fuel (AREA)

Abstract

Provided are a middle combination bunker formed between two boilers through a connection beam and an arranging method thereof. A lateral bunker is not compact in structure and large in occupation area due to the fact that the lateral bunker structure and a boiler structure are independent structures. The middle combination bunker formed between the two boilers through the connection beam comprises a left side boiler (1), a right side boiler (2) and a middle bunker (3). The exhaust structures of the left side boiler and the right side boiler are connected through beams (4) on each layer and horizontal supports (5) to form an integral structure with the boiler steel structure, and the integral structure is the middle bunker. Two rows of coal grinding machines (7) with cranes (6) and coal hoppers (8) are arranged in the middle bunker. The bunker and the method are used for boiler steel structures and lateral bunker arrangement.

Description

Associating coal bunker and method for arranging in the middle of forming by coupling beam between two stoves
technical field:
associating coal bunker and method for arranging in the middle of the present invention relates between a kind of two stoves form by coupling beam.
background technology:
traditional boiler steel structure and side coal bunker structure are respectively absolute construction, mutually noninterfere, and side coal bunker structure is generally xoncrete structure, long construction period.Because side coal bunker structure and boiler structure are absolute construction, so structure is not compact, and floor space is larger.If two structures are unified into to an integral body, more compact structure, functional enhancing, can reduce building structure, and Cost reduction reduces construction period and installation cost, reduces the Engineering Overall cost.
summary of the invention:
the purpose of this invention is to provide a kind of construction cost that reduces whole power plant, and reduced the duration, associating coal bunker and method for arranging in the middle of forming by coupling beam between two stoves that the macroeconomic effect significantly improves.
above-mentioned purpose realizes by following technical scheme:
associating coal bunker in the middle of forming by coupling beam between a kind of two stoves, its composition comprises: port side boiler, starboard boiler, middle coal bunker, described port side boiler and described starboard boiler efflux structure and link together by each layer of beam and horizontal support that enough to become an overall structure with boiler steel structure be middle coal bunker, in the middle of described, in coal bunker, are furnished with coal pulverizer and the coal bunker of two row with crane.
associating coal bunker in the middle of forming by coupling beam between described two stoves, described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude as far as possible.
associating coal bunker in the middle of forming by coupling beam between described two stoves, described back timber, described starboard boiler steel construction, described port side boiler steel construction, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in described side coal bunker.
the method for arranging of associating coal bunker in the middle of forming by coupling beam between a kind of two stoves, described port side boiler and described starboard boiler efflux structure and link together by each layer of beam and horizontal support that enough to become an overall structure with boiler steel structure be middle coal bunker, each rigid plane of boiler steel structure and side coal bunker structure is adjusted on a height as far as possible, form unified rigid plane, make it to form unified structure; If the main rigid plane of unified structure can not the identical height of furnishing, doing supplementary structure and realizing the coordinating and unifying height of two structures, make it become an overall structure, structural analysis will be built the block mold of port side boiler, starboard boiler and side coal bunker and be analyzed.
beneficial effect:
the present invention is unified into an integral body by two structures, makes structure compacter, functional stronger, can reduce building structure, and Cost reduction reduces construction period and installation cost, reduces the Engineering Overall cost.
the accompanying drawing explanation:
accompanying drawing 1 is the structural representation of this product.
accompanying drawing 2 is structural representations of side coal bunker in accompanying drawing 1.
accompanying drawing 3 is structural representations of crane in accompanying drawing 2.
the specific embodiment:
embodiment 1:
associating coal bunker in the middle of forming by coupling beam between a kind of two stoves, its composition comprises: port side boiler, starboard boiler, middle coal bunker, roof and each layer of rigid plane, between described three row columns, the coal pulverizer with crane is housed, described coal pulverizer connects coal bunker.
embodiment 2:
associating coal bunker in the middle of forming by coupling beam between a kind of two stoves, its composition comprises: port side boiler 1, starboard boiler 2, middle coal bunker 3, described port side boiler and described starboard boiler efflux structure and link together by each layer of beam 4 and horizontal support 5 that enough to become an overall structure with boiler steel structure be middle coal bunker, in the middle of described, in coal bunker, are furnished with coal pulverizer 7 and the coal bunker 8 of two row with crane 6.
embodiment 3:
associating coal bunker in the middle of forming by coupling beam between described two stoves of embodiment 1 or 2, described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude as far as possible.
embodiment 4:
associating coal bunker in the middle of forming by coupling beam between described two stoves of embodiment 1 or 2, described back timber, described starboard boiler steel construction, described port side boiler steel construction, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in described side coal bunker.
embodiment 5:
the method for arranging of associating coal bunker in the middle of forming by coupling beam between a kind of two stoves, described port side boiler and described starboard boiler efflux structure and link together by each layer of beam and horizontal support that enough to become an overall structure with boiler steel structure be middle coal bunker, each rigid plane of boiler steel structure and side coal bunker structure is adjusted on a height as far as possible, form unified rigid plane, make it to form unified structure; If the main rigid plane of unified structure can not the identical height of furnishing, doing supplementary structure and realizing the coordinating and unifying height of two structures, make it become an overall structure, structural analysis will be built the block mold of port side boiler, starboard boiler and side coal bunker and be analyzed.
embodiment 6:
the described boiler steel structure of above-described embodiment and side coal bunker structural entity device, port side boiler, starboard boiler and side coal bunker are unified into an integral body: increase by organ timbering in the middle of port side boiler, starboard boiler, with the pillar that effluxes of boiler, share, the side coal bunker of formation and boiler coadunation, be arranged in coal pulverizer in side coal bunker scope.
boiler and side coal bunker gang, the outer organ timbering of boiler shares with the outer organ timbering of side coal bunker, the formation overall structure, coal pulverizer is arranged between two stoves in side coal bunker scope.
with the pillar that effluxes of boiler, share, and be connected with boiler steel structure by beam and horizontal support etc., form the side coal bunker with the boiler structure coadunation, each rigid plane of boiler steel structure structure and side coal bunker structure is adjusted on an absolute altitude as far as possible, form a unified rigid plane, to form unified structure. can not absolute altitude of furnishing as the main rigid plane of structure, need do the coordinating and unifying that supplementary structure is realized two structures, make its one-tenth as a whole; Structure after associating is an integral body, answers the unified Modeling analysis, need build the block mold of port side boiler, starboard boiler and side coal bunker and be analyzed.
embodiment 7:
the described boiler steel structure of above-described embodiment and side coal bunker structural entity device, changed into side coal bunker structure steel construction and combined in aggregates with port side boiler, starboard boiler steel construction by the concrete soil structure.Share with the pillar that effluxes of boiler, and be connected with boiler steel structure by beam and horizontal support etc., the side coal bunker of formation and boiler structure coadunation, and feeder is arranged in the side coal bunker scope between two stoves, as shown in Figure 1.
each rigid plane of boiler steel structure structure and side coal bunker structure is adjusted on an absolute altitude as far as possible, is formed a unified rigid plane.
can not absolute altitude of furnishing as the main rigid plane of structure, need do the coordinating and unifying that supplementary structure is realized two structures, make its one-tenth as a whole.
structure after associating is an integral body, answers the unified Modeling analysis, need build the block mold of port side boiler, starboard boiler and side coal bunker and be analyzed.

Claims (4)

1. form middle associating coal bunker by coupling beam between a stove, its composition comprises: port side boiler, starboard boiler, middle coal bunker, it is characterized in that: described port side boiler and described starboard boiler efflux structure and link together by each layer of beam and horizontal support that enough to become an overall structure with boiler steel structure be middle coal bunker, in the middle of described, in coal bunker, are furnished with coal pulverizer and the coal bunker of two row with crane.
2. associating coal bunker in the middle of forming by coupling beam between two stoves according to claim 1, it is characterized in that: described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude as far as possible.
3. associating coal bunker in the middle of forming by coupling beam between two stoves according to claim 1 and 2, it is characterized in that: described back timber, described starboard boiler steel construction, described port side boiler steel construction, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in described side coal bunker.
4. form middle method for arranging of combining coal bunker by coupling beam between a stove, it is characterized in that: described port side boiler and described starboard boiler efflux structure and link together by each layer of beam and horizontal support that enough to become an overall structure with boiler steel structure be middle coal bunker, each rigid plane of boiler steel structure and side coal bunker structure is adjusted on a height as far as possible, form unified rigid plane, make it to form unified structure; If the main rigid plane of unified structure can not the identical height of furnishing, doing supplementary structure and realizing the coordinating and unifying height of two structures, make it become an overall structure, structural analysis will be built the block mold of port side boiler, starboard boiler and side coal bunker and be analyzed.
CN2012104097172A 2012-10-24 2012-10-24 Middle combination bunker formed between two boilers through connection beam and arranging method thereof Pending CN102865592A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012104097172A CN102865592A (en) 2012-10-24 2012-10-24 Middle combination bunker formed between two boilers through connection beam and arranging method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012104097172A CN102865592A (en) 2012-10-24 2012-10-24 Middle combination bunker formed between two boilers through connection beam and arranging method thereof

Publications (1)

Publication Number Publication Date
CN102865592A true CN102865592A (en) 2013-01-09

Family

ID=47444629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012104097172A Pending CN102865592A (en) 2012-10-24 2012-10-24 Middle combination bunker formed between two boilers through connection beam and arranging method thereof

Country Status (1)

Country Link
CN (1) CN102865592A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2527866Y (en) * 2002-03-18 2002-12-25 何相助 Composite circulating fluidized bed boiler
CN101162087A (en) * 2007-11-27 2008-04-16 云南省电力设计院 300MW circulating fluidized bed boiler island
CN101481958A (en) * 2008-04-17 2009-07-15 上海电气工程设计有限公司 Main power zone island type arrangement of thermal power generation plant
CN202092095U (en) * 2011-06-13 2011-12-28 山东电力工程咨询院有限公司 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2527866Y (en) * 2002-03-18 2002-12-25 何相助 Composite circulating fluidized bed boiler
CN101162087A (en) * 2007-11-27 2008-04-16 云南省电力设计院 300MW circulating fluidized bed boiler island
CN101481958A (en) * 2008-04-17 2009-07-15 上海电气工程设计有限公司 Main power zone island type arrangement of thermal power generation plant
CN202092095U (en) * 2011-06-13 2011-12-28 山东电力工程咨询院有限公司 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
范永春,霍沛强: "1000MW超超临界机组主厂房布置格局探讨", 《电力勘测设计》 *

Similar Documents

Publication Publication Date Title
NZ601123A (en) Panelized structural system for building construction
CN103074959B (en) A kind of steel plate high-strength concrete composite coupling beams
CN103924527A (en) Resource-saving, environment-friendly and frame-making integrated highway beam yard arrangement and construction method thereof
CN202139685U (en) Lattice column of framework structure
CN201738597U (en) Sectional steel and steel pipe combined type support system of beam with high and large cross section
CN202227360U (en) Wide-span prestressed concrete pile beam plate structure used for grounds of buildings, workshops, etc.
CN202831704U (en) Middle joint coal bunker formed by erecting one row of pillars between two furnaces
CN202831750U (en) Middle joint coal bunker formed by erecting three rows of pillars between two furnaces
CN202866340U (en) Combined-coal-bunker with deaerator distributed in the middle and having two rows of upright pillars between two furnaces
CN202835415U (en) Boiler steel structure and side coal bunker structure integrated device
CN202831703U (en) Middle joint coal bunker formed by erecting one row of pillars between two furnaces and with deaerators arranged in between
CN102865592A (en) Middle combination bunker formed between two boilers through connection beam and arranging method thereof
CN202969624U (en) Slotted cutting type building structure soft steel damper
CN102828630B (en) Lateral bunker bay structure of large-scale thermal power plant
CN201713800U (en) Transitional drilling platform
CN102864958A (en) Combined coal bin with a row of stand columns set between two boilers and deaerator arranged in middle and arrangement method
CN102864960A (en) Middle combined coal bunker formed by setting three rows of columns between two boilers and arrangement method
CN102900253A (en) Combined coal bunker with two rows of posts between two furnaces and deaerator in middle and arrangement method
CN102864959A (en) Middle combined coal bin formed by setting a row of stand columns between two boilers and arrangement method thereof
CN202577584U (en) Die modular concrete assembled movable house
CN203701386U (en) Steel-structure floor slab group
CN203007838U (en) Cable tower
CN201738595U (en) Original house independent floor-adding facility without dismantlement or land increasing
CN204590261U (en) A kind of novel prefabricated assembling frame structure
CN103225312A (en) Prefabricated assembled foundation of tower mast structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20130109

RJ01 Rejection of invention patent application after publication