CN102797468A - 盾构隧道浅覆土始发方法 - Google Patents

盾构隧道浅覆土始发方法 Download PDF

Info

Publication number
CN102797468A
CN102797468A CN2012103008557A CN201210300855A CN102797468A CN 102797468 A CN102797468 A CN 102797468A CN 2012103008557 A CN2012103008557 A CN 2012103008557A CN 201210300855 A CN201210300855 A CN 201210300855A CN 102797468 A CN102797468 A CN 102797468A
Authority
CN
China
Prior art keywords
stratum
section
shield
shield tunnel
solid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103008557A
Other languages
English (en)
Other versions
CN102797468B (zh
Inventor
肖明清
韩向阳
刘浩
宁茂权
薛光桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201210300855.7A priority Critical patent/CN102797468B/zh
Publication of CN102797468A publication Critical patent/CN102797468A/zh
Application granted granted Critical
Publication of CN102797468B publication Critical patent/CN102797468B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种盾构隧道浅覆土始发方法,通过采用覆土反压、局部全断面地层加固和门式地层加固相结合的方法对盾构始发段土体进行加固,以提高地层稳定性和顶部土体抵抗泥水劈裂能力,为了防止盾构始发时洞门打开后掌子面土体破坏和地层发生松动等,造成泥水仓中的泥浆漏浆、地层失稳、涌水涌泥等,采用冻结法加固开洞处一定厚度地层。本发明解决了浅覆土条件下始发段地层的稳定问题,同时降低了始发工作井和明挖段深基坑施工风险,降低了工程造价,具有较好的社会及经济效益。

Description

盾构隧道浅覆土始发方法
技术领域
本发明涉及一种盾构隧道的始发方法,具体地指一种盾构隧道浅覆土始发方法。
背景技术
近年来国内盾构隧道得到了迅猛发展,包括地铁、公路、市政、铁路、输水、输气等行业。国内业界在盾构隧道的理论及试验研究上也投入了大量的资金,开展了大量的科研课题,譬如在盾构隧道结构力学性能和设计方法方面,取得了一些成绩。
但是在超大盾构隧道及复杂环境条件下盾构始发方面的仍然存在一些问题,由于大直径盾构隧道掌子面上下的水土压力差别较大,且掌子面上土层条件也不相同,因此浅覆土始发过程中泥水压力与掌子面水土压力的平衡难以掌控,轻微的泥水压力波动即易引起掌子面土体的坍塌,酿成重大的工程安全事故。
针对上述问题,现有技术一般采取增大始发段覆土的厚度,根据经验值选择0.5~0.6倍盾构隧道外径,这样在一定程度上能增大始发段盾构隧道顶部土层抗泥水劈裂能力,降低盾构机泥水压力波动过大而击穿上覆土层,造成地层失稳或坍塌的风险,但却增加了始发工作井和后续明挖段的基坑开挖深度,增大了工程风险和造价;此外,现有技术中多采用单一的地层加固方式,往往难以保证加固质量和效果,始发洞口打开后掌子面土体发生涌水涌泥,或无法承受盾构机泥水仓内的泥水压力而局部出现破坏等等,造成地层失稳或坍塌等。
发明内容
本发明的目的在于克服现有盾构隧道浅覆土始发过程中地层的稳定性问题,提供一种无需增大始发段覆土的厚度,工程造价低,安全的盾构隧道浅覆土始发方法。
为实现上述目的,本发明所设计的盾构隧道浅覆土始发方法,所述方法包括以下步骤:
1)对始发井外,沿盾构掘进方向的地层进行全断面加固、全断面加固体(2)的厚度比盾构机长度长2~3米;
2)以全断面加固体的末端为界,沿盾构掘进方向,对地层进行门式加固,门式加固体的厚度为30~55米,并对全断面加固体和门式加固体范围内的地面进行覆土反压;门式加固体沿盾构掘进方向的长度应能覆盖盾构上方覆土厚度不能满足盾构隧道施工期抗浮需要的地段;
3)然后采用冻结法对靠近始发井的洞门处地层进行界面冻结加固,界面冻结加固体厚度为1~2米;
4)待加固土体和冻结地层达到设计要求,且盾构机组装调试到位后,凿除洞门范围内的工作井围护墙;
5)盾构机前推至掌子面建立泥水密封后掘进。
优选地,所述全断面加固体的横剖面为宽和高均为D+6.1米的大矩形和位于其正下方的宽0.7D-0.1米、高3~6米的小矩形上下接合而成的不规则多边形,盾构隧道面位于所述上方的大矩形的中心,所述D为盾构机直径。小矩形加固体作为承担盾构机自重荷载的基础。
优选地,所述门式加固体的横剖面为宽D+6.1米,高0.7D+2米且下方开有弧形缺口的矩形,所述弧形缺口和盾构隧道面的形状相匹配,且缺口的顶点与所述门式加固体的剖面的宽边的距离为3~3.4米。
优选地,所述界面冻结加固体的横剖面为宽和高均为D+6.1米的矩形,其盾构隧道面位于界面冻结加固体的横剖面的中心。
本发明所述全断面加固、门式加固、界面冻结加固、覆土反压的技术实施过程如下:
全断面加固是指加固体断面能将掘进轴线方向上盾构机的整个横断面全部包住,加固方式可以采用旋喷桩或搅拌桩等。
门式加固是指加固体断面形状似一个“凯旋门”,位于盾构隧道正上方。
界面冻结加固是指在紧邻始发井洞门外侧1~2m范围内的土体采用冻结法加固的方式。
覆土反压是指在现状覆土厚度不能满足盾构隧道施工期抗浮要求的地段通过在既有地面堆土的方式使得盾构隧道覆土满足抗浮要求的方式。
本发明通过采用覆土反压、局部全断面地层加固和门式地层加固相结合的方法对盾构始发段土体进行加固,以提高地层稳定性和顶部土体抵抗泥水劈裂能力,为了防止盾构始发时洞门打开后掌子面土体破坏和地层发生松动等,造成泥水仓中的泥浆漏浆、地层失稳、涌水涌泥等,采用冻结法加固开洞处一定厚度地层。浅覆土始发方式能减少了始发井基坑开挖深度,降低工程风险和工程造价。
本发明的有益效果:所提供的盾构隧道浅覆土始发方法,解决了浅覆土条件下始发段地层的稳定问题,同时降低了始发工作井和明挖段深基坑施工风险,降低了工程造价,具有较好的社会及经济效益。
附图说明
图1为本发明的盾构隧道浅覆土始发方法的平面布置示意图;
图2为图1中盾构隧道浅覆土始发方法的纵断面布置示意图;
图3为图1中全断面加固体的横剖面图;
图4为图1中门式加固体的横剖面图;
图5为图1中界面冻结加固体的横剖面图。
图中:1为明挖盾构分界,2为全断面加固体,3为门式加固体,4为界面冻结加固体,5为盾构隧道管片,6为始发井,7为工作井围护墙,8为工作井内衬墙。
具体实施方式
以下结合附图和具体实施例对本发明作进一步的详细描述。
如图1~5所示,本发明的盾构隧道浅覆土始发方法,包括以下步骤:
1)采用旋喷桩或搅拌桩对始发段盾构穿越的地层进行全断面加固、全断面加固体2的厚度比盾构机长度长2~3米,本实施例中为16.4米;
2)以全断面加固体2的末端为界,沿盾构掘进方向,对地层进行门式加固,门式加固体3的厚度为55米,并对全断面加固体2和门式加固体3范围内地面进行覆土反压;
3)然后采用冻结法对靠近始发井6洞门处地层进行界面冻结加固,界面冻结加固体4厚度为1.6米;
4)待加固土体和冻结地层达到设计要求,且盾构机组装调试到位后,凿除洞门范围内的工作井围护墙7,从而满足盾构始发时顶部地层的稳定和掌子面土体的稳定等要求;
5)盾构机前推至掌子面建立泥水密封后,按设定的泥水压力和掘进参数掘进。
如图3,盾构机直径为15米。全断面加固体2的横剖面为宽21.1米、高21.1米的大矩形和位于其正下方的宽10.4米、高5.2米的小矩形上下接合而成的不规则多边形,盾构隧道面位于宽21.1米、高21.1米的矩形的中心。
如图4,门式加固体3的横剖面为宽21.1米,高12.5米且下方开有弧形缺口的矩形,弧形缺口和盾构隧道面的形状相匹配,且缺口的顶点与门式加固体3的剖面的宽边的距离为3.3米。
如图5,界面冻结加固体4的横剖面为宽21.1米、高21.1米的矩形,盾构隧道面位于全断面加固体2的横剖面的中心。

Claims (4)

1.一种盾构隧道浅覆土始发方法,其特征在于:所述方法包括以下步骤:
1)对始发井外,沿盾构掘进方向的地层进行全断面加固、全断面加固体(2)的厚度比盾构机长度长2~3米;
2)以全断面加固体(2)的末端为界,沿盾构掘进方向,对地层进行门式加固,门式加固体(3)的厚度为30~55米,并对全断面加固体(2)和门式加固体(3)范围内的地面进行覆土反压;
3)然后采用冻结法对靠近始发井(6)的洞门处地层进行界面冻结加固,界面冻结加固体(4)厚度为1~2米;
4)待加固土体和冻结地层达到设计要求,且盾构机组装调试到位后,凿除洞门范围内的工作井围护墙(7);
5)盾构机前推至掌子面建立泥水密封后掘进。
2.根据权利要求1所述的盾构隧道浅覆土始发方法,其特征在于:所述全断面加固体(2)的横剖面为宽和高均为D+6.1米的大矩形和位于其正下方的宽0.7D-0.1米、高3~6米的小矩形上下接合而成的不规则多边形,盾构隧道面位于所述大矩形的中心,所述D为盾构机直径。
3.根据权利要求2所述的盾构隧道浅覆土始发方法,其特征在于:所述门式加固体(3)的横剖面为宽D+6.1米,高0.7D+2米且下方开有弧形缺口的矩形,所述弧形缺口和盾构隧道面的形状相匹配,且缺口的顶点与所述门式加固体(3)的剖面的宽边的距离为3~3.4米。
4.根据权利要求2所述的盾构隧道浅覆土始发方法,其特征在于:所述界面冻结加固体(4)的横剖面为宽和高均为D+6.1米的矩形,盾构隧道面位于所述界面冻结加固体(4)的横剖面的中心。
CN201210300855.7A 2012-08-22 2012-08-22 盾构隧道浅覆土始发方法 Active CN102797468B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210300855.7A CN102797468B (zh) 2012-08-22 2012-08-22 盾构隧道浅覆土始发方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210300855.7A CN102797468B (zh) 2012-08-22 2012-08-22 盾构隧道浅覆土始发方法

Publications (2)

Publication Number Publication Date
CN102797468A true CN102797468A (zh) 2012-11-28
CN102797468B CN102797468B (zh) 2015-04-22

Family

ID=47196746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210300855.7A Active CN102797468B (zh) 2012-08-22 2012-08-22 盾构隧道浅覆土始发方法

Country Status (1)

Country Link
CN (1) CN102797468B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103775096A (zh) * 2014-02-19 2014-05-07 粤水电轨道交通建设有限公司 一种软弱土层的盾构始发方法
CN105569661A (zh) * 2015-10-12 2016-05-11 上海勘测设计研究院有限公司 越江地下广场的布置结构和施工方法
CN107489427A (zh) * 2017-10-10 2017-12-19 南昌轨道交通集团有限公司地铁项目管理分公司 一种富水砂层盾构始发端头加固结构及其施工方法
CN108071400A (zh) * 2016-11-10 2018-05-25 上海宝冶集团有限公司 水平冷冻固结与钢套箱组合盾构进洞施工方法
CN109026055A (zh) * 2018-08-08 2018-12-18 北京建工土木工程有限公司 洞门环梁施工中的冻结壁围护结构及其施工方法
CN111734448A (zh) * 2020-06-22 2020-10-02 上海隧道工程有限公司 地下空间结构与盾构隧道间竖向通道加固的结构及方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1355039A1 (de) * 2002-04-20 2003-10-22 Hochtief Aktiengesellschaft Verfahren zur Erstellung eines langgestreckten Freiraumes zwischen zwei Tunnelröhren
CN1807839A (zh) * 2005-12-27 2006-07-26 上海市隧道工程轨道交通设计研究院 盾构隧道的进洞防水方法
CN101353965A (zh) * 2008-09-05 2009-01-28 上海隧道工程股份有限公司 盾构进洞接收装置及其进洞施工方法
CN101566063A (zh) * 2009-06-04 2009-10-28 上海交通大学 盾构进出洞口土体加固的方法
CN102352753A (zh) * 2011-06-29 2012-02-15 中铁第四勘察设计院集团有限公司 冻结加固+堆土灌水的盾构到达接收方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1355039A1 (de) * 2002-04-20 2003-10-22 Hochtief Aktiengesellschaft Verfahren zur Erstellung eines langgestreckten Freiraumes zwischen zwei Tunnelröhren
CN1807839A (zh) * 2005-12-27 2006-07-26 上海市隧道工程轨道交通设计研究院 盾构隧道的进洞防水方法
CN101353965A (zh) * 2008-09-05 2009-01-28 上海隧道工程股份有限公司 盾构进洞接收装置及其进洞施工方法
CN101566063A (zh) * 2009-06-04 2009-10-28 上海交通大学 盾构进出洞口土体加固的方法
CN102352753A (zh) * 2011-06-29 2012-02-15 中铁第四勘察设计院集团有限公司 冻结加固+堆土灌水的盾构到达接收方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103775096A (zh) * 2014-02-19 2014-05-07 粤水电轨道交通建设有限公司 一种软弱土层的盾构始发方法
CN103775096B (zh) * 2014-02-19 2016-09-07 粤水电轨道交通建设有限公司 一种软弱土层的盾构始发方法
CN105569661A (zh) * 2015-10-12 2016-05-11 上海勘测设计研究院有限公司 越江地下广场的布置结构和施工方法
CN108071400A (zh) * 2016-11-10 2018-05-25 上海宝冶集团有限公司 水平冷冻固结与钢套箱组合盾构进洞施工方法
CN107489427A (zh) * 2017-10-10 2017-12-19 南昌轨道交通集团有限公司地铁项目管理分公司 一种富水砂层盾构始发端头加固结构及其施工方法
CN109026055A (zh) * 2018-08-08 2018-12-18 北京建工土木工程有限公司 洞门环梁施工中的冻结壁围护结构及其施工方法
CN109026055B (zh) * 2018-08-08 2023-12-22 北京建工土木工程有限公司 洞门环梁施工中的冻结壁围护结构及其施工方法
CN111734448A (zh) * 2020-06-22 2020-10-02 上海隧道工程有限公司 地下空间结构与盾构隧道间竖向通道加固的结构及方法

Also Published As

Publication number Publication date
CN102797468B (zh) 2015-04-22

Similar Documents

Publication Publication Date Title
CN102797468B (zh) 盾构隧道浅覆土始发方法
CN102352753B (zh) 采用冻结加固和堆土灌水的盾构到达接收方法
CN102493822B (zh) 一种通过富水断层影响带的隧道的帷幕注浆施工方法
CN103195455B (zh) 软弱地质环境大断面隧道施工支护体系及施工方法
CN103306713B (zh) 一种高突煤层穿层钻孔网络化加固方法
CN105257310A (zh) 一种掘进面超前保护式盾构
CN106761788A (zh) 一种复合地层盾构掘进施工方法
CN106401645A (zh) 一种基于钻孔卸压的深部高应力巷道卸压支护协调控制方法
CN107355226A (zh) Tbm施工隧洞断层破碎带洞段处理结构
CN103114599A (zh) 深基坑封闭降水装置及其施工方法
CN108797620A (zh) 一种opt咬合桩施工方法
CN203256729U (zh) 一种沉井施工的拉森钢板桩围护装置
CN103939105A (zh) 一种于地下工程上方布设施工竖井的施工方法和结构
CN110985012A (zh) 一种适用于软硬不均地层的盾构掘进模式及其转换方法
CN203925513U (zh) 边仰坡陡峻地段的隧道洞口衬砌结构
JP2012036624A (ja) トンネル構築方法
CN103291312A (zh) 能够实现三维注浆的盾构机
CN103806916A (zh) 一种盾构快速检修井的施工工艺
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines
CN204703907U (zh) 一种新型盾构机
CN203835401U (zh) 一种于地下工程上方布设施工竖井的施工结构
CN204140092U (zh) 一种有效加固围岩及封堵地下涌水的斜井深孔注浆结构
CN105926589B (zh) 适应于珊瑚礁地质的钢管桩及其注浆方法
CN106437758A (zh) 上下一体式盾构隧道管片衬砌结构
JP2009174179A (ja) シールド掘削機受口の構築方法およびシールド掘削機の到達方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant