CN201713800U - Transitional drilling platform - Google Patents

Transitional drilling platform Download PDF

Info

Publication number
CN201713800U
CN201713800U CN 201020213978 CN201020213978U CN201713800U CN 201713800 U CN201713800 U CN 201713800U CN 201020213978 CN201020213978 CN 201020213978 CN 201020213978 U CN201020213978 U CN 201020213978U CN 201713800 U CN201713800 U CN 201713800U
Authority
CN
China
Prior art keywords
platform
bridge
fixed supporting
drilling platform
supporting leg
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201020213978
Other languages
Chinese (zh)
Inventor
黄延铮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN 201020213978 priority Critical patent/CN201713800U/en
Application granted granted Critical
Publication of CN201713800U publication Critical patent/CN201713800U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a transitional drilling platform which comprises a truss platform and fixed support legs, wherein the fixed support legs are vertically welded at the bottom of the truss platform, and plug-in support legs are arranged among the fixed support legs. The truss platform is small in size, so that the 24 drilling piles of each main pier are constructed by processing the platform with small number of steel sections and making the plug-in support legs from small number of steel pipe piles. Therefore, the consumptions of steel pipe piles, steel sections and other construction steel materials are greatly reduced, and the construction cost is lowered.

Description

A kind of turnover drilling platform
Technical field
The utility model belongs to a kind of equipment that is used for bridge construction, relates in particular to the portable turnover of pile foundation drilling platform in a kind of bridge water.
Background technology
The form of structure of traditional underwater fixed platform is to set up whole underwater fixed platform in main bridge master pier position (planar dimension is 35m * 13.5m); Use a large amount of steel pipe piles to make bearing column, the suitable bridge of each platform is to setting many steel pipe piles with direction across bridge; And use a large amount of shaped steel (truss) to make the longitudinal and transverse spandrel girder of drilling platform.The weldering assembly is installed in the steel pipe pile top, completely spreads steel plate (or plank) on it; Form whole underwater fixed platform.This structure need be used construction steel such as a large amount of steel pipe piles, shaped steel, causes idle, the waste of construction material.
The utility model content
The purpose of this utility model provides a kind of turnover drilling platform of saving construction material, reducing construction cost.
In order to achieve the above object by the following technical solutions: a kind of turnover drilling platform, comprise truss platform, fixed supporting leg, vertically be welded with fixed supporting leg below the truss platform, be provided with between the fixed supporting leg to insert and make a jack.
The described truss platform of root is that i iron crossbeam direction across bridge is welded in the notch at corresponding two fixed supporting leg tops, on the i iron crossbeam welding one deck along bridge to the i iron longeron, direction across bridge is paved with plank on the i iron longeron.
Described inserting makes a jack cross fixation between adjacent two fixed supporting legs of direction across bridge.
Described fixed supporting leg is to two of four rows, every rows along bridge.
Described longeron i iron is three, and plank thickness is 5cm.
The utility model truss platform is less, and (planar dimension is 9m * 13.5m), only uses a spot of shaped steel processing platform and a spot of several steel pipe piles to make a jack as inserting, and can finish the construction of 24 drilled piles of every main pier.Significantly reduce the use amount of construction steel such as steel pipe pile, shaped steel, reduce construction cost.The utility model also has certain influence to compression the duration, uses in tight project of duration and is subjected to certain restriction, and can adopt increases the turnover drilling platform quantity reduction of erection time.
Description of drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the left view of Fig. 1.
The specific embodiment
As shown in Figure 1, 2, a kind of turnover drilling platform includes suitable bridge that round steel pipe makes fixed supporting leg 1 and the truss platform to two of four rows, every row; I iron crossbeam 2 direction across bridge that consist of of truss platform are welded in the notch at corresponding two fixed supporting leg 1 tops, on i iron crossbeam 2 welding three along bridges to i iron longeron 3, direction across bridge is paved with 5cm plank 4 on the i iron longeron 3; Insert make a jack 5 for the channel-section steel cross fixation between adjacent two fixed supporting legs 1 of direction across bridge.

Claims (5)

1. a turnover drilling platform comprises truss platform, fixed supporting leg, it is characterized in that: vertically be welded with fixed supporting leg below the truss platform, be provided with slotting making a jack between the fixed supporting leg.
2. turnover drilling platform according to claim 1, it is characterized in that: described truss platform is that i iron crossbeam direction across bridge is welded in the notch at corresponding two fixed supporting leg tops, on the i iron crossbeam welding one deck along bridge to the i iron longeron, direction across bridge is paved with plank on the i iron longeron.
3. turnover drilling platform according to claim 1 is characterized in that: described inserting makes a jack cross fixation between adjacent two fixed supporting legs of direction across bridge.
4. according to any described turnover drilling platform in claim 1 or 2 or 3, it is characterized in that: described fixed supporting leg is to two of four rows, every rows along bridge.
5. turnover drilling platform according to claim 1 and 2 is characterized in that: described longeron i iron is three, and plank thickness is 5cm.
CN 201020213978 2010-06-03 2010-06-03 Transitional drilling platform Expired - Fee Related CN201713800U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201020213978 CN201713800U (en) 2010-06-03 2010-06-03 Transitional drilling platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201020213978 CN201713800U (en) 2010-06-03 2010-06-03 Transitional drilling platform

Publications (1)

Publication Number Publication Date
CN201713800U true CN201713800U (en) 2011-01-19

Family

ID=43459799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201020213978 Expired - Fee Related CN201713800U (en) 2010-06-03 2010-06-03 Transitional drilling platform

Country Status (1)

Country Link
CN (1) CN201713800U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747745A (en) * 2011-04-22 2012-10-24 上海庞源机械租赁股份有限公司 Base for underwater tower crane
CN106120833A (en) * 2016-08-24 2016-11-16 江西理工大学 A kind of underground truss-like pile foundation and construction method thereof
CN106149745A (en) * 2016-08-24 2016-11-23 江西理工大学 A kind of truss type steel tube grouting pile basis and construction method thereof
CN106245668A (en) * 2016-08-24 2016-12-21 江西理工大学 A kind of truss-like pile foundation and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747745A (en) * 2011-04-22 2012-10-24 上海庞源机械租赁股份有限公司 Base for underwater tower crane
CN106120833A (en) * 2016-08-24 2016-11-16 江西理工大学 A kind of underground truss-like pile foundation and construction method thereof
CN106149745A (en) * 2016-08-24 2016-11-23 江西理工大学 A kind of truss type steel tube grouting pile basis and construction method thereof
CN106245668A (en) * 2016-08-24 2016-12-21 江西理工大学 A kind of truss-like pile foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN102839678B (en) Structure for improving rigidity and stability of foundation pit steel support
CN102979167B (en) Multi-story high-rise assembled steel structure prestressed centrally-braced system
CN103266720A (en) Composite beam comprising steel beam with concrete at abdomen
CN201713800U (en) Transitional drilling platform
CN103437300A (en) Construction method for erecting double cantilevers for pier top steel beam without pier-side bracket
CN202227360U (en) Wide-span prestressed concrete pile beam plate structure used for grounds of buildings, workshops, etc.
CN102061742B (en) Shockproof reinforced concrete pseudo-classic building structural system
CN202755370U (en) Structure for improving rigidity and stability of foundation pit steel support
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN108999427B (en) Support structure for moving load during building migration in place and construction method thereof
CN203080770U (en) Profiled steel sheet and concrete composite floor
CN202338066U (en) Large-span pre-stressed concrete double-T superimposed sheet
CN206143645U (en) Stride across navigable river ultra -large -span girder steel assembling support
CN204780559U (en) Steel construction case roof beam and concrete bridge panel combination bridge
CN202945820U (en) Inner steel frame reinforced structure of pseudo-classic architecture
CN203603073U (en) Reinforced concrete lattice type composite platform beam of elevated station
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN2714671Y (en) Closed pressing steel plate combined floor board
CN202401384U (en) Ballasting structure of steel-truss cable-stayed bridge
CN202090457U (en) Shearing earthquake-resistant damper for architectural structure with mild steels in parallel
CN206034264U (en) Novel steel construction shelter bridge foundation structure
CN202865731U (en) Saddle weight steel box structure of steel truss cable-stayed bridge
CN204326556U (en) A kind of large-span truss for both wired upper bridge constructions is safe guarding shed
CN203546900U (en) Building
CN203256588U (en) Multifunctional arched combination pre-stress landscape bridge

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110119

Termination date: 20130603