CN102733386A - 采用预应力锚固控制坝基岩体开挖松弛的施工方法 - Google Patents

采用预应力锚固控制坝基岩体开挖松弛的施工方法 Download PDF

Info

Publication number
CN102733386A
CN102733386A CN2012102500402A CN201210250040A CN102733386A CN 102733386 A CN102733386 A CN 102733386A CN 2012102500402 A CN2012102500402 A CN 2012102500402A CN 201210250040 A CN201210250040 A CN 201210250040A CN 102733386 A CN102733386 A CN 102733386A
Authority
CN
China
Prior art keywords
excavation
rock mass
construction method
foundation
dam foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102500402A
Other languages
English (en)
Other versions
CN102733386B (zh
Inventor
赖道平
徐建荣
何明杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN201210250040.2A priority Critical patent/CN102733386B/zh
Publication of CN102733386A publication Critical patent/CN102733386A/zh
Application granted granted Critical
Publication of CN102733386B publication Critical patent/CN102733386B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种采用预应力锚固控制坝基岩体开挖松弛的施工方法。本发明的目的是提供一种采用预应力锚固控制坝基岩体开挖松弛的施工方法,旨在降低开挖解除应力卸荷松弛对建基岩体质量的影响,提高大坝安全度该方法实施方便,施工成本低。本发明的技术方案是:采用预应力锚固控制坝基岩体开挖松弛的施工方法,其特征在于包括以下步骤:a.进行大坝基础开挖施工,建基面以上预留保护层;b.在保护层顶面钻设锚杆孔,孔内置入可拆卸的预应力锚杆,并对其施加预应力;c.在保护层以下锚杆孔内注入锚固砂浆;d.锚固砂浆待强后,拆除保护层内的连接杆;e.最后进行保护层的开挖。本发明适用于水利水电工程中岩体易松弛的基础开挖施工。

Description

采用预应力锚固控制坝基岩体开挖松弛的施工方法
技术领域
本发明涉及一种采用预应力锚固控制坝基岩体开挖松弛的施工方法。适用于水利水电工程中岩体易松弛的基础开挖施工。
背景技术
随着国民经济的发展,需在我国西部大量修建水利水电工程,这些工程建设中常遇到复杂的地质条件,如高地应力、岩体中原生节理裂隙发育。高地应力区未扰动岩体及有围压条件下原生节理发育岩体的物理力学特性往往能满足作为大坝建基面的要求,但开挖引起的解除围压应力卸荷及爆破振动,易导致岩体产生松弛变形,甚至形成水平向卸荷裂缝,从而使影响范围内岩体的抗剪强度、变形模量等力学指标降低,使岩体的透水率增大,严重影响大坝基础岩体质量,降低大坝的安全度。
如何在基础开挖中采取一定措施,最大程度的控制坝基岩体松弛变形,改善建基岩体条件,提高大坝的安全度,是大坝工程设计及施工中的一项关键技术。   
发明内容
本发明要解决的技术问题是:针对上述存在的问题,提供一种采用预应力锚固控制坝基岩体开挖松弛的施工方法,旨在降低开挖解除应力卸荷松弛对建基岩体质量的影响,提高大坝安全度,并且该方法实施方便,施工成本低。  
本发明所采用的技术方案是:采用预应力锚固控制坝基岩体开挖松弛的施工方法,其特征在于包括以下步骤:
a、进行大坝基础开挖施工,在邻近建基面设计高程以上预留保护层;
b、在保护层顶面钻设锚杆孔,该锚杆孔深入建基面以下,孔内置入可拆卸的预应力锚杆,并对其施加预应力;
c、在保护层以下锚杆孔内注入锚固砂浆;
d、待锚固砂浆达到一定强度后,拆除预应力锚杆位于保护层内的连接杆;
e、最后进行保护层的开挖,完成建基面开挖。
所述保护层厚度为2~4m。 
本发明的有益效果是:本发明的施工方法在大坝建基面开挖之前,预留保护层进行预应力锚固,对建基岩体产生预压力,降低开挖解除应力卸荷松弛对建基岩体质量的影响,提高大坝的安全度。该方法实施方便,施工成本低。
附图说明
图1是本发明实施过程的预应力锚固示意图。
图2是本发明实施过程的注浆示意图。
图3是本发明实施过程的拆除连接杆示意图。
图4是本发明实施过程的保护层开挖完成示意图。    
具体实施方式
如图1~图4所示,本实施例为一种采用预应力锚固控制坝基岩体开挖松弛的施工方法,降低开挖解除应力卸荷松弛对建基岩体质量的影响,提高大坝的安全度。本实施例的主要特点在于:在大坝建基面1开挖之前,先进行预应力锚固,对建基岩体8产生预应力。
本实施例的具体施工方法如下:
a、首先在大坝基础开挖施工过程中,邻近建基面1设计高程以上预留出厚度为2~4m的保护层2。
b、然后在保护层2顶面钻设锚杆孔3,锚杆孔3深入至建基面1以下,孔内置入可拆卸的预应力锚杆。本实施例中预应力锚杆采用涨壳式预应力锚杆4,它由涨壳锚固头4-4、锚杆体4-3、连接套4-2和连接杆4-1依次连接而成。具体操作时,首先将涨壳式预应力锚杆4置入锚杆孔3后,连接杆4-1顶端在保护层2顶面露出,连接套4-2顶面与建基面1齐平。然后在涨壳式预应力锚杆4的尾端位置通过冲击转动等手段,使涨壳锚固头4-4固定在锚杆孔3内。接着在连接套4-2顶面位置设置止浆塞4-5。锚杆孔3孔口位置安装带有连通管6的锚垫板5,连通管6穿过止浆塞4-5延伸至建基面1以下,最后对涨壳式预应力锚杆4施加预应力。
c、在保护层2以下锚杆孔3内注入锚固砂浆7。以涨壳式预应力锚杆4的空腔为注浆道,安装在锚垫板5上的连通管6作为排气通道,锚固砂浆7从涨壳式预应力锚杆4尾部进入空腔,并最终注入到锚杆孔3内。
d、待锚固砂浆7达到一定强度后(7天左右),拆除涨壳式预应力锚杆4位于保护层2内的连接杆4-1和止浆塞4-5。连接杆4-1、止浆塞4-5可重复利用,以减少工程投入,降低施工成本。
e、最后进行保护层2的开挖,完成建基面1开挖。
本实施例中涨壳式预应力锚杆4为市售产品,不是本实施例要点所在,故不作展开介绍。
如选用其他形式的预应力锚杆,上述施工方法步骤b中可按所选预应力锚杆的具体操作方法施加预应力,其余步骤与本例相同。 

Claims (2)

1.一种采用预应力锚固控制坝基岩体开挖松弛的施工方法,其特征在于包括以下步骤:
a、进行大坝基础开挖施工,在邻近建基面(1)设计高程以上预留保护层(2);
b、在保护层(2)顶面钻设锚杆孔(3),该锚杆孔深入建基面(1)以下,孔内置入可拆卸的预应力锚杆,并对其施加预应力;
c、在保护层(2)以下锚杆孔(3)内注入锚固砂浆(7);
d、待锚固砂浆(7)达到一定强度后,拆除预应力锚杆位于保护层(2)内的连接杆;
e、最后进行保护层(2)的开挖,完成建基面(1)开挖。
2.根据权利要求1所述的采用预应力锚固控制坝基岩体开挖松弛的施工方法,其特征在于:所述保护层(2)厚度为2~4m。
CN201210250040.2A 2012-07-19 2012-07-19 采用预应力锚固控制坝基岩体开挖松弛的施工方法 Active CN102733386B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210250040.2A CN102733386B (zh) 2012-07-19 2012-07-19 采用预应力锚固控制坝基岩体开挖松弛的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210250040.2A CN102733386B (zh) 2012-07-19 2012-07-19 采用预应力锚固控制坝基岩体开挖松弛的施工方法

Publications (2)

Publication Number Publication Date
CN102733386A true CN102733386A (zh) 2012-10-17
CN102733386B CN102733386B (zh) 2014-11-12

Family

ID=46989643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210250040.2A Active CN102733386B (zh) 2012-07-19 2012-07-19 采用预应力锚固控制坝基岩体开挖松弛的施工方法

Country Status (1)

Country Link
CN (1) CN102733386B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032749A (zh) * 2014-06-20 2014-09-10 中国水电顾问集团华东勘测设计研究院有限公司 一种高地应力、易松弛基础开挖支护方法
CN108517871A (zh) * 2018-03-15 2018-09-11 大连交通大学 一种控制基坑开挖诱发隧道上浮的结构及其施工方法
CN109780950A (zh) * 2019-02-18 2019-05-21 中国三峡建设管理有限公司 一种多层结构岩体坝基开挖松弛处理方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392443A (zh) * 2011-10-19 2012-03-28 山东科技大学 高边坡压力分散型预应力锚索施工工艺

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392443A (zh) * 2011-10-19 2012-03-28 山东科技大学 高边坡压力分散型预应力锚索施工工艺

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032749A (zh) * 2014-06-20 2014-09-10 中国水电顾问集团华东勘测设计研究院有限公司 一种高地应力、易松弛基础开挖支护方法
CN104032749B (zh) * 2014-06-20 2016-05-04 中国水电顾问集团华东勘测设计研究院有限公司 一种高地应力、易松弛基础开挖支护方法
CN108517871A (zh) * 2018-03-15 2018-09-11 大连交通大学 一种控制基坑开挖诱发隧道上浮的结构及其施工方法
CN109780950A (zh) * 2019-02-18 2019-05-21 中国三峡建设管理有限公司 一种多层结构岩体坝基开挖松弛处理方法
CN109780950B (zh) * 2019-02-18 2021-07-09 中国三峡建设管理有限公司 一种多层结构岩体坝基开挖松弛处理方法

Also Published As

Publication number Publication date
CN102733386B (zh) 2014-11-12

Similar Documents

Publication Publication Date Title
CN103527219B (zh) 用于大变形地层的隧道支护结构的施工工法
CN103352581B (zh) 采用内部预应力钢筋锚杆加固烧结粘土砖砌体结构的方法
CN105569049B (zh) 高承压水深基坑支护锚杆施工方法
CN104895072B (zh) 一种预应力锚索以及预应力锚索一次成型施工方法
CN203515604U (zh) 用于大变形地层的隧道支护结构
CN102966360A (zh) 小净距隧道中岩墙加固方法
CN103352582B (zh) 内部预应力钢筋锚杆加固混凝土空心砌块砌体结构的方法
CN203488189U (zh) 用于脱空整治的隧道结构
CN102304927B (zh) 适用于岩石地基上的预应力锚索扶壁式挡墙
CN104895073B (zh) 可多次拆装的锚索施工系统及其施工方法
CN107165661A (zh) 一种高地应力软弱围岩大变形隧道超长扩大头锚索施工方法
CN206319886U (zh) 隧洞衬砌结构
CN102808635B (zh) 一种胀壳式内锚头预应力锚杆及其安装使用方法
CN104863108B (zh) 一种地连墙侧向土压力盒埋设装置
CN102733386B (zh) 采用预应力锚固控制坝基岩体开挖松弛的施工方法
CN103911993B (zh) 一种pha锚杆及其施工方法
CN104264695B (zh) 一种破碎岩体的抗滑装置及其施工方法
CN202936792U (zh) 一种胀壳式内锚头预应力锚杆
CN111379581B (zh) 一种深部巷道预应力全锚支护施工设备及其施工方法
CN105201525B (zh) 一种可修复的防治底鼓方法
CN205954624U (zh) 土地基多索抗拔基础
CN102094658B (zh) 一种浅埋隧道内定向诱导劈裂注浆方法
CN106120817B (zh) 一种坡面建筑混凝土层防滑坡施工工艺
CN203835420U (zh) 一种一边注浆两边紧固的注浆锚索
CN204982874U (zh) 可多次拆装的锚索施工系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant