CN109322412A - Waterproof roll is mechanically fixed construction technology - Google Patents

Waterproof roll is mechanically fixed construction technology Download PDF

Info

Publication number
CN109322412A
CN109322412A CN201811198349.5A CN201811198349A CN109322412A CN 109322412 A CN109322412 A CN 109322412A CN 201811198349 A CN201811198349 A CN 201811198349A CN 109322412 A CN109322412 A CN 109322412A
Authority
CN
China
Prior art keywords
waterproof roll
insulation board
barrier layer
vapor barrier
waterproof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201811198349.5A
Other languages
Chinese (zh)
Inventor
孙军
杨泓斌
黄万禧
刘博�
翟皓月
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Bozhilin Robot Co Ltd
Original Assignee
Building Dream High Tech Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Building Dream High Tech Construction Co Ltd filed Critical Building Dream High Tech Construction Co Ltd
Priority to CN201811198349.5A priority Critical patent/CN109322412A/en
Publication of CN109322412A publication Critical patent/CN109322412A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/665Sheets or foils impervious to water and water vapor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D5/00Roof covering by making use of flexible material, e.g. supplied in roll form
    • E04D5/10Roof covering by making use of flexible material, e.g. supplied in roll form by making use of compounded or laminated materials, e.g. metal foils or plastic films coated with bitumen
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0009PE
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Building Environments (AREA)

Abstract

The present invention proposes that waterproof roll is mechanically fixed construction technology, comprising the following steps: base cleaning is laid with polyethylene film vapor barrier layer, is laid with heat insulation layer, squeegees, the processing of laying water-proof coiled material and primary pressing processing, secondary pressing processing, the fixation of waterproof roll, the overlap joint of waterproof roll and joint strengthening;The present invention using the method for using pressure roller to be flattened while vacuumizing by the way that the closure between polyethylene film vapor barrier layer and base can be improved when being laid with polyethylene film vapor barrier layer, by using the dry method of high wind to substrate surface advertise drying can the moisture in the concrete structure hole to base be dried, improve the drying property of base, to improve between polyethylene film vapor barrier layer and base every vapour effect, waterproof effect is more preferable, improve the waterproofness after waterproof roll is fixed to greatest extent under conditions of not improving larger cost, and the stability maintenance of waterproof roll on construction ground is high.

Description

Waterproof roll is mechanically fixed construction technology
Technical field
The present invention relates to construction engineering technical fields more particularly to waterproof roll to be mechanically fixed construction technology.
Background technique
Waterproof roll is mainly used for construction wall, roofing and tunnel, highway, refuse landfill etc., plays and resists The rollable flexible building material product at web-like of one kind of extraneous rainwater, underground water leakage, as between engineering foundation and building Ne-leakage connection, is the first barrier of entire engineering waterproofing, plays a crucial role to entire engineering.
Waterproof roll generally can be all fixed anti-using the method for being mechanically fixed construction in existing waterproof construction engineering Water coiled material, but existing waterproof roll is mechanically fixed waterproof roll in construction method still will appear that fixed inadequate labor is solid to ask Topic, the waterproof roll after laying are easy to appear alice problem, if largely waterproof roll is fixed excessively using fixing glue Fixation hole can then destroy the waterproof performance of waterproof roll, be likely to result in seepage problem, and close between vapor barrier layer and base Conjunction property is not good enough, is still easy to appear seepage problem, laying of the waterproof roll in heat insulation layer as fixing piece with And the problem that the problem of setting-up piece causes closing seam inadequate, directly affect the waterproof performance of waterproof roll.Therefore, originally Invention proposes that waterproof roll is mechanically fixed construction technology, to solve shortcoming in the prior art.
Summary of the invention
In view of the above-mentioned problems, the present invention is proposed by using one side to vacuumize when being laid with polyethylene film vapor barrier layer The closure between polyethylene film vapor barrier layer and base can be improved using the method that pressure roller is flattened on one side, by using The dry method of high wind to substrate surface advertise drying can the moisture in the concrete structure hole to base be dried, Improve the drying property of base, thus improve between polyethylene film vapor barrier layer and base every vapour effect, waterproof effect is more It is good, improve the waterproofness after waterproof roll is fixed, and waterproof roll to greatest extent under conditions of not improving larger cost The stability maintenance of material on construction ground is high, while applying also for the biggish construction environment of difficulty of construction.
Waterproof roll proposed by the present invention is mechanically fixed construction technology, comprising the following steps:
Step 1: cleaning base
Cleaning removal of impurities, removal surface surface dust, greasy dirt and building waste, for there is ponding are carried out to constructed substrate surface Part needs to clear up discharge ponding, guarantees that substrate surface is covered without ponding and sundries, and extra for substrate surface protrusion Concrete structure carries out cleaning removal, guarantees that substrate surface is smooth;
Step 2: it is laid with polyethylene film vapor barrier layer
Setting-out processing is carried out after base cleaning is good, determines reference line, then carries out being laid with polyethylene film vapor barrier layer, poly- second Alkene film vapor barrier layer takes sky laid process to be laid in base, will be between polyethylene film vapor barrier layer and base after laying Air extraction empties, and the lap width between adjacent polyethylene film vapor barrier layer is greater than 10 centimetres, and adjacent polyethylene film is every vapour Lap-joint between layer is bonded using butyl rubber belt, and the polyethylene film vapor barrier layer on roof-base periphery is prolonged upwards along wall Stretching laying and needing to be higher by insulating layer upper surface cannot be less than 15 centimetres;
Step 3: it is laid with heat insulation layer
Selected insulation board is laid with, heat insulation layer is formed, when laying ensures insulation board setting-up piece and protects Warm plate upper surface flushes, and the fixing piece of insulation board passes through insulation board setting-up piece and insulation board is fixed with pinned layers are held, and fixing piece needs To pass through at least 3 centimetres of base;
Step 4: it squeegees
After heat insulation layer is laid, the gap between adjacent insulation board is filled up, using waterproof squeegee glue carry out It squeegees, guarantees to squeegee glue in the gap between adjacent insulation board full of waterproof, and control waterproof and squeegee glue table on insulation board The smearing width in face is 10-15 centimetres, and waterproof glue of squeegeeing smears height in insulation board upper surface and must not be higher than insulation board upper surface 3 Millimeter.
Step 5: laying water-proof coiled material and primary pressing processing
Selected waterproof roll is cut according to construction drawing parameter request, then will cut the waterproof of size Coiled material is laid in heat insulation layer, and waterproof roll is then carried out to primary pressing processing in heat insulation layer using pressure roller;
Step 6: secondary pressing processing
Secondary pressing processing is carried out using pressure roller again after once flattening processing 0.5-1 hours in above-mentioned steps five, emphatically To the secondary pressing processing of progress at squeegee place and the insulation board setting-up piece of heat insulation layer;
Step 7: the fixation of waterproof roll
Waterproof roll is fixed after waterproof roll is completely in conjunction with heat insulation layer after secondary pressing processing, using point type Fixed method is fixed, and waterproof roll is fixed with working face is needed using screw, the fixed bit of screw is set to anti- Water coil edge extends internally 3-4 centimeters;
Step 8: the overlap joint of waterproof roll
Waterproof roll opens the isolation film on adjacent two width waterproof roll after fixing, by taking for adjacent two width waterproof roll Edge fit is bonded, and controlling is respectively positioned on fixing piece and setting-up piece below waterproof roll, the overlap joint edge lap of waterproof roll Overlap edge is welded using bonding machine after the completion;
Step 9: joint strengthening processing
According to the job specfication of waterproof roll, to the node for the construction site that waterproof roll is laid with, including yin-yang angle, deformation The receipts head of seam and waterproof roll carries out reinforcement processing.
Further improvement lies in that: it is dry using high wind in the step 1 after ponding and sundries the removal cleaning of substrate surface Dry method advertise to substrate surface 2-3 times dry, evaporates the water in substrate surface and substrate concrete structure hole Point.
Further improvement lies in that: draw lines the waterproof roll first reserved according to the sum of waterproof roll when handling in the step 2 Overlap joint hem width degree draws plane horizontal line, and the long side and short side distance of waterproof roll overlap joint hem width degree are all larger than 10 centimetres, further according to Adjacent waterproof roll takes fissure of displacement width size and draws plane ordinate, finally must stay in distance according to facade waterproof coiled material lapping seam The principle of root 60-70 centimeters draws facade ordinate.
Further improvement lies in that: following rule should be followed in polyethylene film vapor barrier layer process of deployment in the step 2: Paving must be smooth, straight, and overlapping the slot and special joint position need sufficiently to be pasted with special adhesive tape, and with roller compaction, really It protects after polyethylene film vapor barrier layer is laid with without pinprick, cavitations.
Further improvement lies in that: use empty laid process to be laid with poly- second during polyethylene film vapor barrier layer in the step 2 Alkene film vapor barrier layer first fixes polyethylene film vapor barrier layer three sides other than overlap edge after being laid with, use and take out on one side after fixed The method of vacuum extracts the air between base and polyethylene film vapor barrier layer out from overlap edge, uses pressure roller from overlap edge on one side Stile is started to flatten, then the overlap edge between adjacent polyethylene film vapor barrier layer is adhesively fixed.
Further improvement lies in that: when insulation board is appointing in rock wool board, mineral wool board or block of glass wool in the step 3 When anticipating a kind of, every piece of insulation board upper fixing element quantity is 2-4;When insulation board is extruded polystyrene board, molding styrofoam or hard bubble When any one in polyurethane sheet, then every piece of insulation board upper fixing element quantity is 4-6 when each side of insulation board is respectively less than 1.2m A, then every piece of insulation board upper fixing element quantity is 8-10 when any side of insulation board is greater than 1.2m.
Further improvement lies in that: keep waterproof roll smooth straight in waterproof roll process of deployment in the step 5, no Twisted phenomena must occur, the lap width of waterproof roll is greater than 12 centimetres, and the width for covering fixing piece is greater than 5 centimetres.
Further improvement lies in that: the secondary applied force for flattening processing is primary pressing processing applied force in the step 6 , for the secondary pressing processing at squeegee place and the insulation board setting-up piece of heat insulation layer using repeatedly light force Principle carry out secondary pressing processing, carry out 5-8 secondary pressing at squeegee place and the insulation board setting-up piece of heat insulation layer Processing, and controlling the secondary applied force for flattening processing is once flatten processing applied force 1/5.
Further improvement lies in that: when working face is profiled sheet in the step 7, screw needs to be fixed on light base steel layer On, and screw is controlled transmissive at least for 25 millimeters of base;When roofing is concrete structure, first drill screw holes are needed, then by screw Screw hole is screwed in, the depth that screw screws in screw hole should be greater than 30 millimeters.
Further improvement lies in that: the reinforcement processing at yin-yang angle is using hand-held welding rifle that yin-yang angle is small in the step 9 Piece is reinforced waterproof roll and is welded on the waterproof roll laid at yin-yang angle;The reinforcement processing of deformation joint is to fill out in deformation joint Foamed plastics is filled, and an elastic heat preserving stick is put into deformation joint, the height that elastic heat preserving stick protrudes insulation layer surface is big Reinforce waterproof roll in 2 centimetres, then by lid deformation joint small pieces are pasted on deformation joint;The receipts head of waterproof roll reinforces processing as using pressure The receipts head of the fixed waterproof roll of item, and be sealed the receipts head of waterproof roll using sealant.
The invention has the benefit that by when being laid with polyethylene film vapor barrier layer using. while being vacuumized Closure between polyethylene film vapor barrier layer and base can be improved using the method that pressure roller is flattened, by using high wind Dry method to substrate surface advertise drying can the moisture in the concrete structure hole to base be dried, improve The drying property of base, thus improve between polyethylene film vapor barrier layer and base every vapour effect, waterproof effect is more preferable, leads to It crosses and adjacent insulation board connection sealing can be improved to the processing that squeegee of the gap between insulation board adjacent in heat insulation layer, Waterproof performance is further improved, waterproof roll and insulation can be improved by carrying out secondary pressing processing to waterproof roll Bond degree between layer, the seepage of water after reducing waterproof roll rupture, improves waterproof effect, construction technique of the present invention Step is simple, improves the waterproofness after waterproof roll is fixed to greatest extent under conditions of not improving larger cost, and The stability maintenance of waterproof roll on construction ground is high, while applying also for the biggish construction environment of difficulty of construction.
Detailed description of the invention
Fig. 1 is construction flow chart of the present invention.
Specific embodiment
In order to deepen the understanding of the present invention, the present invention is further described below in conjunction with embodiment, the present embodiment For explaining only the invention, it is not intended to limit the scope of the present invention..
According to Fig. 1, the present invention proposes a kind of technical solution:
Waterproof roll is mechanically fixed construction technology, comprising the following steps:
Step 1: cleaning base
Cleaning removal of impurities, removal surface surface dust, greasy dirt and building waste, for there is ponding are carried out to constructed substrate surface Part needs to clear up discharge ponding, guarantees that substrate surface is covered without ponding and sundries, using the dry method of high wind to base's table Face carries out advertising drying 3 times, evaporates the moisture in substrate surface and substrate concrete structure hole, and for substrate surface The extra concrete structure of protrusion carries out cleaning removal, guarantees that substrate surface is smooth;
Step 2: it is laid with polyethylene film vapor barrier layer
Setting-out processing is carried out after base cleaning is good, determines reference line, the waterproof roll first reserved according to the sum of waterproof roll Overlap joint hem width degree draws plane horizontal line, and the long side and short side distance of waterproof roll overlap joint hem width degree are all larger than 10 centimetres, further according to Adjacent waterproof roll takes fissure of displacement width size and draws plane ordinate, finally must stay in distance according to facade waterproof coiled material lapping seam The principle of 65 centimeters of root draws facade ordinate, then carries out being laid with polyethylene film vapor barrier layer, polyethylene film vapor barrier layer Take sky laid process to be laid in base, using empty laid process be laid with polyethylene film vapor barrier layer during polyethylene film every Vapour layer first fixes polyethylene film vapor barrier layer three sides other than overlap edge after being laid with, use the side vacuumized on one side after fixed Method extracts the air between base and polyethylene film vapor barrier layer out from overlap edge, uses pressure roller opening stile from overlap edge on one side Beginning is flattened, and then the overlap edge between adjacent polyethylene film vapor barrier layer is adhesively fixed, adjacent polyethylene film Lap width between vapor barrier layer is 12 centimetres, and the lap-joint between adjacent polyethylene film vapor barrier layer is carried out using butyl rubber belt The polyethylene film vapor barrier layer of bonding, roof-base periphery upwardly extends laying along wall and needs to be higher by insulating layer upper surface 20 Centimetre, should follow following rule in polyethylene film vapor barrier layer process of deployment: paving must be smooth, straight, overlapping the slot and special Position of joints needs sufficiently to be pasted with special adhesive tape, and with roller compaction, it is ensured that polyethylene film vapor barrier layer be laid with after without pinprick, Cavitations;
Step 3: it is laid with heat insulation layer
Selected insulation board is laid with, heat insulation layer is formed, when laying ensures insulation board setting-up piece and protects Warm plate upper surface flushes, and the fixing piece of insulation board passes through insulation board setting-up piece and insulation board is fixed with pinned layers are held, and fixing piece needs 3 centimetres of base is passed through, when insulation board is any one in rock wool board, mineral wool board or block of glass wool, every piece of insulation board Upper fixing element quantity is 2;When insulation board is any one in extruded polystyrene board, molding styrofoam or hard-foam polyurethane plate When, then every piece of insulation board upper fixing element quantity is 4 when each side of insulation board is respectively less than 1.2m, and any side of insulation board is greater than Then every piece of insulation board upper fixing element quantity is 8 when 1.2m;
Step 4: it squeegees
After heat insulation layer is laid, the gap between adjacent insulation board is filled up, using waterproof squeegee glue carry out It squeegees, guarantees to squeegee glue in the gap between adjacent insulation board full of waterproof, and control waterproof and squeegee glue table on insulation board The smearing width in face is 15 centimetres, and waterproof glue of squeegeeing in insulation board upper surface smears height as 2 millimeters.
Step 5: laying water-proof coiled material and primary pressing processing
Selected waterproof roll is cut according to construction drawing parameter request, then will cut the waterproof of size Coiled material is laid in heat insulation layer, and waterproof roll is then carried out to primary pressing processing in heat insulation layer using pressure roller, Keep waterproof roll smooth straight in waterproof roll process of deployment, there is not allowed that twisted phenomena, the lap width of waterproof roll are 14 centimetres, the width for covering fixing piece is 6 centimetres;
Step 6: secondary pressing processing
Secondary pressing processing is carried out using pressure roller again after once flattening processing 0.5 hour in above-mentioned steps five, emphatically pair Secondary pressing processing is carried out at squeegee place and the insulation board setting-up piece of heat insulation layer, the secondary applied force for flattening processing is one It is secondary to flatten the 1/3 of processing applied force, the secondary pressing at squeegee place and the insulation board setting-up piece of heat insulation layer is handled Secondary pressing processing is carried out using the principle repeatedly gently to exert a force, is carried out at squeegee place and the insulation board setting-up piece of heat insulation layer 6 secondary pressing processing, and controlling the secondary applied force for flattening processing is once flatten processing applied force 1/5;
Step 7: the fixation of waterproof roll
Waterproof roll is fixed after waterproof roll is completely in conjunction with heat insulation layer after secondary pressing processing, using point type Fixed method is fixed, and waterproof roll is fixed with working face is needed using screw, the fixed bit of screw is set to anti- Water coil edge extends internally 4 centimeters, and when working face is profiled sheet, screw needs to be fixed on light base steel layer, and controls Screw-making penetrates 28 millimeters of base;When roofing is concrete structure, first drill screw holes are needed, then screw is screwed in into screw hole, spiral shell The depth that nail screws in screw hole is 35 millimeters;
Step 8: the overlap joint of waterproof roll
Waterproof roll opens the isolation film on adjacent two width waterproof roll after fixing, by taking for adjacent two width waterproof roll Edge fit is bonded, and controlling is respectively positioned on fixing piece and setting-up piece below waterproof roll, the overlap joint edge lap of waterproof roll Overlap edge is welded using bonding machine after the completion;
Step 9: joint strengthening processing
According to the job specfication of waterproof roll, to the node for the construction site that waterproof roll is laid with, including yin-yang angle, deformation The receipts head of seam and waterproof roll carries out reinforcement processing, and the reinforcement processing at yin-yang angle is to be added yin-yang angle small pieces using hand-held welding rifle Strong waterproof roll is welded on the waterproof roll laid at yin-yang angle;The reinforcement processing of deformation joint is steeped to fill in deformation joint Foam plastics, and an elastic heat preserving stick is put into deformation joint, the height that elastic heat preserving stick protrudes insulation layer surface is 3 centimetres, Lid deformation joint small pieces will be pasted on deformation joint again reinforce waterproof roll;It is fixed anti-using press strip that the receipts head of waterproof roll, which reinforces processing, The receipts head of water coiled material, and be sealed the receipts head of waterproof roll using sealant.
By using pressure roller to be flattened using while being vacuumized when being laid with polyethylene film vapor barrier layer The closure between polyethylene film vapor barrier layer and base can be improved in method, by using the dry method of high wind to base's table Face advertise drying can the moisture in the concrete structure hole to base be dried, improve the drying property of base, from And improve between polyethylene film vapor barrier layer and base every vapour effect, waterproof effect is more preferable, by heat insulation layer Adjacent insulation board connection sealing can be improved in the processing that squeegee of gap between adjacent insulation board, further improves waterproof Performance handles the bond degree that can be improved between waterproof roll and heat insulation layer by carrying out secondary pressing to waterproof roll, Seepage of water after reducing waterproof roll rupture, improves waterproof effect, construction technique step of the present invention is simple, is not mentioning The waterproofness after waterproof roll is fixed is improved under conditions of high larger cost to greatest extent, and waterproof roll is in construction field The stability maintenance on ground is high, while applying also for the biggish construction environment of difficulty of construction.
The basic principles, main features and advantages of the invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the above embodiments and description only describe originals of the invention Reason, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes and improvements It all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (10)

1. waterproof roll is mechanically fixed construction technology, it is characterised in that: the following steps are included:
Step 1: cleaning base
Cleaning removal of impurities, removal surface surface dust, greasy dirt and building waste, for there is the part of ponding are carried out to constructed substrate surface It needs to clear up discharge ponding, guarantees that substrate surface is covered without ponding and sundries, and the coagulation extra for substrate surface protrusion Soil structure carries out cleaning removal, guarantees that substrate surface is smooth;
Step 2: it is laid with polyethylene film vapor barrier layer
Setting-out processing is carried out after base cleaning is good, determines reference line, then carries out being laid with polyethylene film vapor barrier layer, polyethylene is thin Film vapor barrier layer takes sky laid process to be laid in base, by the air between polyethylene film vapor barrier layer and base after laying Extraction emptying, the lap width between adjacent polyethylene film vapor barrier layer are greater than 10 centimetres, adjacent polyethylene film vapor barrier layer it Between lap-joint be bonded using butyl rubber belt, the polyethylene film vapor barrier layer on roof-base periphery upwardly extends paving along wall And if needing to be higher by insulating layer upper surface and cannot be less than 15 centimetres;
Step 3: it is laid with heat insulation layer
Selected insulation board is laid with, heat insulation layer is formed, when laying ensures insulation board setting-up piece and insulation board Upper surface flushes, and the fixing piece of insulation board passes through insulation board setting-up piece and insulation board is fixed with pinned layers are held, and fixing piece needs are worn Cross at least 3 centimetres of base;
Step 4: it squeegees
After heat insulation layer is laid, the gap between adjacent insulation board is filled up, is squeegeeed using waterproof glue of squeegeeing, Guarantee to squeegee glue in the gap between adjacent insulation board full of waterproof, and control waterproof squeegee glue insulation board upper surface painting Smearing width is 10-15 centimetres, and waterproof glue of squeegeeing smears height in insulation board upper surface and must not be higher than 3 millimeters of insulation board upper surface.
Step 5: laying water-proof coiled material and primary pressing processing
Selected waterproof roll is cut according to construction drawing parameter request, then will cut the waterproof roll of size It is laid in heat insulation layer, waterproof roll is then carried out to primary pressing processing in heat insulation layer using pressure roller;
Step 6: secondary pressing processing
Secondary pressing processing is carried out using pressure roller again after once flattening processing 0.5-1 hours in above-mentioned steps five, emphatically to guarantor Secondary pressing processing is carried out at squeegee place and the insulation board setting-up piece of warm thermal insulation layer;
Step 7: the fixation of waterproof roll
Waterproof roll is fixed after waterproof roll is completely in conjunction with heat insulation layer after secondary pressing processing, is fixed using point type Method be fixed, waterproof roll is fixed with working face is needed using screw, the fixed bit of screw is set to waterproof roll Edge edge extends internally 3-4 centimeters;
Step 8: the overlap joint of waterproof roll
Waterproof roll opens the isolation film on adjacent two width waterproof roll after fixing, by the overlap edge of adjacent two width waterproof roll It is bonded, and controlling is respectively positioned on fixing piece and setting-up piece below waterproof roll, the overlap joint edge lap of waterproof roll is completed Overlap edge is welded using bonding machine afterwards;
Step 9: joint strengthening processing
According to the job specfication of waterproof roll, to the node for the construction site that waterproof roll is laid with, including yin-yang angle, deformation joint and The receipts head of waterproof roll carries out reinforcement processing.
2. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: base in the step 1 After ponding and sundries the removal cleaning on surface, advertise to substrate surface 2-3 times dry, evaporation using the dry method of high wind Fall the moisture in substrate surface and substrate concrete structure hole.
3. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: draw lines in the step 2 The waterproof roll overlap joint hem width degree first reserved according to the sum of waterproof roll when processing draws plane horizontal line, and waterproof roll overlaps hem width The long side and short side distance of degree are all larger than 10 centimetres, take fissure of displacement width size further according to adjacent waterproof roll and draw plane ordinate, Facade ordinate is finally drawn according to the principle that facade waterproof coiled material lapping seam must be stayed in apart from root 60-70 centimeters.
4. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: poly- second in the step 2 Following rule should be followed in alkene film vapor barrier layer process of deployment: paving must be smooth, straight, and overlapping the slot and special joint position need Sufficiently pasted with special adhesive tape, and with roller compaction, it is ensured that polyethylene film vapor barrier layer be laid with after without pinprick, cavitations.
5. waterproof roll according to claim 4 is mechanically fixed construction technology, it is characterised in that: used in the step 2 Polyethylene film vapor barrier layer first fixes polyethylene film every vapour during empty laid process laying polyethylene film vapor barrier layer after being laid with It is thin with polyethylene to extract base out using the method vacuumized on one side after fixed from overlap edge for layer three side other than overlap edge Air between film vapor barrier layer is flattened since overlap edge is to stile using pressure roller on one side, then that adjacent polyethylene is thin Overlap edge between film vapor barrier layer is adhesively fixed.
6. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: work as guarantor in the step 3 When warm plate is any one in rock wool board, mineral wool board or block of glass wool, every piece of insulation board upper fixing element quantity is 2-4; When insulation board is any one in extruded polystyrene board, molding styrofoam or hard-foam polyurethane plate, each side of insulation board is small Then every piece of insulation board upper fixing element quantity is 4-6 when 1.2m, then every piece of insulation board when any side of insulation board is greater than 1.2m Upper fixing element quantity is 8-10.
7. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: waterproof in the step 5 Keep waterproof roll smooth straight in coiled material process of deployment, there is not allowed that twisted phenomena, the lap width of waterproof roll is greater than 12 Centimetre, the width for covering fixing piece is greater than 5 centimetres.
8. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: secondary in the step 6 The applied force for flattening processing is the primary 1/3-1/2 for flattening processing applied force, for squeegee place and the insulation board of heat insulation layer Secondary pressing processing at setting-up piece carries out secondary pressing processing using the principle repeatedly gently to exert a force, and heat insulation layer is squeegeeed 5-8 secondary pressing processing is carried out at place and insulation board setting-up piece, and controlling the secondary applied force for flattening processing is primary pressure The 1/5 of flat processing applied force.
9. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: work in the step 7 When face is profiled sheet, screw needs to be fixed on light base steel layer, and controls screw transmissive at least for 25 millimeters of base;Roofing is When concrete structure, first drill screw holes are needed, then screw is screwed in into screw hole, the depth that screw screws in screw hole should be greater than 30 millis Rice.
10. waterproof roll according to claim 1 is mechanically fixed construction technology, it is characterised in that: negative in the step 9 The reinforcement processing of external corner is that small pieces reinforcement waterproof roll in yin-yang angle is welded on laying at yin-yang angle using hand-held welding rifle Waterproof roll on;The reinforcement processing of deformation joint is to be put into change in deformation joint filling foamed plastics, and by an elastic heat preserving stick In shape seam, the height that elastic heat preserving stick protrudes insulation layer surface is to add greater than 2 centimetres, then by lid deformation joint small pieces are pasted on deformation joint Strong waterproof roll;The head of receiving of waterproof roll is reinforced handling to fix the receipts head of waterproof roll using press strip, and will using sealant The receipts head of waterproof roll is sealed.
CN201811198349.5A 2018-10-15 2018-10-15 Waterproof roll is mechanically fixed construction technology Withdrawn CN109322412A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811198349.5A CN109322412A (en) 2018-10-15 2018-10-15 Waterproof roll is mechanically fixed construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811198349.5A CN109322412A (en) 2018-10-15 2018-10-15 Waterproof roll is mechanically fixed construction technology

Publications (1)

Publication Number Publication Date
CN109322412A true CN109322412A (en) 2019-02-12

Family

ID=65262683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811198349.5A Withdrawn CN109322412A (en) 2018-10-15 2018-10-15 Waterproof roll is mechanically fixed construction technology

Country Status (1)

Country Link
CN (1) CN109322412A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944399A (en) * 2019-04-15 2019-06-28 青岛一建集团有限公司 A kind of house roof Waterproof Construction Technique based on waterproof roll
CN111794391A (en) * 2020-07-05 2020-10-20 青岛新华友建工集团股份有限公司 Construction process for high-air-tightness deformation joint of passive house
CN113090293A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repairing and reinforcing mechanical arm equipment
CN113090292A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair reinforcement intelligent complete equipment
CN113090291A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair and reinforcement complete equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499748B1 (en) * 2004-07-29 2005-07-07 주식회사 대흥산업 Complex waterproof structure using partial insulation and a waterproofing method using the same
CN102661015A (en) * 2012-05-16 2012-09-12 中国江苏国际经济技术合作公司 Single-layer waterproof prepared roofing and construction method thereof
CN104533027A (en) * 2014-12-16 2015-04-22 贵州建工集团第五建筑工程有限责任公司 Construction method of steel structure roof waterproof and heat insulation system
CN104762999A (en) * 2015-04-16 2015-07-08 中天建设集团有限公司天津分公司 Self-adhesion coiled material underground waterproof construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499748B1 (en) * 2004-07-29 2005-07-07 주식회사 대흥산업 Complex waterproof structure using partial insulation and a waterproofing method using the same
CN102661015A (en) * 2012-05-16 2012-09-12 中国江苏国际经济技术合作公司 Single-layer waterproof prepared roofing and construction method thereof
CN104533027A (en) * 2014-12-16 2015-04-22 贵州建工集团第五建筑工程有限责任公司 Construction method of steel structure roof waterproof and heat insulation system
CN104762999A (en) * 2015-04-16 2015-07-08 中天建设集团有限公司天津分公司 Self-adhesion coiled material underground waterproof construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
徐泓: "卷材平屋面防水工程施工", 《安徽建筑》 *
杨永起: "《建筑防水施工技术》", 31 October 2015, 中国建材工业出版社 *
王作军: "单层防水卷材屋面机械固定施工技术", 《江苏建材》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944399A (en) * 2019-04-15 2019-06-28 青岛一建集团有限公司 A kind of house roof Waterproof Construction Technique based on waterproof roll
CN111794391A (en) * 2020-07-05 2020-10-20 青岛新华友建工集团股份有限公司 Construction process for high-air-tightness deformation joint of passive house
CN113090293A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repairing and reinforcing mechanical arm equipment
CN113090292A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair reinforcement intelligent complete equipment
CN113090291A (en) * 2021-04-09 2021-07-09 中铁工程服务有限公司 Shield subway tunnel segment repair and reinforcement complete equipment

Similar Documents

Publication Publication Date Title
CN109322412A (en) Waterproof roll is mechanically fixed construction technology
CN101914927B (en) Waterproof system for basement bottom board and wall surface and construction method thereof
CN109779162B (en) Passive building flat roof heat-insulating waterproof system and partition type dry operation construction method
CN101748757B (en) Construction method of bentonite waterproof blankets
CN107313342A (en) The bridging arrangement and construction method of a kind of waterproof roll
CN112081146A (en) Construction method of polymer self-adhesive film waterproof coiled material capable of being constructed in rainy season
CN102661015A (en) Single-layer waterproof prepared roofing and construction method thereof
CN106401083A (en) Roofing project system structure and construction method thereof
CN108797903B (en) Roof waterproof structure and construction process thereof
CN212224363U (en) Sloping roof flashing connection structure
CN104612254A (en) Reaction joining waterproof roll paving waterproof construction method
CN205688670U (en) A kind of roofworks system structure
CN206625375U (en) A kind of waterproof construction of building prefabrication overall assembled exterior wall transverse joint
CN112081143B (en) Anti-seepage construction method for preventing and draining combination of top plate deformation joints
CN206554291U (en) A kind of waterproof construction of building prefabrication overall assembled exterior wall vertical abutment joint
CN206124351U (en) SBS modified asphalt waterproof sheet material
CN106894450A (en) The bridging arrangement and construction method of a kind of waterproof roll
CN207004544U (en) A kind of roof deformation seam percolating water repairs structure
CN205674640U (en) A kind of macromolecule wet-laying self-adhesive asphalt waterproof coiled material
CN202596044U (en) Single-layer waterproof roll roofing
CN109736360A (en) Tunnel open excavation section waterproof construction method
CN212453367U (en) Plant roof height movement joint department and prevent root thorn connected node structure
CN208137152U (en) A kind of paving is in building arc cylinder or the waterproof roll of metope
CN204570957U (en) Vacuum thermal insulation layer for building and heat-insulation system
CN209466788U (en) A kind of impact-resistant waterproof roll

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190927

Address after: 528300 East Office Building 201-11, No. 11 Junye East Road, Beijiao Town, Shunde District, Foshan City, Guangdong Province

Applicant after: Guangdong Bozhilin Robot Co., Ltd.

Address before: 519000 -44144, 105 room 6, Baohua Road, Hengqin New District, Zhuhai, Guangdong (centralized office area)

Applicant before: Building dream high tech Construction Company Limited

WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190212