CN202092095U - Million kilowatt unit tower type boiler system with lateral coal bunker in power plant - Google Patents

Million kilowatt unit tower type boiler system with lateral coal bunker in power plant Download PDF

Info

Publication number
CN202092095U
CN202092095U CN2011201971851U CN201120197185U CN202092095U CN 202092095 U CN202092095 U CN 202092095U CN 2011201971851 U CN2011201971851 U CN 2011201971851U CN 201120197185 U CN201120197185 U CN 201120197185U CN 202092095 U CN202092095 U CN 202092095U
Authority
CN
China
Prior art keywords
power plant
tower type
coal bunker
tower
boiler system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201971851U
Other languages
Chinese (zh)
Inventor
蒋莉
宫俊亭
张乐川
祁金胜
侯振
王妮妮
薛斌
于洪涛
李官鹏
杨俊波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Original Assignee
Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Electric Power Engineering Consulting Institute Corp Ltd filed Critical Shandong Electric Power Engineering Consulting Institute Corp Ltd
Priority to CN2011201971851U priority Critical patent/CN202092095U/en
Application granted granted Critical
Publication of CN202092095U publication Critical patent/CN202092095U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Combustion Of Fluid Fuel (AREA)

Abstract

The utility model relates to a million kilowatt unit tower type boiler system with a lateral coal bunker in a power plant, which adopts the scheme that the coal bunkers of two tower type boilers are combined to locate between two tower type boilers in a centralized manner. The scheme of lateral coal bunker layout can very effectively utilize space between the two tower type boilers, the layout is very compact, the required main pipelines and cables in the power plant are reduced, and the occupied area of the main workshop is also reduced.

Description

Power plant's gigawatt unit tower boiler is joined side coal bunker system
Technical field
The utility model relates to a kind of power plant gigawatt unit tower boiler and joins side coal bunker system.
Background technology
Tower boiler is more and more accepted by large-scale unit power plant, but single with the layout pattern of bunker bay, has all adopted the traditional arrangement form of preceding coal bunker.But it exists the consumption of power plant's four large pipelines and cable big, and main building A is listed as problems such as floor space to chimney is big.
Summary of the invention
The purpose of this utility model is for overcoming above-mentioned the deficiencies in the prior art, provides a kind of layout compact, and power plant's gigawatt unit tower boiler easy for installation is joined side coal bunker system.
For achieving the above object, the utility model adopts following technical proposals:
A kind of power plant gigawatt unit tower boiler is joined side coal bunker system, comprises tower boiler, is furnished with bunker bay between two tower boilers.
Bunker bay between described two tower boilers is provided with a public access path.
The utlity model has following characteristics:
Adopt the bunker bay of two tower-type furnaces to merge, centralized arrangement is in the middle of the two-tower type stove.Effectively utilized the space between the two-tower type stove, very compact on the layout, reduced the consumption of four large pipelines and cable, saved initial cost.Shortened main building A and be listed as distance, made the limited power plant of main building land used to have obtained certain solution to chimney.From pipe arrangement, reduce heat primary air, the duct length of a cold wind.The public access path of the bunker bay of two boilers has been saved one and has been crossed the rail crane.The tower crane that is installed on the burner hearth center is used in the lifting of the big plate-girder of boiler, and having solved in the past, tower crane places two stove centers, the problem that the side coal bunker can't be constructed.
Description of drawings
Fig. 1 is the utility model structural representation;
Among the figure: 1. tower boiler, 2. bunker bay.
The specific embodiment
Below in conjunction with accompanying drawing the utility model is described in further detail.
As shown in Figure 1, a kind of power plant gigawatt unit tower boiler is joined side coal bunker system, comprises tower boiler 1, is furnished with bunker bay 2 between two tower boilers 1.
In the bunker bay 2 that described two tower boilers are 1 a public access path is set.
The utlity model has following characteristics:
Adopt the bunker bay of two tower-type furnaces to merge, centralized arrangement is in the middle of the two-tower type stove.Effectively utilized the space between the two-tower type stove, very compact on the layout, reduced the consumption of four large pipelines and cable, saved initial cost.Shortened main building A and be listed as distance, made the limited power plant of main building land used to have obtained certain solution to chimney.From pipe arrangement, reduce heat primary air, the duct length of a cold wind.The public access path of the bunker bay of two boilers has been saved one and has been crossed the rail crane.The tower crane that is installed on the burner hearth center is used in the lifting of the big plate-girder of boiler, and having solved in the past, tower crane places two stove centers, the problem that the side coal bunker can't be constructed.

Claims (2)

1. power plant's gigawatt unit tower boiler is joined side coal bunker system, it is characterized in that: arrange bunker bay between two tower boilers.
2. power plant according to claim 1 gigawatt unit tower boiler is joined side coal bunker system, it is characterized in that: the bunker bay between described two tower boilers is provided with a public access path.
CN2011201971851U 2011-06-13 2011-06-13 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant Expired - Lifetime CN202092095U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201971851U CN202092095U (en) 2011-06-13 2011-06-13 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201971851U CN202092095U (en) 2011-06-13 2011-06-13 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant

Publications (1)

Publication Number Publication Date
CN202092095U true CN202092095U (en) 2011-12-28

Family

ID=45367162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201971851U Expired - Lifetime CN202092095U (en) 2011-06-13 2011-06-13 Million kilowatt unit tower type boiler system with lateral coal bunker in power plant

Country Status (1)

Country Link
CN (1) CN202092095U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102865592A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Middle combination bunker formed between two boilers through connection beam and arranging method thereof
CN102864958A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Combined coal bin with a row of stand columns set between two boilers and deaerator arranged in middle and arrangement method
CN105421831A (en) * 2015-10-29 2016-03-23 河北省电力勘测设计研究院 Thermal power plant main power house arrangement form based on combined side bunker scheme
CN106379811A (en) * 2016-11-30 2017-02-08 山东电力建设第工程公司 n-type boiler hoisting machinery arrangement structure of side coal bunker structure of unit and hoisting method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102865592A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Middle combination bunker formed between two boilers through connection beam and arranging method thereof
CN102864958A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Combined coal bin with a row of stand columns set between two boilers and deaerator arranged in middle and arrangement method
CN105421831A (en) * 2015-10-29 2016-03-23 河北省电力勘测设计研究院 Thermal power plant main power house arrangement form based on combined side bunker scheme
CN106379811A (en) * 2016-11-30 2017-02-08 山东电力建设第工程公司 n-type boiler hoisting machinery arrangement structure of side coal bunker structure of unit and hoisting method
CN106379811B (en) * 2016-11-30 2017-11-21 山东电力建设第一工程公司 Unit side coal bunker structure π type boiler structural design mechanical arrangement structures and hanging method

Similar Documents

Publication Publication Date Title
CN202092095U (en) Million kilowatt unit tower type boiler system with lateral coal bunker in power plant
CN203201657U (en) Container power station
Yu et al. Five strategies to achieve China’s 2060 carbon neutrality goal
CN204174975U (en) A kind of power plant main power house arrangement
CN103790659A (en) Gas-steam combined cycle cogeneration unit
CN202993186U (en) Air water slag cooler of large circulating fluidized bed boiler
CN204704802U (en) Heated surface at the end of boiler arrangement
CN204420980U (en) Waste Heat Boiler superheater
CN207177379U (en) A kind of main building of steam turbine lateral arrangement
CN206530105U (en) Coal bunker arrangement after tower-type furnace
CN201636850U (en) Flue-type aluminum melting furnace combustion device for converting heat energy by using waste gas afterheat
CN202442327U (en) Boiler top sealing device for circulating fluidized bed (CFB) boiler
CN202945306U (en) Device utilizing flue waste heat to circularly heat plating assistant agent
CN202125094U (en) Main power house capable of improving bunker bay arrangement for high-low-position arrangement steam turbine room
CN215107728U (en) Land-saving type thermal power plant
CN203631049U (en) Hot state experiment device used for combustion organization optimization
CN202530792U (en) Distributed roof energy station structure
CN103700309B (en) Thermal-state experiment device for combustion organization optimization
CN203745213U (en) Large-scale test device used for combustor research and development
CN202125093U (en) Main power house of high-low-position arrangement steam turbine for improving arrangement of deaerator and high-pressure heater
CN108868216B (en) Main plant with steam turbines transversely arranged
CN211647502U (en) Main plant layout structure of indirect air cooling and smoke tower integrated thermal generator set
CN202598576U (en) Bottom air layout structure for boiler
CN202747610U (en) Biomass fuel organic heat carrier furnace with chain grate
CN101598506A (en) Utilize the cold-hot water exchange device of waste gas residual heat

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20111228

CX01 Expiry of patent term