CN202831704U - Middle joint coal bunker formed by erecting one row of pillars between two furnaces - Google Patents

Middle joint coal bunker formed by erecting one row of pillars between two furnaces Download PDF

Info

Publication number
CN202831704U
CN202831704U CN 201220547755 CN201220547755U CN202831704U CN 202831704 U CN202831704 U CN 202831704U CN 201220547755 CN201220547755 CN 201220547755 CN 201220547755 U CN201220547755 U CN 201220547755U CN 202831704 U CN202831704 U CN 202831704U
Authority
CN
China
Prior art keywords
boiler
coal bunker
coal
port side
starboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 201220547755
Other languages
Chinese (zh)
Inventor
张彦军
于泽忠
孟宪国
尹向梅
徐栋
王文浒
宋景阳
朱焱
郑乐宇
刘启军
陈炼非
宫柯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Boiler Co Ltd
Original Assignee
Harbin Boiler Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Boiler Co Ltd filed Critical Harbin Boiler Co Ltd
Priority to CN 201220547755 priority Critical patent/CN202831704U/en
Application granted granted Critical
Publication of CN202831704U publication Critical patent/CN202831704U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

Provided is a middle joint coal bunker formed by erecting one row of pillars between two furnaces. Due to the fact that a side coal bunker structure and a boiler structure are respectively an independent structure, the structures are not compact and the occupied area is large. The middle joint coal bunker formed by erecting the one row of pillars between the two furnaces comprises a left side boiler (1), a right side boiler (2) and a middle coal bunker (3), wherein one line of stand columns (4) are arranged between the left side boiler and the right side boiler, and the stand columns are connected with a left side boiler edge outer row structure and a right side boiler edge outer row structure through each layer of girder (5) and a horizontal support (6) to form the middle coal bunker with a boiler steel structure. A coal mill (7) with a crane (8) is installed between the left side boiler and the stand columns, a coal mill with a crane is installed between the right side boiler and the stand columns, and the coal mill is connected with a coal scuttle (9). The middle joint coal bunker formed by erecting the one row of pillars between the two furnaces is used for arrangement of the boiler steel structure and the side coal bunker.

Description

Associating coal bunker in the middle of a vertical organ timbering forms between two stoves
Technical field:
The utility model relate between a kind of two stoves a vertical organ timbering form in the middle of the associating coal bunker.
Background technology:
Traditional boiler steel structure and side coal bunker structure are respectively absolute construction, mutually noninterfere, side coal bunker knot
Structure is generally concrete structure, long construction period.Because side coal bunker structure and boiler structure are absolute construction, so structure is not compact, and floor space is larger.If two structures are unified into an integral body, more compact structure then, functional enhancing can reduce building structure, and Cost reduction reduces construction period and installation cost, reduces the Engineering Overall cost.
The utility model content:
The purpose of this utility model provides a kind of construction cost that reduces whole power plant, and has reduced the duration, associating coal bunker in the middle of a vertical organ timbering forms between two stoves that the macroeconomic effect significantly improves.
Above-mentioned purpose realizes by following technical scheme:
Associating coal bunker in the middle of a vertical organ timbering forms between a kind of two stoves, its composition comprises: port side boiler, starboard boiler, middle coal bunker, described port side boiler and described starboard boiler intermediate arrangement one row column, described column by each layer beam and horizontal support and described port side boiler limit efflux structure and described starboard boiler efflux structure link together form with boiler steel structure in the middle of coal bunker; Coal pulverizer with crane is housed between described port side boiler and described column, the coal pulverizer with crane is housed between described starboard boiler and described column, described coal pulverizer connects coal bunker.
Associating coal bunker in the middle of a vertical organ timbering forms between described two stoves, described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude.
Associating coal bunker in the middle of a vertical organ timbering forms between described two stoves, described back timber, described starboard boiler steel work, described port side boiler steel work, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in the described side coal bunker.
Beneficial effect:
1. the utility model is unified into an integral body with two structures, makes structure compacter, and is functional stronger, can reduce building structure, and Cost reduction reduces construction period and installation cost, reduces the Engineering Overall cost.
The utility model makes boiler steel structure and side coal bunker structure form an integral body, more compact structure, and functional enhancing can reduce building structure, and Cost reduction reduces construction period and installation cost, reduces the Engineering Overall cost.
The utility model has reduced the construction cost of whole power plant, and has reduced the duration, and the macroeconomic effect is very remarkable.
Description of drawings:
Accompanying drawing 1 is the structural representation of this product.
Accompanying drawing 2 is structural representations of side coal bunker in the accompanying drawing 1.
Accompanying drawing 3 is structural representations of crane in the accompanying drawing 2.
The specific embodiment:
Embodiment 1:
Associating coal bunker in the middle of a vertical organ timbering forms between a kind of two stoves, its composition comprises: port side boiler, starboard boiler, effluxing structure by column between two stoves and boiler links to each other by each layer rigid plane and roof and forms unified structure, coal bunker between forming, coal pulverizer with crane is housed between described port side boiler and described column, coal pulverizer with crane is housed between described starboard boiler and described column, and described coal pulverizer connects coal bunker.
Embodiment 2:
Associating coal bunker in the middle of a vertical organ timbering forms between a kind of two stoves, its composition comprises: port side boiler 1, starboard boiler 2, middle coal bunker 3, described port side boiler and described starboard boiler intermediate arrangement one row column 4, described column by each layer beam 5 and horizontal support 6 and described port side boiler limit efflux structure and described starboard boiler efflux structure link together with boiler steel structure enough become an overall structure form in the middle of coal bunker; Coal pulverizer 7 with crane 8 is housed between described port side boiler and described column, the coal pulverizer with crane is housed between described starboard boiler and described column, described coal pulverizer connects coal bunker 9.
Embodiment 3:
Associating coal bunker in the middle of a vertical organ timbering forms between embodiment 1 or 2 described two stoves, described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude as far as possible.
Embodiment 4:
Associating coal bunker in the middle of a vertical organ timbering forms between embodiment 1 or 2 described two stoves, described back timber, described starboard boiler steel work, described port side boiler steel work, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in the described side coal bunker.
Embodiment 5:
The overall structure method of associating coal bunker in the middle of a vertical organ timbering forms between a kind of two stoves, in the middle of two boilers, increase colonnade, the structure that effluxes of this colonnade and boiler links into an integrated entity by each layer beam and horizontal support and boiler structure, each rigid plane of boiler steel structure and side coal bunker structure is transferred on a height as far as possible, form unified rigid plane, make it to form unified structure; If the main rigid plane of unified structure can not the identical height of furnishing, need supplementary structure to realize the coordinating and unifying of two structures, make it become an overall structure, structural analysis will be built the block mold of two boilers and side coal bunker and be analyzed.
Embodiment 6:
Associating coal bunker in the middle of a vertical organ timbering forms between described two stoves of above-described embodiment, two boilers and integral body of side coal bunker associating: in the middle of two boilers, increase by two organ timberings, share with the pillar that effluxes of boiler, the side coal bunker of formation and boiler coadunation is arranged in coal pulverizer and oxygen-eliminating device in the side coal bunker scope.
Boiler and side coal bunker gang, the outer organ timbering of boiler shares with the outer organ timbering of side coal bunker, the formation overall structure, coal pulverizer and oxygen-eliminating device are arranged between two stoves in the side coal bunker scope.
Form of structure is between two stoves, increase by two organ timberings, and be connected with boiler structure by beam and horizontal support etc., each rigid plane of boiler steel structure structure and side coal bunker structure is transferred on an absolute altitude as far as possible, form a unified rigid plane, to form unified structure. can not absolute altitude of furnishing such as the main rigid plane of structure, need do the coordinating and unifying that supplementary structure is realized two structures, make its one-tenth as a whole
Structure after the associating is an integral body, answers the unified Modeling analysis, need build the block mold of two boilers and side coal bunker and analyze.
Embodiment 7:
Associating coal bunker in the middle of a vertical organ timbering forms between described two stoves of above-described embodiment changes side coal bunker structure into steel work and in aggregates with two boiler steel structure associatings by the concrete soil structure.
In the middle of two boilers, increase by two organ timberings, share with the pillar that effluxes of boiler, and be connected with boiler structure by beam and horizontal support etc., form the side coal bunker with the boiler coadunation, and feeder and oxygen-eliminating device be arranged in two side coal bunker scopes between the stove, as shown in Figure 1.
Each rigid plane of boiler steel structure structure and side coal bunker structure is transferred on an absolute altitude as far as possible, is formed a unified rigid plane.
Can not absolute altitude of furnishing such as the main rigid plane of structure, need do the coordinating and unifying that supplementary structure is realized two structures, make its one-tenth as a whole.

Claims (3)

1. associating coal bunker in the middle of a vertical organ timbering forms between a stove, its composition comprises: port side boiler, starboard boiler, middle coal bunker, it is characterized in that: described port side boiler and described starboard boiler intermediate arrangement one row column, described column by each layer beam and horizontal support and described port side boiler limit efflux structure and described starboard boiler efflux structure link together form with boiler steel structure in the middle of coal bunker; Coal pulverizer with crane is housed between described port side boiler and described column, the coal pulverizer with crane is housed between described starboard boiler and described column, described coal pulverizer connects coal bunker.
2. associating coal bunker in the middle of a vertical organ timbering forms between two stoves according to claim 1, it is characterized in that: described port side boiler and described starboard boiler and middle side coal bunker form unified rigid plane at an absolute altitude.
3. associating coal bunker in the middle of a vertical organ timbering forms between two stoves according to claim 1 and 2, it is characterized in that: described back timber, described starboard boiler steel work, described port side boiler steel work, described column form the side coal bunker, and described coal pulverizer, described coal bunker all are contained in the described side coal bunker.
CN 201220547755 2012-10-24 2012-10-24 Middle joint coal bunker formed by erecting one row of pillars between two furnaces Expired - Lifetime CN202831704U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220547755 CN202831704U (en) 2012-10-24 2012-10-24 Middle joint coal bunker formed by erecting one row of pillars between two furnaces

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220547755 CN202831704U (en) 2012-10-24 2012-10-24 Middle joint coal bunker formed by erecting one row of pillars between two furnaces

Publications (1)

Publication Number Publication Date
CN202831704U true CN202831704U (en) 2013-03-27

Family

ID=47943447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220547755 Expired - Lifetime CN202831704U (en) 2012-10-24 2012-10-24 Middle joint coal bunker formed by erecting one row of pillars between two furnaces

Country Status (1)

Country Link
CN (1) CN202831704U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864959A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Middle combined coal bin formed by setting a row of stand columns between two boilers and arrangement method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864959A (en) * 2012-10-24 2013-01-09 哈尔滨锅炉厂有限责任公司 Middle combined coal bin formed by setting a row of stand columns between two boilers and arrangement method thereof

Similar Documents

Publication Publication Date Title
NZ601123A (en) Panelized structural system for building construction
CN103924797A (en) Country prefabricated steel structure residence system and construction method thereof
CN107165274B (en) A kind of more high-rise assembled modularization Self-resetting steel construction H profile steel column frame systems
CN202831704U (en) Middle joint coal bunker formed by erecting one row of pillars between two furnaces
CN202139685U (en) Lattice column of framework structure
CN202831703U (en) Middle joint coal bunker formed by erecting one row of pillars between two furnaces and with deaerators arranged in between
CN202831750U (en) Middle joint coal bunker formed by erecting three rows of pillars between two furnaces
CN201713800U (en) Transitional drilling platform
CN102828630B (en) Lateral bunker bay structure of large-scale thermal power plant
CN202945820U (en) Inner steel frame reinforced structure of pseudo-classic architecture
CN202866340U (en) Combined-coal-bunker with deaerator distributed in the middle and having two rows of upright pillars between two furnaces
CN203701386U (en) Steel-structure floor slab group
CN202835415U (en) Boiler steel structure and side coal bunker structure integrated device
CN204001190U (en) Building housing box column transformational structure
CN102864958A (en) Combined coal bin with a row of stand columns set between two boilers and deaerator arranged in middle and arrangement method
CN102864959A (en) Middle combined coal bin formed by setting a row of stand columns between two boilers and arrangement method thereof
CN102865592A (en) Middle combination bunker formed between two boilers through connection beam and arranging method thereof
CN203905531U (en) Rural assembled steel structure residence system
CN102864960A (en) Middle combined coal bunker formed by setting three rows of columns between two boilers and arrangement method
CN204590261U (en) A kind of novel prefabricated assembling frame structure
CN103470077A (en) Novel steel-structured plant
CN102900253A (en) Combined coal bunker with two rows of posts between two furnaces and deaerator in middle and arrangement method
CN203546908U (en) Assembly type building wall beam stable connection structure
CN203856101U (en) Lightgage steel joist frame
CN207660096U (en) A kind of prefabricated assembled concrete frame

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20130327