CN102758049A - 特大型转炉高跨施工方法 - Google Patents

特大型转炉高跨施工方法 Download PDF

Info

Publication number
CN102758049A
CN102758049A CN2012102749877A CN201210274987A CN102758049A CN 102758049 A CN102758049 A CN 102758049A CN 2012102749877 A CN2012102749877 A CN 2012102749877A CN 201210274987 A CN201210274987 A CN 201210274987A CN 102758049 A CN102758049 A CN 102758049A
Authority
CN
China
Prior art keywords
tower
converter
dbq3000
tower crane
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102749877A
Other languages
English (en)
Inventor
林钧彪
刘顺宝
王国志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
China 22MCC Group Corp Ltd
Original Assignee
1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP, China 22MCC Group Corp Ltd filed Critical 1 ST CONSTRUCTION CO Ltd OF 22 MCC GROUP
Priority to CN2012102749877A priority Critical patent/CN102758049A/zh
Publication of CN102758049A publication Critical patent/CN102758049A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

本发明涉及转炉高跨的施工方法,特别是特大型转炉高跨的施工方法。 选用一台 DBQ3000 塔吊和两台 C7022 塔吊作为吊装主机进行作业,按如下步骤进行:进行塔吊的布置: DBQ3000 塔吊置于精炼跨,为轨道移动式, 两台 C7022 塔吊置于加料跨靠近转炉高跨一侧的两端并向转炉高跨中心靠拢,为固定式; 加料跨其中一台天车安排在两台C7022塔吊之间进行组装、安装以及转炉炉壳施工时的运行;使用DBQ3000塔吊拆除两台C7022塔吊。本发明具有如下优点:施工机械费大为降低,比传统的大型履带吊施工节约30%以上;施工速度大幅提高,C7022塔吊司机处于高处,有利与地面指挥人员的配合。

Description

特大型转炉高跨施工方法
技术领域:
本发明涉及转炉高跨的施工方法,特别是特大型转炉高跨的施工方法。
背景技术:
大型炼钢高跨的施工工程量占到整个炼钢区的50%以上,所以炼钢高跨的施工进度决定着整个炼钢厂房施工的总进度。传统的施工方法使用大型履带吊配合大型塔吊施工,虽然能够解决所有的施工要求,但是大型吊装机具的运转及起升速度均缓慢,施工效率比较低,无法充分发挥机械的施工效能。且施工机械费用高,导致整个炼钢区的施工进度慢,施工费用高。
发明内容:
本发明的目的在于提供一种充分发挥吊车的施工效能、降低施工机械费用、加快施工进度的特大型转炉高跨施工方法。
本发明采用如下技术方案:
一种特大型转炉高跨施工方法,选用一台DBQ3000塔吊和两台C7022塔吊作为吊装主机进行作业,按如下步骤进行:
    首先,进行塔吊的布置:
DBQ3000塔吊置于精炼跨,为轨道移动式,沿转炉高跨范围移动施工;DBQ3000在精炼跨能够回转210度;覆盖整个转炉高跨以及精炼跨钢柱的施工;
两台C7022塔吊置于加料跨靠近转炉高跨一侧的两端并向转炉高跨中心靠拢,为固定式;确保两台C7022塔吊覆盖95%以上的转炉高跨作业区域;其余未覆盖区域部分由DBQ3000塔吊负责作业;
第二,C7022塔吊与加料跨厂房天车的施工部署:
加料跨其中一台天车安排在两台C7022塔吊之间进行组装、安装以及转炉炉壳施工时的运行;
第三,使用DBQ3000塔吊拆除C7022塔吊:
使用DBQ3000塔吊拆除两台C7022塔吊,将C7022塔吊的使用时间延长到完成转炉高跨及加料跨所有结构的安装。
采用上述技术方案的本发明与现有技术相比,具有如下优点:施工机械费大为降低,比传统的大型履带吊施工节约30%以上;施工速度大幅提高,比传统施工方法的施工进度提高20%以上;各专业同步进行,互不影响,创造了良好的施工环境;C7022塔吊司机处于高处,视线好,有利与地面指挥人员的配合,安全性好。
本发明的优选方案是:两台C7022塔吊在定位线的直线距离是5.94米,距离炉子跨的直线距离是1.3米。
塔吊采用主臂加副臂的工况;两台C7022塔吊为主臂工况。
塔吊主臂66.23m,副臂42 m;两台C7022塔吊采用40m副臂工况。
附图说明:
图1是塔吊布置的俯视图。
图2是塔吊布置的侧视图。
图3是塔吊作业区的俯视图。
图4是加料跨天车作业示意图。
具体实施方式:
下面结合附图及实施例详述本发明:
一种特大型转炉高跨施工方法,参见附图1附图4的布置结构,图中:第一台C7022塔吊1,第二台C7022塔吊2,DBQ3000塔吊3。
选用一台DBQ3000塔吊3和两台C7022塔吊作为吊装主机进行作业,两台C7022塔吊分别是第一台C7022塔吊1和第二台C7022塔吊2。
首先,进行塔吊的布置:DBQ3000塔吊3置于精炼跨,为轨道移动式,沿转炉高跨范围移动施工;DBQ3000在精炼跨能够回转210度;覆盖整个转炉高跨以及精炼跨钢柱的施工;
第一台C7022塔吊1和第二台C7022塔吊2置于加料跨靠近转炉高跨一侧的两端并向转炉高跨中心靠拢,为固定式;确保两台C7022塔吊覆盖95%以上的转炉高跨作业区域;其余未覆盖区域部分由DBQ3000塔吊负责作业。
第二,C7022塔吊与加料跨厂房天车的施工部署:
加料跨其中一台天车安排在两台C7022塔吊之间进行组装、安装以及转炉炉壳施工时的运行;很好的解决了C7022塔吊的使用与转炉炉壳施工的矛盾,使这两个专业间的施工互不干涉,如图4所示,加料跨天车只能在加料跨两台C7022塔吊之间运行及作业。
第三:使用DBQ3000塔吊拆除C7022塔吊:使用DBQ3000塔吊3拆除两台C7022塔吊,将C7022塔吊的使用时间延长到完成转炉高跨及加料跨所有结构的安装;很好的解决了转炉高跨屋面、氧枪平台安装完成后C7022塔吊的拆除问题,最大程度的缩短转炉高跨的施工时间。且使用DBQ3000塔吊拆除一台C7022塔吊只需要一天时间即可完成,大大降低了C7022塔吊的拆除时间。完成这个设计的前提需要确保DBQ3000塔吊在安装完转炉高跨屋面系统后不会因为卡杆而无法拆除C7022塔吊。
本实施的方法通过结合结构、设备、工艺各专业施工流程反复研究,以及在几个炼钢工程实际实施的效果总结,具有如下技术优势:施工机械费大为降低,比传统的大型履带吊施工节约30%以上;施工速度大幅提高,比传统施工方法的施工进度提高20%以上;各专业同步进行,互不影响,创造了良好的施工环境;C7022塔吊司机处于高处,视线好,有利与地面指挥人员的配合,安全性好。

Claims (4)

1.一种特大型转炉高跨施工方法,选用一台DBQ3000塔吊和两台C7022塔吊作为吊装主机进行作业,按如下步骤进行:
    首先,进行塔吊的布置:
DBQ3000塔吊置于精炼跨,为轨道移动式,沿转炉高跨范围移动施工;DBQ3000在精炼跨能够回转210度;覆盖整个转炉高跨以及精炼跨钢柱的施工;
两台C7022塔吊置于加料跨靠近转炉高跨一侧的两端并向转炉高跨中心靠拢,为固定式;确保两台C7022塔吊覆盖95%以上的转炉高跨作业区域;其余未覆盖区域部分由DBQ3000塔吊负责作业;
第二,C7022塔吊与加料跨厂房天车的施工部署:
加料跨其中一台天车安排在两台C7022塔吊之间进行组装、安装以及转炉炉壳施工时的运行; 
第三,使用DBQ3000塔吊拆除C7022塔吊:
使用DBQ3000塔吊拆除两台C7022塔吊,将C7022塔吊的使用时间延长到完成转炉高跨及加料跨所有结构的安装。
2.根据权利要求1所述的特大型转炉高跨施工方法,其特征在于:所述两台C7022塔吊在定位线的直线距离是5.94米,距离炉子跨的直线距离是1.3米。
3.根据权利要求1所述的特大型转炉高跨施工方法,其特征在于:DBQ3000塔吊采用主臂加副臂的工况;两台C7022塔吊为主臂工况。
4.根据权利要求3所述的特大型转炉高跨施工方法,其特征在于:所述DBQ3000塔吊主臂66.23m,副臂42 m;两台C7022塔吊采用40m副臂工况。
CN2012102749877A 2012-08-04 2012-08-04 特大型转炉高跨施工方法 Pending CN102758049A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102749877A CN102758049A (zh) 2012-08-04 2012-08-04 特大型转炉高跨施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102749877A CN102758049A (zh) 2012-08-04 2012-08-04 特大型转炉高跨施工方法

Publications (1)

Publication Number Publication Date
CN102758049A true CN102758049A (zh) 2012-10-31

Family

ID=47052698

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102749877A Pending CN102758049A (zh) 2012-08-04 2012-08-04 特大型转炉高跨施工方法

Country Status (1)

Country Link
CN (1) CN102758049A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113463953A (zh) * 2020-03-31 2021-10-01 上海宝冶集团有限公司 炼钢厂高层框架结构与大型设备同步进行的施工方法
CN114807494A (zh) * 2022-04-28 2022-07-29 重庆钢铁股份有限公司 一种不停产更换炼钢厂接受跨、精炼跨吊车梁的方法
CN115044728A (zh) * 2022-06-02 2022-09-13 鞍钢集团工程技术有限公司 一种未预留工位的炼钢厂房不停产新建转炉工位的方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000226187A (ja) * 1999-02-04 2000-08-15 Kumagai Gumi Co Ltd タワークレーンの設置方法
CN101899904A (zh) * 2010-07-23 2010-12-01 中冶建工有限公司 转炉塔楼钢结构双向吊装施工方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000226187A (ja) * 1999-02-04 2000-08-15 Kumagai Gumi Co Ltd タワークレーンの設置方法
CN101899904A (zh) * 2010-07-23 2010-12-01 中冶建工有限公司 转炉塔楼钢结构双向吊装施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
万卫良等: "多塔作业在大型炼钢工程中的应用", 《2010全国钢结构学术年会》 *
李建彬等: "某炼钢厂40t转炉炉体施工吊装技术", 《山西建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113463953A (zh) * 2020-03-31 2021-10-01 上海宝冶集团有限公司 炼钢厂高层框架结构与大型设备同步进行的施工方法
CN114807494A (zh) * 2022-04-28 2022-07-29 重庆钢铁股份有限公司 一种不停产更换炼钢厂接受跨、精炼跨吊车梁的方法
CN114807494B (zh) * 2022-04-28 2024-01-23 重庆钢铁股份有限公司 一种不停产更换炼钢厂接受跨、精炼跨吊车梁的方法
CN115044728A (zh) * 2022-06-02 2022-09-13 鞍钢集团工程技术有限公司 一种未预留工位的炼钢厂房不停产新建转炉工位的方法

Similar Documents

Publication Publication Date Title
CN101899904B (zh) 转炉塔楼钢结构双向吊装施工方法
CN102758049A (zh) 特大型转炉高跨施工方法
CN100480398C (zh) 高炉大修拆装炉自吊装施工方法及炉顶起重装置
CN110836028B (zh) 一种双高跨炼钢塔楼安装方法
CN202465067U (zh) 一种带行程开关的起重机大车行走机构
CN202441047U (zh) 一种曲面上的吊篮导向装置
CN202324567U (zh) 一种移动式大型操作平台
CN202644495U (zh) 复杂结构多孔竖井滑模施工装置
CN103350971A (zh) 在隧道内进行安装拆卸施工台车的装置
CN203682930U (zh) 玻璃窑炉钢结构安装用吊装装置
CN205477625U (zh) 一种附壁环轨式挖掘机
CN102817611A (zh) 悬挂式掘进迎头除尘装置
CN202465121U (zh) 起重机悬吊臂
CN202245861U (zh) 可整体提升超高、大跨度、重型钢通廊的装置
CN203359892U (zh) 在隧道内进行安装拆卸施工台车的装置
CN202465100U (zh) 一种带双v型支腿的单梁龙门起重机
CN210313200U (zh) 一种竖井压力钢管安装用起吊系统
CN102330497A (zh) 建筑桁车
CN202449760U (zh) 一种轨道式集装箱门式起重机
CN202465117U (zh) 一种起重机悬吊臂
CN105441634A (zh) 脱硫倾翻油顶的防护装置及防护方法
CN106315413B (zh) 一种龙门桁架机器人的控制系统及其控制方法
CN205223287U (zh) 脱硫倾翻油顶的防护装置
CN202465101U (zh) 一种带临时小车的桥式起重机
CN202465057U (zh) 一种单梁龙门起重机支腿

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121031