CN102720187A - 抗拔桩的施工方法 - Google Patents

抗拔桩的施工方法 Download PDF

Info

Publication number
CN102720187A
CN102720187A CN2012101440635A CN201210144063A CN102720187A CN 102720187 A CN102720187 A CN 102720187A CN 2012101440635 A CN2012101440635 A CN 2012101440635A CN 201210144063 A CN201210144063 A CN 201210144063A CN 102720187 A CN102720187 A CN 102720187A
Authority
CN
China
Prior art keywords
mentioned
outer tube
steel
hammer ram
uplift pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101440635A
Other languages
English (en)
Other versions
CN102720187B (zh
Inventor
王继忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD.
Original Assignee
王继忠
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王继忠 filed Critical 王继忠
Priority to CN201210144063.5A priority Critical patent/CN102720187B/zh
Publication of CN102720187A publication Critical patent/CN102720187A/zh
Application granted granted Critical
Publication of CN102720187B publication Critical patent/CN102720187B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明的目的在于提供一种抗拔桩的施工方法,通过该方法可快速简便的形成一种提供较高抗拔力的检测抗拔桩。施工方法包括下述步骤:1)将内壁设有中空钢管的外管外管沉至设计深度;2)在外管内放入内夯锤并击出外管;3)分次填入散体填充料,通过内夯锤进行挤扩;4)分次填入干硬性快硬混凝土,通过内夯锤进行挤扩;5)通过外管内的中空钢管分别插入钢筋;6)在外管内放入内管,内管内放入内夯锤并连接;7)填入干硬性快硬混凝土并通过锤击内管进行挤扩;8)反复进行填充和挤扩,使钢筋底端向外散开被包裹嵌固在干硬性快硬混凝土内;9)在外管内灌注散体材料;10)采用钢质连接盘分别将钢筋和检测设备的传力杆以螺栓固定;11)回收钢质连接圆盘和钢筋。

Description

抗拔桩的施工方法
技术领域
本发明涉及土木工程领域,特别是涉及桩的施工技术。
背景技术
在建筑物的桩基础中,当桩基施工完毕时,需要对桩基承载力进行静载荷试验检测。现今静载荷试验的常用方法是以堆载配重的方式提供荷载压力,这就需要很大质量如钢块、沙袋等配重,其运输费用很高,且堆载和卸载的过程时间很长,要完成一定数量的桩的试验检测是非常麻烦的。静载荷试验也有通过抗拔桩方式进行的,但目前常用的的抗拔桩,单桩提供的反力较小,不得不通过增加抗拔桩的数量的方式来弥补,费时费力,造价较高。
发明内容
本发明是为了解决上述的问题而提出的,目的在于提供一种抗拔桩的施工方法,通过该方法可快速简便的形成一种提供较高抗拔力的检测抗拔桩。
为了实现上述目的,本发明的抗拔桩的施工方法包括下述步骤:
1)在地基中的桩位处,将外管沉至设计深度,上述外管的内壁设有数根较细的中空钢管;
2)在上述外管内放入内夯锤,通过内夯锤在外管中的自由落体运动,将内夯锤底端击出外管一定距离;
3)在上述外管内分次填入一定数量的散体填充料,通过内夯锤在外管中的自由落体运动,对填入的散体填充料进行挤扩;
4)在上述外管内分次填入一定数量的干硬性快硬混凝土,通过内夯锤在外管中的自由落体运动,对填入的干硬性快硬混凝土进行挤扩,上述干硬性快硬混凝土的填料挤扩操作结束时,内夯锤底端击出外管一定距离;
5)通过上述外管内的数根较细的中空钢管,向中空钢管内部分别插入钢筋,钢筋的长度超出外管上端和下端一定长度;
6)在上述外管内放入内管,内管内放入内夯锤,将内管和内夯锤连接;
7)同时提升上述内夯锤和内管,向上述外管底端填入一定数量的干硬性快硬混凝土,通过内夯锤的自由落体运动,锤击内管对干硬性快硬混凝土进行挤扩;
8)反复进行上述快硬干硬性混凝土的填充和挤扩操作,通过干硬性快硬混凝土的挤扩作用,使外管底端处的钢筋向外散开,逐渐被包裹嵌固在干硬性快硬混凝土内;
9)提出上述内夯锤和内管,在外管内灌注一定数量的散体材料;
10)采用钢质连接盘穿过上述钢筋的上端并以螺栓固定,同时将钢质连接盘与检测设备的传力杆以螺栓固定,为检测设备提供抗拔力;
11)检测完成后,提出上述护筒,回收上述钢质连接圆盘和钢筋。
最好,在上述的抗拔桩的施工方法中,上述步骤1)中,中空钢管是固定在外管的内壁上,数量为6根~12根,且中空钢管的长度与外管相同,内径为3cm~5cm。
最好,在上述的抗拔桩的施工方法中,上述步骤2)中,内夯锤击出外管的距离为50cm~100cm。
最好,在上述的抗拔桩的施工方法中,上述步骤3)中,散体填充料是指碎砖或碎瓦或碎石或渣土或卵石或钢渣或水泥土或灰土或干硬性混凝土,或上述材料的混合料。
最好,在上述的抗拔桩的施工方法中,上述步骤4)中,在外管内灌注的干硬性快硬混凝土,是指能在数小时内快速凝固的特种混凝土。
最好,在上述的抗拔桩的施工方法中,上述步骤4)中,内夯锤底端击出外管的距离为50cm~100cm。
最好,在上述的抗拔桩的施工方法中,上述步骤5)中,在中空钢管内部分别插入的钢筋的长度,上端为超出外管10~30cm,下端为超出外管50cm~100cm。
最好,在上述的抗拔桩的施工方法中,上述步骤6)中,内管的长度大于外管长度,且该内管的底端封闭,底端为平底,内管的内部底端填充有一定数量的散粒材料,散粒材料上方放置钢板,钢板上方放置胶垫。
最好,在上述的抗拔桩的施工方法中,上述步骤7)中,对干硬性快硬混凝土进行挤扩,是以较低的能量将干硬性快硬混凝土逐渐挤压出外管的。
最好,在上述的抗拔桩的施工方法中,上述步骤8)中,干硬性快硬混凝土的填充和挤扩操作结束时,内管底端与外管底端持平。
最好,在上述的抗拔桩的施工方法中,上述步骤10)中,钢质连接盘是以一定厚度的钢板制成,其直径大于外管,并在与钢筋的对应位置上和中心位置钻孔。
最好,在上述的抗拔桩的施工方法中,上述步骤10)中,检测设备的传力杆是指以钢筋或钢丝绳或钢管,分别连接钢质连接盘与检测设备。
通过以上方法形成的混凝土桩的特点和优势在于:①充分提高抗拔力。首先在桩孔中进行一定量的散体填充料和干硬性快硬混凝土的填充挤扩,形成一层挤密层后再放入钢筋,通过内夯锤和内管再次进行干硬性快硬混凝土的填料挤扩,使钢筋下端充分的被包裹嵌固在干硬性快硬混凝土内,提供较强的抗拔力。并且由于内夯锤和内管采用较低能量,且填充料起到保护作用,避免了钢筋笼下端的主筋被冲切剪断。②快速提供抗拔力。由于钢筋底端被包裹嵌固在快硬混凝土内,经过几个小时后快硬混凝土就提供足够强度,即可为检测设备提供相应的抗拔力。③快速方便,可再回收利用。采用钢质连接盘,通过螺栓可快速方便的分别与钢筋和检测设备连接,检测设备的拉力可直接传递到钢筋。并且所采用的钢质连接圆盘和钢筋,均可以方便的拆卸回收,可以多次的再利用。
附图说明
图1是作为本发明的一个实施例的抗拔桩的施工方法的工序图。
具体实施方式
作为本发明的一个实施例的混凝土桩的施工方法,其包括下述步骤,首先,如图1a所示,在地基中的桩位处,将内壁固定有中空钢管的外管1沉至设计深度,然后,如图1b所示,在外管1内放入内夯锤2,通过内夯锤2在外管1中的自由落体运动,将内夯锤2底端击出外管1一定距离,然后,如图1c所示,在外管1内分次填入一定数量的散体填充料4,通过内夯锤2在外管1中的自由落体运动,对填入的散体填充料4进行挤扩,然后,如图1d所示,在外管1内分次填入一定数量的干硬性快硬混凝土5,通过内夯锤2在外管1中的自由落体运动,对填入的干硬性快硬混凝土5进行挤扩,干硬性快硬混凝土5的填料挤扩操作结束时,内夯锤2底端击出外管1一定距离,然后,如图1e所示,通过上述外管1内的数根较细的中空钢管,向中空钢管内部分别插入钢筋6,钢筋6的长度超出外管上端和下端一定长度,然后,如图1f所示,在上述外管1内放入内管3,内管3内放入内夯锤2,将内管3和内夯锤2连接,然后,如图1g所示,同时提升内夯锤2和内管3,向外管1底端填入一定数量的干硬性快硬混凝土5,通过内夯锤2的自由落体运动,锤击内管3对干硬性快硬混凝土5进行挤扩,然后,如图1h所示,反复进行干硬性快硬混凝土5的填充和挤扩操作,通过干硬性快硬混凝土5的挤扩作用,使外管1底端处的钢筋6向外散开,逐渐被包裹嵌固在干硬性快硬混凝土5内,然后,如图1i所示,提出内夯锤2和内管3,在外管1内灌注一定数量的散体材料4,然后,如图1j所示,将钢筋6的上端穿过钢质连接盘7,并将钢质连接盘7压至外管1上,将露出的钢筋6以螺栓8固定在钢质连接盘上7,将钢质连接盘7与检测设备的传力杆9通过螺栓连接固定,为检测设备提供抗拔力,最后,如图1k所示,当检测完成后,提出外管1,回收钢质连接圆盘7和钢筋6。

Claims (12)

1.一种抗拔桩的施工方法,该方法包括下述步骤:
1)在地基中的桩位处,将外管沉至设计深度,上述外管的内壁设有数根较细的中空钢管;
2)在上述外管内放入内夯锤,通过内夯锤在外管中的自由落体运动,将内夯锤底端击出外管一定距离;
3)在上述外管内分次填入一定数量的散体填充料,通过内夯锤在外管中的自由落体运动,对填入的散体填充料进行挤扩;
4)在上述外管内分次填入一定数量的干硬性快硬混凝土,通过内夯锤在外管中的自由落体运动,对填入的干硬性快硬混凝土进行挤扩,上述干硬性快硬混凝土的填料挤扩操作结束时,内夯锤底端击出外管一定距离;
5)通过上述外管内的数根较细的中空钢管,向中空钢管内部分别插入钢筋,钢筋的长度超出外管上端和下端一定长度;
6)在上述外管内放入内管,内管内放入内夯锤,将内管和内夯锤连接;
7)同时提升上述内夯锤和内管,向上述外管底端填入一定数量的干硬性快硬混凝土,通过内夯锤的自由落体运动,锤击内管对快硬干硬性混凝土进行挤扩;
8)反复进行上述快硬干硬性混凝土的填充和挤扩操作,通过干硬性快硬混凝土的挤扩作用,使外管底端处的钢筋向外散开,逐渐被挤压包含在干硬性快硬混凝土内;
9)提出上述内夯锤和内管,在外管内灌注一定数量的散体材料;
10)采用钢质连接盘穿过上述钢筋的上端并以螺栓固定,同时将钢质连接盘与检测设备的传力杆以螺栓固定,为检测设备提供抗拔力;
11)检测完成后,提出上述护筒,回收上述钢质连接圆盘和钢筋。
2.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤1)中,上述中空钢管是固定在外管的内壁上,数量为6根~12根,且中空钢管的长度与外管相同,内径为3cm~5cm。
3.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤2)中,上述内夯锤击出外管的距离为50cm~100cm。
4.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤3)中,上述散体填充料是指碎砖或碎瓦或碎石或渣土或卵石或钢渣或水泥土或灰土或干硬性混凝土,或上述
材料的混合料。
5.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤4)中,上述在外管内灌注的干硬性快硬混凝土,是指能在数小时内快速凝固的特种混凝土。
6.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤4)中,上述内夯锤底端击出外管的距离为50cm~100cm。
7.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤5)中,上述在中空钢管内部分别插入的钢筋的长度,上端为超出外管10~30cm,下端为超出外管50cm~100cm。
8.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤6)中,上述内管的长度大于外管长度,且该内管的底端封闭,底端为平底,内管的内部底端填充有一定数量的散粒材料,散粒材料上方放置钢板,钢板上方放置胶垫。
9.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤7)中,上述对干硬性快硬混凝土进行挤扩,是以较低的能量将干硬性快硬混凝土逐渐挤压出外管的。
10.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤8)中,上述干硬性混凝土的填充和挤扩操作结束时,内管底端与外管底端持平。
11.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤10)中,上述钢质连接盘是以一定厚度的钢板制成,其直径大于外管,并在与钢筋的对应位置上和中心位置钻孔。
12.根据权利要求1所述的抗拔桩的施工方法,其特征在于上述步骤10)中,上述检测设备的传力杆是指以钢筋或钢丝绳或钢管,分别连接钢质连接盘与检测设备。
CN201210144063.5A 2012-05-10 2012-05-10 抗拔桩的施工方法 Active CN102720187B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210144063.5A CN102720187B (zh) 2012-05-10 2012-05-10 抗拔桩的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210144063.5A CN102720187B (zh) 2012-05-10 2012-05-10 抗拔桩的施工方法

Publications (2)

Publication Number Publication Date
CN102720187A true CN102720187A (zh) 2012-10-10
CN102720187B CN102720187B (zh) 2014-01-29

Family

ID=46946042

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210144063.5A Active CN102720187B (zh) 2012-05-10 2012-05-10 抗拔桩的施工方法

Country Status (1)

Country Link
CN (1) CN102720187B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104074186A (zh) * 2014-07-22 2014-10-01 王继忠 一种建筑地基中成孔的护筒装置及其施工方法
CN104099925A (zh) * 2014-07-25 2014-10-15 王继忠 混凝土桩的施工装置及其施工方法
CN104153356A (zh) * 2014-07-30 2014-11-19 王继忠 混凝土桩的施工装置及其施工方法
CN106013132A (zh) * 2016-05-23 2016-10-12 王继忠 一种变径组合桩
CN108487226A (zh) * 2018-04-06 2018-09-04 中启胶建集团有限公司 多段式复合套管冲压砂桩施工工法
CN111676962A (zh) * 2020-05-19 2020-09-18 浙江新中源建设有限公司 一种混凝土施工装置及施工方法
CN111794216A (zh) * 2020-07-21 2020-10-20 王继忠 抗拔载体桩的施工方法

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5826119A (ja) * 1981-08-08 1983-02-16 Kitagawa Tekkosho:Kk 既設杭の引抜き装置
WO1995018892A1 (en) * 1994-01-06 1995-07-13 Roxbury Limited Improvements in or relating to apparatus for use in forming piles
NL1000558C2 (en) * 1994-06-16 1995-12-18 Heiwerken P Van T Wout Waddinx In situ concrete piling method for use in built up areas
JP2002070048A (ja) * 2000-09-04 2002-03-08 Nippon Steel Corp 構真柱の施工方法とこれに用いるヤットコおよび鋼管杭
CN1493859A (zh) * 2002-11-01 2004-05-05 董一全 一种小荷载单桩承载力检测方法及装置
KR100440822B1 (ko) * 2003-07-22 2004-07-21 (주)초석건설 해상 대구경 팩 말뚝 공법 및 해상 대구경 팩 말뚝
CN101220592A (zh) * 2008-02-04 2008-07-16 王继忠 混凝土桩的施工方法
CN101768970A (zh) * 2010-01-14 2010-07-07 王继忠 混凝土桩的施工方法
CN101851936A (zh) * 2010-06-10 2010-10-06 杭州银博交通工程材料有限公司 一种塑料衬管抽拔钢管超声波检测孔的施工方法

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5826119A (ja) * 1981-08-08 1983-02-16 Kitagawa Tekkosho:Kk 既設杭の引抜き装置
WO1995018892A1 (en) * 1994-01-06 1995-07-13 Roxbury Limited Improvements in or relating to apparatus for use in forming piles
NL1000558C2 (en) * 1994-06-16 1995-12-18 Heiwerken P Van T Wout Waddinx In situ concrete piling method for use in built up areas
JP2002070048A (ja) * 2000-09-04 2002-03-08 Nippon Steel Corp 構真柱の施工方法とこれに用いるヤットコおよび鋼管杭
CN1493859A (zh) * 2002-11-01 2004-05-05 董一全 一种小荷载单桩承载力检测方法及装置
KR100440822B1 (ko) * 2003-07-22 2004-07-21 (주)초석건설 해상 대구경 팩 말뚝 공법 및 해상 대구경 팩 말뚝
CN101220592A (zh) * 2008-02-04 2008-07-16 王继忠 混凝土桩的施工方法
CN101768970A (zh) * 2010-01-14 2010-07-07 王继忠 混凝土桩的施工方法
CN101851936A (zh) * 2010-06-10 2010-10-06 杭州银博交通工程材料有限公司 一种塑料衬管抽拔钢管超声波检测孔的施工方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104074186A (zh) * 2014-07-22 2014-10-01 王继忠 一种建筑地基中成孔的护筒装置及其施工方法
CN104074186B (zh) * 2014-07-22 2016-02-17 王继忠 一种建筑地基中成孔的护筒装置及其施工方法
CN104099925A (zh) * 2014-07-25 2014-10-15 王继忠 混凝土桩的施工装置及其施工方法
CN104153356A (zh) * 2014-07-30 2014-11-19 王继忠 混凝土桩的施工装置及其施工方法
CN104153356B (zh) * 2014-07-30 2016-08-31 王继忠 混凝土桩的施工装置及其施工方法
CN106013132A (zh) * 2016-05-23 2016-10-12 王继忠 一种变径组合桩
CN106013132B (zh) * 2016-05-23 2018-06-08 王继忠 一种变径组合桩
CN108487226A (zh) * 2018-04-06 2018-09-04 中启胶建集团有限公司 多段式复合套管冲压砂桩施工工法
CN111676962A (zh) * 2020-05-19 2020-09-18 浙江新中源建设有限公司 一种混凝土施工装置及施工方法
CN111676962B (zh) * 2020-05-19 2021-08-13 浙江新中源建设有限公司 一种混凝土施工装置及施工方法
CN111794216A (zh) * 2020-07-21 2020-10-20 王继忠 抗拔载体桩的施工方法

Also Published As

Publication number Publication date
CN102720187B (zh) 2014-01-29

Similar Documents

Publication Publication Date Title
CN102720187B (zh) 抗拔桩的施工方法
CN102733377B (zh) 混凝土桩的施工方法
CN102733378A (zh) 混凝土桩的施工方法
CN101220593A (zh) 一种预应力管桩施工后处理该管桩断裂的加固方法
CN105040692B (zh) 一种预制混凝土桩身载体桩的施工方法
CN101220592A (zh) 混凝土桩的施工方法
CN101768970A (zh) 混凝土桩的施工方法
CN103321203B (zh) 锥形夯锤强力冲扩桩法
CN101831908A (zh) 大直径超深度静压单管沉管夯扩灌注桩施工工艺及设备
CN102733379B (zh) 混凝土桩的施工方法
CN113653032A (zh) 抗拔载体桩的施工方法
CN104294818A (zh) 混凝土桩的施工方法
CN111058475A (zh) 一种高烈度地震区桩基托梁衡重式挡土墙结构及施工方法
CN203034498U (zh) 一种多年冻土区桩的水平承载力试验装置
CN110055948A (zh) 一种深大岩溶地基处理方法和装置
CN104929125A (zh) 一种载体桩的施工设备及其施工方法
CN102720218A (zh) 基于深孔倒t型桩的高层抗震建筑结构
CN105064332A (zh) 一种方形桩身载体桩的施工方法
CN105926594A (zh) 一种静压沉管载体灌注桩的双管施工方法
CN111058464A (zh) 一种陡坡邻近填方工程的危岩防护结构及施工方法
KR100992751B1 (ko) 중공 말뚝의 선단부 결합용 구조체 및 그를 이용한 말뚝 하단부 지반 지지력 강화를 위한 그라우팅 방법
CN103132511A (zh) 静压沉管扩底灌注桩的成桩方法及成桩装置
CN104674857A (zh) 一种即打即压的桩基承载力检测方法
CN108914942A (zh) 一种深基坑支护体系及其施工方法
CN212001171U (zh) 一种陡坡邻近填方工程的危岩防护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD

Free format text: FORMER OWNER: WANG JIZHONG

Effective date: 20140715

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20140715

Address after: 102218, Beijing, Changping District East small town Taiping homes, building 31

Patentee after: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD.

Address before: 102218, Beijing, Changping District East small town Taiping homes, building 31

Patentee before: Wang Jizhong