CN102619524A - 一种煤矿岩巷小断面扩刷成大断面硐室施工方法 - Google Patents

一种煤矿岩巷小断面扩刷成大断面硐室施工方法 Download PDF

Info

Publication number
CN102619524A
CN102619524A CN2012100787554A CN201210078755A CN102619524A CN 102619524 A CN102619524 A CN 102619524A CN 2012100787554 A CN2012100787554 A CN 2012100787554A CN 201210078755 A CN201210078755 A CN 201210078755A CN 102619524 A CN102619524 A CN 102619524A
Authority
CN
China
Prior art keywords
chamber
section
brushing
construction
coal mine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100787554A
Other languages
English (en)
Other versions
CN102619524B (zh
Inventor
陈鹏
彭继勇
殷召元
罗昆
张宏忠
孙传锦
解波
刘洪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Li Juju
Original Assignee
Anhui Hengyuan Coal Industry And Electricity Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Hengyuan Coal Industry And Electricity Power Co Ltd filed Critical Anhui Hengyuan Coal Industry And Electricity Power Co Ltd
Priority to CN201210078755.4A priority Critical patent/CN102619524B/zh
Publication of CN102619524A publication Critical patent/CN102619524A/zh
Application granted granted Critical
Publication of CN102619524B publication Critical patent/CN102619524B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明涉及一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,包括采用在岩巷顶部、硐室设计起始位置的前方,与纵向倾斜70。打眼放炮、分层挑顶、耙矸机出货,边喷浆、刷帮等步骤。本发明的施工方法优化了施工工序,大大提高了生产效率;而且减少了工人的劳动强度,提高了施工时的安全系数。本发明适应性强,在现有的小断面岩巷的基础上就可心扩刷成大断面的硐室,既简约了时间,又避免了资源浪费。

Description

一种煤矿岩巷小断面扩刷成大断面硐室施工方法
技术领域
本发明涉及煤矿井下硐室的施工方法,具体涉及煤矿岩巷小断面扩刷成大断面硐室的施工方法。 
背景技术
目前在矿山井下等作业领域,硐室得到了越来越广泛的应用,用于安装各种设备、机器,存放材料和工具,或做工人休息室、避难室等。由于硐室是在地下进行开凿和建造的断面较大或长度较短的空间构筑物,常处于复杂的地质条件,会受到天然形成的地质状态如地应力、地质岩层、地下水等因素和人工开挖操作等因素影响。根据不同的硐室特点进行不同的掘进施工方法,如传统的大硐室的挖掘采用全断面开挖方法来进行施工,即是按照硐室的掘进断面一次钻眼、分次爆破,并利用矸石堆作为打上面的炮眼和拱顶锚杆眼及安装锚杆的工作台,然后接着进行掘进和排渣,最终达到预定的设计。这种施工方法虽有利于提高机械化施工程度,但爆破与爆破后的烟尘给工人造成来严重的安全隐患,而且排渣工作必须人工来进行,进度慢。 
随着高产高效矿井建设步伐的加快,煤矿井下大断面硐室的功能越来越多,更多的是将现有的煤矿岩巷小断面扩刷成大断面硐室,目前主要施工方法是分层施工,先上层后下层,每层都是通过打眼放炮施工,然后由人工出上层矸石。这种施工方法受工艺复杂和出矸系统影响,效率非常低下,正常情况下施工30米长硐室,需要近40天时间才能完成,并给施工带来很多安全隐患。 
现有技术报道都是关于硐室的施工方法,而没有涉及到对煤矿岩巷小断面扩刷成大断面硐室的施工方法。如CN200910227886.2专利是对煤矿大断面硐室施工方法的介绍,利用上层为矸石层、下层为煤层的特殊地质条件进行炮掘与综掘机割煤相结合的方法来达到对硐室的施工,但此方法需要对大断面硐室的选址有特殊的要求,没有普遍适用性。CN200910237883.7采用的是先是斜坡小断面掘进,再台阶施工,其施工进度比较慢,不利于高产高效矿井的建设。 
发明内容
本发明目的就是解决上述问题,提供一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,目的是为了提高大断面硐室的施工效率,并保障施工安全,具有普遍适用的施工方法。 
为了实现上述发明目的,本发明采用以下技术方案: 
一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,采用如下施工步骤: 
(1)在岩巷顶部、硐室设计起始位置的前方打眼放炮; 
(2)继续上述步骤(1)成扇形向两帮方向打眼放炮,锚网支护,直至硐室的设计宽度。 
(3)对已放炮的地方进行分层挑顶,从下往上挑顶,及时采取锚网支护,直至预定高度; 
(4)沿着硐室方向,进行全断面施工;按照硐室顶部断面轮廓,挑顶直到硐室设计深度; 
(5)将矸石用耙矸机出货,一边出货一边喷浆; 
(6)临时支护,在巷道两帮打眼,待左右帮刷够宽度后,采用打水平进尺眼放炮刷帮直至硐室设计尺寸; 
(7)打帮部锚杆,然后进行一次性喷浆。
本发明的进一步优化方案,上述步骤(1)中打眼放炮的位置是在设计硐室起始位置的前面1-3米、与纵向倾斜70°角处。 
上述步骤(3)中挑顶分二层,先挑下面第一层,接着向前上方挑第二层至设计高度。 
上述步骤(6)中所述的刷帮是自硐室起始位置前1-3米处沿硐室方向依次刷帮。 
上述步骤(6)中所述的巷道两帮打眼是指按照与巷道外扎夹角30-50°在巷道两帮打眼;左帮眼深2-3米,右帮眼深1-2米;所述的水平进尺眼放炮,炮眼深度1-2米。 
在大量的煤矿地下工程实践中,人们普遍认识到其核心问题是开挖与支护,即如何开挖才能更有利于硐室的稳定安全和便于维护;若要支护,又怎样支护才能更有效地保证硐室稳定和便于开挖。这两个因素决定了在硐室施工中,需要对硐室的特点采取对应的施工方法,既有利于施工的安全,又有利于硐的支护与稳定。 
本发明是在已有岩巷小断面的基础上,进行充分利用然后扩刷到大断面硐室,本发明的施工方法是先在设计起始位置提前1-3地方按与水平角度斜上方成70°夹角在巷道顶部打眼放炮,使断面形成一个斜坡,避免了垂直打眼时的安全威胁,即有利于出矸,又便于工人施工。然后进行分层挑顶,挑到设计高度后,工作人员站在矸石上采用一次打眼全断面一次爆破的方法施工,减少了分层施工时的放炮次数,由于采用一次爆破,人员无需分层施工,减 少了因在上层施工下层整体塌落的危险,提高了施工时的安全系数。采用耙矸机出货,边出货边喷浆,无需人工出货,减少了分层施工时的放炮次数,减少了劳动强度,施工时全部采用耙矸机出货,提高了劳动生产率,减轻了工人的劳动强度。整个方法优化了施工工序,进一步提高了生产效率,具体施工30m硐室,只需25天就能完成,比以往的施工方法提前15天完成。 
本发明的有益效果: 
1、在巷道顶部倾斜70°打眼放炮,使断面形成一个斜坡,避免了垂直打眼时的安全威胁,即有利于出矸,又便于工人施工。 
2、采用一次打眼全断面一次爆破的方法施工,减少了分层施工时的放炮次数,提高了施工时的安全系数;施工时全部采用耙矸机出货,减轻了工人的劳动强度,提高了劳动生产率。 
3、本发明的施工方法优化了施工工序,进一步提高了生产效率,减轻了工人的劳动强度。 
附图说明
下面结合附图和具体实施方式对本发明作进一步的详细说明。 
图1是本发明硐室的剖视图; 
图2是硐室的主视图; 
图中:1-现有的岩巷,2-硐室顶部,3-第一层,4-第二层,5-与纵向夹角,6-硐室帮部。 
具体实施方式
下面结合具体实施例来对本发明做进一步的说明,这些实施例并非仅限于本发明的保护范围,所有基于本发明的基本思想而进行修改或变动的都属于本发明的保护范围内。 
实施例一: 
图1所示的是本发明硐室的剖视图,即硐室顶部队2的施工步骤,施工时,在岩巷1顶部、硐室设计起始位置的前方2米处,按与纵向倾斜夹角5为70°方向来打眼放炮。然后进行分二层挑顶,从下往上挑顶,先挑下面的第一层,进行顶板锚网支护后,接着挑第二层,再进行顶板锚网支护,至预定位置时达到挑顶的设计高度。 
实施例二: 
图2是硐室的主视图,即施工后硐室的形状,图中阴影部分为要施工的部分。 
在现有岩巷1的基础上进行扩刷成大断面硐室,先对硐室的顶部2进行打眼放炮,再分层顶,最后喷浆支护;再对硐室的帮部6沿硐室方向依次刷帮、喷浆支护,最后形成所设计的大断面硐室。 
实施例三: 
以钱营煤矿3211风巷为基础扩刷成大断面硐室为例,解决钱营煤矿3211工作面安装起吊综采支架的行车的需要,在3211风巷联巷硐室内施工一组装硐室。设计的硐室的毛断面达到:宽7.6m,高8.093m,断面积61.5m2;净断面为宽7.4m,高7.993,断面积59.15m2,施工长度30m。 
岩巷小断面扩刷成大断面硐室的施工方法,该方法是采用如下的施工方法来实现的: 
(1)在岩巷顶部、硐室设计起始位置的前方2米处,按与纵向倾斜70°方向打眼放炮,炮后进行锚网支护; 
(2)继续上述步骤(1)成扇形向两帮方向打眼放炮,锚网支护,直至硐室的设计宽度。 
(3)对已放炮的地方进行分二层挑顶,从下往上挑顶,先挑下层顶,然后进行顶板锚网支护,接着挑上一层,再进行顶板锚网支护,至预定位置时达到挑顶的设计高度。如果达到预定位置时未达到设计高度,可以采用放小炮的方式进行刷大挑高; 
(4)沿着硐室方向,敲帮问顶找净活矸危岩,挂好合格正规的防片帮网后,工作人员再站在矸石上钻一次眼,进行全断面一次爆破的施工方法进行施工,按照硐室顶部断面轮廓进行挑顶直到硐室设计深度; 
(5)将矸石用耙矸机进行出货,耙矸机一边出货,另一边对硐室顶部进行喷浆支护,即以砂石料、水泥和速凝剂等材料搅拌而形成,借助混凝土喷射机使混合物在压缩空气的作用下,通过软管输送到喷嘴处,在喷嘴处加水混合并形成料束,高速喷敷在围岩表面上,在围岩表面形成一层混凝土层,与围岩自承能力相结合,实现巷道支护的支护形式,并能封闭围岩使之不与不利环境接触,减缓其风化或破坏,达到支护硐室围岩的作用。 
(6)自硐室起始位置前2米处沿硐室方向依次刷帮。先进行敲帮问顶,设临时支护,按照与巷道外扎夹角40°在巷道两帮打眼,左帮眼深2400mm,拨帮后左帮刷宽2050mm,右帮眼深1400mm,拨帮后右帮刷宽950mm。待左右帮刷够尺寸后,采用打水平进尺眼,炮眼深度1600mm,装药放炮后,敲帮问顶,防止危险。 
(7)等将帮部刷够尺寸后打好帮部锚杆,再用耙矸机出货,最后对硐室两帮围岩表面进行一次性喷浆支护。 
最后建成宽7.4m,高7.993m,断面积59.15m2,长度为30m的大断面硐室,费时共计划25天,比以往的施工方法提前15天完成。并解决了钱营煤矿3211工作面安装起吊综采支架的行车的需要。 
本发明的施工方法优化了施工工序,大大提高了生产效率;而且减少了工人的劳动强度,提高了施工时的安全系数。本发明适应性强,在现有的小断面岩巷的基础上就可心扩刷成大断面的硐室,既简约了时间,又避免了资源浪费。 

Claims (5)

1.一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,其特征在于:该方法采用如下施工步骤:
(1)在岩巷顶部、硐室设计起始位置的前方打眼放炮;
(2)继续上述步骤(1)成扇形向两帮方向打眼放炮,锚网支护,直至硐室的设计宽度。
(3)对已放炮的地方进行分层挑顶,从下往上挑顶,及时采取锚网支护,直至预定高度;
(4)沿着硐室方向,进行全断面施工;按照硐室顶部断面轮廓,挑顶直到硐室设计深度;
(5)将矸石用耙矸机出货,一边出货一边喷浆;
(6)临时支护,在巷道两帮打眼,待左右帮刷够宽度后,采用打水平进尺眼放炮刷帮直至硐室设计尺寸;
(7)打帮部锚杆,然后进行一次性喷浆。
2.根据权利要求1所述的一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,其特征在于:步骤(1)中打眼放炮的位置是在设计硐室起始位置的前面1-3米、与纵向倾斜70°角处。
3.根据权利要求1所述的一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,其特征在于:步骤(3)中挑顶分二层,先挑下面第一层,接着向前上方挑第二层至设计高度。
4.根据权利要求1所述的一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,其特征在于:步骤(6)中所述的刷帮是自硐室起始位置前1-3米处沿硐室方向依次刷帮。
5.根据权利要求1所述的一种煤矿岩巷小断面扩刷成大断面硐室的施工方法,其特征在于:步骤(6)中所述的巷道两帮打眼是指按照与巷道外扎夹角30-50°在巷道两帮打眼;左帮眼深2-3米,右帮眼深1-2米;所述的水平进尺眼放炮,炮眼深度1-2米。
CN201210078755.4A 2012-03-16 2012-03-16 一种煤矿岩巷小断面扩刷成大断面硐室施工方法 Expired - Fee Related CN102619524B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210078755.4A CN102619524B (zh) 2012-03-16 2012-03-16 一种煤矿岩巷小断面扩刷成大断面硐室施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210078755.4A CN102619524B (zh) 2012-03-16 2012-03-16 一种煤矿岩巷小断面扩刷成大断面硐室施工方法

Publications (2)

Publication Number Publication Date
CN102619524A true CN102619524A (zh) 2012-08-01
CN102619524B CN102619524B (zh) 2014-05-28

Family

ID=46559705

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210078755.4A Expired - Fee Related CN102619524B (zh) 2012-03-16 2012-03-16 一种煤矿岩巷小断面扩刷成大断面硐室施工方法

Country Status (1)

Country Link
CN (1) CN102619524B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979534A (zh) * 2012-12-11 2013-03-20 安徽恒源煤电股份有限公司 一种tu棚支护工艺
CN105041323A (zh) * 2014-12-31 2015-11-11 龙口矿业集团有限公司 三软岩层切眼大断面施工及其支护方法
CN105937395A (zh) * 2015-09-14 2016-09-14 安徽建筑大学 一种煤矿大断面硬岩巷道综掘与炮掘联合快速高效掘进方法
CN106121689A (zh) * 2016-08-22 2016-11-16 福州大学 一种非煤矿山地下大型硐室的开挖方法
CN106285731A (zh) * 2016-08-05 2017-01-04 湖南科技大学 一种高大硐室的小天井辐射式与台阶式的混合施工法
CN109707384A (zh) * 2018-12-18 2019-05-03 山西宏厦第一建设有限责任公司 一种煤矿盾构机拆解硐室的施工方法
CN110541711A (zh) * 2019-09-03 2019-12-06 山东唐口煤业有限公司 一种硐室刷大加固方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3352649B2 (ja) * 1999-06-16 2002-12-03 前田建設工業株式会社 中壁分割工法による既設トンネルの断面拡幅工法
CN101699030A (zh) * 2009-11-20 2010-04-28 中冶集团华冶资源开发有限责任公司 一种大硐室掘进方法
CN101718199A (zh) * 2009-12-20 2010-06-02 山西晋城无烟煤矿业集团有限责任公司 煤矿大断面硐室施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3352649B2 (ja) * 1999-06-16 2002-12-03 前田建設工業株式会社 中壁分割工法による既設トンネルの断面拡幅工法
CN101699030A (zh) * 2009-11-20 2010-04-28 中冶集团华冶资源开发有限责任公司 一种大硐室掘进方法
CN101718199A (zh) * 2009-12-20 2010-06-02 山西晋城无烟煤矿业集团有限责任公司 煤矿大断面硐室施工方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《矿业安全与环保》 20040630 邓文礼 江南煤矿第一大硐室的施工方法__火铺矿改扩建003大硐室的施工 第130-131页 第31卷, 第3期 *
朱爱章: "浅谈硐室的施工方法", 《矿业研究与开发》, vol. 19, no. 3, 30 June 1999 (1999-06-30), pages 7 - 10 *
邓文礼: "江南煤矿第一大硐室的施工方法――火铺矿改扩建003大硐室的施工", 《矿业安全与环保》, vol. 31, no. 3, 30 June 2004 (2004-06-30), pages 130 - 131 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979534A (zh) * 2012-12-11 2013-03-20 安徽恒源煤电股份有限公司 一种tu棚支护工艺
CN102979534B (zh) * 2012-12-11 2015-12-02 安徽恒源煤电股份有限公司 一种tu棚支护工艺
CN105041323A (zh) * 2014-12-31 2015-11-11 龙口矿业集团有限公司 三软岩层切眼大断面施工及其支护方法
CN105937395A (zh) * 2015-09-14 2016-09-14 安徽建筑大学 一种煤矿大断面硬岩巷道综掘与炮掘联合快速高效掘进方法
CN105937395B (zh) * 2015-09-14 2018-10-26 安徽建筑大学 一种煤矿大断面硬岩巷道综掘与炮掘联合快速高效掘进方法
CN106285731A (zh) * 2016-08-05 2017-01-04 湖南科技大学 一种高大硐室的小天井辐射式与台阶式的混合施工法
CN106121689A (zh) * 2016-08-22 2016-11-16 福州大学 一种非煤矿山地下大型硐室的开挖方法
CN109707384A (zh) * 2018-12-18 2019-05-03 山西宏厦第一建设有限责任公司 一种煤矿盾构机拆解硐室的施工方法
CN110541711A (zh) * 2019-09-03 2019-12-06 山东唐口煤业有限公司 一种硐室刷大加固方法

Also Published As

Publication number Publication date
CN102619524B (zh) 2014-05-28

Similar Documents

Publication Publication Date Title
CN102619524B (zh) 一种煤矿岩巷小断面扩刷成大断面硐室施工方法
CN102619513B (zh) 同在原岩中布置底部出矿结构的房柱式中深孔充填采矿法
CN100554642C (zh) 一种长壁综采回收房式开采煤柱的方法
CN108661646A (zh) 一种假顶房柱式留矿嗣后充填采矿法
CN105735995A (zh) 一种松软顶板切顶下的沿空留巷方法
CN102953732A (zh) 房柱式大直径深孔倒台阶状分段侧向崩矿嗣后充填采矿法
CN104847352A (zh) 预护顶阶段矿房与上向分层联合充填采矿法
CN101699030A (zh) 一种大硐室掘进方法
CN105649635B (zh) 一种采空区内煤层复采巷道掘进方法
CN104613831A (zh) 一种在竖井周边眼外围增设周边辅助眼的施工方法
CN103114854B (zh) 一种再造人工间柱回采矿柱的方法
CN105545353A (zh) 一种基于膏体充填的人工假顶构筑方法
CN109057798A (zh) 一种适用于缓倾斜磷矿床的壁式充填采矿方法
CN104453900A (zh) 一种近水平矿体充填采矿方法
CN105569693A (zh) 应用中深孔爆破施工井下稳固性岩层大型硐室的方法
CN105699629B (zh) 三维物理模型试验方法
CN103982186A (zh) 无底柱后退式竖向倾斜分条分段崩落采矿法
CN103557001A (zh) 一种低段高无底柱留矿嗣后充填采矿法
CN102383795B (zh) 综合机械化岩巷掘进工艺
RU2439323C1 (ru) Способ отработки наклонных рудных залежей
CN110259459B (zh) 一种基于三台阶法的隧道开挖施工组织方法
CN109296368A (zh) 一种阶梯式上向水平分层胶结充填采矿方法
CN111780633B (zh) 一种双线隧道ⅳ~ⅴ级围岩下台阶迈步式快速开挖方法
RU2472932C1 (ru) Способ разработки пологих и наклонных мощных рудных тел
CN107905792A (zh) 一种内嵌式竖井开挖施工工艺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Hongzhong

Inventor after: Han Yanzhi

Inventor after: Jie Bo

Inventor after: He Meisheng

Inventor after: Zhang Kaizhan

Inventor before: Chen Peng

Inventor before: Peng Jiyong

Inventor before: Yin Zhaoyuan

Inventor before: Luo Kun

Inventor before: Zhang Hongzhong

Inventor before: Sun Chuanjin

Inventor before: Jie Bo

Inventor before: Liu Hongwei

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHEN PENG PENG JIYONG YIN ZHAOYUAN LUO KUN ZHANG HONGZHONG SUN CHUANJIN JIE BO LIU HONGWEI TO: ZHANG HONGZHONG HAN YANZHI JIE BO HE MEISHENG ZHANG KAIZHAN

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUANGDONG HUABO ENTERPRISE MANAGEMENT CONSULTING C

Free format text: FORMER OWNER: ANHUI HENGYUAN COAL INDUSTRY AND ELECTRICITY POWER CO., LTD.

Effective date: 20150703

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150703

Address after: 510640 Guangdong city of Guangzhou province Tianhe District gold Yinglu No. 1 was 1106 room two

Patentee after: Guangdong Huabo Enterprise Management Consulting Co., Ltd.

Address before: 234000 Anhui province Suzhou City Yongqiao District Taoyuan town of qianyingzi coal mine

Patentee before: Anhui Hengyuan Coal Industry and Electricity Power Co., Ltd.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160201

Address after: Tianhe District Tong East Road Guangzhou city Guangdong province 510665 B-101 No. 5, room B-118

Patentee after: Guangdong Gaohang Intellectual Property Operation Co., Ltd.

Address before: 510640 Guangdong city of Guangzhou province Tianhe District gold Yinglu No. 1 was 1106 room two

Patentee before: Guangdong Huabo Enterprise Management Consulting Co., Ltd.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Juju

Inventor before: Zhang Hongzhong

Inventor before: Han Yanzhi

Inventor before: Jie Bo

Inventor before: He Meisheng

Inventor before: Zhang Kaizhan

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170308

Address after: Lingshou Lingshou County town of Hebei city in Shijiazhuang Province, 050000 new North Street No. 3 B family unit no. 402 south 3

Patentee after: Li Juju

Address before: Tianhe District Tong East Road Guangzhou city Guangdong province 510665 B-101 No. 5, room B-118

Patentee before: Guangdong Gaohang Intellectual Property Operation Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140528

Termination date: 20180316