CN102704481A - 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法 - Google Patents

一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法 Download PDF

Info

Publication number
CN102704481A
CN102704481A CN2012101904199A CN201210190419A CN102704481A CN 102704481 A CN102704481 A CN 102704481A CN 2012101904199 A CN2012101904199 A CN 2012101904199A CN 201210190419 A CN201210190419 A CN 201210190419A CN 102704481 A CN102704481 A CN 102704481A
Authority
CN
China
Prior art keywords
pile
drill rod
sinking
static pressure
long screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101904199A
Other languages
English (en)
Inventor
朱建新
丁曲
郑毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sunward Intelligent Equipment Co Ltd
Original Assignee
Sunward Intelligent Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sunward Intelligent Equipment Co Ltd filed Critical Sunward Intelligent Equipment Co Ltd
Priority to CN2012101904199A priority Critical patent/CN102704481A/zh
Publication of CN102704481A publication Critical patent/CN102704481A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,设备包括静力压桩机、附加在静力压桩机上的可移位桁架、装配在桁架上的动力头、动力头加压装置、长螺旋钻杆的换杆装置以及钻杆钻具,具体步骤如下:(1)测量桩位,机器就位;(2)吊桩、准备;(3)静压沉桩;(4)接桩;(5)长螺旋钻杆安装;(6)长螺旋引孔静压沉桩;(7)终止压桩。本发明是一种能穿透较厚沙层且施工效率高、施工成本低的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法。

Description

一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法
技术领域
本发明涉及一种建筑物和桥梁基础用的管桩施工方法,特别是涉及一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法。
背景技术
静压沉桩法施工是通过静力压桩机的自重和机架上的配重提供反力而将管桩压入土中的沉桩工艺。此工艺具有无振动,无冲击,无噪音等优点;同时桩身选用高强度预应力预制管桩,以该桩作基础具有工艺简明,质量可靠,造价低,检测方便的特性。但静力压桩机在压桩过程中遇到较厚的沙层时,会因为阻力增大而导致施工困难,这也是制约静力压桩机地层适应性的重要原因。
现有几种解决方案:
1、在压桩前进行引孔,在测定好桩位处钻孔,钻孔直径小于桩径,以减小压桩阻力。但是此种施工方法消耗时间长,增加施工成本。容易塌孔,压桩机对正孔位困难。
2、在无法依靠静压继续沉桩的情况下,采用锤击的方式,依靠对沙层的冲击来穿透沙层,但此方法对于预制管桩的损害较大,会造成桩身的损伤,噪音大,油污飞溅污染环境。
发明内容
本发明所要解决的技术问题是提供一种能穿透较厚沙层且施工效率高、施工成本低的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法。
为了解决上述技术问题,本发明提供的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,设备包括静力压桩机、附加在静力压桩机上的可移位桁架、装配在桁架上的动力头、动力头加压装置、长螺旋钻杆的换杆装置以及钻杆钻具,具体步骤如下:
(1)测量桩位,机器就位:应用压桩机回转机构和长短船行走机构,使压桩机夹持口中心对准桩位中心,可移位桁架处于移位状态;
(2)吊桩、准备:先拴好吊装用的钢丝绳及索具,起吊管桩,并使夹具抱紧桩身,然后对准桩位中心;
(3)静压沉桩:在保证桩身的垂直度后,启动压桩油缸,将管桩压下;
(4)接桩:上、下节桩段保持顺直,接桩后根据设计要求实施静压沉桩;
(5)长螺旋钻杆安装:压桩过程中遇到较厚沙层,起吊组装长螺旋钻杆,插入管桩中心,动力头连接插入管桩中的长螺旋钻杆;
(6)长螺旋引孔静压沉桩:旋转动力头,驱动长螺旋钻杆,切削桩端下方的沙土,渣土随长螺旋钻杆叶片排出,同时由于桩端的阻力减小,继续静压沉桩;
(7)终止压桩:经确定到达设计要求时,随即进行稳压,同时提出长螺旋钻杆,稳压后即终止沉桩,钻机移位进行下一桩位施工。
上述步骤(3)中采用先低压快速压桩,再高压慢速压桩将管桩压下。
上述步骤(5)、长螺旋钻杆安装:吊装长螺旋钻杆至管桩中间空心处,多节长螺旋钻杆通过换杆器将其组装伸入至桩端位置,此时将桁架带动力头回位,调整动力头使其中心对准桩心,动力头连接插入管桩中的长螺旋钻杆。
采用上述技术方案的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,具有如下积极效果及优点:
(1)克服了压桩设备难以穿透较厚沙层的缺点。
(2)同时进行静压与中掘施工,大大提高了施工效率,降低了施工成本。
(3)静压和中掘相结合的施工设备,除具有传统压桩机的优点外还增加了压桩设备的地层适应性,使沉桩基础达到更好的持力层,满足更多的桩基础设计要求。
综上所述,本发明是一种能穿透较厚沙层且施工效率高、施工成本低的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法。
附图说明
图1是本发明钻机就位吊桩示意图。
图2是本发明静压沉桩示意图。
图3是本发明吊装长螺旋钻杆示意图。
图4是本发明长螺旋静压同时钻进示意图。
图5是本发明终止压桩示意图。
具体实施方式
下面结合附图对本发明作进一步详细说明。
如图1所示:钻机就位。设备包括静力压桩机、附加在静力压桩机上的可移位桁架、装配在桁架上的动力头、动力头加压装置、长螺旋钻杆的换杆装置以及钻杆钻具,应用回转机构和长短船行走机构7,使压桩机持口中心对准桩位,可移位桅杆4处于移位状态,先拴好吊装用的钢丝绳及索具2,用桩机上的起重机1起吊管桩3,并使夹具6抱紧桩身,然后对准桩位中心。
如图2所示:静压沉桩,接桩。在保证桩身的垂直度后,启动压桩油缸9,先低压快速压桩,再高压慢速压桩,把管桩3压入土层11;上、下节桩段保持顺直,接桩后跟根据设计要求实施静压沉桩。
如图3所示:长螺旋钻杆安装。压桩过程中遇到较厚沙层12,由于阻力增大管桩3无法继续下压,起重机1吊装长螺旋钻杆10至管桩3中间空心处,多节长螺旋钻杆10通过换杆器8将其组装放入至桩端位置,此时将桁架4带动力头5回位,调整动力头5使其中心对准桩心,动力头5连接插入管桩3中的长螺旋钻杆10;
如图4所示:长螺旋引孔静压沉桩。旋转动力头5,驱动长螺旋钻杆10,切削桩端下方的沙土,随长螺旋钻杆螺旋叶片排出,同时由于桩端的阻力减小,继续使用压桩油缸9静压沉桩。
如图5所示:提出钻杆,终止压桩。经确定到达设计要求时,随即进行稳压,使动力头5与长螺旋钻杆10分离,移位桁架4,用起重机1提出长螺旋钻杆10,稳压后即终止沉桩,钻机移位进行下一桩位施工。

Claims (3)

1.一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,其特征是:设备包括静力压桩机、附加在静力压桩机上的可移位桁架、装配在桁架上的动力头、动力头加压装置、长螺旋钻杆的换杆装置以及钻杆钻具,具体步骤如下:
(1)测量桩位,机器就位:应用压桩机回转机构和长短船行走机构,使压桩机夹持口中心对准桩位中心,可移位桁架处于移位状态;
(2)吊桩、准备:先拴好吊装用的钢丝绳及索具,起吊管桩,并使夹具抱紧桩身,然后对准桩位中心;
(3)静压沉桩:在保证桩身的垂直度后,启动压桩油缸,将管桩压下;
(4)接桩:上、下节桩段保持顺直,接桩后根据设计要求实施静压沉桩;
(5)长螺旋钻杆安装:压桩过程中遇到较厚沙层,起吊组装长螺旋钻杆,插入管桩中心,动力头连接插入管桩中的长螺旋钻杆;
(6)长螺旋引孔静压沉桩:旋转动力头,驱动长螺旋钻杆,切削桩端下方的沙土,渣土随长螺旋钻杆叶片排出,同时由于桩端的阻力减小,继续静压沉桩;
(7)终止压桩:经确定到达设计要求时,随即进行稳压,同时提出长螺旋钻杆,稳压后即终止沉桩,钻机移位进行下一桩位施工。
2.根据权利要求1所述的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,其特征是:上述步骤(3)中采用先低压快速压桩,再高压慢速压桩将管桩压下。
3.根据权利要求1或2所述的建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法,其特征是:上述步骤(5)、长螺旋钻杆安装:吊装长螺旋钻杆至管桩中间空心处,多节长螺旋钻杆通过换杆器将其组装伸入至桩端位置,此时将桁架带动力头回位,调整动力头使其中心对准桩心,动力头连接插入管桩中的长螺旋钻杆。
CN2012101904199A 2012-06-11 2012-06-11 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法 Pending CN102704481A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101904199A CN102704481A (zh) 2012-06-11 2012-06-11 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101904199A CN102704481A (zh) 2012-06-11 2012-06-11 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法

Publications (1)

Publication Number Publication Date
CN102704481A true CN102704481A (zh) 2012-10-03

Family

ID=46897513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101904199A Pending CN102704481A (zh) 2012-06-11 2012-06-11 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法

Country Status (1)

Country Link
CN (1) CN102704481A (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014063556A1 (zh) * 2012-10-24 2014-05-01 山河智能装备股份有限公司 引孔式静压桩机
CN104631458A (zh) * 2014-12-23 2015-05-20 江苏谷登工程机械装备有限公司 一种静力压桩机扩孔沉桩工法
WO2015100688A1 (zh) * 2013-12-30 2015-07-09 恒天九五重工有限公司 一种全程引孔式液压静力压桩机
CN105239574B (zh) * 2014-06-17 2017-08-29 中建二局第一建筑工程有限公司 应用于填海地质的静压预应力管桩的施工方法
CN107476305A (zh) * 2016-06-08 2017-12-15 宜兴市周铁镇生力钻探机械厂 一种桥梁用同步注浆静压沉桩法
CN110952552A (zh) * 2019-12-17 2020-04-03 广东力源液压机械有限公司 大直径phc预制管桩施工方法及实施该方法的打桩机
CN111364450A (zh) * 2020-03-23 2020-07-03 上海宝冶集团有限公司 一种强胶结地层中phc桩施工方法
CN112030968A (zh) * 2020-08-28 2020-12-04 江苏原土建筑设计有限公司 一种用于解决抱压沉桩困难的新型施工工艺
CN113774911A (zh) * 2021-09-30 2021-12-10 山东建筑大学 一种管桩变直径引孔与压桩同步施工设备及其方法
CN113969577A (zh) * 2021-11-29 2022-01-25 何学礼 一种预制桩沉桩工法
CN114215060A (zh) * 2021-12-27 2022-03-22 山河智能装备股份有限公司 引孔式静力压桩机及引孔式静力压桩机的施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102400465A (zh) * 2010-09-10 2012-04-04 湖北毅力机械有限公司 一种静压中掘压桩机及静压中掘压桩施工方法

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102400465A (zh) * 2010-09-10 2012-04-04 湖北毅力机械有限公司 一种静压中掘压桩机及静压中掘压桩施工方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014063556A1 (zh) * 2012-10-24 2014-05-01 山河智能装备股份有限公司 引孔式静压桩机
WO2015100688A1 (zh) * 2013-12-30 2015-07-09 恒天九五重工有限公司 一种全程引孔式液压静力压桩机
CN105239574B (zh) * 2014-06-17 2017-08-29 中建二局第一建筑工程有限公司 应用于填海地质的静压预应力管桩的施工方法
CN104631458A (zh) * 2014-12-23 2015-05-20 江苏谷登工程机械装备有限公司 一种静力压桩机扩孔沉桩工法
CN104631458B (zh) * 2014-12-23 2016-08-24 江苏谷登工程机械装备有限公司 一种静力压桩机扩孔沉桩工法
CN107476305A (zh) * 2016-06-08 2017-12-15 宜兴市周铁镇生力钻探机械厂 一种桥梁用同步注浆静压沉桩法
CN110952552A (zh) * 2019-12-17 2020-04-03 广东力源液压机械有限公司 大直径phc预制管桩施工方法及实施该方法的打桩机
CN111364450A (zh) * 2020-03-23 2020-07-03 上海宝冶集团有限公司 一种强胶结地层中phc桩施工方法
CN112030968A (zh) * 2020-08-28 2020-12-04 江苏原土建筑设计有限公司 一种用于解决抱压沉桩困难的新型施工工艺
CN113774911A (zh) * 2021-09-30 2021-12-10 山东建筑大学 一种管桩变直径引孔与压桩同步施工设备及其方法
CN113969577A (zh) * 2021-11-29 2022-01-25 何学礼 一种预制桩沉桩工法
CN114215060A (zh) * 2021-12-27 2022-03-22 山河智能装备股份有限公司 引孔式静力压桩机及引孔式静力压桩机的施工方法

Similar Documents

Publication Publication Date Title
CN102704481A (zh) 一种建筑或桥梁用静压沉桩和中掘引孔相结合的施工方法
CN105649083B (zh) 全套管一次性旋切式清桩装置及其清桩方法
CN205840770U (zh) 一种适用于大口径施工的冲击式旋挖钻机装置
CN101173517A (zh) 一种拔桩施工方法
CN101851922B (zh) 用全套管钻机切断地下锚索/杆的处理方法
CN103835287B (zh) 一种挤密变径桩的施工方法
CN102383431A (zh) 中掘预应力离心管桩(方桩)沉桩装置及其新型沉桩法
CN102926413A (zh) 一种灌注桩桩端取样预埋管
CN100494617C (zh) 中心安放式锚杆钻机的施工方法
CN105113976B (zh) 钢丝刷钻头回旋钻机及解决埋钻、掉钻、卡钻的方法
CN212129131U (zh) 一种挤土成孔锚杆施工结构
CN102535452A (zh) 一种新型工程桩
CN202544737U (zh) 一种加压型钻机
CN201635074U (zh) 地锚
CN104372793A (zh) 采用旋喷桩法预应力锚索用于既有地下室抗浮的方法
CN209339143U (zh) 一种混凝土管桩施工设备
CN207331690U (zh) 管桩沉入式桩机
CN111749231A (zh) 一种双套管双驱动全回转式成桩装置及成桩工艺
CN106836202A (zh) 高效管桩内钻土、压桩、喷粉、喷浆一体机及其施工工艺
CN110273413A (zh) 一种预制桩的高效施工方法
CN109339044A (zh) 一种混凝土管桩施工设备
CN103821137A (zh) 一种长螺旋钻孔嵌岩、扩底压灌桩的施工方法及装置
CN101349059A (zh) 长螺旋钻机压灌钢筋混凝土新技术
CN101476444A (zh) 振冲式辐射井水平辐射管施工设备
CN103572760A (zh) 钻孔压灌桩全桩长振捣施工方法及装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121003