CN102787607B - A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area - Google Patents

A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area Download PDF

Info

Publication number
CN102787607B
CN102787607B CN201210309944.8A CN201210309944A CN102787607B CN 102787607 B CN102787607 B CN 102787607B CN 201210309944 A CN201210309944 A CN 201210309944A CN 102787607 B CN102787607 B CN 102787607B
Authority
CN
China
Prior art keywords
water
steel plate
coastal area
foundation ditch
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210309944.8A
Other languages
Chinese (zh)
Other versions
CN102787607A (en
Inventor
郑培壮
韩莹
杨向东
程龙
纪俊宁
左大虎
韩超
侯坤平
仲娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAYUAN JIANYE GROUP Co Ltd
Original Assignee
DAYUAN JIANYE GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAYUAN JIANYE GROUP Co Ltd filed Critical DAYUAN JIANYE GROUP Co Ltd
Priority to CN201210309944.8A priority Critical patent/CN102787607B/en
Publication of CN102787607A publication Critical patent/CN102787607A/en
Application granted granted Critical
Publication of CN102787607B publication Critical patent/CN102787607B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area, comprise the steps: to scrape out foundation ditch by predetermined space shape, and form support pile and water-stop curtain in this foundation ditch periphery;Steel plate water-stopping stake is set at described foundation ditch inwall, light well point is set between described steel plate water-stopping stake and support pile.Of the present invention be applicable to the deep foundation pit precipitation construction method for supporting of coastal area, according to the distribution situation that coastal area drifting sand layer and water barrier are staggered, Application of light well point precipitation and steel plate water-stopping stake are set targetedly so that the dewatering effect of deep basal pit is ensured;Further, the setting of steel plate water-stopping stake can block subsoil water and walk around the passage of water-stop curtain, and is prevented from piping and quicksand, it is ensured that the construction quality of the deep basal pit of coastal area.

Description

A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area
Technical field
The present invention relates to a kind of deep foundation pit precipitation construction method for supporting, particularly relate to one and be applicable to littoral The deep foundation pit precipitation construction method for supporting in district.
Background technology
Along with expanding economy, each industrial and mining establishment constantly carry out economic expansion to coastal area, each enterprise Resettlement, reconstruction etc. are made that indelible contribution to coastal economy circle.
In the resettlement, process of reconstruction of enterprise, coastal area is different from hinterland soil property gives construction band Carry out no small difficulty.Owing to the underground mean water of coastal area is high, hydraulic pressure is big, subsoil water is the richest Richness, and there is complex drifting sand layer and situation that water barrier is interspersed, therefore, the deep base i.e. having Hole de-watering and shoring construction method is not particularly suited for these areas.
Summary of the invention
The present invention is directed to the drawback of prior art, it is provided that a kind of deep foundation pit precipitation being applicable to coastal area props up Protect construction method.
The deep foundation pit precipitation construction method for supporting being applicable to coastal area of the present invention, including walking as follows Rapid:
Step one, scrapes out foundation ditch by predetermined space shape, and forms support pile and sealing in this foundation ditch periphery Curtain;
Step 2, arranges steel plate water-stopping stake at described foundation ditch inwall, in described steel plate water-stopping stake and supporting Light well point is set between Zhuan.
Of the present invention be applicable to the deep foundation pit precipitation construction method for supporting of coastal area, described step Farther include after two,
Step 3, the increase excavation pit hole end degree of depth is to preliminary dimension, and uses rubble to be backfilled to design mark High and form metalling;Filter well is set in described metalling.
Of the present invention be applicable to the deep foundation pit precipitation construction method for supporting of coastal area, wrap further Include following steps: form bank protection at described foundation ditch top.
It is of the present invention be applicable to the step one of the deep foundation pit precipitation construction method for supporting of coastal area, Described support pile is double bored concrete pile;Wherein, a diameter of 700 millimeters of first row bored concrete pile, spacing is 1.1 Rice;A diameter of 1 meter of second row bored concrete pile, spacing is 1.5 meters.Further, in described first irrigation and drainage Note stake arranges armored concrete straining beam, to form gate rigid frame with second row bored concrete pile top.
It is of the present invention be applicable to the step one of the deep foundation pit precipitation construction method for supporting of coastal area, The occlusion of double cement earth pile is used to form described water-stop curtain.
It is of the present invention be applicable to the step 2 of the deep foundation pit precipitation construction method for supporting of coastal area, Carry out outside described steel plate water-stopping stake unloading to prevent steel plate water-stopping stake from toppling.
It is of the present invention be applicable to the step 3 of the deep foundation pit precipitation construction method for supporting of coastal area, Described filter well is bright row's precipitation.
Of the present invention be applicable to the deep foundation pit precipitation construction method for supporting of coastal area, according to coastal The distribution situation that area drifting sand layer and water barrier interlock, arranges Application of light well point precipitation targetedly and steel plate stops Water stake so that the dewatering effect of deep basal pit is ensured;Further, the setting of steel plate water-stopping stake can block Subsoil water walks around the passage of water-stop curtain, and is prevented from piping and quicksand, it is ensured that coastal area deep The construction quality of foundation ditch.
Accompanying drawing explanation
Fig. 1 is that the flow process of the deep foundation pit precipitation construction method for supporting being applicable to coastal area of the present invention is shown It is intended to.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art's reference Description word can be implemented according to this.
As it is shown in figure 1, the deep foundation pit precipitation construction method for supporting being applicable to coastal area of the present invention, Comprise the steps:
Step 101, scrapes out foundation ditch by predetermined space shape, and forms support pile in this foundation ditch periphery and stop Water curtain.
In this step, scrape out the foundation ditch of predetermined space shape according to actual demand and the construction standards of demanding party, And support pile and water-stop curtain are set in this foundation ditch periphery.
The support pile that described foundation ditch periphery is arranged can be double bored concrete pile, and its construction technology is according to national standard And carry out.The concrete size of this double bored concrete pile can adjust according to practice of construction demand, but should ensure that buried depth The degree of depth, to guarantee having enough antidumping intensity, such as, makes a diameter of 700 millis of first row bored concrete pile Rice, spacing is 1.1 meters;A diameter of 1 meter of second row bored concrete pile, spacing is 1.5 meters.Further, exist Described first row bored concrete pile and second row bored concrete pile top arrange armored concrete straining beam, firm to form gate Frame, to strengthen the supporting intensity of support pile.
Described water-stop curtain can use the occlusion of double cement earth pile to be formed, in view of the construction of this water-stop curtain Technique has been maturation process, does not sew at this and chats.In practice of construction, deep-layer stirring mode can be used to increase The intensity of strong water-stop curtain.
Step 102, arranges steel plate water-stopping stake at described foundation ditch inwall, described steel plate water-stopping stake with Light well point is set between fender pile.
Owing to coastal area geology water content is in saturation, and owing to the distribution of water barrier makes soil layer Water penetration extreme difference, according to conventional tube well dewatering, effect is the most undesirable.Although, have aforesaid stopping Water curtain realizes the purpose blocked water, but, in view of the subsoil water of coastal area is extremely abundant, hydraulic pressure is high, Therefore, subsoil water is entirely possible walks around water-stop curtain and penetrates into foundation ditch from the bottom of foundation ditch;Simultaneously for For deep basal pit, the most easily there is piping and quicksand phenomenon.
To this end, in this step, be provided with the steel plate water-stopping with block-water effect at the inwall of described foundation ditch Stake, makes this steel plate water-stopping stake block subsoil water and walks around the passage of water-stop curtain.The stake of described steel plate water-stopping stake Long and stake top with and distance can adjust according to actual geological conditions.Inner side in this steel plate water-stopping stake Carry out the vertical cut earthwork, meanwhile, in order to prevent steel plate water-stopping stake from toppling, preferably outside steel plate water-stopping stake Side carries out the unloading of necessity.
For the special geologic condition of above-mentioned coastal area, in this step, additionally use light-duty node precipitation Mode, the conventional tube well dewatering mode in inland will be improved to light-duty node dewatering mode.This light-duty node Precipitation is to have pressure drop water, i.e. forces precipitation by pressure, is very suitable for the geological conditions of coastal area. Described well depth and floral tube can adjust according to on-site actual situations, but should ensure that floral tube is under water barrier. Need to process through sand prevention simultaneously at floral tube, with the upper husky amount reduced in Precipitation Process in well, make fall Well carries out precipitation directly through water barrier.
Further, if still having subsoil water inside the foundation ditch of excavation, then following step can be passed through further 103 and carry out precipitation.
Step 103, the increase excavation pit hole end degree of depth is to preliminary dimension, and uses rubble to be backfilled to design Absolute altitude and form metalling;Filter well is set in described metalling.
In this step, cutting depth at the bottom of the hole of foundation ditch is increased, and use rubble to backfill, be beneficial to Filter well is set and carries out bright row's precipitation.Such as, cutting depth at the bottom of the hole of foundation ditch is increased by 500 millimeters, then makes It is backfilled to designed elevation with rubble and forms metalling, this metalling arranges filter well at predetermined intervals Carry out bright row's precipitation, so that it is guaranteed that the dewatering effect of deep basal pit.
Further, bank protection can also be formed at the top of foundation ditch according to national standard.
Of the present invention be applicable to the deep foundation pit precipitation construction method for supporting of coastal area, according to coastal The distribution situation that area drifting sand layer and water barrier interlock, arranges Application of light well point precipitation targetedly and steel plate stops Water stake so that the dewatering effect of deep basal pit is ensured;Further, the setting of steel plate water-stopping stake can block Subsoil water walks around the passage of water-stop curtain, and is prevented from piping and quicksand, it is ensured that coastal area deep The construction quality of foundation ditch.
Although embodiment of the present invention are disclosed as above, but it is not restricted to description and embodiment party Listed utilization in formula, it can be applied to various applicable the field of the invention completely, for being familiar with ability For the personnel in territory, be easily achieved other amendment, therefore without departing substantially from claim and etc. homotype Enclosing under limited general concept, the present invention is not limited to specific details and shown here as the figure with description Example.

Claims (1)

1. the deep foundation pit precipitation construction method for supporting being applicable to coastal area, it is characterised in that step Including:
Step one, scrapes out foundation ditch by predetermined space shape, and forms support pile and sealing in this foundation ditch periphery Curtain;Described support pile is double bored concrete pile;Wherein, a diameter of 700 millimeters of first row bored concrete pile, Away from for 1.1 meters;A diameter of 1 meter of second row bored concrete pile, spacing is 1.5 meters;Double cement earth pile is used to sting Close and form described water-stop curtain;At described first row bored concrete pile and second row bored concrete pile top, reinforcing bar is set Concrete straining beam, to form gate rigid frame;
Step 2, arranges steel plate water-stopping stake at described foundation ditch inwall, in described steel plate water-stopping stake and supporting Light well point is set between Zhuan;Carry out outside described steel plate water-stopping stake unloading to prevent steel plate water-stopping stake from toppling;
Step 3, the increase excavation pit hole end degree of depth is to preliminary dimension, and uses rubble to be backfilled to design mark High and form metalling;Arranging filter well in described metalling, described filter well is bright row's precipitation;
Bank protection is formed at described foundation ditch top.
CN201210309944.8A 2012-08-28 2012-08-28 A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area Active CN102787607B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210309944.8A CN102787607B (en) 2012-08-28 2012-08-28 A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210309944.8A CN102787607B (en) 2012-08-28 2012-08-28 A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area

Publications (2)

Publication Number Publication Date
CN102787607A CN102787607A (en) 2012-11-21
CN102787607B true CN102787607B (en) 2016-09-14

Family

ID=47153181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210309944.8A Active CN102787607B (en) 2012-08-28 2012-08-28 A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area

Country Status (1)

Country Link
CN (1) CN102787607B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120828A (en) * 2016-06-23 2016-11-16 程华清 A kind of Sandwich biscuit type curtain water stop construction method of diaphragm wall

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114599B (en) * 2013-03-04 2016-05-18 济南城建集团有限公司 Deep basal pit sealing dewatering device and construction method thereof
CN103726495B (en) * 2014-01-10 2016-01-13 上海建工五建集团有限公司 Coastal waters deep foundation pit supporting structure and construction method thereof
CN104294806B (en) * 2014-09-18 2017-01-11 中铁十二局集团有限公司 Excavation, diversion and drainage method for inter-pile water above water-resisting layer of deep foundation pit
CN104975607A (en) * 2015-07-22 2015-10-14 中建八局第二建设有限公司 Offshore area local deep foundation pit stanching pit construction method
CN106284387B (en) * 2016-08-11 2018-12-18 中国建筑第八工程局有限公司 Steel sheet pile precipitation well construction
CN112030935A (en) * 2020-08-31 2020-12-04 广东劲拓建设工程有限公司 Method for treating piping of deep foundation pit
CN113356229A (en) * 2021-06-21 2021-09-07 中铁十二局集团有限公司 Safe and efficient comprehensive construction method for garage under high-speed railway base

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2190725C1 (en) * 2001-11-20 2002-10-10 Общество с ограниченной ответственностью "Трансстройтоннель-99" Method for construction of foundation pit
CN1296571C (en) * 2004-04-09 2007-01-24 南京大学 Method for supporting foundation trench for agitation piles of soil cement with concrete as the core
CN102011404B (en) * 2010-11-24 2012-07-04 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN102140798A (en) * 2011-01-28 2011-08-03 东南大学 Steel sheet pile and tubular pile combined base pit supporting structure and supporting method therefor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120828A (en) * 2016-06-23 2016-11-16 程华清 A kind of Sandwich biscuit type curtain water stop construction method of diaphragm wall

Also Published As

Publication number Publication date
CN102787607A (en) 2012-11-21

Similar Documents

Publication Publication Date Title
CN102787607B (en) A kind of deep foundation pit precipitation construction method for supporting being applicable to coastal area
CN105863671A (en) Frame type low-position draining system tunnel lining structure
CN104947686B (en) Soft clay area basement supporting construction
CN102296572B (en) Earth and rockfill dam body seepage monitoring structure provided with abandoned dreg site behind dam and construction method thereof
CN106437748A (en) Separated maintainable tunnel lining structure
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN108979659A (en) The ruggedized construction and method of structures are worn under weak soil rich water large cross-section tunnel group
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN109339079B (en) Foundation pit water stopping system adjacent to river permeable stratum and construction process thereof
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN203684245U (en) Waterproof curtain with floral tubes
CN203939036U (en) A kind of steel sheet pile cofferdam structure that is applicable to river course
CN106120822B (en) A kind of method for protecting support and device that prevent mud stone from coming down
CN105569062A (en) Dewatering method implemented through permeation, weakening and emission reduction
CN106149736B (en) The stable construction method of hillside fields bury excavation slope is kept based on draining is cut
CN216275788U (en) Drainage device used after failure of water interception curtain of deep foundation pit
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method
CN105064373A (en) Foundation pit supporting structure for bridge main pier bearing platform on riverway abrupt slope bed rock and construction method of foundation pit supporting structure
CN204435321U (en) A kind of steam power station water intaking open channel
CN204899930U (en) Secretly dig leading dry out well in subway hole
CN111287205A (en) Deep multi-stage dynamic foundation pit dewatering system and dewatering method thereof
CN112609672A (en) Prevention and treatment remediation method for directional drilling pipeline to penetrate through soft dike foundation
CN110284511A (en) The cofferdam open cutting construction method of the more storehouse rollers of overlength lake Tunnel
CN212026297U (en) Deep multistage dynamic foundation pit dewatering system
CN206034456U (en) Soft clay foundation pit slope stable control construction structures in hillside fields

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant