CN102661015B - Single-layer waterproof prepared roofing and construction method thereof - Google Patents

Single-layer waterproof prepared roofing and construction method thereof Download PDF

Info

Publication number
CN102661015B
CN102661015B CN201210151450.1A CN201210151450A CN102661015B CN 102661015 B CN102661015 B CN 102661015B CN 201210151450 A CN201210151450 A CN 201210151450A CN 102661015 B CN102661015 B CN 102661015B
Authority
CN
China
Prior art keywords
layer
coiled material
basic unit
fixed
roofing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210151450.1A
Other languages
Chinese (zh)
Other versions
CN102661015A (en
Inventor
王作军
杨蔚清
王继胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA JIANGSU INTERNATIONAL ECONOMIC TECHNICAL COOPERATION CORP
Original Assignee
CHINA JIANGSU INTERNATIONAL ECONOMIC TECHNICAL COOPERATION CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA JIANGSU INTERNATIONAL ECONOMIC TECHNICAL COOPERATION CORP filed Critical CHINA JIANGSU INTERNATIONAL ECONOMIC TECHNICAL COOPERATION CORP
Priority to CN201210151450.1A priority Critical patent/CN102661015B/en
Publication of CN102661015A publication Critical patent/CN102661015A/en
Application granted granted Critical
Publication of CN102661015B publication Critical patent/CN102661015B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The invention discloses a single-layer waterproof prepared roofing and a construction method thereof. The roofing comprises a base layer, a vapor-proof layer, a heat preservation layer and a waterproof layer, wherein the base layer is a concrete roofing board or a steel plate; the vapor-proof layer, the heat preservation layer and the waterproof layer are sequentially arranged on the base layer; the vapor-proof layer is a polyethylene film layer which is laid on the base layer in a border adhibiting way; the heat preservation layer is fixed on the base layer through a fastening gasket and a fastening nail; and the waterproof layer is a single-layer thermoplastic polyolefin waterproof roll layer or a single-layer polyvinyl chloride waterproof roll layer, and is fixed on the base layer in a mechanical fixing way. The roofing is simple in structural hierarchy and high in degree of design freedom; and in addition, the single-layer operation of a wide roll is adopted, so that structural layers and operation levels are reduced, the weight is reduced, the materials are saved, and the construction cost is lowered.

Description

A kind of job practices of single ply waterproofing prepared roofing
Technical field
The invention belongs to roofworks field, be specifically related to a kind of single ply waterproofing prepared roofing and job practices thereof.
Background technology
Roof is that going along with sb. to guard him of covering effect and load-carrying members play in the house the superiors, and one of its topmost function is " rain of becalming ".Roofing is different according to drainage grade, can be divided into flat roof deck and pitched roof.The gradient of general flat roof deck is below 10%, and the most frequently used gradient is 2 ~ 3%, and the gradient of pitched roof is more than 10%.China's building adopts pitched roof traditionally, has two-sided slope, slope, four sides etc.This roof pitch is larger, capable of expansion and contraction, and draining is rapid, waterproof effect is also relatively good.Since the sixties, for alleviating roofing deadweight, reduce construction costs, improving prefabricated roof assembling degree, generally change reinforced concrete flat roof into, adopt prefabricated circular hole roof panel and cast-in-situ steel reinforced concrete roof panel etc. more.Flat roof deck cost is lower, easy construction, simple structure, and outward appearance is succinct, is applicable to various shapes and big or small architectural plane, and current this class roofing is most widely used.
The typical construction level of existing roofing comprises following several part: A. structure basic unit: mostly be roof panel on prefabricated circular hole slab or cast in place reinforced bar coagulation, small part is steel plate layer; B. every vapour layer: for preventing that moisture from entering insulation layer setting, mostly be one deck adhesive bitument primer or one deck malthoid; C. insulation layer: have two kinds of cast-in-place and prefabrication and assembly constructions, conventional heat insulating material has cement perlite, piece, polystyrol plastic foam plate etc. on cinder, aerating coagulation; D. waterproofing course: the flexible waterproof layer such as can be coiled material, film can be also that pea gravel concreten adds the rigid waterproof layer that flexible filleting forms.
Along with the development of China's Building technology in recent years, large span, light-duty and highrise building is increasing, make the distortion of roof structure occur larger variation, and parking lot, the appearance of the roofing such as sports ground, garden, make again roofing function greatly increase, but since the eighties, building leakage problem becomes in China's engineering construction very distinct issues, in order to solve Water-proof Measures of Roofs, in construction, constantly increase roof structure level, the buildings and resources expending yet effect many and that obtain is not clearly, does not meet the requirement of national building energy conservation.
Summary of the invention
Goal of the invention: the object of the invention is to for the deficiencies in the prior art, a kind of single ply waterproofing prepared roofing and job practices thereof are provided, being applicable to long-span roofing construction and the house roof engineerings such as industrial factory building, stadiums, commercial building, exhibition hall, airport, waiting hall and public building, is a kind of new type roof system that reduces roof structure level, economizes on resources and improve building energy conservation.
Technical scheme: a kind of single ply waterproofing prepared roofing of the present invention, comprise basic unit, every vapour layer, insulation layer and waterproofing course, described basic unit is concrete face-board for room or steel plate, in described basic unit, be disposed with described every vapour layer, insulation layer and waterproofing course, described is film layer every vapour layer, and described film layer sky is layered in described basic unit; Described insulation layer is fixed in described basic unit by setting-up piece and staple; Described waterproofing course is monolayer thermoplastic coiled water-proof polyolefine material layer or individual layer Polyvinyl chloride plastic sheets for waterproofing layer, and described waterproofing course is fixed in described basic unit by mechanical Fixing Method.
Further, adjacent described film layer lap width is more than or equal to 100 ㎜, and the described vinyl film layer of roofing edge is along the metope continuous laying that makes progress, and it exceeds described insulation layer upper surface and is more than or equal to 150mm.
Further, described setting-up piece is concordant with warming plate upper surface, and described staple is vertically fixed in described basic unit, and described staple at least penetrates described steel plate 25mm or embeds described concrete face-board for room 30mm.
The job practices of above-mentioned single ply waterproofing prepared roofing, comprises the steps: that (one) removes substrate surface foreign material, chip; (2) lay every vapour layer, between described Ge Qicengyu basic unit, adopt empty paving; (3) lay thermal insulation separation thermosphere; (4) overlay waterproof roll; (5) waterproof roll is fixed; Adopting mechanical Fixing Method to fix is fixed on waterproof roll in described basic unit: (six) coiled material lapping, adopts bonding machine to weld each overlap edge; (7) processing of thin portion node, the coiled material sheet material of respective nodes, adopts hand-held welding gun that sheet material is welded on large face coiled material; (8) check finishing; (9) tissue is checked and accepted.
Described mechanical Fixing Method comprises that point type is fixing and linear fixing, and described point type is fixed as and adopts the fixedly method of coiled material of pad and staple, described linearity to be fixed as the fixedly method of coiled material of press strip and staple that adopts.
Compared with prior art, its beneficial effect is in the present invention: (1) roof structure level is simple, and design freedom is large; (2) adopt the operation of wide cut coiled material individual layer, reduce roof structure level and operation level, weight reduction, save material, reduce cost; (3) realize multiple material construction integrated, can, by being connected operation every vapour layer, insulation layer, waterproofing course, speed up the work; (4) job practices is various, constructs convenient rapid; Coiled material lapping adopts the method for welding, hot melt, and sealing waterproof effect is reliable; (5) operational level is all dry operation, and easy construction, is easy to control quality, and the relative traditional work of labour intensity is lighter; (6) can under lower temperature environments, construct, be subject to Base Smoothness and moisture effect less, flames of anger operation, construction environment safety and environmental protection; (7) thin portion processes easily, and strong adaptability is easy to maintenance, good endurance, recoverable.
Accompanying drawing explanation
Fig. 1 is the partial structurtes schematic diagram of this single ply waterproofing prepared roofing.
The specific embodiment
Below technical solution of the present invention is elaborated, but protection scope of the present invention is not limited to described embodiment.
A prepared roofing, comprises basic unit 1, every vapour layer 2, insulation layer 3 and waterproofing course 4, and described basic unit 1 is concrete face-board for room, is disposed with described every vapour layer 2, insulation layer 3 and waterproofing course 4 in described basic unit 1.
Described is the film layer of 0.3 millimeters thick every vapour layer 2, adjacent film layer lap width 100 ㎜, and the described vinyl film layer of roofing edge is along the metope continuous laying that makes progress, and it exceeds described insulation layer 3 upper surface 150mm.
Described insulation layer 3 adopts hard-foam polyurethane plate, by setting-up piece 8 and staple 7, be fixed in described basic unit 1, described each length of side of hard-foam polyurethane plate is 1.2m, respectively 6 of the setting-up piece 8 of every plate use and staples 7, described setting-up piece 8 is concordant with warming plate upper surface, described staple 7 is vertically fixed in described basic unit 1, and described staple 7 embeds described concrete face-board for room 30mm.
Described waterproofing course 4 is monolayer thermoplastic coiled water-proof polyolefine material layer, and described waterproofing course is fixed in described basic unit by screw 6, metallic gasket 5 and stainless steel press strip.
The job practices of above-mentioned single ply waterproofing prepared roofing, comprises the steps:
(1) remove basic unit's 1 surface irregularities, chip;
(2) lay every vapour layer 2, describedly between vapour layer 2 and basic unit 1, adopt empty paving, the overlap joint of described film layer and closing in place adopt butyl rubber belt to seal, and form air curtain closely and continuous in vapour layer 2;
(3) lay insulation layer 3, described insulation layer 3 adopts hard-foam polyurethane plate, by setting-up piece 8 and staple 7, be fixed in described basic unit 1, described each length of side of hard-foam polyurethane plate is 1.2m, respectively 6 of the setting-up piece 8 of every plate use and staples 7, described setting-up piece 8 is concordant with warming plate upper surface, and described staple 7 is vertically fixed in described basic unit 1, and described staple 7 embeds described concrete face-board for room 30mm;
(4) overlay waterproof roll, waterproof roll is arranged on insulation layer 3 by snap the line control position, it is vertical with the profiled sheet ripple direction of insulation layer 3 that coiled material is laid direction, makes coiled material naturally loose; It is smooth straight that coiled material keeps, must not distortion, and lap width is no less than 120mm, and the width that covers setting-up piece 8 and staple 7 is 50mm;
(5) waterproof roll is fixed; Adopt mechanical Fixing Method that waterproof roll is fixed in described basic unit 1, described mechanical Fixing Method comprises that point type is fixing and linear fixing, described point type is fixed as and adopts fixedly coiled material of metallic gasket 5 and screw 6, described linearity is fixed as and adopts fixedly coiled material of stainless steel compressing tablet and screw 6, and screw 6 and metallic gasket 7 and stainless steel press strip are along the fixing coiled material apart from coil edge 30mm place shown in mark line;
(6) coiled material lapping, a secondary coiled material lapping, on another width coiled material, is overlying under waterproof roll screw 8 and metallic gasket 7 and stainless steel compressing tablet, then adopts bonding machine to weld each overlap edge;
(7) processing of thin portion node, described thin portion node comprises the positions such as inner corner trim, external corner, deformation joint and roof pipeline and coiled material receipts head, the coiled material sheet material of respective nodes, adopts hand-held welding gun that sheet material is welded on large face coiled material; Coiled material is received head position and is adopted press strip to fix, and uses fluid sealant to obturage.
(8) check finishing;
(9) tissue is checked and accepted.
As mentioned above, although represented and explained the present invention with reference to specific preferred embodiment, it shall not be construed as the restriction to the present invention self.Not departing under the spirit and scope of the present invention prerequisite of claims definition, can make in the form and details various variations to it.

Claims (1)

1. the job practices of a single ply waterproofing prepared roofing, it is characterized in that, described roofing comprises basic unit, every vapour layer, insulation layer and waterproofing course, described basic unit is concrete face-board for room or steel plate, is disposed with described every vapour layer, insulation layer and waterproofing course in described basic unit;
Described is the film layer of 0.3 millimeters thick every vapour layer, described film layer sky is layered in described basic unit, adjacent described film layer lap width is more than or equal to 100 ㎜, the described film layer of roofing edge is along the metope continuous laying that makes progress, and it exceeds described insulation layer upper surface and is more than or equal to 150mm;
Described insulation layer adopts hard-foam polyurethane plate, by setting-up piece and staple, is fixed in described basic unit;
Described waterproofing course is monolayer thermoplastic coiled water-proof polyolefine material layer or individual layer Polyvinyl chloride plastic sheets for waterproofing layer, and described waterproofing course is fixed in described basic unit by mechanical Fixing Method;
Comprise the steps: that (one) removes substrate surface foreign material, chip; (2) lay every vapour layer, between described Ge Qicengyu basic unit, adopt empty paving, the overlap joint of described film layer and closing in place adopt butyl rubber belt sealing, form air curtain closely and continuous in vapour layer; (3) lay thermal insulation separation thermosphere, described insulation layer adopts hard-foam polyurethane plate, by setting-up piece and staple, be fixed in described basic unit, described each length of side of hard-foam polyurethane plate is 1.2m, each 6 of the setting-up piece of every plate use and staples, described setting-up piece is concordant with warming plate upper surface, and described staple is vertically fixed in described basic unit, and described staple at least penetrates described steel plate 25mm or embeds described concrete face-board for room 30mm; (4) overlay waterproof roll, waterproof roll is arranged on insulation layer by snap the line control position, it is vertical with the profiled sheet ripple direction of insulation layer that coiled material is laid direction, makes coiled material naturally loose; It is smooth straight that coiled material keeps, must not distortion, and lap width is no less than 120mm, and the width that covers setting-up piece and staple is 50mm; (5) waterproof roll is fixed; Adopting mechanical Fixing Method to fix is fixed on waterproof roll in described basic unit, described mechanical Fixing Method comprises that point type is fixing and linear fixing, described point type is fixed as and adopts fixedly coiled material of metallic gasket and screw, described linearity is fixed as and adopts fixedly coiled material of stainless steel compressing tablet and screw, and screw and metallic gasket and stainless steel press strip are along the fixing coiled material apart from coil edge 30mm place shown in mark line; (6) coiled material lapping, a width coiled material lapping, on another width coiled material, is overlying under waterproof roll screw and metallic gasket and stainless steel compressing tablet, then adopts bonding machine to weld each overlap edge; (7) processing of thin portion node, described thin portion node comprises inner corner trim, external corner, deformation joint and roof pipeline position and coiled material receipts head, the coiled material sheet material of respective nodes, adopts hand-held welding gun that sheet material is welded on large face coiled material; Coiled material is received head position and is adopted press strip to fix, and uses fluid sealant to obturage; (8) check finishing; (9) tissue is checked and accepted.
CN201210151450.1A 2012-05-16 2012-05-16 Single-layer waterproof prepared roofing and construction method thereof Active CN102661015B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210151450.1A CN102661015B (en) 2012-05-16 2012-05-16 Single-layer waterproof prepared roofing and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210151450.1A CN102661015B (en) 2012-05-16 2012-05-16 Single-layer waterproof prepared roofing and construction method thereof

Publications (2)

Publication Number Publication Date
CN102661015A CN102661015A (en) 2012-09-12
CN102661015B true CN102661015B (en) 2014-01-15

Family

ID=46770583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210151450.1A Active CN102661015B (en) 2012-05-16 2012-05-16 Single-layer waterproof prepared roofing and construction method thereof

Country Status (1)

Country Link
CN (1) CN102661015B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453108A (en) * 2014-12-12 2015-03-25 武汉一冶建筑安装工程有限责任公司 Flexible waterproof construction method of light steel roofing
CN108136748A (en) * 2015-10-23 2018-06-08 北京东方雨虹防水技术股份有限公司 A kind of single-layer roof waterproof roll and preparation method thereof
CN112160510A (en) * 2017-12-12 2021-01-01 江苏凯伦建材股份有限公司 Construction method of waterproof coiled material
CN109927159B (en) * 2017-12-19 2020-12-29 路港集团有限公司 Water saving device for uniformly watering concrete
CN109252665A (en) * 2018-03-31 2019-01-22 深圳市科顺防水工程有限公司 A kind of PVC waterproof roll integration is laid with bottom surface and facade method
CN108978898B (en) * 2018-03-31 2020-06-23 深圳市科顺防水工程有限公司 Method for integrally laying external corner and internal corner of PVC waterproof coiled material
CN109322412A (en) * 2018-10-15 2019-02-12 筑梦高科建筑有限公司 Waterproof roll is mechanically fixed construction technology
CN109695319B (en) * 2018-12-28 2021-07-27 中冶天工集团天津有限公司 Pre-sealing structure around roof rainwater pipe and construction method
CN112681623A (en) * 2020-12-24 2021-04-20 何峰 Construction method of water-proof layer of roof coating assembled on skyscraper plate at plate joint
CN113482247A (en) * 2021-06-07 2021-10-08 五冶集团上海有限公司 TPO waterproof coiled material non-perforation fixing method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4016323A (en) * 1975-09-29 1977-04-05 Volovsek Anton F Method and construction of roof system
US5088259A (en) * 1987-11-16 1992-02-18 Myers J Milton Roof construction system
CN1107923A (en) * 1993-06-16 1995-09-06 徐功明 Water proof and thermal insulating construction method for full-closed roof
CN201090001Y (en) * 2007-09-19 2008-07-23 乔金栋 Composite heat preservation water-proof roofing
CN201221161Y (en) * 2008-07-10 2009-04-15 上海建工股份有限公司 Greening roof covering water-proof system
CN201245933Y (en) * 2008-08-25 2009-05-27 黄萍 Novel energy-saving water-proof roof system
CN201972321U (en) * 2010-12-30 2011-09-14 山东杭萧钢构有限公司 Flexible water-proof roof
CN202596044U (en) * 2012-05-16 2012-12-12 中国江苏国际经济技术合作公司 Single-layer waterproof roll roofing

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7765756B2 (en) * 2005-02-25 2010-08-03 Bontrager Ii Arley L Low noise roof deck system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4016323A (en) * 1975-09-29 1977-04-05 Volovsek Anton F Method and construction of roof system
US5088259A (en) * 1987-11-16 1992-02-18 Myers J Milton Roof construction system
CN1107923A (en) * 1993-06-16 1995-09-06 徐功明 Water proof and thermal insulating construction method for full-closed roof
CN201090001Y (en) * 2007-09-19 2008-07-23 乔金栋 Composite heat preservation water-proof roofing
CN201221161Y (en) * 2008-07-10 2009-04-15 上海建工股份有限公司 Greening roof covering water-proof system
CN201245933Y (en) * 2008-08-25 2009-05-27 黄萍 Novel energy-saving water-proof roof system
CN201972321U (en) * 2010-12-30 2011-09-14 山东杭萧钢构有限公司 Flexible water-proof roof
CN202596044U (en) * 2012-05-16 2012-12-12 中国江苏国际经济技术合作公司 Single-layer waterproof roll roofing

Non-Patent Citations (10)

* Cited by examiner, † Cited by third party
Title
五棵松体育馆屋面系统施工技术;葛兆;《中国建筑防水》;20070515(第9期);11-13页 *
刘锋 等.西卡渗耐PVC单层防水屋面系统在旧屋面翻新工程中的应用.《中国建筑防水》.2011,(第19期),24-29,40页.
单层屋面系统质量保障三要素与某失效屋面的翻新;吴经德等;《中国建筑防水》;20111215(第23期);14-18,23页 *
卷材机械固定法防水系统在钢结构屋面中的应用;尹亚鸿;《工程质量》;20100130(第1期);26-29页 *
吴经德等.单层屋面系统质量保障三要素与某失效屋面的翻新.《中国建筑防水》.2011,(第23期),14-18,23页.
大面积柔性轻型屋面施工技术在大型建筑工程中的应用;韩建聪 等;《工业建筑》;20111231;第41卷(第5期);139-142页 *
尹亚鸿.卷材机械固定法防水系统在钢结构屋面中的应用.《工程质量》.2010,(第1期),第26-29页.
葛兆.五棵松体育馆屋面系统施工技术.《中国建筑防水》.2007,(第9期),11-13页.
西卡渗耐PVC单层防水屋面系统在旧屋面翻新工程中的应用;刘锋 等;《中国建筑防水》;20111015(第19期);24-29,40页 *
韩建聪 等.大面积柔性轻型屋面施工技术在大型建筑工程中的应用.《工业建筑》.2011,第41卷(第5期),139-142页.

Also Published As

Publication number Publication date
CN102661015A (en) 2012-09-12

Similar Documents

Publication Publication Date Title
CN102661015B (en) Single-layer waterproof prepared roofing and construction method thereof
US3909998A (en) Roof construction system
US8713864B1 (en) Skylight for metal panel roof
US20010039781A1 (en) Waterproofing method by using plastic panels
EP2422025B1 (en) Thermal isolation and facade finishing panel, its production and installation processes
US4619100A (en) Method for fabricating a water impervious roof membrane
CA2896599A1 (en) Sustainable energy efficient roof system
WO2017023668A1 (en) Magnetically attached building composite
US3914916A (en) Roof construction system
US4706432A (en) Air vapor securement closure for a membrane roofing system
US11933051B2 (en) Rolled roof standing seam system and method of construction
CN202596044U (en) Single-layer waterproof roll roofing
US20050011155A1 (en) Composite water-resistant panels
CN102587598A (en) Split mounting type heat-insulation and waterproof roof structure
KR100496627B1 (en) Complex waterproof layer construction method having improved waterproof layer adhereing method
AU2009213882B2 (en) Building roof system
CN212689251U (en) Heat preservation corrugated tile pitched roof and gable connection node structure
CN104005503A (en) Plane roof modularized structure
US20060037280A1 (en) Metal roof system
JPH0735955Y2 (en) Insulation and waterproof device for thatched roof
CN212984379U (en) Heat preservation pitched roof ventilation ridge connection structure
JPH10306519A (en) Heat insulating roof and heat insulating wall
CN221168519U (en) Ultra-low energy consumption assembled composite floor board
CN219491510U (en) Assembled integrated roof structure
GB2508650A (en) Insulated flashing construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant