CN102839747A - 超高层异型结构钢结构桁架施工方法 - Google Patents

超高层异型结构钢结构桁架施工方法 Download PDF

Info

Publication number
CN102839747A
CN102839747A CN2012103591432A CN201210359143A CN102839747A CN 102839747 A CN102839747 A CN 102839747A CN 2012103591432 A CN2012103591432 A CN 2012103591432A CN 201210359143 A CN201210359143 A CN 201210359143A CN 102839747 A CN102839747 A CN 102839747A
Authority
CN
China
Prior art keywords
truss
assembly unit
coordinate
steel structure
rod member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103591432A
Other languages
English (en)
Inventor
黄波
周方华
姜滨厚
卢育坤
吴洪章
郭青松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN2012103591432A priority Critical patent/CN102839747A/zh
Publication of CN102839747A publication Critical patent/CN102839747A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种超高层异型结构钢结构桁架施工方法,包括以下步骤:建立桁架的三维立体仿真模型;深化设计桁架钢结构;制作所述桁架的各构件;地面预拼装;高空整拼。由于采用了本发明的一种超高层异型结构钢结构桁架施工方法,实现了一种成功解决屋顶施工工作面小、异型结构定位困难、精准定位难度大、重型结构吊装危险性高等难点的超高层异型结构钢结构桁架施工方法,具有施工质量可靠性强,生产率高,施工进度快,经济与社会效益强的特点。

Description

超高层异型结构钢结构桁架施工方法
技术领域
本发明涉及一种桁架施工方法,尤指一种超高层异型结构钢结构桁架施工方法。
背景技术
目前,国内的超高层建筑方兴未艾,钢结构以其强度高、刚度大、施工周期短以及抗震能力强的诸多优势被人们广泛地应用在了超高层建筑中,各类钢结构施工技术也呈蓬勃发展趋势。
但是在超高层的环境下,钢结构的安装也同时面临着众多挑战,一般情况下,构件堆放场地狭隘及构件繁多的冲突、塔吊性能偏低与重型构件的冲突以及高空作业与环境恶劣的冲突等等因素都时刻影响着钢结构安装和工程整体的进度,而超高层屋顶异型结构的钢桁架施工除了受上述因素影响之外还存在屋顶施工工作面小、异型结构定位困难、精准定位难度大、重型结构吊装危险性高等难点。如何科学、有序、经济、合理地组织施工将对工程整体质量、进度及成本的有效控制起到关键性的作用。
发明内容
本发明的目的在于克服现有技术的缺陷,而提供一种超高层异型结构钢结构桁架施工方法,实现了一种成功解决屋顶施工工作面小、异型结构定位困难、精准定位难度大、重型结构吊装危险性高等难点的超高层异型结构钢结构桁架施工方法,具有施工质量可靠性强,生产率高,施工进度快,经济与社会效益强的特点。
实现上述目的的技术方案是:
本发明的一种超高层异型结构钢结构桁架施工方法,包括以下步骤:
建立桁架的三维立体仿真模型;
深化设计桁架钢结构;
制作所述桁架的各构件;
地面预拼装;
高空整拼。
上述建立桁架的三维立体仿真模型步骤包括:
根据施工要求建立整体模型的点坐标并形成线模型;
利用所述线模型配合施工要求形成初步立体模型;
对所述初步立体模型的每个节点单独细化;
将节点细化后的所述初步立体模型叠放于主楼层屋面层结构图并对齐原点,形成三维立体仿真模型。
上述深化设计桁架钢结构步骤包括:
将桁架结构划分为复数个单榀桁架,所述单榀桁架包括主榀桁架和次榀桁架,并利用所述三维立体仿真模型设定所述单榀桁架的结构;
根据杆件重量数据,对所述单榀桁架中相邻杆件进行合理组合形成复数个构件,并将所述单榀桁架划分为复数个组件,形成单榀桁架的三维立体模型;
仿真模拟土建与钢结构交叉施工处,确认土建与钢结构的交叉位置,定位预埋件的钢筋预留孔开孔位置及尺寸。
上述地面预拼装步骤包括:
胎架搭设;
胎架底部抄平;
坐标预拼装;
拟合法复核预拼装尺寸。
上述坐标预拼装步骤包括:
建立一预拼装坐标系,将所述单榀桁架的三维立体模型放置于所述预拼装坐标系中;
从预拼装坐标系中获取控制点坐标;
根据所述控制点坐标,按照先主后次,先中间后两边的拼接顺序在所述胎架上进行杆件预拼装;
连接相邻杆件和构件并临时连接板和构件,形成各所述组件。
上述拟合法复核预拼装尺寸步骤进一步包括:
在现场建立一个随机坐标系;
在所述随机坐标系中,使用全站仪测出各杆件控制点的三维坐标数据;
利用各杆件控制点的三维坐标数据建立一拟合点模型图,并与原三维立体仿真模型进行拟合,获得各杆件控制点的偏差数据;
当一杆件控制点偏差数据数值大于10mm,对该控制点相邻杆件重新调整连接,并使用全站仪重新测量复测。
上述安装桁架步骤包括:
以从中间向两边的顺序每两个为一组地对称吊装主榀桁架,每吊装完一组主榀桁架后,在当前吊装的两主榀桁架与相邻主榀桁架之间分别吊装一次榀桁架,再将所述次榀桁架分别与相邻主榀桁架固定连接,直至桁架整体成形;
桁架坐标复核。
上述吊装主榀桁架和次榀桁架步骤包括:
根据三维立体仿真模型定位桁架柱脚的安装位置;
利用三维立体仿真模型模拟桁架分段安装过程,并获得拼装坐标数据;
使用塔吊将各组件吊装到位,并根据所述拼装坐标数据对组件的实际安装位置进行调整并将各组件点焊固定;
比对点焊固定后的各组件的现场坐标和所述拼装坐标数据,在确认偏差在合理范围后将所述各组件之间满焊固定。
上述桁架坐标复核包括步骤:
对整体桁架的关键控制点进行整体复核,将现场检测坐标与拼装坐标进行比较,偏差值超过5mm时割除重新焊接。
本发明由于采用了以上技术方案,使其具有以下有益效果是:
通过利用计算机建立三维立体仿真模型模拟现场施工,钢结构深化设计实现了对桁架安装进行了合理的分段。利用首层现场空地搭设胎架进行地面预拼装,配合三维立体仿真模型的坐标数据,实现了桁架组件的结构高精确组装,解决了屋顶施工工作面小、异型结构定位困难、精准定位难度大的问题。经拟合法复核预拼装尺寸无误后,对桁架组件进行高空整拼,解决了重型结构吊装危险性高的问题的同时,也有效地控制施工质量,加快施工进度,具有施工质量可靠性强,生产率高,施工进度快,经济与社会效益强的特点。
附图说明
图1为本发明超高层异型结构钢结构桁架施工方法的流程图;
图2为本发明超高层异型结构钢结构桁架施工方法的桁架结构示意图;
图3为本发明超高层异型结构钢结构桁架施工方法的单榀桁架结构示意图;
图4为本发明超高层异型结构钢结构桁架施工方法的单榀桁架分段结构示意图。
具体实施方式
下面结合具体实施例对本发明作进一步说明。
请参阅图1,本发明的一种超高层异型结构钢结构桁架施工方法,包括以下步骤:
首先,建立桁架的三维立体仿真模型;
步骤一:利用预设节点坐标列表,输入AutoCAD中,建立整体模型的点坐标。根据侧视图和正视图,将节点连接成线模型;
步骤二:根据预设杆件截面图结合杆件截面尺寸表,利用线模型,将各连线作为杆件的定位控制轴线,运用三维扫掠、拉伸、放样等绘图命令生成初步立体模型;
步骤三:利用线模型简单生成的立体模型是不完整的,因未考虑到杆件与杆件的连接方式,杆件与杆件交点错位,多根杆件交叉在在同一个地方并嵌入其他杆件内部,造成节点不清,针对节点处的连接,结合钢结构节点做法,得出最优接连方式后,综合利用布尔运算中的交集、差集、并集,及剖切、拖拽、抽壳对每个节点单独细化;
步骤四:将细节连接深化完成后的立体模型叠放于主楼层屋面层结构图上,将模型原点与平面图原点对齐,以便后续施工利用仿真模型读取坐标用于现场定位安装,形成三维立体仿真模型。
然后,深化设计桁架钢结构;
请参阅图2,将桁架1结构划分为复数个单榀桁架10,单榀桁架10包括主榀桁架101和次榀桁架102,并利用三维立体仿真模型设定单榀桁架10的结构;以主杆件为主,大杆件、支撑及附带的小杆件组合成单榀桁架10,将整体桁架拆分成7榀,其中4主榀桁架101,3次榀桁架102;每榀桁架10单独预拼装,每榀桁架10中间的短横杆现场可调节的空间较大,可不进行整体预拼装,在整体安装时再安装,运用该思想解决预拼装区域不足问题。
请参阅图3、图4,根据杆件重量数据,对单榀桁架10中相邻杆件进行合理组合形成复数个构件,并通过分割线104将单榀桁架10划分为复数个组件103,形成单榀桁架10的三维立体模型;
仿真模拟土建与钢结构交叉施工处,核对土建的柱定位图,将钢筋生成简单的柱状立体模型,根据预埋件的定位图纸,将预埋件与土建的钢筋模型相重合,从而确认具体的交叉位置,定位预埋件的钢筋预留孔开孔位置及尺寸。
接着,制作桁架的各构件;
再接着,地面预拼装,包括步骤:
1、胎架搭设;现场使用28a#工字钢搭设胎架。胎架尺寸为12000×16000mm。主受力构件为28a工字钢,间距1500mm,中间采用A48×3.5钢管连接,间距1500mm,钢管与工字钢焊接连接,使整个胎架构成整体。
2、胎架底部抄平;胎架底部根据底标高高差的不同,采用两种方式抄平。底标高相差不大的位置,使用10mm或20mm高的钢板做垫板将标高调整到位。标高相差较大的位置,测量具体的尺寸,直接使用28a工字钢垫平。
3、坐标预拼装;
(1)以现场预拼装施工方便、定位精准为前提,建立一预拼装坐标系,将单榀桁架的三维立体模型放置于预拼装坐标系中,以主杆件顶端为原点,沿主杆件中线为X轴,垂直主杆件为Y轴,垂直胎架平面向上为Z轴。
(2)从预拼装坐标系中获取控制点坐标;
(3)根据控制点坐标,按照先主后次,先中间后两边的拼接顺序在胎架上进行杆件预拼装;
(4)连接相邻杆件和构件并临时连接板和构件,形成各组件103。钢结构深化时已将每榀桁架10合理分段,为了现场安装的吊装施工方便和定位准确,局部小杆件与主杆件满焊,大杆件分成几个构件,构件之间点焊固定,并预先做好临时连接板。
4、拟合法复核预拼装尺寸。
(1)在现场建立一个随机坐标系,即任取地上的一个点作为坐标原点,任一个方向的一条直线为X轴,地面竖直向上为Z轴;
(2)在随机坐标系中,使用全站仪测出各杆件控制点的三维坐标数据;
(3)利用各杆件控制点的三维坐标数据建立一拟合点模型图,并与原三维立体仿真模型进行拟合,获得各杆件控制点的偏差数据;
记录好收集到的各杆件控制点的数据,主要需要以下的数据:杆件圆心点、杆件切分点。测量完全部杆件的控制点坐标后,将坐标输入CAD中,可以建立一个拟合点模型图。将拟合点模型图与原三维模型进行拟合,使最多的点与原模型重合或在最近距离范围内。理论上,点模型与圆模型可以完全重合,每个输入点都与原模型的控制点重合。因为施工误差,点与原模型控制点不在同一坐标,两点的距离就是现场预拼装的施工误差。
(4)针对拟合法复核尺寸偏差后的三种情况做如下处理:
杆件控制点偏差数据数值在5mm内,拼装合格,无须整改。
杆件控制点偏差数据数值大于5mm小于10mm的,为尺寸微偏差。着重注意,该偏差尚可在现场安装中进行局部微调,故亦无须整改。
杆件控制点偏差数据数值大于10mm的,对该控制点相邻杆件重新调整连接,并使用全站仪重新测量复测,合格后方可满焊用于现场安装。
最后,高空整拼。
请参阅图2,以从中间向两边的顺序每两个为一组地对称吊装主榀桁架101,每吊装完一组主榀桁架101后,在当前吊装的两主榀桁架101与相邻主榀桁架101之间分别吊装一次榀桁架102,再将次榀桁架102分别与相邻主榀桁架101固定连接,直至桁架1整体成形;
即先安装内侧的一组主榀桁架101,然后暂时用揽风绳固定住,然后立即开始安装吊装最中间的次榀桁架102,吊装到位后,立即将已安装好的三个单榀桁架10连成整体,拆去揽风绳;
接着安装外侧的两主榀桁架101,为最大的单榀桁架。最后安装另外两个次榀桁架102。这次榀桁架102亦为小杆件构成的桁架,一步安装到位。最后将全部横杆件吊装到位,形成一个完整的整体。
桁架1坐标复核;对整体桁架1的关键控制点进行整体复核,将现场检测坐标与拼装坐标进行比较,偏差值超过5mm时割除重新焊接。
另外,吊装主榀桁架和次榀桁架时:
首先根据三维立体仿真模型定位桁架柱脚的安装位置;
然后利用三维立体仿真模型模拟桁架分段安装过程,并获得拼装坐标数据;根据已经明确的分段要求,将模型分解成不同的分段,模拟每个分段的拼装情况,事先电脑模拟,找出高空整拼需要的数据及相应的准备;
再根据三维坐标对构件的实际安装位置进行调整。在两个构件的连接处进行微调,分别在两个构件接口处焊接调节板,将千斤顶嵌入调节板中间,配合撬棍,将构件调整到位。考虑到高空操作,风荷载很大,使用手拉葫芦和钢丝绳做缆风绳使用。将构件调整到位后,点焊进行固定;
最后,比对点焊固定后的各组件的现场坐标和拼装坐标数据,在确认偏差在合理范围后将各组件之间满焊固定。
现场主要采用管相贯CO2焊,焊丝为E501T-1,直径Φ1.2mm。
焊接要求:
1)焊接前应对焊缝坡口区域进行彻底打磨,去除油污、铁锈、氧化皮等杂物直至露出金属光泽。
2)焊前、焊后均不得对试板进行预热、后热、锤击、热处理。
3)焊接过程中不得对层间和表面焊缝进行打磨和修补,但焊后应清除焊渣、飞溅等。
4)焊接工艺参数详见焊接工艺指导书。
可采用管相贯焊试件的检验:
焊缝外观检查用5倍放大镜目测,表面质量合格后方可进行其它项目的检验,其表面质量应符合下列要求:
1)试件焊缝表面无裂纹、未焊满、未熔合、气孔、夹渣、焊瘤等缺陷。
2)焊缝边缘应圆滑过渡到母材;焊缝表面咬边和表面凹陷深度不应大于0.5mm,咬边总长应不大于焊缝全长的5﹪,且不大于12mm。
也可采用超声波探伤:
超声波探伤应符合《钢结构超声波探伤及质量分级法》
(JG/T203-2007)规定的要求(见图5.3.3-2焊工考试检测、图5.3.3-3现场实体检测)。
试件经UT检测后,每件试件均应在趾部区、侧部区、及跟部区各取一宏观酸蚀试样。试验应符合国家现行标准《钢的低倍组织及缺陷酸蚀检验法》(GB-226)的规定;试样的尺寸应符合标准要求。
经宏观酸蚀试验,试样接头及热影响区表面不应有肉眼可见的裂纹、未熔合等缺陷。
通过利用计算机建立三维立体仿真模型模拟现场施工,钢结构深化设计实现了对桁架安装进行了合理的分段。利用首层现场空地搭设胎架进行地面预拼装,配合三维立体仿真模型的坐标数据,实现了桁架组件的结构高精确组装,解决了屋顶施工工作面小、异型结构定位困难、精准定位难度大的问题。经拟合法复核预拼装尺寸无误后,对桁架组件进行高空整拼,解决了重型结构吊装危险性高的问题的同时,也有效地控制施工质量,加快施工进度,具有施工质量可靠性强,生产率高,施工进度快,经济与社会效益强的特点。
以上结合附图实施例对本发明进行了详细说明,本领域中普通技术人员可根据上述说明对本发明做出种种变化例。因而,实施例中的某些细节不应构成对本发明的限定,本发明将以所附权利要求书界定的范围作为本发明的保护范围。

Claims (9)

1.一种超高层异型结构钢结构桁架施工方法,其特征在于,包括以下步骤:
建立桁架的三维立体仿真模型;
深化设计桁架钢结构;
制作所述桁架的各构件;
地面预拼装;
高空整拼。
2.如权利要求1所述超高层异型结构钢结构桁架施工方法,其特征在于:所述建立桁架的三维立体仿真模型步骤包括:
根据施工要求建立整体模型的点坐标并形成线模型;
利用所述线模型配合施工要求形成初步立体模型;
对所述初步立体模型的每个节点单独细化;
将节点细化后的所述初步立体模型叠放于主楼层屋面层结构图并对齐原点,形成三维立体仿真模型。
3.如权利要求1所述超高层异型结构钢结构桁架施工方法,其特征在于:所述深化设计桁架钢结构步骤包括:
将桁架结构划分为复数个单榀桁架,所述单榀桁架包括主榀桁架和次榀桁架,并利用所述三维立体仿真模型设定所述单榀桁架的结构;
根据杆件重量数据,对所述单榀桁架中相邻杆件进行合理组合形成复数个构件,并将所述单榀桁架划分为复数个组件,形成单榀桁架的三维立体模型;
仿真模拟土建与钢结构交叉施工处,确认土建与钢结构的交叉位置,定位预埋件的钢筋预留孔开孔位置及尺寸。
4.如权利要求1所述超高层异型结构钢结构桁架施工方法,其特征在于:所述地面预拼装步骤包括:
胎架搭设;
胎架底部抄平;
坐标预拼装;
拟合法复核预拼装尺寸。
5.如权利要求4所述超高层异型结构钢结构桁架施工方法,其特征在于:所述坐标预拼装步骤包括:
建立一预拼装坐标系,将所述单榀桁架的三维立体模型放置于所述预拼装坐标系中;
从预拼装坐标系中获取控制点坐标;
根据所述控制点坐标,按照先主后次,先中间后两边的拼接顺序在所述胎架上进行杆件预拼装;
连接相邻杆件和构件并临时连接板和构件,形成各所述组件。
6.如权利要求4所述超高层异型结构钢结构桁架施工方法,其特征在于:所述拟合法复核预拼装尺寸步骤进一步包括:
在现场建立一个随机坐标系;
在所述随机坐标系中,使用全站仪测出各杆件控制点的三维坐标数据;
利用各杆件控制点的三维坐标数据建立一拟合点模型图,并与原三维立体仿真模型进行拟合,获得各杆件控制点的偏差数据;
当一杆件控制点偏差数据数值大于10mm,对该控制点相邻杆件重新调整连接,并使用全站仪重新测量复测。
7.如权利要求1所述超高层异型结构钢结构桁架施工方法,其特征在于:所述高空整拼步骤包括:
以从中间向两边的顺序每两个为一组地对称吊装主榀桁架,每吊装完一组主榀桁架后,在当前吊装的两主榀桁架与相邻主榀桁架之间分别吊装一次榀桁架,再将所述次榀桁架分别与相邻主榀桁架固定连接,直至桁架整体成形;
桁架坐标复核。
8.如权利要求7所述超高层异型结构钢结构桁架施工方法,其特征在于:所述吊装主榀桁架和次榀桁架步骤包括:
根据三维立体仿真模型定位桁架柱脚的安装位置;
利用三维立体仿真模型模拟桁架分段安装过程,并获得拼装坐标数据;
使用塔吊将各组件吊装到位,并根据所述拼装坐标数据对组件的实际安装位置进行调整并将各组件点焊固定;
比对点焊固定后的各组件的现场坐标和所述拼装坐标数据,在确认偏差在合理范围后将所述各组件之间满焊固定。
9.如权利要求7所述超高层异型结构钢结构桁架施工方法,其特征在于:所述桁架坐标复核包括步骤:
对整体桁架的关键控制点进行整体复核,将现场检测坐标与拼装坐标进行比较,偏差值超过5mm时割除重新焊接。
CN2012103591432A 2012-09-24 2012-09-24 超高层异型结构钢结构桁架施工方法 Pending CN102839747A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103591432A CN102839747A (zh) 2012-09-24 2012-09-24 超高层异型结构钢结构桁架施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103591432A CN102839747A (zh) 2012-09-24 2012-09-24 超高层异型结构钢结构桁架施工方法

Publications (1)

Publication Number Publication Date
CN102839747A true CN102839747A (zh) 2012-12-26

Family

ID=47367447

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103591432A Pending CN102839747A (zh) 2012-09-24 2012-09-24 超高层异型结构钢结构桁架施工方法

Country Status (1)

Country Link
CN (1) CN102839747A (zh)

Cited By (39)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114734A (zh) * 2013-03-08 2013-05-22 北京工业大学 一种适用于具有充气膜压杆桁架的快速施工方法
CN103806530A (zh) * 2014-03-14 2014-05-21 中国建筑第二工程局有限公司 一种异形悬挑钢结构及其施工方法
CN104278862A (zh) * 2014-09-30 2015-01-14 武汉武船重型装备工程有限责任公司 一种超大异形垂直升降舞台桁架安装方法
CN104481155A (zh) * 2014-11-05 2015-04-01 北京崇建工程有限公司 仿古建筑大木结构制作安装方法
CN104679516A (zh) * 2015-03-10 2015-06-03 浙江精工钢结构集团有限公司 一种基于vb插件的虚拟预拼装算法及应用
CN105003081A (zh) * 2015-05-06 2015-10-28 浙江东南网架股份有限公司 一种三角形截面弯扭构件的双向斜交网格安装定位方法
CN105019665A (zh) * 2015-07-20 2015-11-04 中国二十二冶集团有限公司 基于全站仪的大跨度结构梁安装方法
CN105625732A (zh) * 2015-12-30 2016-06-01 常州第一建筑集团有限公司 超高悬挑钢结构桁架无支撑施工方法
CN106223623A (zh) * 2015-06-02 2016-12-14 五冶集团上海有限公司 钢结构箱型拱形屋架安装方法
CN106337564A (zh) * 2016-08-30 2017-01-18 上海二十冶建设有限公司 高空超大悬挑钢结构无支撑施工方法
CN106609561A (zh) * 2015-10-22 2017-05-03 江苏沪宁钢机股份有限公司 一种球形网壳分块层叠式拼装方法
CN106785314A (zh) * 2016-11-17 2017-05-31 上海卫星工程研究所 多层复杂桁架结构装配成型方法
CN107273607A (zh) * 2017-06-13 2017-10-20 北京工业大学 一种基于bim的钢结构厂房预拼装方法
CN108252524A (zh) * 2017-12-22 2018-07-06 上海市机械施工集团有限公司 一种拼装胎架及一种双曲桁架拼装方法
CN108733950A (zh) * 2018-05-30 2018-11-02 中铁宝桥(扬州)有限公司 一种多曲面扭曲形钢塔的线性测量控制方法
CN108731647A (zh) * 2018-03-14 2018-11-02 江苏恒久钢构有限公司 一种桁架安装对接测量方法
CN108894580A (zh) * 2018-08-01 2018-11-27 南通蓝岛海洋工程有限公司 一种火炬塔的建造工艺
CN109098336A (zh) * 2018-08-27 2018-12-28 苏州园林发展股份有限公司 一种穹顶装置的施工方法
CN109184225A (zh) * 2018-10-23 2019-01-11 中建三局安装工程有限公司 一种四弦棱形弯扭圆管桁架结构体系及拼装方法
CN109488029A (zh) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 回风夹道钢结构整榀吊装的施工方法
CN109750845A (zh) * 2017-11-08 2019-05-14 上海宝冶集团有限公司 用于开口型平面桁架的地面拼装方法
CN109829239A (zh) * 2019-02-16 2019-05-31 中建一局集团第一建筑有限公司 一种基于三维软件的钢管桁架模拟预拼装施工方法
CN110065887A (zh) * 2019-05-10 2019-07-30 中建八局第四建设有限公司 空间网架钢结构双向旋转提升施工方法
CN110130183A (zh) * 2018-02-09 2019-08-16 上海宝冶集团有限公司 用于雪橇竞赛项目的制冷管道的安装方法
CN110124298A (zh) * 2018-02-09 2019-08-16 上海宝冶集团有限公司 用于雪橇竞赛项目的制冷管道支架的分段拼装方法
CN110409840A (zh) * 2019-07-29 2019-11-05 中国人民解放军63926部队 屋架吊装方法
CN110439171A (zh) * 2019-07-03 2019-11-12 中国十七冶集团有限公司 一种装配式反吊顶龙骨安装方法
CN110499921A (zh) * 2019-09-04 2019-11-26 中亿丰建设集团股份有限公司 多层空间曲面网壳骨架支撑式膜结构屋面施工方法
CN110512877A (zh) * 2019-08-30 2019-11-29 中国二十二冶集团有限公司 张弦梁安装检测控制方法
CN110781610A (zh) * 2019-11-11 2020-02-11 中国工程物理研究院机械制造工艺研究所 一种适宜于焊接的板状结构轻量化设计方法及轻量化结构
CN111764730A (zh) * 2020-06-30 2020-10-13 诚邦生态环境股份有限公司 螺旋桁式塔分层组合安装施工工法
CN113431340A (zh) * 2021-07-22 2021-09-24 中建八局第二建设有限公司 一种玫瑰状异形空间网格钢结构施工方法
CN113513173A (zh) * 2021-04-02 2021-10-19 上海二十冶建设有限公司 一种大型异型钢结构累积连续预拼装施工方法
CN113548592A (zh) * 2021-06-30 2021-10-26 广州文冲船舶修造有限公司 一种起重机吊臂托架的建造方法
CN114604391A (zh) * 2022-03-24 2022-06-10 中船黄埔文冲船舶有限公司 一种固桩架搭建方法
CN115045450A (zh) * 2022-04-22 2022-09-13 中铁二十局集团第二工程有限公司 建筑结构屋面面板的安装方法及其建筑结构
CN115248948A (zh) * 2022-08-16 2022-10-28 北京首钢建设集团有限公司 一种钢结构滑雪大跳台顶部装置结构安装方法
CN115422645A (zh) * 2022-09-22 2022-12-02 北京首钢建设集团有限公司 一种大跨度异型钢桁架结构三维测量空间坐标转换的方法
CN115434520A (zh) * 2022-09-30 2022-12-06 中冶(上海)钢结构科技有限公司 一种代替复杂重型桁架立体预拼装的方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101458731A (zh) * 2008-12-21 2009-06-17 中铁宝桥股份有限公司 钢结构组件计算机模拟拼装方法
CN101556704A (zh) * 2009-05-19 2009-10-14 武汉一冶钢结构有限责任公司 一种钢结构拼装临时支撑胎架体系的建立方法
CN101619603A (zh) * 2009-07-21 2010-01-06 上海市第一建筑有限公司 一种网架结构吊装及屋面围护施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101458731A (zh) * 2008-12-21 2009-06-17 中铁宝桥股份有限公司 钢结构组件计算机模拟拼装方法
CN101556704A (zh) * 2009-05-19 2009-10-14 武汉一冶钢结构有限责任公司 一种钢结构拼装临时支撑胎架体系的建立方法
CN101619603A (zh) * 2009-07-21 2010-01-06 上海市第一建筑有限公司 一种网架结构吊装及屋面围护施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周方华,吴洪章,等: "超高层异形结构钢桁架施工技术", 《第四届全国钢结构工程技术交流会论文集》, 31 July 2012 (2012-07-31) *

Cited By (48)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114734B (zh) * 2013-03-08 2015-10-28 北京工业大学 一种适用于具有充气膜压杆桁架的快速施工方法
CN103114734A (zh) * 2013-03-08 2013-05-22 北京工业大学 一种适用于具有充气膜压杆桁架的快速施工方法
CN103806530A (zh) * 2014-03-14 2014-05-21 中国建筑第二工程局有限公司 一种异形悬挑钢结构及其施工方法
CN103806530B (zh) * 2014-03-14 2015-11-18 中国建筑第二工程局有限公司 一种异形悬挑钢结构及其施工方法
CN104278862A (zh) * 2014-09-30 2015-01-14 武汉武船重型装备工程有限责任公司 一种超大异形垂直升降舞台桁架安装方法
CN104481155A (zh) * 2014-11-05 2015-04-01 北京崇建工程有限公司 仿古建筑大木结构制作安装方法
CN104679516A (zh) * 2015-03-10 2015-06-03 浙江精工钢结构集团有限公司 一种基于vb插件的虚拟预拼装算法及应用
CN104679516B (zh) * 2015-03-10 2018-02-06 浙江精工钢结构集团有限公司 一种基于vb插件的虚拟预拼装算法及应用
CN105003081A (zh) * 2015-05-06 2015-10-28 浙江东南网架股份有限公司 一种三角形截面弯扭构件的双向斜交网格安装定位方法
CN106223623A (zh) * 2015-06-02 2016-12-14 五冶集团上海有限公司 钢结构箱型拱形屋架安装方法
CN106223623B (zh) * 2015-06-02 2018-07-13 五冶集团上海有限公司 钢结构箱型拱形屋架安装方法
CN105019665A (zh) * 2015-07-20 2015-11-04 中国二十二冶集团有限公司 基于全站仪的大跨度结构梁安装方法
CN106609561A (zh) * 2015-10-22 2017-05-03 江苏沪宁钢机股份有限公司 一种球形网壳分块层叠式拼装方法
CN105625732A (zh) * 2015-12-30 2016-06-01 常州第一建筑集团有限公司 超高悬挑钢结构桁架无支撑施工方法
CN106337564A (zh) * 2016-08-30 2017-01-18 上海二十冶建设有限公司 高空超大悬挑钢结构无支撑施工方法
CN106785314A (zh) * 2016-11-17 2017-05-31 上海卫星工程研究所 多层复杂桁架结构装配成型方法
CN107273607A (zh) * 2017-06-13 2017-10-20 北京工业大学 一种基于bim的钢结构厂房预拼装方法
CN109750845A (zh) * 2017-11-08 2019-05-14 上海宝冶集团有限公司 用于开口型平面桁架的地面拼装方法
CN108252524A (zh) * 2017-12-22 2018-07-06 上海市机械施工集团有限公司 一种拼装胎架及一种双曲桁架拼装方法
CN110130183A (zh) * 2018-02-09 2019-08-16 上海宝冶集团有限公司 用于雪橇竞赛项目的制冷管道的安装方法
CN110130183B (zh) * 2018-02-09 2021-06-01 上海宝冶集团有限公司 用于雪橇竞赛项目的制冷管道的安装方法
CN110124298A (zh) * 2018-02-09 2019-08-16 上海宝冶集团有限公司 用于雪橇竞赛项目的制冷管道支架的分段拼装方法
CN108731647A (zh) * 2018-03-14 2018-11-02 江苏恒久钢构有限公司 一种桁架安装对接测量方法
CN108733950B (zh) * 2018-05-30 2021-05-25 中铁宝桥(扬州)有限公司 一种多曲面扭曲形钢塔的线性测量控制方法
CN108733950A (zh) * 2018-05-30 2018-11-02 中铁宝桥(扬州)有限公司 一种多曲面扭曲形钢塔的线性测量控制方法
CN108894580A (zh) * 2018-08-01 2018-11-27 南通蓝岛海洋工程有限公司 一种火炬塔的建造工艺
CN109098336A (zh) * 2018-08-27 2018-12-28 苏州园林发展股份有限公司 一种穹顶装置的施工方法
CN109184225A (zh) * 2018-10-23 2019-01-11 中建三局安装工程有限公司 一种四弦棱形弯扭圆管桁架结构体系及拼装方法
CN109488029A (zh) * 2018-11-07 2019-03-19 中建三局第建设工程有限责任公司 回风夹道钢结构整榀吊装的施工方法
CN109829239A (zh) * 2019-02-16 2019-05-31 中建一局集团第一建筑有限公司 一种基于三维软件的钢管桁架模拟预拼装施工方法
CN110065887A (zh) * 2019-05-10 2019-07-30 中建八局第四建设有限公司 空间网架钢结构双向旋转提升施工方法
CN110439171A (zh) * 2019-07-03 2019-11-12 中国十七冶集团有限公司 一种装配式反吊顶龙骨安装方法
CN110409840A (zh) * 2019-07-29 2019-11-05 中国人民解放军63926部队 屋架吊装方法
CN110512877A (zh) * 2019-08-30 2019-11-29 中国二十二冶集团有限公司 张弦梁安装检测控制方法
CN110499921A (zh) * 2019-09-04 2019-11-26 中亿丰建设集团股份有限公司 多层空间曲面网壳骨架支撑式膜结构屋面施工方法
CN110781610A (zh) * 2019-11-11 2020-02-11 中国工程物理研究院机械制造工艺研究所 一种适宜于焊接的板状结构轻量化设计方法及轻量化结构
CN111764730A (zh) * 2020-06-30 2020-10-13 诚邦生态环境股份有限公司 螺旋桁式塔分层组合安装施工工法
CN113513173A (zh) * 2021-04-02 2021-10-19 上海二十冶建设有限公司 一种大型异型钢结构累积连续预拼装施工方法
CN113548592A (zh) * 2021-06-30 2021-10-26 广州文冲船舶修造有限公司 一种起重机吊臂托架的建造方法
CN113431340A (zh) * 2021-07-22 2021-09-24 中建八局第二建设有限公司 一种玫瑰状异形空间网格钢结构施工方法
CN114604391A (zh) * 2022-03-24 2022-06-10 中船黄埔文冲船舶有限公司 一种固桩架搭建方法
CN115045450A (zh) * 2022-04-22 2022-09-13 中铁二十局集团第二工程有限公司 建筑结构屋面面板的安装方法及其建筑结构
CN115248948A (zh) * 2022-08-16 2022-10-28 北京首钢建设集团有限公司 一种钢结构滑雪大跳台顶部装置结构安装方法
CN115248948B (zh) * 2022-08-16 2023-10-20 北京首钢建设集团有限公司 一种钢结构滑雪大跳台顶部装置结构安装方法
CN115422645A (zh) * 2022-09-22 2022-12-02 北京首钢建设集团有限公司 一种大跨度异型钢桁架结构三维测量空间坐标转换的方法
CN115422645B (zh) * 2022-09-22 2024-02-02 北京首钢建设集团有限公司 一种大跨度异型钢桁架结构三维测量空间坐标转换的方法
CN115434520A (zh) * 2022-09-30 2022-12-06 中冶(上海)钢结构科技有限公司 一种代替复杂重型桁架立体预拼装的方法
CN115434520B (zh) * 2022-09-30 2023-10-27 中冶(上海)钢结构科技有限公司 一种代替复杂重型桁架立体预拼装的方法

Similar Documents

Publication Publication Date Title
CN102839747A (zh) 超高层异型结构钢结构桁架施工方法
CN112012340B (zh) 一种用于大跨度悬挑钢桁架悬挂连接节点及其施工方法
CN103806660B (zh) 劲性混凝土结构梁-柱节点施工方法
CN103541474B (zh) 分层法制作双曲面不锈钢幕墙的施工方法
CN104652827B (zh) 一种大跨度弧形桁架三级接力抬吊施工方法
CN103321350B (zh) 一种多连接大截面组合箱型厚板边柱及其建造方法
CN111364615A (zh) 一种异形、曲面悬挂式钢结构体系的安装方法
CN101100902A (zh) 斜拉钢桁架高支模结构体系及其施工方法
CN102518204B (zh) 一种大佛宝盖及其制作方法
CN113250468A (zh) 一种高层建筑的对称悬挑钢桁架施工方法及施工结构
CN203947771U (zh) 一种贝雷梁悬吊模板支撑体系
CN107988908A (zh) 钢管拱总拼装方法
CN107035060A (zh) 一种大截面厚壁焊接箱型构件及其制作方法
CN114033051A (zh) 一种基于钢结构球幕影院工程大跨度双曲桁架施工工艺
CN103321324B (zh) 一种桁架节点区超厚钢板墙及其建造方法
CN107964864A (zh) 一种体内锚固索的渐变梯形弯扭构件及制造方法
CN107491619A (zh) 一种基于bim技术的旧改项目钢结构定位吊装施工方法
CN107165317B (zh) 一种用于异形幕墙骨架的钢制圆盘形节点构件及应用方法
CN115324359A (zh) 一种基于bim的弧形多曲面异形幕墙设计施工方法
CN106544959B (zh) 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法
CN103321325B (zh) 一种巨型组合l形箱型厚板剪力墙柱的建造方法
CN205152802U (zh) 一种提高拱桥劲性骨架工地现场制作精度的结构
CN106223209B (zh) 一种后张法预应力混凝土箱梁施工的深埋锚盒及施工方法
CN202023298U (zh) 适用于交叉式塔吊吊装的整榀分段式屋面钢梁结构
CN104563525B (zh) 一种箱式钢拱梁整体卧式组对方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121226