CN102635359B - Energy-saving rapid construction method for ventilating shafts of tunnels - Google Patents
Energy-saving rapid construction method for ventilating shafts of tunnels Download PDFInfo
- Publication number
- CN102635359B CN102635359B CN201210106819.7A CN201210106819A CN102635359B CN 102635359 B CN102635359 B CN 102635359B CN 201210106819 A CN201210106819 A CN 201210106819A CN 102635359 B CN102635359 B CN 102635359B
- Authority
- CN
- China
- Prior art keywords
- construction
- shaft
- wall seat
- wall
- lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 66
- 238000000034 method Methods 0.000 claims abstract description 25
- 238000009412 basement excavation Methods 0.000 claims abstract description 7
- 238000005728 strengthening Methods 0.000 claims abstract description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 18
- 239000010959 steel Substances 0.000 claims description 18
- 239000004567 concrete Substances 0.000 claims description 13
- 238000009423 ventilation Methods 0.000 claims description 12
- 238000012423 maintenance Methods 0.000 claims description 9
- 238000004134 energy conservation Methods 0.000 claims description 8
- 230000003014 reinforcing effect Effects 0.000 claims description 7
- 238000004880 explosion Methods 0.000 claims description 6
- 210000003205 muscle Anatomy 0.000 claims description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 5
- 238000004140 cleaning Methods 0.000 claims description 3
- 238000005259 measurement Methods 0.000 claims description 3
- 238000012545 processing Methods 0.000 claims description 3
- 230000001360 synchronised effect Effects 0.000 abstract description 3
- 238000005422 blasting Methods 0.000 abstract description 2
- 238000005553 drilling Methods 0.000 abstract 1
- 238000005265 energy consumption Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000003449 preventive effect Effects 0.000 description 3
- 239000011435 rock Substances 0.000 description 3
- 239000011150 reinforced concrete Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 238000004378 air conditioning Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 125000004122 cyclic group Chemical group 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000009792 diffusion process Methods 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 239000002360 explosive Substances 0.000 description 1
- 239000003500 flue dust Substances 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 239000003517 fume Substances 0.000 description 1
- 238000007654 immersion Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
- 239000000779 smoke Substances 0.000 description 1
- 238000004162 soil erosion Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention specifically relates to an energy-saving rapid construction method for ventilating shafts of tunnels, which solves the problem that shortcomings exist in the construction on the existing ventilating shafts of tunnels by using a downward driving method. The method comprises the following steps of: a, measuring the position of a positioned shaft; b, carrying out strengthening construction on the geologic status of a shaft mouth, meanwhile, excavating a vertical ballast-discharge hole downwards from the shaft mouth, and carrying out excavation from the front hole of a tunnel to the position of the shaft until the excavating position meets the vertical ballast-discharge hole; c, carrying out shaft excavation by using a drilling and blasting combined method; d, when the shaft is excavated to a certain depth, carrying out secondary lining construction on the upper part of the shaft, wherein the secondary lining construction and the shaft construction are performed synchronously; and e, installing a shaft ventilating device. According to the invention, through adopting a mode of carrying out equidirectional and synchronous operation flow on the shaft excavation construction and the shaft secondary-lining construction, the method has the significant advantages of small safety risk, high construction speed, high working efficiency, energy saving, consumption reduction, easiness in construction drainage in shafts, low comprehensive construction cost, and capabilities of reducing the equipment investment, saving the occupied land and the cost of ecological restoration engineering, and obviously improving the construction work environment.
Description
Technical field
The present invention relates to the construction technology of tunnel ventilation vertical shaft, be specially the energy-conservation rapid constructing method of a kind of tunnel ventilation vertical shaft.
Background technology
In speedway, Large Railway Tunnel hole operation stage, air quality declines obviously, and design adopts airshaft (diameter is generally at 6~10m) to change air in hole, reaches the object of improving air quality.
At present, engineering circles adopts positive its sequence of construction of well method to be more: bore quick-fried driving, borehole wall temporary lining from top to bottom; Behind the extremely positive hole of driving, then carry out the borehole wall and median septum reinforced concrete lining layer from bottom to top.
At present, the driving method adopting is mostly: boring pops digs, temporary lining, vertical lifting muck removal, abandon quarrel nearby, the preventive works that prevent erosion be set, spoil disposal area recovery natural vegetation afforestation project, this method is applicable to major diameter tunnel and other underground construction To Construction of Silo of various geology.
Adopt positive well method construction to have following drawback:
1, bore quick-fried weak effect, driving speed is slow, every cyclic advance is about 1.0m only;
2, all quarrels of abandoning all need be promoted to well head by shaft bottom, and energy consumption is large, the muck removal time is long;
3, promote muck removal and very easily fall piece, underground construction personnel are caused to the danger side of body;
4, each inter process disturb large, synchronous continuous productive process, long construction period;
5, after vertical shaft explosion, flue dust diffusion is slow, causes the long-time pause of construction;
Once 6, meet underground water in vertical shaft, the expense of drawing water is high, have softening country rock to cause the security risk of caving in;
7, need spoil disposal area be set separately, soil erosion preventive works be set and recover the afforestation project of vegetation, natural environment is had a certain impact;
8, integrated construction cost is high, energy consumption is high, potential safety hazard is many.
Summary of the invention
The present invention adopts positive well method construction to have the problem of above-mentioned weak point in order to solve existing tunnel airshaft, provides a kind of tunnel ventilation vertical shaft energy-conservation rapid constructing method.
The present invention adopts following technical scheme to realize: the energy-conservation rapid constructing method of tunnel ventilation vertical shaft, and step is as follows: a, measurement and positioning Shaft Location; B, pit mouth geology is carried out to strengthening construction, meanwhile, from pit mouth excavation vertical deslagging hole downwards, and from tunnel positive hole to Shaft Location driving to communicating with vertical deslagging hole; The method that c, employing boring are combined with explosion is carried out shaft sinking; D, when shaft sinking reaches after certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions are synchronizeed and carried out with To Construction of Silo; E, installation vertical shaft ventilation equipment.
In work progress, pit mouth geology is reinforced to (fore shaft) and guarantee that well head is firm, be convenient to installation, the debugging of ground derrick and crane gear, with the construction synchronization job of vertical deslagging hole, improved efficiency of construction; Adopt method that boring is combined with explosion to carry out To Construction of Silo and accelerated construction speed, from vertical deslagging hole muck removal, energy-conservation and do not affect the two lining constructions of vertical shaft top, overcome existing tunnel airshaft and adopted positive well method to construct to have the problem of above-mentioned weak point.
The concrete steps that two lining constructions are carried out on vertical shaft top are as follows: a, carry out wall seat cleaning reinforce by construction hanging scaffold; B, also fixed at the latter half mounting shaft font steel I-beam of wall seat; C, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D, the assembly wall seat top borehole wall and median septum side form, and firm supporting; E, cast wall seat the first half and the borehole wall two lining and median septum concrete the maintenances of wall seat top; F, remove groined type steel I-beam and be arranged on the latter half of next wall seat fixed; G, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; H, the next wall seat top borehole wall and median septum side form are installed, and firm supporting; I, pour into a mould next wall seat the first half, the next wall seat top borehole wall and two lining and median septum concrete the maintenances of wall seat the latter half; J, the horizontal joint of wall seat the first half, the latter half is carried out to anti-water seal processing, circulation construction.
This two linings construction method stable operation performance is high, and synchronizes and carry out with To Construction of Silo, and when guaranteeing security performance, efficiency of construction significantly promotes, and energy-saving effect is obvious simultaneously, has simplified working procedure.
Beneficial effect of the present invention is as follows:
1, adopt the conventional rigs such as Churn drill to implement boring, form vertical deslagging hole, quicker, economical compared with raise boring machine;
2, utilize vertical deslagging hole, solved deslagging problem, change original vertical lifting muck removal in positive hole horizontal muck removal, save a large amount of daily energy consumptions and large-scale lifting means and purchase maintenance cost, and improve positive hole, tunnel muck removal utilization rate of equipment and installations;
3, the maintenance cost of purchasing of daily vertical drainage energy consumption and pumping equipment, with vertical drainage function, is saved in vertical deslagging hole;
4, thoroughly eliminate lifting muck removal and fallen the potential safety hazards such as piece is hurted sb.'s feelings, ponding immersion country rock borehole well instability;
5, downward muck removal fast, shortens the muck removal time, can increase driving cycle-index, improves efficiency of construction;
6, realize borehole wall concrete lining follow-up, shorten Sidewall Surrounding Rock open-assembly time, can suitably reduce temporary lining grade, save temporary lining expense, shorten total time of construction;
7, the vertical deslagging of preboring hole provides free face for the follow-up chambering of vertical shaft, has improved demolition effect, reduces perforating explosion energy consumption, saves explosive consumption, has alleviated blasting fume and pollute;
8, vertical deslagging hole and positive hole, tunnel connect in advance, for vertical shaft and the smoke evacuation of positive hole provide condition, have improved vertical shaft and positive hole construction environment, have reduced vertical shaft and positive hole construction ventilation cost;
9, needn't spoil disposal area be set specially and quarrel sidewalk is abandoned in build for vertical shaft, save in a large number and take up an area; Save spoil disposal area preventive works and Ecological Restoration Works expense;
The present invention changes former positive well method driving and the reverse form of construction work of lining cutting substep into shaft sinking construction and vertical shaft two linings are constructed in the same way, synchronous flow system, there is security risk little, speed of application is fast, work efficiency is high, energy-saving and cost-reducing, reduce equipment investment, save spoil disposal area and abandon quarrel sidewalk and take up an area and Ecological Restoration Works expense, construction operation environment obviously improves, in vertical shaft, construction drainage is easy, the low remarkable advantage that waits of construction integrated cost, be applicable to degree of depth 150m with interior highway tunnel ventilation vertical shaft, railway tunnel airshaft, water conservancy project construction of Diversion Tunnels, also can be applicable to the similar construction of the latter half 150m scope compared with deep shaft, two lining technology also can be applicable to the field of the energy-conservation vertical shaft of building air conditioning simultaneously.
The specific embodiment
The energy-conservation rapid constructing method of tunnel ventilation vertical shaft, step is as follows: a, measurement and positioning Shaft Location; B, pit mouth geology is carried out to strengthening construction, meanwhile, from pit mouth excavation vertical deslagging hole downwards, and from tunnel positive hole to Shaft Location driving to communicating with vertical deslagging hole; The method that c, employing boring are combined with explosion is carried out shaft sinking; D, when shaft sinking is after certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions are synchronizeed and carried out with To Construction of Silo; E, installation vertical shaft ventilation equipment.
The concrete steps that two lining constructions are carried out on vertical shaft top are as follows: a, carry out wall seat cleaning reinforce by construction hanging scaffold; B, also fixed at the latter half mounting shaft font steel I-beam of wall seat; C, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D, the assembly wall seat top borehole wall and median septum side form, and firm supporting; E, cast wall seat the first half and the borehole wall two lining and median septum concrete the maintenances of wall seat top; F, remove groined type steel I-beam and be arranged on the latter half of next wall seat fixed; G, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; H, the next wall seat top borehole wall and median septum side form are installed, and firm supporting; I, pour into a mould next wall seat the first half, the next wall seat top borehole wall and two lining and median septum concrete the maintenances of wall seat the latter half; J, the horizontal joint of wall seat the first half, the latter half is carried out to anti-water seal processing, circulation construction.
In specific implementation process, pit mouth geology is reinforced to (fore shaft) construction, and reinforced concrete construction is carried out to pit mouth surrounding after loosening the soil in the earth's surface that needs first artificial cooperative mechanical to excavate certain depth (5-8m), when concrete reaches after some strength, with soil, the peripheral backfill of pit mouth is closely knit; In To Construction of Silo, by boring, powder charge, detonate, muck removal, the clear end, wall seat excavation, borehole wall combined bolting and shotcrete step circulate driving downwards.
On the wall seat apart from driving face certain distance, concrete lining support system is installed, carries out the operations such as assembling reinforcement, rigging, fluid concrete, form removal maintenance, joint treatment.
Claims (1)
1. the energy-conservation rapid constructing method of tunnel ventilation vertical shaft, is characterized in that: step is as follows: a, measurement and positioning Shaft Location; B, pit mouth geology is carried out to strengthening construction, meanwhile, from pit mouth excavation vertical deslagging hole downwards, and from tunnel positive hole to Shaft Location driving to communicating with vertical deslagging hole; The method that c, employing boring are combined with explosion is carried out shaft sinking; D, when shaft sinking is after certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions synchronize and carry out with To Construction of Silo, the concrete steps that two lining constructions are carried out on vertical shaft top are as follows: d1, by construction hanging scaffold, carry out wall seat cleaning reinforcing; D2, also fixed at the latter half mounting shaft font steel I-beam of wall seat; D3, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D4, the assembly wall seat top borehole wall and median septum side form, and firm supporting; D5, cast wall seat the first half and the borehole wall two lining and median septum concrete the maintenances of wall seat top; D6, remove groined type steel I-beam and be arranged on the latter half of next wall seat fixed; D7, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; D8, the next wall seat top borehole wall and median septum side form are installed, and firm supporting; D9, pour into a mould next wall seat the first half, the next wall seat top borehole wall and two lining and median septum concrete the maintenances of wall seat the latter half; D10, the horizontal joint of wall seat the first half, the latter half is carried out to anti-water seal processing, circulation construction; E, installation vertical shaft ventilation equipment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210106819.7A CN102635359B (en) | 2012-04-13 | 2012-04-13 | Energy-saving rapid construction method for ventilating shafts of tunnels |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210106819.7A CN102635359B (en) | 2012-04-13 | 2012-04-13 | Energy-saving rapid construction method for ventilating shafts of tunnels |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102635359A CN102635359A (en) | 2012-08-15 |
CN102635359B true CN102635359B (en) | 2014-04-09 |
Family
ID=46619920
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210106819.7A Expired - Fee Related CN102635359B (en) | 2012-04-13 | 2012-04-13 | Energy-saving rapid construction method for ventilating shafts of tunnels |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102635359B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102900367A (en) * | 2012-11-01 | 2013-01-30 | 陕西彬长文家坡矿业有限公司 | Methods for drilling in cylinder of semi-finished vertical shaft and discharging water from cylinder of gangue-removal vertical shaft |
CN104806249B (en) * | 2015-04-03 | 2016-05-04 | 核工业井巷建设公司 | A kind of short vertical shaft pilot shaft tunneling construction method |
CN104989409B (en) * | 2015-06-17 | 2018-04-27 | 中铁十六局集团第五工程有限公司 | A kind of full face tunneling method after vertical shaft light section pore-forming |
CN109826654A (en) * | 2019-03-12 | 2019-05-31 | 四川省交通运输厅公路规划勘察设计研究院 | Tunnel ventilation well supporting construction and its construction method |
CN112943257B (en) * | 2021-01-25 | 2022-10-14 | 中铁十四局集团建筑工程有限公司 | Method for treating reverse borehole collapse of deep large vertical shaft |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3528278A1 (en) * | 1985-08-07 | 1987-02-19 | Gesteins & Tiefbau Gmbh | Drilling apparatus for shafts |
JPH02304196A (en) * | 1989-05-16 | 1990-12-17 | Maeda Corp | Shaft excavation construction method |
CN101082217A (en) * | 2006-06-02 | 2007-12-05 | 韩国石油公社 | Excavation method of vertical hole |
CN101906972A (en) * | 2010-07-23 | 2010-12-08 | 中铁十七局集团第四工程有限公司 | Method for synchronously constructing second shaft wall lining and intermediate baffle of vertical shaft |
CN102305075A (en) * | 2011-06-28 | 2012-01-04 | 中国水利水电第五工程局有限公司 | Vertical shaft construction method under unfavorable geological condition |
-
2012
- 2012-04-13 CN CN201210106819.7A patent/CN102635359B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3528278A1 (en) * | 1985-08-07 | 1987-02-19 | Gesteins & Tiefbau Gmbh | Drilling apparatus for shafts |
JPH02304196A (en) * | 1989-05-16 | 1990-12-17 | Maeda Corp | Shaft excavation construction method |
CN101082217A (en) * | 2006-06-02 | 2007-12-05 | 韩国石油公社 | Excavation method of vertical hole |
CN101906972A (en) * | 2010-07-23 | 2010-12-08 | 中铁十七局集团第四工程有限公司 | Method for synchronously constructing second shaft wall lining and intermediate baffle of vertical shaft |
CN102305075A (en) * | 2011-06-28 | 2012-01-04 | 中国水利水电第五工程局有限公司 | Vertical shaft construction method under unfavorable geological condition |
Also Published As
Publication number | Publication date |
---|---|
CN102635359A (en) | 2012-08-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110821503B (en) | Construction method for main body of ultra-deep shield section air shaft after tunnel advance | |
CN103615250B (en) | The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes | |
CN102268993B (en) | Method for excavating tunnel in high liquid limit soil | |
CN102635359B (en) | Energy-saving rapid construction method for ventilating shafts of tunnels | |
CN103835661B (en) | A kind of local excavation pre support mine shaft rising boring technique | |
CN103835648B (en) | One improves rock stratum performance mine shaft rising boring technique by surface grout injection | |
CN103469817B (en) | Existing subway station main structure broadening construction method | |
CN103835651B (en) | A kind of single hole directional drilling local slip casting mine shaft rising boring technique | |
CN109736827B (en) | Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing | |
CN105298507A (en) | Underground pipe gallery construction method of machine performing open excavation on upper portion and tunneling on lower portion | |
CN104747075A (en) | Anti-collapsing drilling method for grout spraying of soft coal seam | |
CN103939135B (en) | A kind of fully-mechanized mining working removes frame passage rapid constructing method | |
CN101694159A (en) | Technology for rapidly constructing air shaft under chill condition and process for sinking vertical shaft pit shaft | |
CN104389618A (en) | Method for constructing multiple-arch tunnel hole body large room-free pipe shed support | |
CN111075478A (en) | Pre-grouting reinforcement process for ground construction of broken belt of excavation working face structure | |
CN102678126A (en) | Method for excavating mountain tunnels in weak surrounding rock-fractured zones or shallow covered slope sections | |
CN104533425B (en) | Vertical shaft overall pouring section walling crib and vertical shaft overall pouring section walling crib construction method | |
CN205638458U (en) | Accelerate construction structures of broken system construction speed of underground swift current | |
CN212985227U (en) | Underground shared cavern structure for dismounting TBM | |
CN102155227B (en) | Vertical direction continuous mining method and application in whole ore body continuous mining | |
CN204002832U (en) | A kind of shield tunnel portal structure | |
CN103775102B (en) | Hidden hole drilling is stablized free face with pipe pore-forming backfill concrete and is processed landslide construction method | |
CN101487394B (en) | External slip-casting pipe type tunnel shielding portal construction method | |
CN105545330A (en) | Water prevention and control process in construction of metallurgical underground mining ore pass fragmenting system | |
CN105545315A (en) | Normal pressure tool replacing method for reinforcing excavation face soil layer in shield tunnel construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140409 |